Section 130 Blocks 1 - 20
Section 130 Blocks 1 - 20
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil pr ofile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions due to fill placed in the north eastern
corner of the block. It must be noted that part of the block would be equivalent to Class S* (slightly reactive/filled) conditions.
Therefore the classification must be reassessed should the soil profile change either by adding fill or removing soil from the
block and/or if the presence of service trenches or retaining walls are within the zone of influence of the block. Reference
must be made to the comments provided below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be conf irmed by a structural engineer taking into
consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minimal to
reduce potential site costs.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This rep
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the current soil
profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the soil profile
would be equivalent to high range Class M* (moderately reactive/filled) conditions. The site classification must be reassessed
should the subsurface profile change by either cutting or filling and/or if the presence of service trenches, retaining walls or
submerged structures are within the zone of influence of the proposed footings. Reference must be made to the comments
provided below.
Footing Systems: Given the high range nature of the site classification, consideration should be given to adopting a
footing system stiffer than the typical class M systems. All footings must found within a uniform bearing stratum of suitable
strength/material, below the zone of influence of any service trenches, backfill zones, retaining walls or underground
structures. Masonry walls should be articulated in accordance with current best practice. Dwelling design must ensure
suitable drainage and uniform moisture conditions are maintained in the vicinity of footings. Footing systems must be
confirmed by a structural engineer taking into consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Depending on the depth of site cut and trenches, hard rock excavation may be required.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This report must be read in conjuncti
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the current soil
profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the so il profile
would be equivalent to high range Class M* (moderately reactive/filled) conditions. The site classification must be reassessed
should the subsurface profile change by either cutting or filling and/or if the presence of service trenches, retaining walls or
submerged structures are within the zone of influence of the proposed footings. Reference must be mad e to the comments
provided below.
Footing Systems: Given the high range nature of the site classification, consideration should be given to adopting a
footing system stiffer than the typical class M systems. All footings must found within a uniform bear ing stratum of suitable
strength/material, below the zone of influence of any service trenches, backfill zones, retaining walls or underground
structures. Masonry walls should be articulated in accordance with current best practice. Dwelling design must e nsure
suitable drainage and uniform moisture conditions are maintained in the vicinity of footings. Footing systems must be
confirmed by a structural engineer taking into consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Depending on the depth of site cut and trenches, hard rock excavation may be required.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This report must be read in conjuncti
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the current soil
profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the soil profile
would be equivalent to high range Class M* (moderately reactive/filled) conditions. The site classification must be reassessed
should the subsurface profile change by either cutting or filling and/or if the presence of service trenches, retaining walls or
submerged structures are within the zone of influence of the proposed footings. Reference must be made to the comments
provided below.
Footing Systems: Given the high range nature of the site classification, consideration should be given to adopting a
footing system stiffer than the typical class M systems. All footings must found within a uniform bearing stratum of suitable
strength/material, below the zone of influence of any service trenches, backfill zones, retaining walls or underground
structures. Masonry walls should be articulated in accordance with current best practice. Dwelling design must ensure
suitable drainage and uniform moisture conditions a re maintained in the vicinity of footings. Footing systems must be
confirmed by a structural engineer taking into consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Depending on the depth of site cut and trenches, hard rock excavation may be required.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This report must be read in conjuncti
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the current soil
profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the so il profile
would be equivalent to high range Class M* (moderately reactive/filled) conditions. The site classification must be reassessed
should the subsurface profile change by either cutting or filling and/or if the presence of service trenches, retaining walls or
submerged structures are within the zone of influence of the proposed footings. Reference must be mad e to the comments
provided below.
Footing Systems: Given the high range nature of the site classification, consideration should be given to adopting a
footing system stiffer than the typical class M systems. All footings must found within a uniform bear ing stratum of suitable
strength/material, below the zone of influence of any service trenches, backfill zones, retaining walls or underground
structures. Masonry walls should be articulated in accordance with current best practice. Dwelling design must e nsure
suitable drainage and uniform moisture conditions are maintained in the vicinity of footings. Footing systems must be
confirmed by a structural engineer taking into consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Depending on the depth of site cut and trenches, hard rock excavation may be required.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This report must be read in conjuncti
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the current soil
profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the soil profile
would be equivalent to Class M* (moderately reactive/filled) conditions. The site classification must be reassessed should
the subsurface profile change by eit her cutting or filling and/or if the presence of service trenches, retaining walls or
submerged structures are within the zone of influence of the proposed footings. Reference must be made to the comments
provided below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Foot ing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Depending on the depth of site cut and trenches, hard rock excavation may be required.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This report must be read in conjuncti
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the current soil
profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the so il profile
would be equivalent to high range Class M* (moderately reactive/filled) conditions. The site classification must be reassessed
should the subsurface profile change by either cutting or filling and/or if the presence of service trenches, retaining walls or
submerged structures are within the zone of influence of the proposed footings. Reference must be mad e to the comments
provided below.
Footing Systems: Given the high range nature of the site classification, consideration should be given to adopting a
footing system stiffer than the typical class M systems. All footings must found within a uniform bear ing stratum of suitable
strength/material, below the zone of influence of any service trenches, backfill zones, retaining walls or underground
structures. Masonry walls should be articulated in accordance with current best practice. Dwelling design must e nsure
suitable drainage and uniform moisture conditions are maintained in the vicinity of footings. Footing systems must be
confirmed by a structural engineer taking into consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Depending on the depth of site cut and trenches, hard rock excavation may be required.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This report must be read in conjuncti
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the current soil
profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the soil profile
would be equivalent to high range Class M* (moderately reactive/filled) conditions. The site classification must be reassessed
should the subsurface profile change by either cutting or filling and/or if the presence of service trenches, retaining walls or
submerged structures are within the zone of influence of the proposed footings. Reference must be made to the comments
provided below.
Footing Systems: Given the high range nature of the site classification, consideration should be given to adopting a
footing system stiffer than the typical class M systems. All footings must found within a uniform bearing stratum of suitable
strength/material, below the zone of influence of any service trenches, backfill zones, retaining walls or underground
structures. Masonry walls should be articulated in accordance with current best practice. Dwelling design must ensure
suitable drainage and uniform moisture conditions a re maintained in the vicinity of footings. Footing systems must be
confirmed by a structural engineer taking into consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Depending on the depth of site cut and trenches, hard rock excavation may be required.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This report must be read in conjuncti
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil pr ofile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions. It must be noted that the eastern end
of the block would be equivalent to Class S* (slightly reactive/filled) conditions. Therefore the classification must be
reassessed should the soil profile change either by adding fill or removing soil from the block and/or if the pr esence of service
trenches or retaining walls are within the zone of influence of the block. Reference must be made to the comments provided
below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropria te for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minimal to
reduce potential site costs.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This rep
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions due to fill placd in the north western
corner of the block. It must be noted that part of the block would be equivalent to Class S* (slightly reactive/filled) conditions.
Therefore the classification must be reassessed should the soil profile change either by adding fill or removing soil from the
block and/or if the presence of service trenches or retaining walls are within the zone of influence of the block. Reference
must be made to the comments provided below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are a ppropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minimal to
reduce potential site costs.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This rep
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil pr ofile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions due to fill placed in the northern end
of the block. It must be noted that part of the block would be equivalent to Class S* (slightly reactive/filled) conditions.
Therefore the classification must be reassessed should the soil profile change either by adding fill or remo ving soil from the
block and/or if the presence of service trenches or retaining walls are within the zone of influence of the block. Reference
must be made to the comments provided below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or under ground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface drai nage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minimal to
reduce potential site costs.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This rep
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions due to fill placed in the north eastern
corner of the block. It must be noted that the majority of the block would be equivalent to Class S* (slightly rea ctive/filled)
conditions. Therefore the classification must be reassessed should the soil profile change either by adding fill or removing
soil from the block and/or if the presence of service trenches or retaining walls are within the zone of influence of the block.
Reference must be made to the comments provided below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearin g stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ens ure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
soils and in particular in respect to maintaining good surface drainage. It note s that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minimal to
reduce potential site costs.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides gu idance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in th e subsoil profile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions. It must be noted that the eastern
boundary of the block would be equivalent to Class S* (slightly reactive/filled) conditions. Therefore the cla ssification must
be reassessed should the soil profile change either by adding fill or removing soil from the block and/or if the presence of
service trenches or retaining walls are within the zone of influence of the block. Reference must be made to the c omments
provided below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, be low the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
Maintenance Guidelines: Reference should be made to the attached CSIRO Sheet BTF
soils and in particular in respect to maintaining good surface drainage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minimal to
reduce potential site costs.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
This report must be read in conjuncti
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the current soil
profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the so il profile
would be equivalent to high range Class M* (moderately reactive/filled) conditions. The site classification must be reassessed
should the subsurface profile change by either cutting or filling and/or if the presence of service trenches, retaining walls or
submerged structures are within the zone of influence of the proposed footings. Reference must be mad e to the comments
provided below.
Footing Systems: Given the high range nature of the site classification, consideration should be given to adopting a
footing system stiffer than the typical class M systems. All footings must found within a uniform bear ing stratum of suitable
strength/material, below the zone of influence of any service trenches, backfill zones, retaining walls or underground
structures. Masonry walls should be articulated in accordance with current best practice. Dwelling design must e nsure
suitable drainage and uniform moisture conditions are maintained in the vicinity of footings. Footing systems must be
confirmed by a structural engineer taking into consideration any onsite or offsite constraints.
soils and in particular in respect to maintaining good surface drainage. It no tes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Depending on the depth of site cut and trenches, hard rock excavation may be required.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions. It must be noted that the south
western corner of the block would be equivalent to Class S* (slightly reactive/filled) conditions. Therefore the classification
must be reassessed should the soil profile change either by adding fill or removing soil from the block and/or if the presence
of service trenches or retaining walls are within the zone of influence of the block. Reference must be made to the comments
provided below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. D welling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good su rface drainage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798: 2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwa ter may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minim al to
reduce potential site costs.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions. It must be noted that the southern
end of the block would be equivalent to Class S* (slightly reactive/filled) conditions. Therefore the classification m ust be
reassessed should the soil profile change either by adding fill or removing soil from the block and/or if the presence of ser vice
trenches or retaining walls are within the zone of influence of the block. Reference must be made to the comments provi ded
below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
Maintenance Guidelines: on
soils and in particular in respect to maintaining good surface drainage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798: 2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwat er seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minimal to
reduce potential site costs.
The above site classification is provided on the basis that all build ing materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions. It must be noted that the southern
end of the block would be equivalent to Class S* (slightly reactive/filled) conditions. Therefore the classification must be
reassessed should the soil profile change either by adding fill or removing soil from the block and/or if the presence of ser vice
trenches or retaining walls are within the zone of influence of the block. Reference must be made to the comments provided
below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface dr ainage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798: 2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwa ter may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minim al to
reduce potential site costs.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions. It must be noted that the south
western corner of the block would be equivalent to Class S* (slightly reactive/filled) conditions. Therefore the classifi cation
must be reassessed should the soil profile change either by adding fill or removing soil from the block and/or if the presence
of service trenches or retaining walls are within the zone of influence of the block. Reference must be made to the commen ts
provided below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
soils and in particular in respect to maintaining good surface drainage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798: 2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwat er seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minimal to
reduce potential site costs.
The above site classification is provided on the basis that all build ing materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the current soil
profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the soil profile
would be equivalent to Class S* (slightly reactive/filled) conditions. If the building pad, following site excavations exposes
entirely weathered rock, a Class A (non-reactive) classification may be appropriate. Therefore the si te classification must be
reassessed should the subsurface profile change by either cutting or filling and/or if the presence of service trenches,
retaining walls or submerged structures are within the zone of influence of the proposed footings. Reference must be made
to the comments provided below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling design must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
soils and in particular in respect to maintaining good surface drainage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their own interpretations, deductions and c onclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798: 2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minimal to
reduce potential site costs.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1
Site Classification: Site classification in accordance with AS2870:2011 provides guidance on the patterns and
magnitude of moisture related seasonal ground movements that must be considered in design. Based on the worst case
current soil profile / state, on limited subsurface information, soil reactivity and allowing for variation in the subsoil profile, the
site would be equivalent to worst case Class M* (moderately reactive/filled) conditions due to fill placed in the north eastern
corner of the block. It must be noted that part of the block would be equivalent to Class S* (slightly reactive/filled) conditions.
Therefore the classification must be reassessed should the soil profile change either by adding fill or removing soil from the
block and/or if the presence of service trenches or retaining walls are within the zone of influence of the block. Reference
must be made to the comments provided below.
Footing Systems: Reference must be made to AS2870:2011 which indicates footing systems that are appropriate for
each site classification. All footings must found within a uniform bearing stratum of suitable strength/material, below the
zone of influence of any service trenches, backfill zones, retaining walls or underground structures. Masonry walls should
be articulated in accordance with current best practice. Dwelling d esign must ensure suitable drainage and uniform moisture
conditions are maintained in the vicinity of footings. Footing systems must be confirmed by a structural engineer taking into
consideration any onsite or offsite constraints.
Maintenance Guidelines:
soils and in particular in respect to maintaining good surface dra inage. It notes that minor cracking in most structures is
inevitable, and it describes site maintenance practices aimed at minimising foundation movements that can lead to cracking
damage.
Comments/ The successful purchaser must make their ow n interpretations, deductions and conclusions from the
information made available and will need to accept full responsibility for such interpretations,
Limitations: deductions and conclusions.
Development specific geotechnical investigations must be undertaken.
Additional topsoils / fill may have been spread subsequent to the investigation.
Site preparation prior to the construction should include removal of all vegetation, tops oil and any
uncontrolled fill.
All new fill must be placed under controlled conditions (AS 3798:2007), otherwise Class P conditions
would be warranted in those fill areas.
Some variability in subsurface conditions must be anticipated.
Moisture condition of site soils and/or the presence of groundwater may vary considerably from time
of investigation compared to at the time of construction. Groundwater seepages are highly likely after
heavy or prolonged rain.
Hard rock excavation must be anticipated. It is recommended that excavation depths be minimal to
reduce potential site costs.
The above site classification is provided on the basis that all building materials/waste and stockpiles
are removed from site and have not been spread across the site.
It is recommended that footing excavations be inspected by a geotechnical engineer.
Limitations
Douglas Partners (DP) has prepared this report for this project at Taylor 3 Stage 3, Taylor in accordance
dated 20 February 2019 and acceptance received from Indesco Consulting Engineers
Pty Ltd dated 22 June 2020. . This report
is provided for the exclusive use of Indesco Consulting Engineers Pty Ltd for this project only and for the
purposes as described in the report. It should not be used by or relied upon for other projects or purposes
on the same or other site or by a third party. Any party so relying upon this report beyond its exclusive use
and purpose as stated above, and without the express written consent of DP, does so entirely at its own risk
and without recourse to DP for any loss or damage. In preparing this report DP has necessarily relied upon
information provided by the client and/or their agents.
The results provided in the report are indicative of the sub-surface conditions on the site only at the specific
sampling and/or testing locations, and then only to the depths investigated and at the time the work was
carried out. Sub-surface conditions can change abruptly due to variable geological processes and also as a
provided by DP in this report may be affected by undetected variations in ground conditions across the site
between and beyond the sampling and/or testing locations. The advice may also be limited by budget
constraints imposed by others or by site accessibility.
This report must be read in conjunction with all of the attached and should be kept in its entirety without
separation of individual pages or sections. DP cannot be held responsible for interpretations or conclusions
made by others unless they are supported by an expressed statement, interpretation, outcome or conclusion
stated in this report.
This report, or sections from this report, should not be used as part of a specification for a project, without
review and agreement by DP. This is because this report has been written as advice and opinion rather than
instructions for construction.
The scope for work for this investigation/report did not include the assessment of surface or sub-surface
materials or groundwater for contaminants, within or adjacent to the site. Should evidence of filling of
unknown origin be noted in the report, and in particular the presence of building demolition materials, it should
be recognised that there may be some risk that such filling may contain contaminants and hazardous building
materials.
The contents of this report do not constitute formal design components such as are required, by the Health
and Safety Legislation and Regulations, to be included in a Safety Report specifying the hazards likely to be
encountered during construction and the controls required to mitigate risk. This design process requires risk
assessment to be undertaken, with such assessment being dependent upon factors relating to likelihood of
occurrence and consequences of damage to property and to life. This, in turn, requires project data and
analysis presently beyond the knowledge and project role respectively of DP. DP may be able, however, to
assist the client in carrying out a risk assessment of potential hazards contained in the Comments section of
this report, as an extension to the current scope of works, if so requested, and provided that suitable
additional information is made available to DP. Any such risk assessment would, however, be necessarily
restricted to the geotechnical components set out in this report and to their application by the project
designers to project design, construction, maintenance and demolition.
July 2010
Site Anomalies
In the event that conditions encountered on site
during construction appear to vary from those
which were expected from the information
contained in the report, DP requests that it be
immediately notified. Most problems are much
more readily resolved when conditions are
exposed rather than at some later stage, well after
the event.
Site Inspection
The company will always be pleased to provide
engineering inspection services for geotechnical
and environmental aspects of work to which this
report is related. This could range from a site visit
to confirm that conditions exposed are as
expected, to full time engineering presence on
site.
July 2010
Sampling reliability, due to the remoulding, possible mixing
Sampling is carried out during drilling or test pitting or softening of samples by groundwater.
to allow engineering examination (and laboratory
testing where required) of the soil or rock.
Non-core Rotary Drilling
Disturbed samples taken during drilling provide The borehole is advanced using a rotary bit, with
information on colour, type, inclusions and, water or drilling mud being pumped down the drill
depending upon the degree of disturbance, some rods and returned up the annulus, carrying the drill
information on strength and structure. cuttings. Only major changes in stratification can
be determined from the cuttings, together with
Undisturbed samples are taken by pushing a thin- some information from the rate of penetration.
walled sample tube into the soil and withdrawing it Where drilling mud is used this can mask the
to obtain a sample of the soil in a relatively cuttings and reliable identification is only possible
undisturbed state. Such samples yield information from separate sampling such as SPTs.
on structure and strength, and are necessary for
laboratory determination of shear strength and
compressibility. Undisturbed sampling is generally Continuous Core Drilling
effective only in cohesive soils. A continuous core sample can be obtained using a
diamond tipped core barrel, usually with a 50 mm
internal diameter. Provided full core recovery is
Test Pits achieved (which is not always possible in weak
Test pits are usually excavated with a backhoe or rocks and granular soils), this technique provides a
an excavator, allowing close examination of the in- very reliable method of investigation.
situ soil if it is safe to enter into the pit. The depth
of excavation is limited to about 3 m for a backhoe
and up to 6 m for a large excavator. A potential Standard Penetration Tests
disadvantage of this investigation method is the Standard penetration tests (SPT) are used as a
larger area of disturbance to the site. means of estimating the density or strength of soils
and also of obtaining a relatively undisturbed
sample. The test procedure is described in
Large Diameter Augers Australian Standard 1289, Methods of Testing
Boreholes can be drilled using a rotating plate or Soils for Engineering Purposes - Test 6.3.1.
short spiral auger, generally 300 mm or larger in
diameter commonly mounted on a standard piling The test is carried out in a borehole by driving a 50
rig. The cuttings are returned to the surface at mm diameter split sample tube under the impact of
intervals (generally not more than 0.5 m) and are a 63 kg hammer with a free fall of 760 mm. It is
disturbed but usually unchanged in moisture normal for the tube to be driven in three
content. Identification of soil strata is generally successive 150 mm increments and the 'N' value
much more reliable than with continuous spiral is taken as the number of blows for the last 300
flight augers, and is usually supplemented by mm. In dense sands, very hard clays or weak
occasional undisturbed tube samples. rock, the full 450 mm penetration may not be
practicable and the test is discontinued.
Continuous Spiral Flight Augers The test results are reported in the following form.
The borehole is advanced using 90-115 mm In the case where full penetration is obtained
diameter continuous spiral flight augers which are with successive blow counts for each 150 mm
withdrawn at intervals to allow sampling or in-situ of, say, 4, 6 and 7 as:
testing. This is a relatively economical means of 4,6,7
drilling in clays and sands above the water table. N=13
Samples are returned to the surface, or may be In the case where the test is discontinued
collected after withdrawal of the auger flights, but before the full penetration depth, say after 15
they are disturbed and may be mixed with soils blows for the first 150 mm and 30 blows for
from the sides of the hole. Information from the the next 40 mm as:
drilling (as distinct from specific sampling by SPTs 15, 30/40 mm
or undisturbed samples) is of relatively low
July 2010
The results of the SPT tests can be related
empirically to the engineering properties of the
soils.
July 2010
Description and Classification Methods
The methods of description and classification of The proportions of secondary constituents of soils
soils and rocks used in this report are generally are described as follows:
based on Australian Standard AS1726:2017, In fine grained soils (>35% fines)
Geotechnical Site Investigations. In general, the
Term Proportion Example
descriptions include strength or density, colour,
of sand or
structure, soil or rock type and inclusions.
gravel
And Specify Clay (60%) and
Soil Types
Sand (40%)
Soil types are described according to the
predominant particle size, qualified by the grading Adjective >30% Sandy Clay
of other particles present: With 15 30% Clay with sand
Trace 0 - 15% Clay with trace
Type Particle size (mm) sand
Boulder >200
Cobble 63 - 200 In coarse grained soils (>65% coarse)
- with clays or silts
Gravel 2.36 - 63
Term Proportion Example
Sand 0.075 - 2.36
of fines
Silt 0.002 - 0.075
And Specify Sand (70%) and
Clay <0.002 Clay (30%)
Adjective >12% Clayey Sand
The sand and gravel sizes can be further
With 5 - 12% Sand with clay
subdivided as follows:
Trace 0 - 5% Sand with trace
Type Particle size (mm) clay
Coarse gravel 19 - 63
In coarse grained soils (>65% coarse)
Medium gravel 6.7 - 19 - with coarser fraction
Fine gravel 2.36 6.7 Term Proportion Example
Coarse sand 0.6 - 2.36 of coarser
Medium sand 0.21 - 0.6 fraction
Fine sand 0.075 - 0.21 And Specify Sand (60%) and
Gravel (40%)
Adjective >30% Gravelly Sand
Definitions of grading terms used are: With 15 - 30% Sand with gravel
Well graded - a good representation of all Trace 0 - 15% Sand with trace
particle sizes gravel
Poorly graded - an excess or deficiency of
particular sizes within the specified range The presence of cobbles and boulders shall be
Uniformly graded - an excess of a particular specifically noted by beginning the description with
particle size
Gap graded - a deficiency of a particular order indicating the dominant first and the
particle size with the range proportion of cobbles and boulders described
together.
May 2019
Cohesive Soils Estuarine soil deposited in coastal estuaries;
Cohesive soils, such as clays, are classified on the Marine soil deposited in a marine
basis of undrained shear strength. The strength environment;
may be measured by laboratory testing, or Lacustrine soil deposited in freshwater
estimated by field tests or engineering lakes;
examination. The strength terms are defined as
follows: Aeolian soil carried and deposited by wind;
Colluvial soil soil and rock debris
Undrained transported down slopes by gravity;
Description Abbreviation
shear strength Topsoil mantle of surface soil, often with
(kPa) high levels of organic material.
Very soft VS <12
Fill any material which has been moved by
Soft S 12 - 25 man.
Firm F 25 - 50
Stiff St 50 - 100
Very stiff VSt 100 - 200 Moisture Condition Coarse Grained Soils
Hard H >200 For coarse grained soils the moisture condition
Friable Fr - should be described by appearance and feel using
the following terms:
Dry (D) Non-cohesive and free-running.
Cohesionless Soils Moist (M) Soil feels cool, darkened in
Cohesionless soils, such as clean sands, are colour.
classified on the basis of relative density, generally Soil tends to stick together.
from the results of standard penetration tests Sand forms weak ball but breaks
(SPT), cone penetration tests (CPT) or dynamic
easily.
penetrometers (PSP). The relative density terms
are given below: Wet (W) Soil feels cool, darkened in
colour.
Relative Abbreviation Density Index Soil tends to stick together, free
Density (%) water forms when handling.
Very loose VL <15
Loose L 15-35
Medium dense MD 35-65 Moisture Condition Fine Grained Soils
Dense D 65-85 For fine grained soils the assessment of moisture
content is relative to their plastic limit or liquid limit,
Very dense VD >85 as follows:
May 2019
Rock Strength
Rock strength is defined by the Unconfined Compressive Strength and it refers to the strength of the rock
substance and not the strength of the overall rock mass, which may be considerably weaker due to defects.
The Point Load Strength Index Is(50) is commonly used to provide an estimate of the rock strength and site
specific correlations should be developed to allow UCS values to be determined. The point load strength
test procedure is described by Australian Standard AS4133.4.1-2007. The terms used to describe rock
strength are as follows:
Degree of Weathering
The degree of weathering of rock is classified as follows:
May 2019
Degree of Fracturing
The following classification applies to the spacing of natural fractures in diamond drill cores. It includes
bedding plane partings, joints and other defects, but excludes drilling breaks.
Term Description
Fragmented Fragments of <20 mm
Highly Fractured Core lengths of 20-40 mm with occasional fragments
Fractured Core lengths of 30-100 mm with occasional shorter and longer sections
Slightly Fractured Core lengths of 300 mm or longer with occasional sections of 100-300 mm
Unbroken Core contains very few fractures
where 'sound' rock is assessed to be rock of low strength or stronger. The RQD applies only to natural
fractures. If the core is broken by drilling or handling (i.e. drilling breaks) then the broken pieces are fitted
back together and are not included in the calculation of RQD.
Stratification Spacing
For sedimentary rocks the following terms may be used to describe the spacing of bedding partings:
May 2019
3 85 9 87
D 30 8
ROA 83
7 86
81
6
5 84 89
79 4 82 10
3 130 91 11
2 80 12
42 93 88
42 95 14 13 90
78 15 SITE
4 1 138
139 16 92
17 104
20 18 94
97 102
19 96
RO
103 5
100
4
AD
98 5 3
D 30
30
2 105
5
ROA 05 1
D3 101 6
ROA 99
143
114
15 106
7 107
23 14
5 46 8
0 5
A D3 129 137
113 13 112
RO 44
4 47 109 42
45 108
9
3 42 Locality Plan
4
2 6 12 136
42 1 43 49 10
7 111
8 48 110 D 328
11 ROA
22 50 FIRE
9
ROAD 305
51
64
21
65
63 1
12410
52 12 127
20 66
11 77
62
5
53
OPEN OPEN
SP ACE
19 76
11 2 140
SPACE 4
12 43
131
4
13 aa
61 a
2
RO
AADD
54 10 125 A RO
D
18 115 135
ROAD 30
13 75 67 25 RO pp bb
60 3 p
55 9 141 ii
17 142
i
74 24
ROAD 30
14 68 oo
59 DF
o
8 4 129 jj
56 69 116 j
16
1
23 tt
ROAD 327
57 15 134 t
58
7 6 22 kk
73 k aa
ss
30130
72
5 s a
71 DF
ADAD
70 l
l
117 rr
ROAD 30
7 118 21 l r
RORO
bb
26 133 b
1 28 30
126 m
qq
q cc
2 20
144 m c
3 1 m
25 27 16 4 32 119
5 dd
6 7 19 pp
p d
OPEN 29 nn
SP ACE 120
31 n
40 OPEN
SP ACE
15 ee
14 13 37 132 e
oo
123
OPEN
8 33 18 ooo
o
41
12 34 145 FA
SPACE FA
39 10 121 FA ff
38 11 DF
f
9 pp nn
36 122 17 p n
35
127
gg
42 131 g
ROAD 137
qq m
m
ROAD 30
42 5 16 q m
4
2 123
ROAD 137
hh
4 124 h
1 15 rr ll
2 r l
3 3
4 130
ii
OPEN
1 SP ACE
i
kk
125 27 k
5 126
23 14
4
24 5 jjj
6 11 128
22 13 GA
D 13
23 6 127
RG
12 E TT
7 ST
ROA
21 aa
122 7 a
22 8 bb
b cc
FK LEGEND
20 8 tt
21 9 t
ROAD 132
ACE
j
j Approximate Controlled Fill Depth Contour
j OPEN
SP ACE
kk 24 11
k
7
10
18 12
NE T
32
19
11 126 Section Number
CRO
17 13
FLOODWAY 2 18
ROAD
12 1 Block Number
16 14
16
14 13
15
17
15
2 0 50 100
ROAD 13
CLIENT: Indesco Consulting Engineers Pty Ltd TITLE: Test Pit Location Plan-Overall PROJECT No: 77418.41
OFFICE: Canberra DRAWN BY: APH Proposed Residential Subdivision DRAWING No: 1