NS2-DH01-P0ZEN-740009 - ITP For Crane & Hoist Installation - REV.D

This document is an inspection and test plan for crane and hoist installation at the Nghi Son 2 BOT Thermal Power Plant Project. It outlines 8 key inspection items to be completed during material receiving, erection, testing, and final inspection. Inspections include checking for elevation, straightness, span, fit-up, welding, trolley bar, non-destructive testing, load testing, touch-up painting, and a final walk down. Inspections will be held, witnessed, and records reviewed by the contractor, sub-contractor and owner according to the acceptance criteria and standards specified.

Uploaded by

Anh Vàng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views12 pages

NS2-DH01-P0ZEN-740009 - ITP For Crane & Hoist Installation - REV.D

This document is an inspection and test plan for crane and hoist installation at the Nghi Son 2 BOT Thermal Power Plant Project. It outlines 8 key inspection items to be completed during material receiving, erection, testing, and final inspection. Inspections include checking for elevation, straightness, span, fit-up, welding, trolley bar, non-destructive testing, load testing, touch-up painting, and a final walk down. Inspections will be held, witnessed, and records reviewed by the contractor, sub-contractor and owner according to the acceptance criteria and standards specified.

Uploaded by

Anh Vàng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

FOR APPROVAL

ADDED THE TROLLEY BAR INSPECTION


D 13-Nov-19 S.K.Yoon M.S.Jang D.G.Kang
ITEM (2.6)
C 30-Sep-19 S.K.Yoon M.S.Jang D.G.Kang REVISED AS PER OWNER'S COMMENTS

B 5-Sep-19 S.M.Ham M.S.Jang D.G.Kang REVISED AS PER OWNER'S COMMENTS

A 31-Jul-19 S.M.Ham M.S.Jang D.G.Kang FOR APPROVAL

Rev. Date Prepared Checked Approved Details of Revision


Owner

Owner's Engineer

Contractor

DOOSAN HEAVY INDUSTRIES VIETNAM

Sub-Supplier

LILAMA CORPORATION

Project
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
(2 x 600MW)
Title

INSPECTION AND TEST PLAN FOR CRANE & HOIST INSTALLATION

Document No. Rev. Pages.


NS2-DH01-P0ZEN-740009 D 12
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT ID No : NS2-DH01-P0ZEN-740009
(2 x 600MW) Rev : D

TITLE: INSPECTION AND TEST PLAN FOR CRANE & HOIST INSTALLATION
Applicable Specification or Participation by Sampling
No Description of Inspection and Test Acceptance Criteria Record Format Remark
Procedure Sub-Con Contractor Owner frequency

1 Material Reveiving Inspection

- Correct Item, No Damage


1.1 Material Reveiving Inspection Construction Drawing Refer to Material Inspection Report & QCR H W W 100%
- Refer to the Approved Drawing & Packing List

2 Erection

Construction Drawing
2.1 Elavation Check ISO 12488-1 Table 2 Inspection Report For Elevation Check (Form #1) H W RW -
ISO 12488-1

Construction Drawing Inspection Report For Straightness Check (Form


2.2 Straightness Check ISO 12488-1 Table 2 H W RW -
ISO 12488-1 #2)

Construction Drawing
2.3 Span Check ISO 12488-1 Table 2 Inspection Report For Span Check (Form #3) H W RW -
ISO 12488-1

2.4 Fit-up Inspection (If any) AWS D1.1 Refer to AWS D1.1 Fig 5.3 Inspection Report For Fit-Up (Form #4) H W W 100%

Crack: No
Undercut: Max 1 mm for T<25mm
2.5 Welding Visual Inspection (If any) AWS D1.1 Max 2 mm for T≥ 25mm Inspection Report For Welding Visual (Form #5) H W W 100%
Reinforcement: 0 ~3 mm for T≤ 25mm
0~ 5 mm for 25< T≤ 50 mm

2.6 Inspection for Trolley Bar Construction Drawing Construction Drawing Inspection Report For Trolley Bar (Form #5-1) H W W 100% D
NDE Procedure No.: NS2-QE03-P0ZEN- - MT or PT
NDE Procedure No.: NS2-QE03-P0ZEN-040010
2.7 NDE (If any) 040010 - NDE Report H W R 100% Butt
Para PTC.NS2.MT.01, PTC.NS2.PT.01
Para. PTC.NS2.MT.01, PTC.NS2.PT.01 welding

Dynamic load test 110% of rated load (Except QTKĐ 001:2008/BLĐTBXH Inspection Report For Dynamic Load Test (Form Load Testing shall be witnessed by
2.8 Refer to Section 4.3.2 – TCVN 4244:2005 H W W 100%
Chain Block) TCVN 4244:2005 #6) Local Authorized Third Party

Static load test 125% of rated load (Except Chain QTKĐ 001:2008/BLĐTBXH Load Testing shall be witnessed by
2.9 Refer to Section 4.3.2 – TCVN 4244:2005 Inspection Report For Static Load Test (Form #6) H W W 100%
Block) TCVN 4244:2005 Local Authorized Third Party

3 Touch up painting inspection


1. Surface Preparation: SSPC SP 3
2. Dry Film Thickness (Total thickness)
Monorail, Crane, Hoist (Including Canopy)
Refer to Painting Procedure Outdoor:
3.1 Painting inspection (If any) Outside: 240µm (1st:80µm; 2nd:110µm; H W RW -
NS2-YR01-P0ZEN-070001 Touch up Painting Report (Form #7)
3rd:50µm)
Indoor:
Outside: 160µm (1st: 80µm; 2nd:80µm)

4 Final Inspection
4.1 Final Inspection & Walk down Approved Construction Drawing Approved Construction Drawing - Punch List Report (Form #8) H W W 100%
Abbreviation : S: Surveillance R: Report Review RW: Random Witness Inspection W: Witness Inspection H: Hold Inspection
INSPECTION AND TEST PLAN FOR ITP. NS2-DH01-P0ZEN-740009
CRANE & HOIST INSTALLATION Rev. D

CONTENTS

1 INSPECTION REPORT FOR ELEVATION CHECK

2 INSPECTION REPORT FOR SPAN CHECK

3 INSPECTION REPORT FOR STRAIGHTNESS CHECK

4 INSPECTION REPORT FOR FIT-UP

5 INSPECTION REPORT FOR WELDING VISUAL

5-1 INSPECTION REPORT FOR BUS BAR D

6 INSPECTION REPORT FOR DYNAMIC/ STATIC LOAD TEST

7 INSPECTION REPORT FOR TOUCH UP PAINTING

8 PUNCH LIST REPORT


NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
EPC Contractor

Inspection Report For Elevation Check

Report No. Sub-Contractor

Building/Structure Unit

Inspection Item Date

Drawing Number Joint No.

ISO 12488-1

Tolerance of height related to opposite measuring points at right angles at each point of travelling track
Class Class 1 Class 2 Crane Type

Tolerance ±E ±5 max ±10 max Applicable Class

E Result
Point no. Remarks
Design Actual Deviation Accept Reject

<Remarks & Comments>

Subcontractor Contractor Owner/ Owner's Engineer

Signature

Full Name

Date

ITP No.NS2-DH01-P0ZEN-740009 (1)


NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
EPC Contractor

Inspection Report For Straightness Check

Report No. Sub-Contractor LILAMA

Building/Structure Unit

Inspection Item Date

Drawing Number Joint No.

ISO 12488-1

Tolerance of straightness related to height of crane at each point of travelling track ( C )

Tolerance of straightness related to test length of 2000 mm at each point of height of crane rail ( c )

Class Class 1 Class 2 Crane Type


Applicable
Tolerance (C) ±5 ±10
Class
Tolerance (c) 1 2

C c Result
Point no. Remarks
Design Actual Deviation Design Actual Deviation Accept Reject

<Remarks & Comments>

Subcontractor Contractor Owner/ Owner's Engineer

Signature

Full Name

Date
ITP No.NS2-DH01-P0ZEN-740009 (2)
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
EPC Contractor

Inspection Report For Span Check

Report No. Sub-Contractor LILAMA

Building/Structure Unit

Inspection Item Date

Drawing Number Joint No.

ISO 12488-1

Tolerance of span S of the crane rails related to rail centre at each point of travelling track
Class Class 1 Class 2 Crane Type
±3 ±5 Applicable
Tolerance valid for all spans S≤16 m valid for all spans S≤16 m Class
+A= Smax-S
-A=Smin-S ±10 ±15
valid for all spans S>16 m valid for all spans S>16 m

A Result
Point no. Remarks
Design Actual Deviation Accept Reject

<Remarks & Comments>

Subcontractor Contractor Owner/ Owner's Engineer

Signature

Full Name

Date

ITP No.NS2-DH01-P0ZEN-740009 (3)


NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
EPC Contractor
Inspection Report For Fit-up
Report No Sub-contractor LILAMA

Building / Structure Unit

Inspection Item Date

Drawing Number Spool/Joint No.

Construction Drawing/
Inspection Item Accept Reject Remarks
Code & Standard

Follow to AWS D1.1 Fig 5.3 & C-5.21

WPS no DVN-WPS-SMAW-001 and/or DVN-WPS-FCAW-001

1) Root gap (R) Max 2mm

2) Beveling (α) As per drawing requirement -5 °, +10°

3) Root face (f) Max 2mm

Example sketches

Root Gap ( R ) Beveling (α) Root face (f) Results


Joint No. Remarks
Actual Deviation Actual Deviation Actual Deviation Accept Reject

<Remarks & Comments>

Subcontractor Contractor Owner/ Owner's Engineer

Signature

Full Name

Date
ITP No.NS2-DH01-P0ZEN-740009 (4)
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
EPC Contractor

Inspection Report For Welding Visual

Report No Sub-contractor LILAMA

Building / Structure Unit

Inspection Item Date

Drawing Number Spool/ Joint No.


Construction Drawing/
Inspection Item Accept Reject Remarks
Code & Standard

AWS D1.1 Table 6.1 & 5.9

Max 1 mm for T<25mm


- Under cut  
Max 2 mm for T≥ 25mm

- Crack No  

- Slag & Spatter, Arc-Strike and overlap Smoothly grinding  

0~ 3 mm for T≤ 25mm
- Reinforcement  
0~ 5 mm for 25< T≤ 50 mm
<Remarks & Comments>

Subcontractor Contractor Owner/ Owner's Engineer

Signature

Full Name

Date
ITP No.NS2-DH01-P0ZEN-740009 (5)
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
EPC Contractor

Inspection Report For Trolley Bar

Report No. Sub-Contractor

Building/Structure Unit

Inspection Item Date

Drawing Number Joint No.

Inspection Item Requirments Accept Reject Remarks D

- Visual check for the installation of Power


Drawing
Supply Bracket.
- Visual check for the alignment of Bus bar
Drawing
installation.
- Visual check for the installation Main Isolator
Drawing
Switch.

- Visual check for grounding connection. Drawing

- Ensure that all the accessories are installed. Drawing

- Visual check for tagging and wire marking for


Drawing
cable as per approved drawing.
Construction drawing shall be attached during inspection

<Remarks & Comments>

Subcontractor Contractor Owner/ Owner's Engineer

Signature

Full Name

Date
ITP No.NS2-DH01-P0ZEN-740009 (5-1)
NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
EPC Contractor
Inspection Report for Dynamic/Static Load Test
Report No. Sub-Contractor LILAMA

Building/Structure Unit

Inspection Item Date

Drawing Number Joint No.

Section 4.3.2 – TCVN 4244:2005

Test specification :

Design Load Test :

Testing Load Test :

Testing Holding Time : (10 min)

Result
Description (Dynamic/Static
No Item No. Test date Remark
Load Test)
Accept Reject

<Remarks & Comments>

Subconrtactor Contractor Owner/Owner's Engineer Third Party

Signature

Full Name

Date

ITP No.NS2-DH01-P0ZEN-740009 (6)


NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
EPC Contractor
Inspection Report For Touch up Painting
Report No. Sub-Contractor

Building/Structure Unit

Inspection Item Date

Drawing Number Joint/ Item No.

Construction Drawing /
Inspection Item Accept Reject Remarks
Code & Standard

1) Document

1.1. Painting procedure NS2-YR01-P0ZEN-070001 □ □


2) Surface Preparation

2.1. Surface Preparation SSPC SP3 □ □


2.2. Relative Humidity ≤ 85% □ □
2.3. Temperature of painting surface
above Dew point
Not less than 3°C □ □

3) Coating Thickness (DFT) Requirement Accept Reject Remarks

Outdoor:
Outside: 240µm (1st:80µm; 2nd:110µm; 3rd:50µm)
3.1 Exterior Coating Inspection
Indoor: □ □
Outside: 160µm (1st: 80µm; 2nd:80µm)
Exterior
DFT checking Remarks
1st 2nd 3rd

Actual result 3

Note: The actual DFT not less than requirement mentioned 3.1 above
<Remarks/Comments>

Subcontractor Contractor Owner/ Owner's Engineer

Signature

Full Name

Date

ITP No.: NS2-DH01-P0ZEN-740009 (7)


NGHI SON 2 BOT THERMAL POWER PLANT PROJECT
EPC Contractor
Punch List Report
Report No Sub-Contractor LILAMA

Building/Structure Unit

Inspection Item Date

Drawing Number Boundary

Ref. Report No. / TOP No.


Completed Checked Agreed
Defects, Deficiencies, Date By By Closed By
Item No. Location Cat. Remarks
Outstanding Works Completed Owner/Owner'
Subcontractor Contractor
s Engineer

Notes :
Category A Comment that commissioning can proceed only after closure of this comment
Category B Comment that commissioning can proceed even if comment still not closed
<Remarks & Comments>

Subcontractor Contractor Owner/ Owner's Engineer

Signature

Full Name

Date
ITP No.NS2-DH01-P0ZEN-740009 (8)