Operating Procedures
Operating Procedures
Operating Procedures
Now that the PHA’s Are
Competed or Underway…
Operating Procedures
& Safety Programs
Must Be Developed
Describe Shut-down
SOP’s
Operating Procedures
Company Must Have a Method for Developing
Procedures With Elements Such As:
SOP Preparation
SOP Review and Approval
Frequency of Revisions and Reviews
Checklists
Document Control
SOP Document Tracking and Archival
Standardized Format
Operating Procedures - Start
Up…We Must
Include Sections such as:
Objectives
Purpose
Concerns
Procedures
Department
Operator
Equipment Involved
Location
Related Documents
Operating Procedures
Let’s Look at an Example
Operating Procedure for NASA E-Complex
1.0 INTRODUCTION
1.1 PURPOSE
The purpose of this procedure is to establish a step-by-step detailed method for assuring
a safe transfer of liquid hydrogen at the E-1 facility low pressure liquid hydrogen
transfer and storage system by purging/inerting and transfer of liquid hydrogen from
trucks at the trailer transfer stations to the liquid hydrogen storage sphere.
1.2 SCOPE
This procedure contains only those instructions pertaining directly with control of the
systems configuration to perform necessary purging/inerting of the system to assure
elimination of oxygen and the transfer of liquid hydrogen. The LH2 will be transferred
from trailers to the liquid hydrogen (LH2) storage sphere. The procedure contains
instruction for
a. Facility Status/Set Up
b. Pre-transfer Purging/Inerting
c. Liquid Hydrogen Transfer
d. Facility Securing/Shutdown
1.0 REFERENCES
2.1 DOCUMENTS
SSP-8715-0001 John C. Stennis Space Center Safety and Health Handbook
2.2 DRAWINGS
PSK-E1-1001-FAC, Sheet 1 – LH Trailer Unloading Storage and Transfer Piping
and Instrument Diagram
PSK-E1-9001-FAC, Sheet 9 – E1 LH2 Storage Area MFP
3.0 RESPONSIBILITIES
3.1 Personnel
The Test Stand Director shall be responsible for the operations as outlined in
the procedure and personnel requirements. Personnel must either be certified
per the requirements or be approved as trainees. The number of Test
Operations personnel required to perform the operating tasks and functions set
forth in this procedure is three. The test team shall comprise of the test
conductor, two LH2 Storage Area Valve Operators and an LH2 Trailer crew.
Any change in the number of personnel must be approved by the Test Stand
Director or supervisor.
The assigned personnel performing this DOP shall buy off each Step upon
completion on the buy off sheet.
3.2 Safety
4.1.1 Personnel not directly involved with the transfer operation shall be
cleared back from the transfer/storage area during offloading operations.
4.1.2 Hot work activity (i.e., welding, cutting, usage of spark producing
equipment, smoking, etc.) shall not be permitted within 100 feet of the
transfer system/operation.
6.1 Verify Flex Hoses are secured in holders with caps installed.
6.2 Verify Site GN2 at LH2 Storage Area Panel pressure is > 2,000
psig using PI-10H41-GN.
6.3 Verify Site GHE at LH2 Storage Area Panel pressure is > 1,800
psig using PI-10H39-HE.
6.4 Verify Site GH2 at LH2 Storage Area Panel pressure is > 1,500
psig using PI-10H42-GH.
7.1.4 Verify LH2 Storage Area Deluge Water Isolation Valve VA-
10G32-DW is Open on East Side of Sphere.
7.1.7 Request the Truck Driver to disconnect the liquid transfer flex
hose from the holder and connect to the trailer at Trailer Unloading Station
No. 1. Maintain clean to Level 2. MIP
Operating Procedures
and
Graphic Illustrations
Operating Procedures
Refinery Operation Flow Chart
Operating Procedures
Must be Developed for Each Equipment
Operation in the Covered Process
Operating Limits
Operating Limits Must
be Understood
Pressures
Flows
Electrical Potential
Tolerances
Operating Procedures