VTL - WCR

This document provides a work completion report for a solar project. It includes: 1) Details of the equipment installed including the pump capacity, solar panel capacity and make, number of solar modules, and specifications of the automation boxes, structures, and cleaning equipment. 2) Strings and voltage details including the open circuit voltage, current, and number of modules for 8 strings as well as the voltages at the automation panel and inverter end. 3) Earth pit and resistivity details including names, test values, and voltages for 5 earth pits.

Uploaded by

pinak power
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
151 views2 pages

VTL - WCR

This document provides a work completion report for a solar project. It includes: 1) Details of the equipment installed including the pump capacity, solar panel capacity and make, number of solar modules, and specifications of the automation boxes, structures, and cleaning equipment. 2) Strings and voltage details including the open circuit voltage, current, and number of modules for 8 strings as well as the voltages at the automation panel and inverter end. 3) Earth pit and resistivity details including names, test values, and voltages for 5 earth pits.

Uploaded by

pinak power
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Vindhya Telelinks Limited

Annexure-I
Solar: Work Completion Report

Project Title: Date:

Name of GP/Site:
Block Name & District Name:
Name of Sub-Contractor:

Name of EPC Contractor: Vindhya Telelinks Limited- Gaja Engineering Pvt Ltd (JV)

A. Equipment Details

Pump Capacity : (HP) Solar Capacity (DC)- kWp

Solar Panel make & Watt


Nos. of Solar modules
Particulars Serial No/Capacity/Qty. Make Remarks
AJB – 1 : SPD & Fuses,
Disconnector
AJB – 2 : SPD & Fuses,
Disconnector
No. of Structure Table
1. 2 X 10 Table

2. 2 X 5 Table

3. 2 X 4 Table

Telescopic Wiper- 6 meter

1. Cleaning pipe with hose


Vindhya Telelinks Limited
B. Strings & Voltage Details

VOC (V) Current (I) No. of Module VOC (V) Current (I) No. of Module
String - 1 String – 5

String - 2 String – 6

String - 3 String – 7

String - 4 String - 8

Voltage of AJB Voltage of AJB at


O/P at Inverter End
Automation (Aux. Load)
Panel (Pump)

C. Earth Pit & Resistivity Details

DC Earth Pit DC Earth Pit VFD Earth Pit Lightening Arrestor Earth Pit
Earth Pit Name DC- EP-1 DC- EP-2 VFD EP- 3 LA EP- 4 LA EP-5
Earth Test
Value (ohm)
Voltage between Earth &
Neutral (V)

EPC Contractor: Representative of Vindhya Telelinks Limited

Name: Name:

Designation: Designation:

Signature with Stamp: Signature: