Problems Booklet

This document provides problems related to the textbook "Reliability of Safety-Critical Systems" by Marvin Rausand and Mary Ann Lundteigen. It contains problems for chapters 1 through 12 of the textbook. The problems cover key concepts in reliability engineering and functional safety such as safety-critical systems, safety instrumented systems, safety integrity levels, failure rates, common cause failures, and standards such as IEC 61508 and sector-specific standards. The document is intended to help students and practitioners test their understanding of topics covered in the textbook.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views

Problems Booklet

This document provides problems related to the textbook "Reliability of Safety-Critical Systems" by Marvin Rausand and Mary Ann Lundteigen. It contains problems for chapters 1 through 12 of the textbook. The problems cover key concepts in reliability engineering and functional safety such as safety-critical systems, safety instrumented systems, safety integrity levels, failure rates, common cause failures, and standards such as IEC 61508 and sector-specific standards. The document is intended to help students and practitioners test their understanding of topics covered in the textbook.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 66

Problems for:

http://www.ntnu.edu/ross/books/sis

Marvin Rausand Mary Ann Lundteigen

(Revision: July 2017)

RAMS Group
Department of Production and Quality Engineering
Norwegian University of Science and Technology
Trondheim, Norway

1
Contents

1 Introduction 4

2 Concepts and Requirements 9

3 Failures and Failure Analysis 18

4 Testing and Maintenance 22

5 Reliability Quantification 25

6 Reliability Data Sources 30

7 Demand Modes and Performance Measures 33

8 Average Probability of Failure on Demand 35

9 Average Frequency of Dangerous Failures 49

10 Common-Cause Failures 54

11 Imperfect Proof-Testing 58

12 Spurious Activation 62

13 Uncertainty Assessment 66

2
Preface

This booklet contains problems related to the book Reliability of Safety-Critical


Systems, Wiley, 2014. Problems are presented for the first 12 of the 13 chapters
of the book.
In most cases, the answers to the questions may be found by studying the
book, but there are also a few cases where you have to obtain information from
other sources. These sources are available on the Internet and you may need to
make a search or visit a given Internet page.A solution booklet covering solution
proposals for some of the problems, has also been prepared, and may be obtained
on request.
This booklet is always under construction. If you have downloaded the file,
please check that you have the most recent version (Version (given by month-year)
appears on the front page). An update may be expected once or twice per year.

Marvin Rausand Mary Ann Lundteigen


[email protected] [email protected]

3
Chapter 1

Introduction

Problem 1. Safety-critical systems and related concepts


Explain the following terms and how they are related to each other:

 Safety-critical system

 Active safety barrier

 Functional safety

 Safety-instrumented system (SIS)

Problem 2. Equipment under control (EUC)


A definition and analysis of the equipment under control (EUC) is the starting
point for identifying needs for safety-critical systms.
(a) What do we mean by EUC?
(b) It is not always straight forward to define EUC, at least restrict the scope to
one EUC. Why is this the case?
(c) What methods may be used to identify the need for safety-critical systems for
an EUC?

Problem 3. Safety barriers


Safety barriers is a commonly used term in risk analysis.
(a) What do we mean by safety barriers, and to what extent does this concept
overlap with the meaning of safety-critical systems?

4
(b) Why is it useful to classify safety barriers? Give some examples of such
classification.
(c) What measures can be used to define the performance of a safety barrier?

Problem 4. Safety performance criteria and risk reduction


(a) The textbook suggest five safety performance criteria for safety barriers:

 Risk reduction

 Functionality/effectiveness

 Reliability/availability

 Response time

 Robustness

Explain what is meant by each of these, and why they are important characteristics
of a safety-barrier.
(b) A safety barrier may be installed to either prevent hazardous events from
occuring or to mitigate the consequences of hazardous events. Due to this, the
textbook suggest two different ways to calculate the risk reduction for each of
these. Explain these two approaches.
(c) How can you formuulate a reliability or availability requirement on the basis
of required amout of risk reduction?

Problem 5. Safety barriers and mode of operation


(a) What are the main differences between safety barriers operating in low-
demand mode compared to safety barriers operated in high-demand mode?
(b) List some automobile safety barriers that operate in low-demand mode and
some that operate in high-demand mode.

Problem 6. Fail-safe design


Fail-safe is an important design principle for safety-critical systems.
(a) What do we mean by fail-safe, and in what way can fail-safe design be
achieved?
(b) Give some examples for fail-safe design principle in relation to:

5
 Sensors

 Logic solver

 Final or actuating devices/elements

(c) What is the difference between de-energize to trip and energize-to trip, and
which of these two principles would you select for a shutdown valve?
(d) What is the difference between fail-safe passive, fail-safe active, and fail-safe
operational?
(e) Which of these fail-safe design principles should be selected to allow:

 Fly-by-wire (avionics)

 Ensure that red light is activated if if the interlock system detects a failure
the green light has been set (railway)

 A shutdown valve closes automatically upon loss of signal to actuator (pro-


cess industry)

Problem 7. Fail-safe design


(a) What do we mean by the following terms:

 Safe state

 Fail-safe

 De-energize to trip

 Energize to trip

(b) What characterizes a shutdown valve that is fail-safe?


(c) Would it be reasonable to select an energize to trip solution to operate this
valve or a de-energize to trip?

Problem 8. Generic standard


IEC 61508 is a so-called generic standard for electrical, electronic, and programmable-
electronic (E/E/PE) systems. Several sector-specific standards related to IEC
61508 have been published.

6
(a) What are the main characteristics of a generic standard?
(b) What do we mean by a sector-specific standard?
(c) IEC 61508 is often referred to as a to be a risk-based standard. What is
meant by risk-based in this context, and what is the main implication of taking
this approach?
(d) Some other sectors (like maritime sector) prefer rule-based standards for de-
sign of safety-critical systems. What can be arguments for and against rule-based
and risk-based standards?
(e) IEC 61508 takes a life cycle approach in the structuring of requirements. Why
is reasonable to address the whole life cycle of a system, and not only the design
phases, in order to achieve functional safety?

Problem 9. Special considerations in process industry sector


(a) What are typical examples of EUC at a process plant?
(b) What may explain why the process industry relies on layers of protections,
rather than a single layer?
(c) What are the SISs within the layers of protection model, and why is it impor-
tant that each of them are independent? In some cases, it is still relevant to rely on
IEC 61508 even if a sector-specific standard is available. This is the case for the
IEC 61511, the standard that applies to the process industry sector.

 Give some examples when IEC 61508 must be used in stead of IEC 61511
when designing a new safety-critical system for a process plant

 Why can it be reasonable to refer to IEC 61508 as the manufacturer standard


and IEC 61511 as the end-user or system integrator standard?

Problem 10. Special considerations for machinery


(a) What characterizes a SRECS for machinery (in comparison with e.g. a SIS
for the process industry)?
(b) What is the EUC in relation to machinery?
(c) What standards are relevant for design of SRECSs?

Problem 11. Special considerations for railway industry standards

7
(a) What subsystems constitute a signaling system, and how are they related?
(b) Give some examples of safety functions associated with signaling systems?
(c) Give some examples of scenarios that must be treated by a signaling system
in relation to a two-track station with single tracks to and from the station.
(d) What standards are applicable for the design of a signaling system?
(e) What do we mean by a safety case, and what is the difference between a
generic product safety case, a generic application safety case and a specific appli-
cation safety case?

Problem 12. Automotive


(a) Give some examples of safety-critical systems installed in a car?
(b) What would be examples of EUC in relation to a car?
(c) What are some of fundamental differences in designing safety-critical systems
for cars and for a process plant? Hint: Accident severity, type of users, ability to
separate systems.
(d) What is the sector specific implementation of IEC 61508 for automotive?
(e) If you where to compare the 6 parts of IEC 61508 and the 10 parts of the
automotive standard: To what extent are the different parts of IEC 61508 covered
by the automotive standard?

8
Chapter 2

Concepts and Requirements

Problem 1. SIS, SIF and other related terms


The textbook has adopted the terms SIS and SIF as generic terms for E/E/PE
safety-related system and E/E/PE safety-related safety function.
(a) Explain the difference between safety instrumented system (SIS) and safety
instrumented function (SIF).
(b) Why is it important to relate reliability assessment to individual functions,
and not to the system as such?
(c) A SIF may be characterized by several attributes. Explain what we mean by
by the following terms:

 Channel

 Element

 Voted group

 Subsystem

Problem 2. Redundancy
Redundancy is often introduced to enhance reliability of SIFs.
(a) What do we mean by the term redundancy?
(b) Give some arguments for and against the use of redundancy as a means to
improve reliability.

9
(c) Give several examples of devices that are often made redundant in safety
instrumented systems for the process industry.
(d) What are the differences between active and passive redundancy? Give some
illustrative examples.
(e) What do we mean by partly loaded redundancy? Give some examples.

Problem 3. Redundancy and hardware fault tolerance


Redundancy level may be expressed by the hardware fault tolerance (HFT).
(a) What do we mean by HFT?
(b) What do we mean by the term “k-out-of-n (koon) voted system”? What is
the corresponding HFT?
(c) Assume that you have four alternative votings to select among: 1oo4, 2oo4,
3oo4, or 4oo4. Which of these configurations would be best for safety (and explain
why)?
(d) Subsystems with high HFT are often prone to spurious/unintended activa-
tions, resulting in unscheduled stops. Which configuration would you choose for
a sensor subsystem if you would like to avoid unscheduled stops?

Problem 4. Hardware fault tolerance


Hardware fault tolerance is a concept that is closely related to redundancy and
voting.
(a) What is meant by hardware fault tolerance (HFT) ?
(b) What is the hardware fault tolerance of a 2oo4 voted group?
(c) What is the hardware fault tolerance of a koon voted group?
(d) Give examples of some voted groups with HFT D 2

Problem 5. Safe state


It is important to define and account for the safe state in the design of a SIS.
(a) What do we mean by the term safe state?
(b) In what kind of situations can it be difficult to define unique safe state?

Problem 6. Demands and demand rate

10
Demands and demand rate are two important issues to address during a risk as-
sessment of the EUC.
(a) What do we mean by the term demand?
(b) Give several examples of typical demands within different application areas
(c) What do we mean by the term demand rate?
(d) Why is the demand rate of importance for the design of a SIF?
(e) The demand rate is de D 5:2  10 5 per hour. How many demands should we
expect during a period of 20 years? What is the probability that we will have at
least one demand during one year?
(f) Give examples of demands where the demand duration may be important.

Problem 7. Risk reduction and RRF


Risk-reduction factor, RRF, has been introduced in standards like IEC 61511.
(a) What is meant by the term risk-reduction factor, RRF?
(b) A SIF has risk-reduction factor, RRF D 150. What is the PFDavg of the SIF?

Problem 8. Safety barriers


Safety barriers are installed to either prevent hazardous events, or mitigate their
consequences if they occur.
(a) What do we mean by the term hazardous event?
(b) What is the main difference between an intermediate barrier and an ultimate
barrier?
(c) Describe possible effects of a hazardous event after a ultimate barrier failure.
Give an example.

Problem 9. Safety integrity

Safety integrity and safety integrity level (SIL) are two key concepts in IEC
61508. In fact, some may refer to IEC 61508 as a SIL-standard.
(a) What do we mean by the term safety integrity?
(b) Which quantitative reliability measures are used for safety integrity? Give a
brief explanation.

11
(c) IEC 61508 defines three categories of requirements that must be met in order
to achieve a certain level of safety integrity. Explain the meaning of each category.
(d) The safety integrity requirements are given as four distinct safety integrity
levels, SIL 1-4, where SIL 4 is the most strict requirement. What is, according to
your opinion, the rationale for splitting the requirements into four levels (SILs)?
Give a brief explanation.
(e) The process industry (see IEC 61511) does not recommend the use of SIL 4
requirements. Why may this be a reasonable position to take?
(f) What is the principal difference between a SIL requirement and the achieved
SIL for a SIF?

Problem 10. Architectural constraints


Architectural constraints pose restrictions on the design of SIS.
(a) Explain briefly what is meant by architectural constraints in IEC 61508.
(b) Why do you think these constraints have been introduced?
(c) The architectural constraints lead to a statement about the minimum required
hardware fault tolerance (HFT) of a subsystem. Explain what input information
or data you need to derive the minimum HFT a subsystem.
(d) The safe failure fraction (SFF), which is one type of information needed to
find the minimum HFT, is heavily disputed. Give some arguments for and against
the use of this parameter as an ability to act safely in response to failures.
(e) Explain how you can find the minimum HFT for a subsystem of pressure
transmitters that has been assigned a SIL 3. Write down the assumptions you
make and the result you get.

Problem 11. Systematic safety integrity

For channels that are not proven in use, it is necessary to also demonstrate
compliance with the requirements for systematic safety integrity. Systematic safety
integrity is mainly met by following certain qualitative requirements. Some of the
requirements are SIL independent (meaning that they apply to all SILs), whereas
others are SIL dependent. The SIL dependent requirements are listed in separate
tables in IEC 61508- 2 and 3.
(a) Give some rationales to why systematic safety integrity is a meaningful con-
cept (in view of what is covered and not covered by hardware safety integrity)

12
(b) Why can it be argued that software safety integrity is a subset of systematic
safety integrity?
(c) Explain the difference between a highly recommended (HR) requirement and
a recommended (R) requirement.
(d) Why are some requirements classified as not recommended (NR)?
(e) Go through tables B.1 and B.2 in IEC 61508-2 (with the support from IEC
61508-7) and discuss how easy it is to apply these requirements.

Problem 12. SIL allocation

SIL allocation is the process of defining SIL requirements for individual safety
instrumented functions (SIFs), based on the overall need for risk reduction as
defined by the risk acceptance criteria.
(a) Mention some methods/approaches that can be used to allocate SILs to SIFs.
(b) Give a brief description of the risk graph method and discuss pros and cons
related to this method
(c) Give a brief description of the LOPA method and give some pros and cons
related to this method.
(d) What are the main differences between the IEC 61508 and the NOG Guide-
line 70 with respect to principles for determining the required SIL? Mention and
discuss some pros and cons for the NOG guideline 070 approach compared to the
IEC approach. Hint: To solve this problem it may be feasible to read selected
sections of Norsk Olje og Gass (NOG) guideline 070, which can be found at
www.norskoljeoggass.no/no/Publikasjoner (select “Retningslinjer” on
this page). You may read sections 7.2 (Approach), 7.6 (Minimum SIL require-
ments), and e.g. Appendix A.3.3 for an practical example).
(e) The SIL requirements derived at in Appendix A in NOG guideline 070, and
presented in table 7.2, are highly influenced by the choice of failure rates used
for the underlying calculations. Discuss some effects on the SIL requirement
setting from using overly conservative ( “too high”) failure rates versus using
overly optimistic ( “too low”) failure rates.

Problem 13. SIL versus PFD and PFH


A SIL requirement gives the target range of the PFDavg and PFH for a safety
instrumented function (SIF). The target value selected within the range defines

13
what is sometimes referred to as the SIL budget for the function, from end to end.
(a) The SIL budget may be distributed down to individual subsystems of the SIF.
What could be possible strategies to distribute this SIL budget (i.e., what could be
possible ways to define how much each subsystem can “consume” of the total SIL
budget)?
(b) Consider a SIF that must fulfill SIL 3. Assume that the subsystem of final
elements is allowed to consume 70% of the maximum allowed PFDavg for the SIF.
What is the PFDavg requirement for this subsystem?

Problem 14. Safety requirements specification


Safety requirements specification, SRS, is a key document for the design of a
safety instrumented system (SIS).
(a) Describe briefly the main contents of an SRS and at what phase(s) in the safety
lifecycle it is developed.
(b) The SRS should include information about functional safety requirements
and safety integrity requirements. Explain these two terms.
(c) A proposed structure of an SRS is presented in NOG guideline 070. Here,
it is suggested that the SRS is developed in three revisions. What could be the
rationales for developing the SRS in stages, and not in one single step.

Problem 15. Safety analysis report (SAR)


A safety analysis report (SAR) is a document type introduced in the NOG guide-
line 070. The SAR is therefore not a well known concept outside Norway, but
with the new revision of IEC 61508 (that came in 2010) a similar document was
introduced; the safety manual in IEC 61508 (see appendix D in IEC 61508-2).
(a) What is the main purpose of a SAR (or alternatively, a safety manual) and by
whom is the document developed?
(b) What type of information does the SAR (or alternatively, the safety manual)
provide?
(c) In what way does this type of document relate to the SRS?

Problem 16. Functional safety assessment (FSA)


A functional safety assessment (FSA) is a key activity within what we define as
management of functional safety.

14
(a) Explain the main objectives of a functional safety assessment (FSA).
(b) IEC 61508-1 gives requirements to the level of independence for those car-
rying out an FSA. Explain briefly how this level of independence is defined, and
describe the factors contributing to a high level of independence.
(c) Assume that you would like to carry out an FSA just after the SIL allocation
process has been completed (the design of the SIFs has not yet started). Assume
further that at least one SIF of the SIFs within the scope of the FSA has been
assigned a SIL 3 requirement. You suggest that an independent group in your
company, for example from an office within your company that is situated in an-
other city. Would this be an acceptable approach? Hint: The SIL 3 requirement
is not part of your decision here, but still it may indicate the severity level of
consequences if a SIF with a SIL 3 requirement fails to perform its functions.
(d) Assume now that your project has proceeded and that you are close to finaliz-
ing the detail design phase. You decide to carry out an FSA before the construction
starts, so ensure that no major issues are overlooked. This time you suggest using
an external consultant company to carry out the FSA who has not been involved
in any previous phases of the project. Is this a feasible approach according to IEC
61508? Explain.
(e) Assume now instead that this external company was involved in the develop-
ment of the SRS. Would you still think it was feasible to use this company to carry
out the FSA? Explain.

Problem 17. Risk graph


A risk graph may require calibration.
(a) Why is a calibration required?
(b) Assume that the a specific EUC design has been studied, and that it has been
found that reasonable estimates for FA and PA are 0.1 and 0.3 respectively (PB
and PB are equal to 1). Calibrate the risk graph considering the following critera:
The tolerable frequencies for consequence A, B, C and D are 1E-4, 1E-5, 1E-6
and 1E-7 per year respectively. W1 , W2 , and W3 . W3 corresponds to demands
less than once per year, W2 to demands less than once every 10 years, and W1 to
demands less than once every 100 years.

Problem 18. Minimum SIL requirements


Read paragraph A.3.1 “Process segregation through PSD” in NOG 070 (accessed
from https:/www.norskoljeoggass.no/en/Publica/Guidelines/). The

15
section argues why a minimum SIL 2 requirement can be set for this function. The
arguments are based on calculated values of PFDavg and some expert judgment,
but do not check the architectural constraints.
(a) Check if the SIL2 requirement is met when the architectural constraints are
taken into account
(b) Architectural constraints are introduced to compensate for uncertainty in re-
liability calculations. However, there may be uncertainty associated with the as-
sumptions and calculations made to determine the minimum HFT. Discuss main
uncertainties that are made to find the architectural constraints.

Problem 19. Reading SIL table

SIL tables give a relationship between the selected reliability measure and the
achievable SIL.
(a) A SIF has PFDavg D 5  10 3 . Which SIL can the SIF fulfill?
7
(b) A SIF has PFH D 4  10 per hour. Which SIL can the SIF fulfill?
(c) When the demand rate is close to once per year, we may, according to IEC
61508, use either PFH or PFDavg as reliability measure. A careful analysis has
shown that PFD of a single system is PFDavg D 8:0  10 4 such that the SIL 3
requirement is fulfilled. It has been assumed that the system is tested four times
every year (1 year =8760 hours). Is it possible to say if the same system would
also meet SIL 3 in the high demand mode, and how would you do this evaluation?

(d) The SIL table can also be used the opposite way. If a SIL requirement has been
stated, it outlines the required PFDavg or PFH range. Assume that you would like
to select one value as a PFDavg or PFH target value (so that you have one specific
value to compare with the calculated PFDavg or PFH for a SIF). Discuss where in
the range you would select the target value (upper, lower, or in the middle)?

Problem 20. Precisions in the use of terms

(a) Is it correct to say that a SIS has SIL 3? (explain your position)
(b) Is it correct to say that a subsystem fulfills SIL 2, given that the architectural
constraints for SIL 2 are met? (explain your position)
4 3
(c) Will a SIF with a PFDavg between 10 and 10 automatically fulfill the SIL

16
3 requirements? Explain.

Problem 21. Architctural constraints


Assume that a SIL 3 requirement has been specified for a SIF, and that one of the
subsystems is a voted group of identical component, each with a SFF = 92%:
(a) What is the minimum HFT for this subsystem, considering the SIL 3 require-
ment and that the components are of type A?
(b) Why is it reasonable that the minimum HFT increases if the components are
reclassified as type B?

Problem 22. Architectural constraints

Assume that a subsystem comprises two non-identical components, where


component 1 has a SFF = 75% and component 2 has a SFF = 95%. Assume
that one component is type A (component 1) and one is type B (component B).
What is the SIL achieved for this architecture?

17
Chapter 3

Failures and Failure Analysis

Problem 1. Failure, fault, and error


Explain, discuss and compare the following terms
(a) Failure
(b) Fault
(c) Error
(d) What are the differences between the three concepts?
(e) A valve is not able to close as designed, is this a failure or a fault?

Problem 2. Failure modes


Failure analysis usually includes the identification of failure modes.
(a) What do we mean by the term failure mode?
(b) List and explain briefly the main failure modes of a water pump
(c) OREDA data handbooks (www.oreda.org distinguish between critical fail-
ures, degraded failures, and incipient failures. Classify the failure modes you
identified into these categories, and give a brief explanation to why a failure mode
is assigned to this category. Make sure that at all failure mode categories include
at least two failure modes.

Problem 3. Other failure terms


Explain the following terms and give examples:
(a) Failure cause

18
(b) Failure mechanism
(c) Failure effect
(d) What are the main differences between a failure mode and a failure effect?

Problem 4. Failure classification in IEC 61508


IEC 61508 classifies failure modes into the following categories: Dangerous de-
tected (DD), dangerous undetected (DU), safe detected (SD) and safe undetected
(SU). A category called no part/no effect failures are also suggested in the stan-
dard.
(a) Assume that a water pump is used as a fire pump. The pump is normally
passive and started on demand in case of a fire. Suggest at least one failure mode
in each of the categories: DD, DU, SD and SU. List your assumptions.
(b) What does it mean that a dangerous (or safe) failure is detected (DD or SD),
i.e. what requirements apply for a failure to be defined as detected? Explain
(c) Assume now that the pump instead is used for boosting fluid pressure in a
pipeline, and that the pump must close in case of a downstream restriction to
avoid over-pressurization of pipeline. How would this change in functionality
affect your classification? Explain.
(d) It is not always straight forward to judge if a failure is safe or dangerous.
Consider the two cases: It is found during a proof test that a level transmitter
(with low low set-point) indicates a too high level (compared to real level). On the
same vessel, another level transmitter (with high high set-point) is also indicating
too high level. How would you classify these two failures (too high level) for
these two cases. Explain.

Problem 5. Failiure classification in IEC 61508

Failures may be classified according to their causes. IEC 61508 distinguishes


between a random hardware failure and a systematic failure, and the two failures
are treated quite differently in the design of a safety instrumented system (SIS).
(a) Explain what we mean by a random hardware failure and argue why it is a
physical failure
(b) Random hardware failures are given different definitions in this book and by
the PDS method. Discuss these definitions and present your own view on this
concept.

19
(c) What is a systematic failure/fault? Give some examples.
(d) Would you classify an excessive stress failure as random or systematic, and
why?
(e) Are there any relationships between common-cause failures and systematic
failures? Give some illustrative examples.
(f) How are failures/faults classified in the OREDA project (and data handbooks)?

Problem 6. FMECA and FMEDA

Failure mode, effects and criticality analysis (FMECA) is a widely used method
for identifying and classifying failures of a system and its components.
(a) Why is it possible to argue that FMECA may be used to achieve reliability
growth in a design process?
(b) A similar approach, the failure modes, effects, and diagnostics analysis (FMEDA),
is often used to document compliance to the IEC 61508. In fact, an FMEDA is of-
ten included in an equipment safety manual or safety analysis report (SAR). What
is the main difference between an FMECA and an FMEDA?
(c) Assume that you would like to use an FMEDA to determine DU, DD, SU
and SD failure rates. Assume further that the component in question constitutes
some parts with high level of redundancy (on the control side) and other parts
that has only single elements. One such example could be a blow out preventer
(BOP) used to shut in the well in case of a well kick or rig problem. A BOP
manufacturer may want to provide failure rates for the BOP as such, since the
BOP from their perspective is a single unit of delivery. Discuss some challenges
in applying FMEDA in this case. Would you argue that it is reasonable to calculate
DU, DD, SD and SU failure rates for the BOP as such?

Problem 7. Failure classification

Assume that you are part of a team reviewing failures reported for safety-
critical items. The failures found in relation to point gas detectors are described in
the table below. Detection method means how the failure was discovered. Detec-
tion method PM means that the failure was found during regular preventive main-
tenance, such as function testing. Alarm means that the failure was announced
by an alarm from the self-diagnostic system of the component, or the fire and gas
central.

20
Hint: If you are not familiar with point gas detectors, you may do a search
on the internet to find some useful sources. Here is one example accessed in July
2017: https://www.gmiuk.com/wp-content/uploads/2014/09/GD10P_
Operator_Manual.pdf

Table 3.1: Failure description for gas (point) detector


Tag no Short text Comments Detection Cat.
method
70-GD-001 Gas detection May be due to Alarm
comes in with fault snow
70-GD-008 Need to flush test Dirty test line PM
line
70-GD-118 Unstable measure- Indicated too low PM
ment value
70-GD-004 Defect detector Unknown cause Alarm
70-GD-001 Change of filter Decayed filter PM
70-GD-011 Dirty lens Dusty lens. Needs Alarm
cleaning
70-GD-098 Gas detector fails Need better Alarm
when rainy weather weather pro-
tection/cover
70-GD-026 Gas detector show- Zero point adjusted PM
ing too high value and span calibrated

(a) Classify failures using failure categories DU, DD, S, NA (NA means here Not
Applicable, due to not being a failure at all or the equipment being in a degraded,
but still functioning state).
(b) Discuss some of the challenges you face when you do the classification. What
would you do to clarify missing information?
(c) What types of failures seem to be of a type that is reoccurring. How easy is it
to avoid such failures in operation?

21
Chapter 4

Testing and Maintenance

Problem 1. Importance of regular testing


Testing is of particular importance for safety instrumented functions (SIFs) that
are operating in the (low) demand mode.
(a) Why is regular testing more important (on a general basis) for low demand
SIFs than high demand SIFs?
(b) In what situations may it also be reasonable to argue for testing of high de-
mand SIFs?

Problem 2. Proof testing


IEC 61508 uses the term proof testing.
(a) What are the main differences between the more general term function test
and a proof test as it is defined in IEC 61508 and in the book? Illustrate your
answer by an example.
(b) A proof test should ideally be performed under realistic demand conditions.
Discuss why this is difficult to achieve (and in some cases not wanted) for (1) a
SIF that includes pressure transmitters, (2) a SIF that include gas detectors, (3) a
SIF that releases CO2 into an local equipment room, and (4) a SIF that shears a
pipe (such as closure of blow out preventer shear ram).
(c) At what stage in the life cycle of a SIS should considerations to proof testing
be introduced? Explain.
(d) The need to carry out proof testing may have design implications. It may,
for example, be necessary to add new components (e.g., to to allow confirma-
tion of test) and new logic (for inhibiting input signals, overriding output signals,

22
forcing input/output signals). Discuss the possible implications that these design
measures may have on the reliability in light of random hardware failures and
systematic failures.

Problem 3. Partial testing


The term partial testing is often used, but sometimes with different meaning.
(a) One example of a partial proof test is partial stroke testing. With basis in this
particular type of test: What are the main differences between a full proof test and
a partial proof test? Give examples.
(b) A partial proof test may also be used to characterize a proof test that has been
split into sub-proof tests, so that the sum of the sub-proof tests covers the scope
of the full proof test. This is, however, not most common interpretation, and sub-
tests could maybe be a a more suitable term. Discuss some of the differences
between this way of defining a partial proof test (in the meaning of sub-tests) and
way it was defined in bullet a, including the implication on test coverage.

Problem 4. Partial versus imperfect test


Partial proof test and imperfect (or non-perfect) proof test are two terms that may
be used with similar meaning. In the book, however, a small distinction has been
made between the two. With basis in this distinction, what are the main differ-
ences between a partial proof test and an imperfect proof test?

Problem 5. Partial proof test coverage


Proof test coverage is an important concept in relation to partial proof testing.
(a) How can we define proof test coverage?
(b) What do we mean when we say that the proof test coverage is 95%?

Problem 6. Classification of tests


In what categories would you be able to place a diagnostic test among the follow-
ing test strategies:

– Partial test

– Full test

– Manual test

– Automatic test

23
– Imperfect test

– Online test

– Offline test

Include a brief explanation of your choice(s).

Problem 7. Spurious activations as tests


False or unintended activations (also referred to as spurious activations) may result
in a full or partial activation of the SIF.
(a) Why can it be of useful to credit spurious activations as tests?
(b) What would be some of the differences between a regular proof test (or func-
tion test) and a spurious activation?

Problem 8. Staggered testing


There are different strategies forhow proof tests are carried out. Explain briefly
each of these approaches, and give some pros and cons for each of these strategies:

– Staggered testing

– Sequential testing

– Simultaneous testing

Problem 9. Introducing human errors during testing


The main purpose of a proof test is to reveal failures. However, failures may also
be introduced during a proof test.
(a) Give examples of failures that may be introduced during a proof test. Hint:
You may consider reading the Health and Safety Executive (HSE) guideline Prin-
ciples for proof-testing of safety instrumented systems in the chemical industry,
which is referenced in the book.
(b) Would you define such failures as systematic failures or the random hardware
failure category. Explain.
(c) To what extent would it be reasonable to include such failures in the total
failure rate, and what could be possible challenges? For example, the occurrence
rate of systematic failures would be highly dependent on how frequent proof tests
are carried out. Discuss, but it is not necessary to make any calculations.

24
Chapter 5

Reliability Quantification

Problem 1. RBDs

Consider the system represented by the reliability block diagram in Figure 5.1.

(a) Carry out the following:

– Explain what we mean by the concept minimal cut set in a reliability block
diagram (RBD).

– Find the minimal cut sets of the system in Figure 5.1.

– Explain what we mean by saying that a cut set is of order 2.

(b) Find the structure function of the system in Figure 5.1.

Assume that the components of the system are independent with the following
function probabilities (reliabilities):
p1 D 0:90; p2 D 0:95; p3 D 0:85; p4 D 0:90; p5 D 0:80.

2 4

1 5

Figure 5.1: System to analyze

25
1 4

2 5

Figure 5.2: System to analyze

(c) Find the system reliability pS .

Problem 2. RBDs
A system has two minimal cut sets: C1 D f1; 2; 3g and C2 D f1; 3; 4; 5g.
(a) Carry out the following:
– Draw the corresponding reliability block diagram.

– Redraw the reliability block diagram (RBD) to obtain an as simple layout


as possible.

– Find the minimal path sets of the system.

(b) Carry out the following:


– Establish the structure function for the system.

– Which component do you consider to be the most important in this system


(justify your answer).

Problem 3. RBDs

Consider the system described by the reliability block diagram in Figure 5.2.
The six components are assumed to be independent with reliabilities: p1 D 0:90,
p2 D 0:95, p3 D 0:85, p4 D 0:80, p5 D 0:95, and p6 D 0:85.
(a) Carry out the following:
– Identify the minimal cut sets of the system

26
– Explain, with words, what a minimal cut set is

– Establish the structure function for the system

– Determine the reliability pS of the system

(b) Determine Birnbaum’s measure of reliability importance, I B .i/, for compo-


nent i D 4. What does this number tell? Give a brief explanation.

Problem 4. Survivability using Weibull distribution


The time to failure of a pump is assumed to be Weibull distributed with scale
parameter  D 2:7  10 4 per hour and shape parameter ˛ D 2:2.
(a) Write the expression for the failure rate function of the pump and make a
sketch of this function.
(b) Find the mean time to failure (MTTF) of the pump.
(c) Find the probability that the pump survives 1 500 hours in operation. Assume
then that the pump has survived t1 D 1 500 hours, and find the probability that it
will survive another 1 500 hours. Comment the result.

Problem 5. Case study: Production system


A production system has two identical channels and is running 24 hours a day
all days. Each channel can have 3 different states, representing 100%, 50%, and
0% capacity, respectively. The failure rate of a channel operating with 100%
capacity is assumed to be constant, 1 00 D 2:410 P 4 hours 1 . When a failure
occurs, the capacity will go to 50% with probability 60% and to 0% capacity
with probability 40%. When a channel is operated with 50% capacity, it may
fail (and go to 0% capacity) with constant failure rate 1 00 D 1:810 P 3 hours 1 .
The system is further exposed to external shocks that will take down the system
P 6 hours 1 .
irrespective of the state it is in. The rate of these shocks is 1 00 D 510
(A shock will take down all channels at the same time)
The two channels are assumed to operate and fail independent of each other.
When both channels have capacity of 50% or less, the whole system is closed
down, and it is not started up again until both channels have been repaired. When
a channel enters 50% capacity, a repair action is “planned” and then carried out.
The planning time includes bringing in spare parts and repair teams. The planning
time is 30 hours in which case the channel continues to operate with 50% capacity.
The active repair time is so short that it can be neglected. When a channel enters
0% capacity (and the other channel is operating with 100% capacity), the planning
time is compressed to 20 hours and the active repair time is still negligible. After

27
a system stop, the mean time to bring the system back to operation is 48 hours,
irrespective of state of the system when it entered the idle state.
Record any additional assumptions you have to make to answer the questions
below.
(a) Define the relevant system states. Use as few states as possible.
(b) Draw the corresponding state transition diagram (Markov diagram).
(c) Establish the transition rate matrix A for the production system.
(d) Establish the Markov steady-state equations on matrix form.
(e) Explain (briefly) what we mean by the concept steady-state probability in this
case.
(f) Find the steady-state probability of the production system.
(g) Establish the Petri net model for this system.
(h) Identify markings with 100%, 50%, and 0% capacity respectively.
(i) Compare the pros and cons of using Markov method and Petri net for this
particular problem and in general.

Problem 6. Case study: Gas detection system


A gas detector is assumed to have constant failure rate DU D 1:6  10 6 per hour
with respect to the DU failure mode “gas detector does not raise alarm when gas
is present.” Assume that the failure rate with respect to the failure mode “false
alarm” is S D 2:1  10 6 per hour. Further, assume that the two failure modes
are independent. Record any extra assumptions you have to make to answer the
questions below.
(a)
– Find the probability that the gas detector will survive 6 months without any
of the two failure modes.

– Find the mean time to failure, MTTF, of the gas detector (with respect to all
(both) failures).

– Explain (briefly) why the assumption of independent failure modes may be


dubious in this case.

(b) Assume that one of the two failure modes has occurred. Carry out the follow-
ing:

28
– What is the probability that this failure is a DU failure?

– Explain (briefly) how you determine this probability (or, develop the for-
mula).

(c) Assume that the production of the gas detectors is subject to variations. When
we buy a gas detector, it will have a constant DU failure rate DU , but the failure
rate may vary from detector to detector. The variation may be described by a
gamma distribution with probability density function

ˇ˛ ˛ 1 ˇDU
fƒ .DU / D  e for DU > 0 (5.1)
€.˛/ DU

The mean value of this distribution is ˛=ˇ and the variance is ˛=ˇ 2 . Based on
earlier experience, we assume that the mean value of the failure rate DU is 1:6 
10 6 påer hour, and that the standard deviation is 0:5  10 6 per hour. Carry out
the following:

– Determine the values of ˛ and ˇ.

– Assume that we choose a gas detector at random from the production and
find the survivor function RDU .t/ for this detector with respect to the DU
failure mode.

– Determine the corresponding failure rate function zDU .t/ for the gas detec-
tor and make a sketch of the function. Discuss the result.

Problem 7. Case study: 2oo3 system

Consider the 2oo3 system that is modeled in figure 5.18 and 5.19 in the text
book.
(a) Verify the formulas and the numerical results of example 5.23 (which does
not include CCFs) and example 5.24 which does include CCFs.
(b) Determine the MTTF for both cases and compare the results.

29
Chapter 6

Reliability Data Sources

Problem 1. Reliability data types and sources


Reliability assessments require access to applicable data to support the models.
(a) Give some examples of reliability data sources that may be applicable?
(b) Discuss some of the differences between generic and application-specific data
(c) Give also some examples of standards that may be used to derive application-
specific data.

Problem 2. Reliability data types and sources (Part of tutorial 2)


What are the pros and cons of using manufacturer provided data in reliability
assessments at at design stage?

Problem 3. Reliability data types and sources


How can failure rates of a device be determined using FMEDA? Give a brief
explanation.

Problem 4. Reliability data for Machinery


ISO 13849-1 suggests that dangerous failure rates are calculated based on the
following formula for mean time to failure ofa dangerous failure (MTTFd ):
B10d
M T TFd D
0:1  nop
where nop is the mean number of annular operation of the component and
B10d is the mean number of cycles till 10% of the components fail dangerously.

30
Table 6.1: Influencing factors
Influencing factor Weight Score
Working principle 0.1 1.0
Location 0.2 1.5
Frequency of use 0.2 0.9
Environmental exposure 0.2 1.2
Frequency and quality of maintenance 0.3 1.2

The latter parameter is determined by the manufacturer based on relevant product


standards for test methods (see ISO 13489 for relevant references).
(a) Give some arguments why it is reasonable to let the MTTF (and thereby the
failure rate) be influenced by the number of cycles/operations per year, rather
than being constant as we often assume for components that are part of safety
instrumented functions (SIF) being operated on demand.
(b) The PDS data handbook (2013 edition) suggests a failure rate D D 0:2  10 6
failures per hour for relays. In ISO 13849-1 suggests that relays (with maximum
load) has a B10d D 400000. How many mean annual operations would this failure
rate correspond to?
(c) ISO 13849-1 also suggests B10d for small load. In this case B10d D 20000000.
How many annular operations does this B10d correspond to? Discuss the results
with respect to applicability for operation in the low demand mode.

Problem 5. Transfer of historical data for new applications (Part of tutorial 2)

A generic failure rate, as it is given in e.g. the PDS data handbook, may not
necessarily capture plant-specific conditions. Brissaud et. al (2010) has suggested
an approach where the generic failure rate may be adjusted, see chapter 6.5.2 in
text book. Assume that an analysis has been carried out and that the following
weight has been assigned for the most important influencing factors, see Table
6.1:
(a) Explain the meaning of weight and score in this model.
(b) Assume that you are considering a shutdown valve. Calculate the plant spe-
cific dangerous undetected (DU) failure rate P if the generic DU failure rate,
B D 1:9  10 6 failures per hour.
(c) Compare the approach (at a high level) of this model with the approach used

31
in MIL-HDBK-217F. What are some of the differences?

Problem 6. Data dossier

(a) What do we mean by a (reliability) data dossier and what type of information
is provided here?
(b) Study one specific reliability data dossier, for example the sample pages pro-
vided for the PDS data handbook at http://www.sintef.no/projectweb/
pds-main-page/pds-handbooks/pds-data-handbook/. Explain in more
detail the information provided and why this information is important in relation
to a reliability assessment.

32
Chapter 7

Demand Modes and Performance


Measures

Problem 1. PFD versus PFH

Probability of failure on demand (PFD) and average frequency of a dangerous


failure per hour (PFH) are two suggested failure measures in IEC 61508.
(a) Define PFD and PFH and discuss some of the differences between the two
measures.
(b) The textbook also introduces the term “Hazardous event frequency” (HEF)
and relates this term to PFD and PFH. Based on these relationships: Why is it
reasonable to claim that HEF  PFH for a SIF that operates in the high-demand
mode and in the low demand mode that HEF D PFDavg de , where de is the
demand frequency?

Problem 2. Demand duration and PFD


A fire extinguishing system must both start on demand (a fire) and continue dis-
tributing water as long as required to stop fire and cool down equipment. In some
cases, it is specified in design for how many hours the fire extinguishing system
must continue to run, once started.
(a) Why is it important to include demand duration when assessing the reliability
of a SIF in this case?
(b) How would you suggest to include the prolonged demand duration in the
analysis of hazardous event frequency (HEF)?

33
Problem 3. Safe failure fraction (SFF)
The safe failure fraction (SFF) is a disputed reliability parameter.
(a) Explain briefly what the SFF is and what it is used for
(b) Assume that you want to purchase a valve. Would the SFF be different if the
valve is to be used to open on demand or close on demand? Explain your position.
(c) A SFF=99% may be obtained for a component with high dangerous failure
rates as well as for low dangerous failure rates. Why is it so? Under what condi-
tions would this statement apply?
(d) Assume that you have designed a component and that you have determined
the SFF to be 72%. However, you would like to initiate a reliability improvement
program to increase the SFF to 95%. What could you do and what would be the
consequences (pros/cons) of your approach?

34
Chapter 8

Average Probability of Failure on


Demand

Problem 1. Failure categories to include in assessment


Which failure mode(s) and corresponding failure rate(s) are the most important
ones for calculating the PFDavg , and why? (using failure classification in IEC
61508 as basis)

Problem 2. Using Taylor expansion


The PFDavg of a subsystem can be calculated using exact formula or approxima-
tion formula (using Taylor series expanstion). Consider a subsystem of indepen-
dent and identical channels that are voted 1oo3 with failure rate DU D 1:9  10 7
per hour. The system is proof-tested with test interval  D 8760 hours.
(a) Set up the formulas for PFDavg using (i) exact formula and (ii) approximation
formula (it is not necessary to develop (ii), just set it up)
(b) Calculate the PFDavg for (i) and (ii) and compare the results. Which one is
the most conservative one?

Problem 3. Total PFD


The overall PFDavg is normally calculated by adding the average PFD for each
subsystem of the SIF. Why are we allowed to do this (with negligible inaccuracy),
and in what situations should we use the exact formulas?

Problem 4. Underlying assumptions

35
(a) What are the underlying assuptions for using the average value of PFD as a
reliability measure?
(b) The PFD is the (average) probability of failure on demand. But demand rate
is not a parameter of the formula for PFDavg . Why do you think on demand has
been added to the term?
(c) Mean fractional downtime (MFDT) is another term used with the same mean-
ing as PFD. Why may it be argued that MFDT is a better (or more prescriptive)
term than PFD?

Problem 5. Selection of Methods


The PFDavg may be calculated by using one of the folloiwng methods:

– Simplified formulas (as described in the textbook)

– Simplified formulas in IEC 61508, part 6

– Fault tree analysis

– Markov analysis

– Petri nets

– Monte Carlo simulation

Mention some pros and cons related to each of these methods. Suggest some
criteria that would be useful when selecting which method to use.

Problem 6. Simplified formulas in the textbook


The textbook has introduced a set of simplified formulas for PFD.
(a) It is often reasonable to regard the unknown downtime due to DU failures
as the main contributors. What is meant by unknown downtime, and why is this
contribution often dominating compared to other contributions?
(b) In some cases, it may also be reasonable to add contribution from known
downtime due to DU failures. What is mean by known downtime in this case,
and what are some of the challenges involved in setting up the formula for this
contribution?
(c) There are situations where also DD failures can influence the PFD. Give some
examples of such situations. Would you regard this contribution as a known down-
time or unknown downtime (and why)?

36
(d) Indicate how you may include the contribution from DD failures for a single
element and a subsystem comprising two elements voted 1oo2.

Problem 7. Fault tree analysis


Fault tree analysis is a widely used approach for reliability analysis, and many
companies use their own or purchased fault tree analysis software.
(a) Many software programs may underestimate PFD. Why is this the case?
(b) What could be an alternative way to determine the PFD using conserviative
approximations, if you had the possibility to list all the minimal cutsets?

Problem 8. Markov analysis


Markov analysis can be a useful alternative to calculate PFD.
(a) It is possible to use Markov to derive analytical expressions for PFD, in situ-
ations where it is not so easy to set up the formulas directly from reliability block
diagrams. In what situations could this apply?
(b) The long term PFD requires that we introduce a non-Markovian transition in
the Markov model. Why is this the case?
(c) For those that would like to investigate on topics beyond the scope of the
textbook: Multiphase Markov has been introduced as an alternative to solve the
problem with the non-Markovian transition. The approach is explained in e.g. IEC
61508, part 6, and in ISO TR 12489. Give a brief explanation of this approach,
using a simple system (e.g. single) as an example.

Problem 9. IEC 61508 formulas


IEC 61508 formulas introduce parameters like:

– Channel-equivalent mean downtime (tCE )

– Group-equivalent mean downtime (tGE )

– Dangerous group frequency (DGF)

– Beta factors (ˇ and ˇD )

(a) Explain briefly each of these parameters


(b) Explain their application for a single element and a subsystem of two identical
elements voted 1oo2

37
(c) Comment the principle difference between ˇ and ˇD .

Problem 10. PDS method


The PDS method has been widely adopted in the Norwegian process industry, see
www.sintef.no/pds

(a) Explain and discuss briefly the following terms used by the PDS method:

– Critical safety unavailability (CSU)

– Downtime unavailability (DTU)

– Probability of test-independent failure (pTIF )

(b) What is terms are included in PFD, and what is included in CSU?
(c) Based on the previous question: What is the main difference between CSU
and PFD?

Problem 11. Comparing results of using different methods (Part of tutorial 3)


Determine the PFDavg of a 2oo4 system using the following methods and the data
provided in Table 7.2 in textbook:
(a) Simplified formulas, assuming DU failures only
(b) IEC 61508 formulas, including both DU and DD failures
(c) Fault tree analysis, including DU failures only
(d) Markov methods, including DU failures only
Compare and discuss the differences in the results. Note that CCFs should be
included.

Problem 12. Petri Net


Consider a system of one component that may fail due to DU failure. The com-
ponent is subject to regular tests.
(a) Set up the Petri Net model for the single component, that allow markings for
functioning state, failed (due to DU) state and repair (state)
(b) Suggest how the regular tests may be added to this model, and include this
approach into the Petri Net model.
(c) Indicate what place would be of interest for the quantification of PFDavg.

38
(d) Assume that the DU failure rate of the component is DU D 1  10 6 per hour,
that the mean time to repair (MTR) is 8 hours, and that the test is carried out every
year (1 year is 8760 hours). Calculate the PFDavg using GRIF (google “GRIF
workshop”, trial version).

Problem 13. Petri Net


Consider a system of two components that may fail due to DU failures. The
components are subject to regular tests.
(a) Explain the meaning of the following three types of proof tests: simultaneous
tests, sequential tests, and staggered tests.
(b) Set up the Petri Net model for the situation with sequential testing
(c) Suggest in this model how you may change the model to include staggered
testing
(d) Assume that the DU failure rate of the components is DU D 1  10 6 per
hour, that the mean time to repair (MTR) is 8 hours, and that the test is carried out
every year (1 year is 8760 hours). For the option of staggered testing, we assume
a staggered time of 3 months. Calculate the PFDavg using GRIF (google “GRIF
workshop”, trial version) for the two options. Compare the results.

Problem 14. Case study: Smoke detector system


A 2oo4 voted group of smoke detectors are installed in a production room. The
voted group shall give a shutdown signal when at least two of the four detectors
are activated. Assume that each of the smoke detectors has a constant failure rate
DU D 7  10 6 per hour, with respect to the DU failure mode “unable to provide
signal when sufficient amount of smoke is present.”
The four detectors are tested and, if necessary, repaired once per year. It is
assumed that the test and the repair times are negligible. Record possible extra
assumptions you have to make to solve the following problems.
(a) Assume that the smoke detectors are independent.

– Determine the PFDavg for the voted group

– Explain verbally what PFDavg expresses

(b) Now, assume that the four detectors are not independent, but that 10% of
all DU failures of a detector are common cause failures (CCFs), and assume that
CCFs can be modeled by a beta-factor model with ˇ D 0:10.

39
– Determine the PFDavg of the 2oo4 voted group

– How much safer is a 2oo4 voted group compared with a 2oo3 voted group
when ˇ D 0:10?

– Would you recommend that a 2oo3 voted group is installed instead of a


2oo4 voted group? Justify your recommendation.

(c) Common cause failures (CCFs) represent a main contributor to PFD.

 Explain briefly why the parameter ˇ can be interpreted as the conditional


probability of multiple failures when a detector fails.

 Discus, briefly, the realism of the beta-factor model.

 Draw a sketch of the PFDavg as a function of ˇ, for 0  ˇ  1, and


comment on the shape of the function.

(d) How many test intervals may pass before the subsystem is found in a failed
state considering the situation with and without CCFs? Does the result seem rea-
sonable?
(e) What is the mean time to the a failed state of the subsystem considering the
two cases in 14(d)?

Problem 15. Case study: Gas detection system


A gas detector has constant failure rate DU D 2:4  10 6 per hour with respect
to the DU failure mode “gas detector does not raise alarm when gas is present.”
Assume that the failure rate with respect to the SU failure mode “false alarm”
is SU D 3:5  10 6 per hour. Further, assume that the two failure modes occur
independent of each other. Record any extra assumptions you have to make to
answer the questions below.
(a) Carry out the following:

– Find the probability that the gas detector survives 6 months (in continuous
operation) without any of the two failure modes.

– Find the mean time to failure, MTTF, of the gas detector (with respect to all
(both) failures).

– Explain briefly why the assumption about independent failure modes may
be a bit doubtful in this case.

40
(b) The gas detector is therefore proof-tested after regular intervals of length
 D 6 months. The time required to test and repair a failed detector is so short
that it may be neglected. After a test/repair, the gas detector is assumed to be
as-good-as-new. Carry out the following:

– Determine the PFDavg for the gas detector.

– Briefly explain (with words) the meaning of the PFDavg .

– How many hours per year are we not “protected” by the gas detector – when
we assume that the gas detector should always be functioning?

(c) Assume now that we have four gas detectors of the same type. The four
detectors are connected to a logic solver with a 3-out-of-4 (3oo4) logic. The
gas detectors are tested at the same time every six months. Otherwise the same
assumptions as in point (c) apply. The logic solver is assumed to be so reliable
that its failure rate may be set to zero. In this question we assume that the four
detectors are independent. Carry out the following:

– Find the survivor function for the 3oo4 voted group.

– Find the PFDavg for the 3oo4 voted group.

(d) Now, assume that the gas detectors are exposed to common cause failures that
can be modeled by a beta-factor model with ˇ D 0:08. Carry out the following:

– Explain (briefly) what the parameter ˇ tells us in the beta-factor model.

– Find the PFDavg of the 3oo4 voted group in this case. Specify the proportion
of the PFDavg that is caused by independent failures and the proportion
caused by common-cause failures.

– List the main strengths and weaknesses of the beta-factor model.

(e) Establish a Markov diagram for the 3oo4 system (with common-cause fail-
ures). Define the states required, the relevant transitions between these states, and
include the transition rates. You may assume that no repair actions are carried out.
Explain briefly how this model can be used to determine the PFDavg of the system.

Problem 16. Case study: Fire pump system


Two identical fire pumps are installed with a 1oo2 configuration as part of a fire
fighting system. The relevant data are given in Table 8.1

41
Table 8.1: Reliability data
Components Value
DU-failure rate 3:0  10 5 per hour
DD-failure rate 5:0  10 5 per hour
Test interval 6 months
Mean repair time (DD and DU) 8 hours
ˇDD and ˇDU 0.1

Remember to list any additional assumptions you have to make to answer the
questions below.
(a) Calculate the PFD of the pumps with IEC 61508 formula, PDS formula, and
Markov model.

In a fire situation, the pumps need to run for a period of time to successfully
put out the fire. If the pumps stop in this period, the fire fighting is not successful.
This period of time is not accounted for in PFD calculation. During fire fighting,
the pumps are normally under much higher stress than when they are idle, so the
failure rate is higher. If the pumps need to run for 8 hours to put out a fire and a
running pump is 10 times as likely to failure as an idle pump.
(b) What is the probability of an unsuccessful fire fighting when we know that the
pump group has started?
(c) An unsuccessful fire fighting is a critical event, assume that fires break out
once every second year, what is the average frequency of critical events? Discuss,
and preferably show, how this measure may be calculated using e.g., an analytical
approach and Markov.

Problem 17. Case study: Overpressure protection system


Consider the safety-critical system in Figure 8.1. The system is an overpres-
sure protection system for an oil/gas pipeline. Four identical pressure transmitters
are installed in the pipeline. When two of the four pressure transmitters signal
high pressure, the logic solver sends signal to both shutdown valves, ESDV1 and
ESDV2 , to close. The pressure transmitters are therefore configured as a 2oo4
voted group with respect to the system’s main safety function. The two valves
are identical. They are kept open in normal operation and should shut the flow in
the pipeline when high pressure is “detected” by the pressure transmitters. The
system is a passive safety system and critical failures are only detected during

42
Pressure transmitters voted 2oo4

SIS
logic solver

PT1 PT2 PT3 PT4

Pipeline

ESDV1 ESDV2

Figure 8.1: Safety instrumented system (SIS).

proof-testing. The whole system is proof-tested at the same time at regular inter-
vals – with test interval  D 1 year.
(a) Carry out the following:
– Establish a reliability block diagram of the whole system with respect to the
system’s main function as a safety barrier.
– List the minimal cut sets of the system.
The two valves, ESDV1 and ESDV2 , have two main failure modes: dangerous
undetected (DU) failures and safe (S) failures. The failure rate with respect to
DU failures is DU;V D 2:5  10 6 per hour, and the failure rate with respect to S
failures is S;V D 3:0  10 6 per hour. To act as a safety barrier, it is sufficient that
one of the valves is functioning.
(b) Carry out the following:
– Find the mean time to a DU-failure for one of the valves
– Determine the probability that both valves survive a test interval without
any failures.
– Consider one single valve, and find the probability that an S failure occurs
before a DU failure.
A pressure transmitter is has failure rate DU;PT D 3:0  10 7 per hour with
respect to DU failures and failure rate S;PT D 5:0  10 6 per hour with respect to
S failures.
(c) Carry out the following:
– Explain (briefly) what we mean by a DU failure and an S failure for a pres-
sure transmitter.

43
– Calculate the probability that the 2oo4 voted group of pressure transmitters
survives a test interval (1 year) without any DU failures – when you assume
that all items are independent.

– Calculate the PFDavg for the 2oo4 voted group (when you assume that the
pressure transmitters are independent – and when you assume that the time
required to test and repair the transmitters is negligible).

– List and explain the assumptions you make in order to calculate PFDavg .

The logic solver (LS) has failure rate DU;LS D 7:010 7 per hour with respect
to DU failures and failure rate S;LS D 1:010 6 per hour with respect to S failures.
(d) Carry out the following:

– Calculate the PFDavg of the whole system when you assume that all the
items are independent.

– List the assumptions you make to calculate this PFD, and explain (briefly)
what we mean by this PFD.

When a (single) signal about high pressure from a pressure transmitter is re-
ceived by the logic solver, the control room is alarmed and a repair-man is sent to
check and fix the problem. When the signal is “false” (safe), the repair-man needs
around 2 hours to repair the problem.
(e) Carry out the following:

– Calculate the total frequency of S failures from the SIS (that give production
shutdown).

– How many production shutdowns caused by S failures from the SIS must
we expect during a period of 10 years?

Assume now that the pressure transmitters are not independent, but that they
are exposed to common-cause failures that can be modeled by a beta-factor model.
Assume that the ˇ-factor with respect to DU-failures is ˇDU;PT D 0:10 while the
ˇ-factor with respect to S-failures is ˇS;PT D 0:25. The two shutdown valves and
the logic solver are still assumed to be independent.
(f) Carry out the following:

– Calculate the PFDavg of the system.

– Calculate the frequency of shutdowns caused by S failures in the SIS.

44
– How many production shutdowns caused by S failures from the SIS must
we now expect during a period of 10 years?

Problem 18. Case study: Overpressure protection system at a chemical plant


In a chemical process plant, several compounds are mixed in a chemical reactor.
Here, we consider the pipeline where one of these compounds is fed into the
reactor. If too much of this compound enters into the reactor, the mixture will
come out of balance and the pressure in the reactor will increase. This is a very
critical event and is controlled by the safety instrumented system (SIS) illustrated
in Figure8.2. Three flow transmitters are installed in the pipeline. When at least
two of the three flow transmitters detect and alarm “high flow”, a signal is sent
to the main logic solver that will transmit a signal to close the two shutdown
valves in the pipeline. In addition, three pressure transmitters are installed in the
reactor. When at least two of the three pressure transmitters detect and alarm “high
pressure”, a signal enters the main logic solver that will transmit a signal to close
the two shutdown valves in the pipeline – and stop the flow of the compound into
the reactor.
Any unplanned shutdown of the reactor, may also lead to dangerous situations,
and spurious shutdowns (i.e., caused by false alarms) should therefore be avoided.
The three flow transmitters are of the same type and are, as illustrated in Fig-
ure 8.2, configured as a 2-out-of-3 (2oo3) system. In the same way, the three
pressure transmitters are of the same type and also configured as a 2oo3 system.
The logic solver transmits a shutdown signal to the valves if it receives a sig-
nal from either the flow transmitters or the pressure transmitters. The main logic
solver is therefore a 1-out-of-2 (1oo2) configuration. It is sufficient that one of
the two shutdown valves (of the same type) is able to close to stop the flow of the
compound into the reactor. The shutdown valves are therefore a 1oo2 system. The
2oo3 votings for the flow and pressure transmitters are physically modules of the
logic solver, even if they are drawn as separate entities in Figure 8.2.
The two shutdown valves are kept open in normal operation and should shut
the flow in the pipeline when high flow or high pressure is “detected” by the
transmitters. The system is a passive safety system and critical failures are only
detected during proof testing (also called function testing). The whole system is
proof tested at the same time at regular intervals – with test interval  D 6 months.
Record any additional assumptions you have to make to answer the questions
below.

Remark:Some of these questions require that also chapters 9-12 have been cov-
ered.

45
Flow
transmitter 1
2oo3
Flow
transmitter 2

Flow 1oo2 1oo2


transmitter 3 Shutdown
valve 1
Logic
solver
Pressure Shutdown
transmitter 1 valve 2
2oo3
Pressure
transmitter 2

Pressure
transmitter 3

Figure 8.2: Safety instrumented system (SIS).

(a) Set up a reliability block diagram of the whole system with respect to the
system’s main function as a safety barrier.
(b) Explain briefly why a 2oo3 configuration of transmitters may have been cho-
sen for this particular SIS.

For the following analyses, we consider two failure modes dangerous undetected
(DU) failures and safe (S) failures. The times required for periodic proof testing
and the possible repair after a failure has been detected are first considered to be
negligible.
The failure rates for the various components are listed in Table 8.2.

Table 8.2: Failure rates for the SIS components in Figure 8.2.
Component DU-failure rate Safe failure rate
(hours 1 ) (hours 1 )
Flow transmitter DU;FT D 6:0  10 7 S;FT D 1:1  10 6
Pressure transmitter DU;PT D 3:0  10 7 S;PT D 4:5  10 7
Logic solver DU;LS D 1:0  10 8 S;LS D 5:0  10 8
Shutdown valve DU;V D 2:1  10 6 S;V D 2:3  10 6

(c) Find the probability that the whole system survives a test interval without any
failures at all.
It is first assumed that all components are independent.

46
A consultant claims that the PFD of the system can be determined by the upper
bound approximation formula.
(d) Use fault tree analysis along with the upper bound approximation formula to
find the PFD of the system.
(e) Discuss (briefly) the accuracy of the result you obtain.
Another consultant claims that it would be better to first find the PFD of each
of the 2oo3 transmitter subsystems by using approximation formulas and then
combine these to find the system PFD.
(f) Perform this calculation. Which of the two approaches would you prefer? Will
the last approach give a more correct result?

The flow transmitters are exposed to common-cause DU-failures (CCF-DUs)


that can be modeled by a beta-factor model with ˇDU;FT D 0:10, and the the
pressure transmitters are exposed to CCF-DUs that can be modeled by a beta-
factor with ˇDU;PT D 0:08. The flow transmitter subsystem and the pressure
transmitter subsystem are assumed to be independent. The two shutdown valves
are assumed to be exposed to CCF-DUs that can be modeled by a beta-factor
model with ˇDU;V D 0:20.
(g) Find the PFD of the whole system when you assume that the main modules
of the system are independent.
Hint: We may assume no dependency between flow transmitters and pressure
transmitters.
When a (single) signal about high pressure from a transmitter is received by
the logic solver, the control room is alarmed and a repair-man is sent to check and
fix the problem. When the signal is “false” (safe), the repair-man needs around 1
hour to repair the problem.
(h) Find the total frequency of S-failures from the SIS-system (that give produc-
tion shutdown) when you assume that all safe failures are independent.
(i) How many production shutdowns caused by S-failures from the SIS must we
expect during a period of 10 years?
Assume now that the transmitters are not independent, but that they are exposed
to common cause failures that can be modeled by a beta-factor model. Assume
that the beta-factor with respect to safe (S) failures is ˇS;FT D 0:12 for the flow
transmitters, while the corresponding ˇ-factor is ˇS;PT D 0:15. The two shutdown
valves are assumed to be independent with respect to S-failures.

47
(j) Find the frequency of shutdowns caused by S-failures in the SIS-system.
How many production shutdowns caused by S-failures from the SIS must we now
expect during a period of 10 years?

Improving the reliability (unavailability) of the valve group can significantly


reduce the overall PFD. One consultant suggests to introduce stagger testing for
the valves as a means to reduce the PFD. It is proposed to maintain the 6 montly
test interval, but always carry out the test of one valve 3 months later than the
other valve.
(k) Calculate the PFD of the valve group when stagger testing is applied.

Another consultant suggests using partial stroke testing (PST) of the valves
instead of staggered testing. A 60% coverage for the partial stroke test is assumed
for each valve.
(l) Calculate the PFD of the valve group when PST is conducted every month.
(m) Discuss briefly the pros and cons of stagger testing and partial stroke testing,
and tell us which testing technique you prefer.

48
Chapter 9

Average Frequency of Dangerous


Failures

Problem 1. Meaning of PFH


(a) PFH is introduced as a reliability measure for safety-critical systems operat-
ing in the high-demand and continuous mode. Why is this measure a reasonable
choice for this mode of operation?
(b) PFH is a frequency measure, but the abbreviation means probability of having
a dangerous failure per hour. Why is the probability per hour introduced (what is
the underlying assumptions)? Hint: Review the assumptions when setting up the
formula where PFH  F T.T /
(c) The formula above applies only when T is not too long. Why is this the case?
(d) PFH may be regarded as the rate of occurrence of failures (ROCOF) with
respect to dangerous failures. What do we mean by ROCOF?

Problem 2. Simplified formulas for PFH as defined in textbook


(a) Demonstrate how PFH formulas are set up in the textbook for a single element
and for a subsystem of two elements voted 1oo2. Explain briefly how DU failures
and DD failures, including CCFs, are incorporated into the formula.
(b) Under what assumptions can we disregard the contributions from DD failures?

Problem 3. Simplified formulas for PFH in IEC 61508, part 6


(a) PFH is the dangerous group frequency (DGF) already introduced in rela-

49
Table 9.1: Failure rates for the PSD system components in Figure 9.1.
Component DU-failure rate ˇ
(hours 1 )
Pressure transmitter (PT) DU;PT D 3:0  10 7 5%
Logic solver (LS) DU;LS D 1:0  10 7
Shutdown valve (XV) DU;V D 2:1  10 6 10%

tion to PFD formulas. What is the main difference between DGF in the high-
demand/continuous demand mode and the low-demand mode? Include one ex-
ample.
(b) Under what assumptions can we disregard the contributions from DD failures?
(c) Explain how to set up the formula for a single element and for a subsystem
of two elements voted 1oo2. Explain briefly how DU failures and DD failures,
including CCFs, are incorporated into the formula.

Problem 4. Determine PFH from Fault tree analysis


(a) How may the PFH be calculated using fault tree analysis?
(b) PFH may also be calculated on the basis of the Birnbaum measure. Briefly
explain this approach, and indicate any advantages of using this approach.

Problem 5. Case study: Process shutdown system (Part of tutorial 4)

Most systems in the process industry are designed such that the demand for a
process shutdown is rather infrequent (<<once per year), therefore most process
shut down (PSD) systems are operated in the low demand mode and their reliabil-
ity are quantified by PFD. Due to more extensive use of automatic trips, one may
find that PSD systems on oil and gas installations offshore are demanded more
often than once per year (up to once per month). In such a situation, it may be
reasonable to calculate the PFH rather than the PFDavg.
Consider a PSD function that shall close one shutdown valve (XV) upon
pipeline pressure above specified setpoint, as shown in Fig. 9.1. The pressure
transmitters are voted 1oo2. All the components are proof tested at the same time
with an interval of 12 months. The failure data of the components are given in
Table 9.1, and for simplicity we include the contribution from DU failures only.
(a) Set up a reliability block diagram for the PSD function.

50
Figure 9.1: Process shutdown (PSD) function

(b) Calculate the PFH using what is referred to as simplified formula presented
in the SIS book and the IEC 61508 formulas. Since no information is provided
about DD failures, we ommit these failures from the calculations.
(c) Assume that demands occur with some months between (but still more often
than once per year, on the average). Is it reasonable to also use PFDavg for this
function, despite being in the high demand mode?

A high pressure pipeline protection system (HIPPS) is installed as a secondary


protection of the pipeline, as shown in Fig. 9.2. The HIPPS has a logic solver
that is separated from the PSD system, and dedicated pressure transmitters and
shutdown valves. The setpoints of the HIPPS pressure transmitters (voted 2oo3)
are set slightly higher than for the PSD function.When a demand occurs, the PSD
function shall respond first, and a HIPPS response is required only in the situation
where the PSD function fails.
We assume for simplicity that different types of pressure transmitters and
valves are selected for the HIPPS and the PSD system, so that dependency be-
tween the PSD system and the HIPPS system can be disregarded.
(d) Set up a reliability block diagram for the HIPPS function.
(e) Assume that the PSD function is demanded on the average 2 times per year.
What is the average demand rate for the HIPPS system? (hint: You may want to
calculate the PFDavg for the PSD function in this case, to find the probability of
being down in the test interval).

51
Figure 9.2: Pressure protection systems for a pipeline section.

(f) Calculate the PFD for the HIPPS systems using simplified formulas and IEC
61508 formula and the formula presented in the book. Since no information is
provided about DD failures, we ommit these failures from the calculations.
(g) Assume that a tolerable frequency of overpressuring the pipeline is 1  10 5
per year. Will the PSD system and the HIPPS system provide the necessary risk
reduction? What could you do if they don’t?

Problem 6. Determine PFH from Markov model (Part of tutorial 4)

Consider the Markov model in Figure 9.5 in textbook, and also shown in Fig-
ure 9.3.
The states are shown in Table 6:

State State description


0 Both channels are functioning (OK)
1 One channel has a DD-fault, one is OK
2 One channel has a DU-fault, one is OK
3 Both channels have DD-faults
4 Both channels have DU-faults
5 One channel has a DD-fault and the other a DU-fault
6 The EUC is brought to a safe state (upon double DD fault)

(a) Add the transitions needed to prepare the model for calculating steady-state

52
Safe
state
6 μSS

μS0
2DU 2DD
4 3
λDU λDD
βλDU βλDD
β
2(1-β)λDU

1OK 1DU
2(1-β)λDD
2OK 1OK 1DD
2 0 1
μDD
μDD

λDD 1DU 1DD λDU


5

Figure 9.3: Markov model for a 1oo2 system exposed to DU and DD failures

solution for PFH. Explain the meaning of each added transition.


(b) Set up the equation for PFH (as a function of the steady state probabilities)
(c) Insert data from table 7.2 in SIS book, and calculate the average PFH in a test
interval.

53
Chapter 10

Common-Cause Failures

Problem 1. CCF definition and interpretation


(a) Elaborate on the meaning of a CCF, using e.g. the definition in the text book
as basis.
(b) What is a root cause and a coupling factor, and why are these two terms useful
when explaining why CCFs occur?
(c) It is possible to argue that a CCF is sometimes a systematic (multiplicity of)
failure and sometimes a random failure? Why is this the case?

Problem 2. Properties of beta factor model


The standard beta-factor model is often a preferred way to include CCFs, due to
its simplicity. However, the model has some non-realistic properties:
(a) Comment on the effect on the independent failure rate when introducing mea-
sures to reduce the value of ˇ. Why is this effect questionable?
(b) A 1oo3 voted system and 2oo3 voted system would obtain approximately
the same value for PFD, assuming identical components and CCFs. Why is this
the case, and what is the realism in having this effect on the PFD? In what situa-
tions would the effect be realistic scenario, and in what situations would it be less
realistic?

Problem 3. C-factor model


(a) Describe and discuss the main differences between the beta-factor model and
the C-factor model.

54
(b) In some cases, it may be argued that the C-factor model is more realistic than
the beta-factor model. Why is this the case?

Problem 4. Extensions of beta factor model


(a) Describe and discuss the main differences between the beta-factor model and
the PDS model.
(b) Study the CM ooN formula and verify some of the values in the table for CM ooN
presented in the PDS method

Problem 5. Effects of CCFs


Consider 1oo3 and 2oo3 architectures and reflect on how vulnerable of CCFs with
respect to dangerous failures and spurious (unintended) activations.

Problem 6. Determining the value of beta


Checklists are sometimes used to determine the value of the beta factor.
(a) Explain the approach advocated in IEC 61508-6 for determining beta
(b) Compare this approach with the approach by Humphrey that is included in
the textbook. Which one do you think is better, and why?

Problem 7. Other CCF models

Consider a 2oo3 architecture may fail due to independent failures, external


non-lethal shocks, and external lethal shocks.

Parameter description Value


.I / Internal (independent) failures 2  10 5

.L/ External lethal shocks (causing all components to fail) 1  10 6

.S / External non-lethal shocks causing x components to fail 1  10 5

P The probability that a component fails given the shock 0.25


 Test interval 3730
For the non-lethal shocks: Assume that X, the number of component failures
given a shock, is distributed binomial with parameter .n; P /, where n is the num-
ber of components failing and P is the probability that a component fails given
the shock respectively.
(a) Explain how you will calculate the PFDavg (set up the formula).

55
(b) Make a reflection on the way CCFs are included here versus in the standard
beta factor model and the PDS CCF model.

Problem 8. Case study: Gas detector system


Consider a voted group of four identical detectors. The DU-failure rate of a detec-
tor is DU D 2:5  10 6 per hour. The four detectors are tested and, if necessary,
repaired once per year. It is assumed that the test and the repair times are negligi-
ble. Record possible extra assumptions you have to make to solve the following
problems. Assume that the four detectors are not independent, but that 10% of
all DU-failures of a detector are common cause failures (CCFs), and assume that
CCFs can be modeled by a beta-factor model with ˇ D 0:10.
(a) Determine the PFDavg of the 2oo4 voted group
(b) How much safer is a 2oo4 voted group compared with a 2oo3 voted group
when ˇ D 0:10?
(c) Would you recommend that a 2oo3 voted group is installed instead of a 2oo4
voted group? Justify your recommendation.
(d) Explain briefly why the parameter ˇ can be interpreted as the conditional
probability of multiple failures when a detector fails.
(e) Discuss, briefly, the realism of the beta-factor model.

Problem 9. Case study: Use of different CCF models


Consider a 2oo3 voted group of identical channels. Let .iDU
/
be the rate of channel
DU-failures caused purely by natural aging. These failures are assumed to be
independent. A consultant claims that the causes of the natural aging failures can
be considered as internal shock processes within the channels, and these processes
are independent between the channels. Let  be the rate of external shocks that
might cause a DU-failure of a cannel. If such a shock occurs, assume that there is a
probability p that each channel will get a DU-failure. Assume that given a shock,
the channels fail independent of each other, hence the number of channels failing
is binomial distributed with parameters n D 3 and p. The following parameter
values are assumed: .iDU
/
D 1:5  10 6 per hour,  D 10 7 per hour, and p D 0:5.
(a) Compare the model described above with (i) the PDS model, and (ii) the
standard beta-factor model when p D 1. Describe similarities and differences.
(b) Determine the total DU-failure rate of a single channel in this model. Further,
determine the total rate of single DU-failures, double DU-failures and triple DU-
failures for the three channels (when both natural aging and external shock failures

56
are considered).
(c) Establish a Markov model for possible transitions within one test period, and
find the PFDavg when the test interval  is 6 months.
Hint: After a DU-failure, there will be only two channels left, and n in the bino-
mial distribution is reduced to two.
(d) When using the beta-factor model, the effect adding more redundancy is very
small. What would we gain by introducing four channels, and vote them 2oo4,
when using the above shock model? (You may use approximation formulas).
Discuss what will be the result when p ! 1?

57
Chapter 11

Imperfect Proof-Testing

Problem 1. Importance of partial and imperfect testing


(a) What is the difference between partial and imperfect testing?
(b) The effect on reliability may be positive if introducing partial testing. Why is
this the case?
(c) What is the meaning of partial and imperfect test coverage, and what would
influence the value that this coverage factor takes in each case?
(d) The effect of introducing partial stroke testing for shutdown valves may be
used enhance reliability or to reduce operating costs. Explain how you would
apply partial stroke testing for achieving each of these two purposes (you may use
a single element as basis for the explanation)
(e) The effect on reliability may be underestimated if not including the effect of
imperfect testing. Why is this the case?
(f) Partial testing and imperfect testing is mainly an issue with safety-critical
systems operating in the low-demand mode. Why is this the case? Can you foresee
situations where it would be reasonable to also include the contribution for safety-
critical systems operating in the high-demand and continuous demand mode?
(g) The approach to model perfect and imperfect testing into the formula for PFD
is the same. Explain the main principles for how this can be done.

Problem 2. Different PST implementations

Partial stroke testing of a valve is a partial proof test designed to operate the

58
valve partially at regular intervals. This means that the valve is moved e.g. 20%
of its full stroke, before returned to its initial (open) position. Since the partial
operation does not cause any significant disturbances in the process, it is possible
to carry out this type of testing more often than a full proof test. Partial stroke
testing of HIPPS valves was introduced for the HIPPS system subsea at the Kristin
field (see the case study for more details).
Manually
activated PST

SIS
logic solver Solenoid
Pilot valve
Actuator
Pump
Pressure To process
PT PT control system Tank
transmitters
Pipeline
Shutdown valve

Manually or automatically
activated PST

Vendor
PST package
SIS
logic solver

Actuator
Pressure To process
PT PT control system
transmitters
Pipeline
Shutdown valve

Figure 11.1: Two alternative implementations of PST

One out of possible implementations may be selected, see Fig. 11.1:

1. PST activated via SIS/HIPPS logic solver: A timer starts to count when the
power is removed to the solenoid, and which repower the solenoid when the
timer has reached its setting.

2. PST activated via vendor/manufacturer “package” for partial stroke testing:


Separate PST circuit is directly interacting in the hydraulic supply to the
valve.

(a) Why do you think partial stroke testing may be a desired option?
(b) What are the pros and cons of each of these options?

59
Failure mode Revaled by PST?
Fail to close (FTC)
Delayed operation (DOP)
Leakage in closed position (LCP)
Premature closure (PC)
Fail to open (FTO)
Leakage to environment (LTE)

Figure 11.2: Failure modes of a shutdown valve

Table 11.1: Data for shutdown valve


Failure mode DU %Revaled by PST Importance/weight
FTC x 100% 30%
DOP x 20% 30%
LCP x 0% 15%
PC NA 10%
FTO NA 10%
LTE NA 5%

(c) Assume that the following failure modes are applicable for the valve, see
Figure 11.2. Which ones of these may be revealed by partial stroke testing?

Problem 3. Determine PST coverage

Assume that you have been given the following data for a shutdown valve, and
you are asked to use this as input for determining the partial stroke test coverage.
(a) What do we mean by partial stroke test coverage, and what are the factors
influencing its value?
(b) What is the partial stroke test coverage, ‚PS T , using the data in Table 11.1?
(c) Assume that the DU failure rate is 8  10 6 failures per hour. What is the
DU failure rate revealed by full proof test, DU;F T , and what is the DU failure
rate,DU;PS T , revealed by partial stroke testing?

Problem 4. Assume now that you have calculated the PST coverage factor and

60
the DU failure rates from from Problems 3(b) and 3(c) .
(a) Calculate the effects of introducing partial stroke testing compared to not
using partial stroke testing (give also the percentage reduction). You may assume
that the partial stroke testing is carried out every month (every 730 hours), and the
full proof test every year (8760 hours).

Problem 5. We often say that partial stroke testing can be used for either improv-
ing safety or reducing costs.
(a) How would you explain this statement with basis in the formula for PFDavg ?
Assume now that the PFD requirement (and thereby the SIL requirement) was
developed under the assumption that the HIPPS function is subject to full proof
test every 6 months, and no PST implemented (you may now calculate the PFDavg
using this assumption). Consider the simplified HIPPS architecture with 1oo2
voted pressure transmitter, a single logic solver, a single solenenoid valve, and a
single shutdown valve. The DU failure rate of the pressure transmitters is 5  10 6
per hour, the DU failure rate of the logic solver 1  10 7 per hour, and the DU
failure rate of the solenoid valve is 4  10 6 per hour. The beta factor for the
pressure transmitters is assumed 5%.
(b) Consider the two alternative implementations of PST introduced in Problem
2. How would you calculate the PFDavg for these two SIFs, when including the
effects of PST. You may use the PST coverage factor for the valve as calculated
in Problem 3(b) for both options, but you may want to make other assumptions
about the PST coverage factor of the solenoid valve.
(c) How much can you extent the full proof test, when PST is added (consider e.g.,
option 1), without comprimising the required PFDavg ? Would you recommend
this new interval? We assume that PST is carried out every month.
(d) Assume now that you consider two valves voted 1oo2 (rather than one valve
voted 1oo1). How would you calculate the PFDavg in this case (consider the
valves only, and not the rest of the SIF).

61
Chapter 12

Spurious Activation

Problem 1. Meaning of spurious activation


(a) What is the meaning of spurious activations, and why is this type of activation
of relevance to consider for a safety-critical system?
(b) It is sometimes suggested to distinguish between the following three types of
spurious activations:

– Spurious operation

– Spurious trip

– Spurious shutdown

What is the difference between these terms, and why may it be important to dis-
tinguish them?
(c) What do we mean by the spurious trip rate (STR), and what failure rates may
be included in the calculation of this measure?
(d) Give one example for how the STR formula is set up for a subsystem com-
prising three elements, voted e.g. 1oo3. Explain in each case, the different types
of contributions.
(e) Assume that you have identified value for ˇ for e.g. pressure transmitters.
Would you use this value for safe as well as for dangerous failures? Why or why
not?

Problem 2. Case study: High integrity pressure protection system (HIPPS)

62
Consider a HIPPS system comprising four pressure transmitters voted 2oo4,
one logic solver, and two shutdown valves voted 1oo2 located subsea.
(a) Consider the pressure transmitters and discuss the interpretation of the terms
spurious operation, spurious trip, and spurious shutdown in relation to these.
(b) It is suggested that both DD and spurious operation (SO)/safe failures may
result in spurious trips. Why do you think that DD failures are considered?
(c) What is the hardware fault tolerance (HFT) of the 2oo4 system with respect
to spurious trips (hint: A 2oo4 system means that 2-out-of-4 elements must carry
out the function in order for the SIF to be carried out. In relation to spurious
trips, the function is “to avoid spurious trips”, so the question should be: How
many spurious operation failures are tolerated without getting a spurious trip of
the SIF?) What is the HFT for a general koon system with respect to spurious
trips.
(d) Common cause failures may also be an issue with spurious trips, and we may
introduce ˇS for this purpose (considering just only spurious operation failures).
Why is it reasonable to assume that ˇS may be different from ˇ (for DU failures)
and ˇD (for DD failures). Give some examples, using either pressure transmitters
or shutdown valves as examples.
Assume that SO failure rates for pressure transmitters, logic solver, valves are
1  10 6 , 1  10 7 and 1  10 5 respectively. ˇS is set to 5% for all components.
Assume further that the downtime of a channel after an SO failure is 6 hours. For
the missing ones use input data from table 7.2 in textbook.
(e) Calculate the total spurious trip rate for the HIPP system, by consider SO
and DD failures only, but exclude the contribution from false demands. Indicate
the percentage contribution from the independent part and the CCF part for each
subsystem.
(f) Calculate the probability of having exactly 1 (spurious) failures during a period
of 5 years?
(g) How many spurious trips due to spurious operation of the valves will you,
on the average, experience in a period of 5 years, if SO D 1  10 5 ? Would
you find this result satisfactory? If you don’t, what could you recommend to the
engineering department? Some control question to base your discussions:

 Would a change in test interval matters?

 Would a more reliable valve type help?

63
 Would you recommend that a 2oo2 configuration was chosen instead, to
reduce the contribution from spurious trips?

Problem 3. Case study: Shutdown valves


Assume that a SIF includes two shutdown valves, voted 1oo2. The two valves
are of identical type with failure rate DU D 1:9  10 6 failures per hour. The
safe (spurious) failure rate for this type of valve is DU D 2:3  10 6 failures per
hourThe valves are tested every year (one year corresponds to 8760 hours). The
demand rate is assumed to be 0:1 per year.
(a) What is the probability that the subsystem of two valves survives the proof
test interval without any DU failure?
(b) Assume that a DU failure has been found in one of the proof tests. What is
the probability that no demand will occur while this DU failure is present?
(c) How many tests will be carried out before one of the valves has a spurious
failure?
(d) What is the probability that exactly one spurious trip failure is experienced
for the two valves in a period of 50 years?
(e) What is the probability that one or more spurious trips have been experienced
for the two valves in the 50 years period?

Figure 12.1: Markov model considering spurious trips

64
Problem 4. Using Markov to calculate STR

Calculate the STR for the Markov transition diagram shown in Figure 12.1.
Use input data from table 7.2 in the textbook for the ones not given in problem 1.

65
Chapter 13

Uncertainty Assessment

Nothing yet.