11 April
11 April
VERSUS
JUDGMENT
process.
Digitally signed by
Sanjay Kumar
Date: 2023.04.10
13:30:12 IST
Reason:
Page 1 of 27
Short facts giving rise to the filing of the petition under Section 11
of the Act and leading to the impugned decision of the High Court
are as follows.
Page 2 of 27
5. On 14.05.2019, NTPC informed SPML that the Bank
taken by NTPC, SPML moved the Delhi High Court by filing Writ
Petition No. 7213 of 2019 under Article 226 of the Constitution, for
the release of the Bank Guarantees. The prayer in the Writ Petition
is to:
Page 3 of 27
(b) Pass any other order or such other orders as may be
necessary in the interests of justice, equity and good
conscience.”
Guarantees alive.
21.09.2020.
filed the present application under Section 11(6) of the Act in the
Page 4 of 27
Delhi High Court on 10.10.20204. In this Arbitration Petition,
Page 5 of 27
Secondly, that the disputes between the parties were settled by
Page 6 of 27
that allegedly prevailed in signing the Settlement Agreement, the
Trading (P) Ltd. v. Pradyuat Deb Burman6, Vidya Drolia and Ors. v.
Port Ltd.8, Sanjiv Prakash v. Seema Kukreja and Ors.9, and Oriental
Insurance Co. Ltd. and Anr. v. Dicitex Furnishing Ltd.10, the High
Arbitrator.
Page 7 of 27
submitted that the Settlement Agreement dated 27.05.2020 was
arrived at during the pendency of the Writ Petition before the High
Page 8 of 27
is restricted to the examination of whether an arbitration
Tribunal.
the Act and would like to underscore the limited scope within
considered.
Page 9 of 27
of a dispute will have to be examined by the court in cases where
Page 10 of 27
18. In a legislative response to these precedents, through the
“(6-A) The Supreme Court or, as the case may be, the
High Court, while considering any application under sub-
section (4) or sub-section (5) or sub-section (6), shall,
notwithstanding any judgment, decree or order of any
court, confine to the examination of the existence of an
arbitration agreement.”
(emphasis supplied)
Duro Felguera (supra), noted that post the 2015 Amendments, the
20. However, in the year 2019, in United India Insurance Co. Ltd.
16 Arbitration and Conciliation (Amendment) Act 2015 (Act 3 of 2016); hereinafter referred to
as ‘the 2015 Amendments’.
17 Duro Felguera supra note 7, para 59 (concurring opinion of Kurian Joseph, J).
18 (2019) 5 SCC 362:
“21. In the instant case, prima facie no dispute subsisted after the discharge voucher
being signed by the respondent without any demur or protest and claim being finally
settled with accord and satisfaction and after 11 weeks of the settlement of claim a
letter was sent on 27-7-2016 for the first time raising a voice in the form of protest that
the discharge voucher was signed under undue influence and coercion with no
supportive prima facie evidence being placed on record in absence thereof, it must
follow that the claim had been settled with accord and satisfaction leaving no arbitral
dispute subsisting under the agreement to be referred to the arbitrator for
adjudication.
22. In our considered view, the High Court has committed a manifest error in passing
the impugned order and adopting a mechanical process in appointing the arbitrator
without any supportive evidence on record to prima facie substantiate that an arbitral
dispute subsisted under the agreement which needed to be referred to the arbitrator
for adjudication.”
Page 11 of 27
accepted an objection of ‘accord and satisfaction’ in opposition to
21. It did not take much time for this Court to reverse the
“10. This being the position, it is clear that the law prior
to the 2015 Amendment that has been laid down by this
Court, which would have included going into whether
accord and satisfaction has taken place, has now been
legislatively overruled. This being the position, it is
difficult to agree with the reasoning contained in the
aforesaid judgment, as Section 11(6-A) is confined to the
examination of the existence of an arbitration agreement
and is to be understood in the narrow sense as has been
laid down in the judgment in Duro Felguera, SA.”
22. The entire case law on the subject was considered by a three-
under Section 11(6) of the Act was laid down. The relevant portion
Page 12 of 27
including the question of jurisdiction and non-
arbitrability.
154. Discussion under the heading “Who Decides
Arbitrability?” can be crystallised as under:
154.1. Ratio of the decision in Patel Engg. Ltd. [SBP &
Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] on the scope of
judicial review by the court while deciding an application
under Sections 8 or 11 of the Arbitration Act, post the
amendments by Act 3 of 2016 (with retrospective effect
from 23-10-2015) and even post the amendments vide
Act 33 of 2019 (with effect from 9-8-2019), is no longer
applicable.
154.2. Scope of judicial review and jurisdiction of the
court under Sections 8 and 11 of the Arbitration Act is
identical but extremely limited and restricted.
154.3. The general rule and principle, in view of the
legislative mandate clear from Act 3 of 2016 and Act 33
of 2019, and the principle of severability and
competence-competence, is that the Arbitral Tribunal is
the preferred first authority to determine and decide all
questions of non-arbitrability. The court has been
conferred power of “second look” on aspects of non-
arbitrability post the award in terms of sub-clauses (i), (ii)
or (iv) of Section 34(2)(a) or sub-clause (i) of Section
34(2)(b) of the Arbitration Act.
154.4. Rarely as a demurrer the court may interfere at
Section 8 or 11 stage when it is manifestly and ex facie
certain that the arbitration agreement is non-existent,
invalid or the disputes are non-arbitrable, though the
nature and facet of non-arbitrability would, to some
extent, determine the level and nature of judicial
scrutiny. The restricted and limited review is to check
and protect parties from being forced to arbitrate when
the matter is demonstrably “non-arbitrable” and to cut off
the deadwood. The court by default would refer the
matter when contentions relating to non-arbitrability are
plainly arguable; when consideration in summary
proceedings would be insufficient and inconclusive;
when facts are contested; when the party opposing
arbitration adopts delaying tactics or impairs conduct of
arbitration proceedings. This is not the stage for the court
to enter into a mini trial or elaborate review so as to usurp
the jurisdiction of the Arbitral Tribunal but to affirm and
uphold integrity and efficacy of arbitration as an
alternative dispute resolution mechanism.”
(emphasis supplied)
Page 13 of 27
23. The limited scope of judicial scrutiny at the pre-referral stage
explained as under:
Page 14 of 27
integrity and efficacy of arbitration as a dispute
resolution mechanism. Conversely, if the court becomes
too reluctant to intervene, it may undermine effectiveness
of both the arbitration and the court. There are certain
cases where the prima facie examination may require a
deeper consideration. The court’s challenge is to find the
right amount of and the context when it would examine
the prima facie case or exercise restraint. The legal order
needs a right balance between avoiding arbitration
obstructing tactics at referral stage and protecting parties
from being forced to arbitrate when the matter is clearly
non-arbitrable.
140. Accordingly, when it appears that prima facie
review would be inconclusive, or on consideration
inadequate as it requires detailed examination, the
matter should be left for final determination by the
Arbitral Tribunal selected by the parties by consent. The
underlying rationale being not to delay or defer and to
discourage parties from using referral proceeding as a
ruse to delay and obstruct. In such cases a full review by
the courts at this stage would encroach on the
jurisdiction of the Arbitral Tribunal and violate the
legislative scheme allocating jurisdiction between the
courts and the Arbitral Tribunal. Centralisation of
litigation with the Arbitral Tribunal as the primary and
first adjudicator is beneficent as it helps in quicker and
efficient resolution of disputes.”
(emphasis supplied)
24. Following the general rule and the principle laid down in Vidya
Drolia (supra), this Court has consistently been holding that the
Ltd. v. Galaxy Infra and Engg. Pvt. Ltd.19, Sanjiv Prakash v. Seema
Kukreja and Ors.20, and Indian Oil Corporation Ltd. v. NCC Ltd.,21
Page 15 of 27
the parties were referred to arbitration, as the prima facie review
principle that the court may not refer parties to arbitration when
demonstrably time-barred.
under Section 11(6) of the Act is very narrow and inheres two
Page 16 of 27
26. As a general rule and a principle, the arbitral tribunal is the
demurrer, the referral court may reject claims which are manifestly
primary first review26 and let facts speak for themselves. This also
facts must lead to a clear conclusion that there is not even a vestige
Page 17 of 27
of doubt that the claim is non-arbitrable.28 On the other hand, even
arbitration29.
and the Court32. Therefore, this Court or a High Court, as the case
Page 18 of 27
arbitrator33, as explained in DLF Home Developers Limited v.
30. SPML duly completed the stipulated work under the subject
during the subsistence of the contract or till the release of the final
33DLF Home Developers Limited v. Rajapura Homes Pvt. Ltd 2021 SCC OnLine SC 781, paras
18, 20.
Page 19 of 27
ground that there are certain disputes between the parties with
these claims.
the body or the Prayer of the Writ Petition. Conspicuously, the Writ
Guarantees.
Page 20 of 27
36. Pending disposal of the Writ Petition, the High Court, by an
the Bank Guarantees alive. The relevant portions of the order are:
“…
2. Issue notice. The learned counsel appearing for the
respondent accepts notice.
3. Admittedly, the contract pursuant to which the bank
guarantees in question had been furnished has been
completed and there is no dispute that the petitioner’s
performance of the contract was satisfactory. The
petitioner also claims that it has received the entire
consideration for the same. The petitioner’s claims that
the release of the bank guarantees is being withheld
contrary to the terms of the contract between the parties,
in order to pressurize the petitioner in respect of certain
disputes in relation to other contracts, which are pending
adjudication before the Arbitral Tribunal.
…
6. In the meanwhile, the respondents are restrained from
invoking the bank guarantees, subject to the petitioner
keeping the same alive.”
Clause.
38. During the pendency of the Writ Petition, the parties engaged
follows:
Page 21 of 27
“NOW THEREFORE, in consideration of the premises and
mutual promises contained herein, the parties agree as
follows:
1. That the Agency undertakes to withdraw WP No.
7213/2019 filed in the Hon’ble High Court upon
execution of the present agreement immediately upon
receipt of original Bank Guarantees stated herein below
lying with NTPC as mentioned herein below at Para 4.
2. That the Agency has agreed not to initiate any further
proceedings in relation with the present contract
agreement and work executed by the Agency, of any
nature whatsoever. Further, the Agency has undertaken
not to raise any claim of any nature whatsoever against
the NTPC Ltd. in relation with the present contract
agreement and work executed by the Agency, be it
Arbitration proceedings, civil suit, writ petition, or any
other proceedings before any judicial or quasi-judicial
forum.
3. That the Agency has confirmed it has received entire
payments arising out of the present contract and the
same stands closed, and no further sum/money is
payable to the Agency in any manner whatsoever by
NTPC Ltd. under the subject contract.
…
5. That NTPC Ltd. has further agreed not to raise any
contempt proceedings against the Agency for not keeping
alive the BGs as directed by the Hon’ble High Court of
Delhi in pending Writ Petition.”
Page 22 of 27
Agreement, NTPC did not file any contempt proceedings against
SPML.
Settlement Agreement.
pointed out that SPML never raised any claims with respect to the
duress are not bona fide, and that there were no pending claims
Page 23 of 27
between the parties for submission to arbitration. The
45. The whole dispute revolves around the solitary act of the
contracts. This was precisely the argument before the High Court,
issuing notice and injuncting NTPC. This fact clearly indicates that
Page 24 of 27
the plea of coercion and economic duress leading to the Settlement
Agreement is an afterthought.
Writ Petition and the High Court’s interim order, when SPML had
complete protection of the Court, that the parties entered into the
alia provided for (i) the release of Bank Guarantees by NTPC, (ii)
Page 25 of 27
repudiation was issued by SPML on 22.07.2020. This letter was
present application under Section 11(6) of the Act was filed. The
Settlement Agreement.
48. The foregoing clarifies beyond doubt that the claims sought
the execution of the Settlement Agreement lack bona fide. They are
themselves, we are of the opinion that this is a case where the High
Court should have exercised the prima facie test to screen and
are the kinds of cases where the High Court should exercise the
Page 26 of 27
50. Accordingly, we have no hesitation in holding that the High
Section 11(6) of the Act. High Court ought to have examined the
51. For the reasons stated above, the decision of the High Court
is set aside, and Civil Appeal No. 4778 of 2022 stands allowed.
....................................CJI.
[Dr Dhananjaya Y Chandrachud]
........................................J.
[Pamidighantam Sri Narasimha]
New Delhi;
April 10, 2023
Page 27 of 27