Structure Monthly Report May 2023

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 13

Project Construction Works of KESSA GEMJABET AZENA AMBELLA ROAD PROJECT

Federal Democratic Republic of Ethiopia


Employer
Ethiopian Roads Administration (ERA)

Consultant Niche Infrastucture Consulting with HUB Engineering

Contractor China Civil Engineering Construction Corporation (CCECC)

Description Summary of all Major, Minor & Drainage's Structure

Date 26-Apr-23 - 25-May-23

Total Aproved Shop Total Construction


Total Qty Drawing As of Completed As of
Accomplishment
No. Description unit in the Remain Remark
in Percentage(%)
project

25/May/23 25/May/23

Bridge No 5 142 142.00 0%


1

Slab culvert No 25 25 25 0%
2

pipe culvert No 3 3 2.00 1 67%


3

Retaining wall Km 3500 2.5 #REF! #REF! #REF!


4

Prepared by: Fiseha Shimeles ( Consultant IQS) Checked by:________________________

Date:________________________________ Date:______________________________

Signature:____________________________ Signature:__________________________
Project Construction Works of Jinka-Hana Road Design and Build Project
Contract I Jinka-Mendir 49.56km + Jinka Town Section 3.2 Km
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Authority (ERA)
Consultant Highway Engineers And Consultants /HEC/ PLC
Contractor Ethiopian Construction Works Corporation
Description Ditch With cover and Curb Stone Status Report For Payment
Station Office Date Err:509 - 25/May/21

Ditch Cover Median Edge


Excavatio
Location of Ditch Masonry (Pedestrian and Curb Curb Total
n
Vehicular) Stone Stone Linear Total Length
Construction
No executed in Grading Remark
Status
Linear 0.130116 0.461896 0.136234 0.136234 0.135518 1.000000 length Section (km)
From To Meter in Side
km 13.01 46.19 13.62 13.62 13.55 100.00
0+00 ~ 3+00
1 0+040 3+000 2.96 RHS 13.01 46.19 - 12.26 12.20 83.66 2.48 Onprogress
4.95 Km
2 0+040 3+000 2.96 LHS 13.01 46.19 - 12.26 12.20 83.66 2.48 Onprogress
3+00 ~ 6+00
3 3+000 3+860 0.86 RHS 13.01 46.19 - 12.26 12.20 83.66 0.72 Onprogress
1.44 Km
4 3+000 3+860 0.86 LHS 13.01 46.19 - 12.26 12.20 83.66 0.72 Onprogress
6+00 ~ 9+00
0.00 0.00 Km
9+00 ~ 12+00
0.00 0.00 Km
12+00 ~ 15+00
5 14+110 15+100 0.99 RHS 13.01 46.19 - 12.26 12.20 83.66 0.83 Onprogress
1.66 Km
6 14+110 15+100 0.99 LHS 13.01 46.19 - 12.26 12.20 83.66 0.83 Onprogress
15+00 ~ 18+00
7 15+100 15+275 0.18 RHS 13.01 46.19 - 12.26 12.20 83.66 0.15 Onprogress
8 15+275 15+470 0.20 RHS 13.01 46.19 - - - 59.20 0.12 Onprogress
9 15+470 15+540 0.07 RHS 13.01 46.19 - 12.26 - 71.46 0.05 Onprogress
10 15+540 15+590 0.05 RHS 13.01 46.19 - 12.26 - 71.46 0.04 Onprogress
11 15+720 15+910 0.19 RHS 13.01 46.19 - 12.26 - 71.46 0.14 Onprogress
12 15+910 15+975 0.07 RHS 13.01 46.19 - 12.26 12.20 83.66 0.05 Onprogress
13 15+985 16+030 0.05 RHS 13.01 27.71 - 12.26 - 52.99 0.02 Onprogress
14 16+040 16+225 0.19 RHS 13.01 46.19 - 12.26 12.20 83.66 0.15 Onprogress
15 16+225 16+300 0.08 RHS 13.01 46.19 - 12.26 12.20 83.66 0.06 Onprogress
16 16+300 16+910 0.61 RHS 13.01 46.19 - 12.26 10.84 82.30 0.50 3.05 Km Onprogress
17 16+910 17+180 0.27 RHS 9.11 32.33 - 12.26 - 53.70 0.14 Onprogress

18 15+100 15+275 0.18 LHS 13.01 46.19 - 12.26 12.20 83.66 0.15 Onprogress
19 15+275 15+425 0.15 LHS 13.01 46.19 - 12.26 - 71.46 0.11 Onprogress
20 15+425 15+620 0.20 LHS 13.01 46.19 - 12.26 12.20 83.66 0.16 Onprogress
21 15+720 15+940 0.22 LHS 13.01 46.19 - 12.26 12.20 83.66 0.18 Onprogress
22 15+940 16+400 0.46 LHS 13.01 46.19 - 12.26 12.20 83.66 0.38 Onprogress
23 16+400 17+070 0.67 LHS 13.01 46.19 - 9.54 9.49 78.22 0.52 Onprogress
24 17+070 17+270 0.20 LHS 13.01 32.33 - 9.54 - 54.88 0.11 Onprogress

Prepared By: Binyam Geremew


Date: 25,May,2021
Signature:______________
18+00 ~ 21+00
Total Length in km 11.09 Km

Prepared By: Binyam Geremew


Date: 25,May,2021
Signature:______________
Variation Order (Jinka Town Ditch)
Ditch Cover Median Edge
Excavatio
No Masonry (Pedestrian and Curb Curb Total
n
Vehicular) Stone Stone
Linear Total Length
Construction
Side 0.130116 0.461896 0.136234 0.136234 0.135518 1.000000 executed in Grading Remark
Linear Status
length Section (km)
From To Meter in
km 13.01 46.19 13.62 13.62 13.55 100.00

0+00 ~ 1+00
01 0+240 0+740 0.50 RHS 13.01 46.19 - 12.26 12.20 83.66 0.418 Onprogress
02 0+240 0+740 0.50 LHS - - - 12.26 - 12.26 0.061 0.48 Km Onprogress

1+00 ~ 2+00
03 1+280 1+460 0.18 RHS 13.01 46.19 - - - 59.20 0.11 Onprogress
04 1+460 1+590 0.13 RHS 13.01 46.19 - - - 59.20 0.08 Onprogress
0.32 Km
05 1+590 1+780 0.19 RHS 13.01 23.09 - - - 36.11 0.07 Onprogress
06 1+880 2+000 0.12 RHS 13.01 46.19 - - - 59.20 0.07 Onprogress

2+000 - 3+000
07 2+000 2+205 0.21 RHS 13.01 46.19 - 12.26 - 71.46 0.15 Onprogress
08 2+800 2+880 0.08 RHS 13.01 46.19 - - - 59.20 0.05 Onprogress
09 2+780 2+870 0.09 LHS 13.01 46.19 - - - 59.20 0.05 0.32 Km Onprogress
10 2+900 2+960 0.06 RHS 13.01 46.19 - - - 59.20 0.04 Onprogress
11 2+895 2+960 0.07 LHS 13.01 46.19 - - - 59.20 0.04 Onprogress

Total Length in km 1.12 Km

Prepared By: Binyam Geremew


Date: 25,May,2021
Signature:______________
Project Construction Works of Jinka-Hana Road Design and Build Project
Contract I Jinka-Mendir 49.56km + Jinka Town Section 3.2 Km
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Authority (ERA)
Consultant Highway Engineers And Consultants /HEC/ PLC
Contractor Ethiopian Construction Works Corporation
Description U-Ditch Status Report For Payment
Station Office Date Err:509 - 25/May/21
Excavatio
Location of Ditch Bedding Masonry Pointing Total Linear Total Length in
n Constructio
No executed Grading Section Remark
Linear n Status
From To Side 20 10 60 10 100 length (km)
Meter in km
01 7+000 7+500 0.50 LHS 20.00 10.00 60.00 10.00 100.00 0.50 Complete
02 7+000 7+500 0.50 RHS 20.00 10.00 60.00 10.00 100.00 0.50 Complete
3.00 Km
03 8+200 9+200 1.00 LHS 20.00 10.00 60.00 10.00 100.00 1.00 Complete
04 8+200 9+200 1.00 RHS 20.00 10.00 60.00 10.00 100.00 1.00 Complete
9+00 ~ 12+00 None
05 26+120 26+180 0.06 RHS 20.00 10.00 60.00 10.00 100.00 0.06 Complete
06 26+180 26+230 0.05 RHS 20.00 10.00 60.00 10.00 100.00 0.05 Complete
07 26+230 26+285 0.06 RHS 20.00 10.00 60.00 10.00 100.00 0.06 Complete
08 26+285 26+330 0.05 RHS 20.00 10.00 60.00 10.00 100.00 0.05 Complete
09 26+330 26+400 0.07 RHS 20.00 10.00 54.00 9.00 93.00 0.07 Onprogress
10 26+120 26+200 0.08 LHS 20.00 10.00 60.00 10.00 100.00 0.08 Complete
11 26+200 26+300 0.10 LHS 20.00 10.00 60.00 10.00 100.00 0.10 Complete
12 26+380 26+480 0.10 LHS 20.00 10.00 60.00 10.00 100.00 0.10 Complete
13 26+480 26+560 0.08 LHS 20.00 10.00 60.00 10.00 100.00 0.08 1.10 Km Complete
14 26+300 26+340 0.04 LHS 20.00 10.00 60.00 10.00 100.00 0.04 Complete
15 26+380 26+480 0.10 RHS 20.00 10.00 60.00 10.00 100.00 0.10 Complete
16 26+480 26+560 0.08 RHS 20.00 10.00 60.00 10.00 100.00 0.08 Complete
17 26+340 26+380 0.04 LHS 20.00 10.00 60.00 10.00 100.00 0.04 Complete
18 26+615 26+685 0.07 RHS 20.00 10.00 60.00 10.00 100.00 0.07 Complete
19 26+615 26+685 0.07 LHS 20.00 10.00 60.00 10.00 100.00 0.07 Complete
20 26+685 26+725 0.04 RHS 20.00 10.00 45.00 7.50 82.50 0.03 Onprogress
21 26+685 26+725 0.04 LHS 20.00 10.00 45.00 7.50 82.50 0.03 Onprogress
27+00 ~ 30+00
22 27+175 27+225 0.05 RHS 20.00 10.00 60.00 10.00 100.00 0.05 Complete
23 26+970 27+115 0.15 RHS 20.00 10.00 60.00 10.00 100.00 0.15 Complete
24 27+115 27+175 0.06 RHS 20.00 10.00 60.00 10.00 100.00 0.06 Complete
25 26+695 26+945 0.25 LHS 20.00 10.00 36.00 6.00 72.00 0.18 Onprogress
26 26+980 27+040 0.06 LHS 20.00 10.00 60.00 10.00 100.00 0.06 Complete
27 27+110 27+190 0.08 LHS 20.00 20.00 60.00 10.00 100.00 0.08 Complete
28 27+265 27+320 0.06 RHS 20.00 10.00 57.00 9.50 96.50 0.05 Onprogress
29 27+265 27+320 0.06 LHS 20.00 10.00 57.00 9.50 96.50 0.05 Onprogress
30 27+420 27+860 0.44 RHS 20.00 10.00 60.00 10.00 100.00 0.44 Complete Ahead
31 27+420 27+650 0.23 LHS 20.00 10.00 60.00 10.00 100.00 0.23 Complete Back

Prepared By: Binyam Geremew


Date: 25,May,2021
Signature:______________ 2.96 Km
32 27+340 27+380 0.04 LHS 20.00 10.00 60.00 10.00 100.00 0.04 Complete
33 27+380 27+480 0.10 LHS 20.00 10.00 60.00 10.00 100.00 0.10 Complete Ahead
2.96 Km

Prepared By: Binyam Geremew


Date: 25,May,2021
Signature:______________
34 27+315 27+480 0.17 RHS 20.00 10.00 60.00 10.00 100.00 0.17 2.96 Km Complete Ahead
35 27+480 27+520 0.04 RHS 20.00 10.00 60.00 10.00 100.00 0.04 Complete
36 27+315 27+440 0.13 RHS 20.00 10.00 60.00 10.00 100.00 0.13 Complete Back
37 27+520 27+540 0.02 LHS 20.00 10.00 60.00 10.00 100.00 0.02 Complete Ahead
38 27+560 27+600 0.04 RHS 20.00 10.00 60.00 10.00 100.00 0.04 Complete Ahead
39 27+600 27+653 0.05 RHS 20.00 10.00 60.00 10.00 100.00 0.05 Complete Ahead
40 27+580 27+880 0.30 LHS 20.00 10.00 60.00 10.00 100.00 0.30 Complete
41 27+880 28+100 0.22 LHS 20.00 10.00 60.00 10.00 100.00 0.22 Complete
42 27+900 28+000 0.10 RHS 20.00 10.00 60.00 10.00 100.00 0.10 Complete
43 28+010 28+180 0.17 RHS 20.00 10.00 60.00 10.00 100.00 0.17 Complete
44 28+000 28+100 0.10 LHS 20.00 10.00 60.00 10.00 100.00 0.10 Complete
45 28+100 28+150 0.05 LHS 20.00 10.00 60.00 10.00 100.00 0.05 Complete
46 28+150 28+240 0.09 LHS 20.00 10.00 60.00 10.00 100.00 0.09 Complete
30+00 ~ 33+00
47 31+710 31+790 0.08 LHS 20.00 10.00 60.00 10.00 100.00 0.08 Complete
48 31+790 31+940 0.15 LHS 20.00 10.00 60.00 10.00 100.00 0.15 Complete
49 31+940 32+000 0.06 LHS 20.00 10.00 60.00 10.00 100.00 0.06 Complete
50 31+710 31+790 0.08 RHS 20.00 10.00 60.00 10.00 100.00 0.08 Complete
51 31+790 31+940 0.15 RHS 20.00 10.00 60.00 10.00 100.00 0.15 Complete
52 31+940 32+055 0.12 RHS 20.00 10.00 60.00 10.00 100.00 0.12 1.38 Km Complete
53 32+055 32+250 0.20 RHS 20.00 10.00 60.00 10.00 100.00 0.20 Complete
54 32+250 32+400 0.15 RHS 20.00 10.00 60.00 10.00 100.00 0.15 Complete
55 32+080 32+280 0.20 LHS 20.00 10.00 60.00 10.00 100.00 0.20 Complete
56 32+280 32+400 0.12 LHS 20.00 10.00 60.00 10.00 100.00 0.12 Complete
57 32+000 32+080 0.08 LHS 20.00 10.00 60.00 10.00 100.00 0.08 Complete
33+00 ~ 36+00
39+00 ~ 42+00
58 39+740 39+860 0.12 LHS 20.00 10.00 40.38 - 70.38 0.08 Onprogress
59 39+880 39+960 0.08 LHS 20.00 10.00 60.00 5.00 95.00 0.08 Onprogress
60 39+960 40+025 0.07 LHS 20.00 10.00 60.00 5.00 95.00 0.06 0.37 Km Onprogress
61 39+760 39+880 0.12 RHS 20.00 10.00 18.00 - 48.00 0.06 Onprogress
62 39+880 40+020 0.14 RHS 20.00 10.00 34.20 - 64.20 0.09 Onprogress
42+00 ~ 45+00
Total Length in km 8.81 Km

Prepared By: Binyam Geremew


Date: 25,May,2021
Signature:______________
Project Construction Works of KESSA GEMJABET AZENA AMBELLA ROAD PROJECT
Contract I Kessa Gimjabet Azena Ambella Road Project
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Administration (ERA)
Consultant Niche Infrastucture Consulting with HUB Engineering
Contractor China Civil Engineering Construction Corporation (CCECC)
Description Pipe Cuvert Status Report For Payment
Station Office Date 26/Apr/23 - 25/May/23
Location of Productio Installatio
No Excavation Bedding Masonry Waterway Pointing Backfill Total Constructi
Pipe culvert n n Remark
on Status
Percentage 50% 10% 2.2.5% 15% 5% 5% 2.2.5% 10% 95%
1 0+000 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Not Started
2 0+005 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Not Started
3 0+443 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% Not Started
4 0+701 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
5 1+048 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
6 1+383 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
7 1+485 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
8 1+593 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
9 1+737 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
10 1+880 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
Onprogres
11 3+280 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 5.0% 95.0% RHS backfill filled by false fill
s
Onprogres
11 3+940 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 5.0% 95.0% RHS backfill filled by false fill
s
Onprogres
11 4+178 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 0.0% 90.0% FW backfill filled by false fill
s
12 4+290 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
13 4+432 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
14 4+666 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
15 6+397 0.0% % 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
16 8+993 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
17 9+943 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
18 10+535 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
19 11+676 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
20 13+283 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
21 12+790 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
22 13+283 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
23 13+641 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
24 14+029 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
25 14+283 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
26 14+700 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
27 15+191 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
28 16+150 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
29 18+263 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
30 19+870 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
31 20+376 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
32 22+136 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
33 23+940 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
34 24+184 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
35 26+610 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
36 27+005 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
37 27+835 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
Prepared By: Zerihun Mulugeta (Int. Structural Engineer) and Eleni H/Micheal (Structural Inspector )
09/09/2023
Signature:______________
Project Construction Works of KESSA GEMJABET AZENA AMBELLA ROAD PROJECT
Contract I Kessa Gimjabet Azena Ambella Road Project
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Administration (ERA)
Consultant Niche Infrastucture Consulting with HUB Engineering
Contractor China Civil Engineering Construction Corporation (CCECC)
Description Pipe Cuvert Status Report For Payment
Station Office Date 26/Apr/23 - 25/May/23
Location of Productio Installatio
No Excavation Bedding Masonry Waterway Pointing Backfill Total Constructi
Pipe culvert n n Remark
on Status
Percentage 50% 10% 2.2.5% 15% 5% 5% 2.2.5% 10% 95%
38 28+924 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
39 29+424 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
40 35+390 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
41 35+786 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
42 36+061 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
43 36+888 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
44 37+167 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
Onprogres
45 37+442 50.0% 10.0% 2.5% 15.0% 0.0% 0.0% 0.0% 0.0% 77.5%
s
Onprogres
46 37+774 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 0.0% 90.0%
s
47 38+276 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 10.0% 100.0% Complete
48 40+595 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
49 40+835 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
50 42+003 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
51 42+318 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
52 43+904 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
53 44+739 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
54 45+747 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
55 46+071 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
56 46+536 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
57 46+790 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
58 47+082 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
59 49+636 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
60 49+636 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
61 50+730 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
62 51+827 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
63 52+248 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
64 52+327 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
65 52+723 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
66 53+252 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
67 53+447 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
68 53+990 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
69 54+703 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
70 55+897 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
71 56+120 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
72 57+659 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
73 58+070 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
74 58+220 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
75 58+859 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
76 58+939 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
Prepared By: Zerihun Mulugeta (Int. Structural Engineer) and Eleni H/Micheal (Structural Inspector )
09/09/2023
Signature:______________
Project Construction Works of KESSA GEMJABET AZENA AMBELLA ROAD PROJECT
Contract I Kessa Gimjabet Azena Ambella Road Project
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Administration (ERA)
Consultant Niche Infrastucture Consulting with HUB Engineering
Contractor China Civil Engineering Construction Corporation (CCECC)
Description Pipe Cuvert Status Report For Payment
Station Office Date 26/Apr/23 - 25/May/23
Location of Productio Installatio
No Excavation Bedding Masonry Waterway Pointing Backfill Total Constructi
Pipe culvert n n Remark
on Status
Percentage 50% 10% 2.2.5% 15% 5% 5% 2.2.5% 10% 95%
77 59+148 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
78 59+416 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
79 59+505 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
80 59+689 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
Spur Azena (Ayehu)
81 0+605 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
82 0+976 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
83 2+212 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
84 4+152 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
85 4+810 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
86 5+308 Not Started
Spur Road (Access to Lake Terba)
Onprogres
87 00+167 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 0.0% 90.0%
s
Onprogres
88 00+651 50.0% 10.0% 2.5% 15.0% 5.0% 5.0% 2.5% 0.0% 90.0%
s
Onprogres
89 01+545 50.0% 10.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 60.0%
s
Total 11% 2% 1% 3% 1% 1% 2% 21%
Total Number of Completed 23.00
Total Number of Onprogress 8.00
Total Number of Not Started 60.00

Prepared By: Zerihun Mulugeta (Int. Structural Engineer) and Eleni H/Micheal (Structural Inspector )
09/09/2023
Signature:______________
Project Construction Works of KESSA GEMJABET AZENA AMBELLA ROAD PROJECT
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Administration (ERA)
Consultant Niche Infrastucture Consulting with HUB Engineering
Contractor China Civil Engineering Construction Corporation (CCECC)
Description Slab Cuvert Status Report For Payment
Station Office Date 26/Apr/23 - 25/May/23
Location of Excavatio Class C Deck slab
No Masonry Formwork Waterway Backfill Total Constructio
Slab Culvert n concrete casting Remark
n Status
Weightage 10.00% 5.00% 30.00% 2.00% 40.00% 3.00% 10.00% 100.00%
1 1+048 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
2 6+397 10.0% 5.0% 30.0% 2.0% 40.0% 3.0% 10.0% 100.0% Complete
3 7+130 10.0% 5.0% 30.0% 2.0% 35.0% 3.0% 8.0% 93.0% Onprogress
4 9+528 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
5 10+012 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
6 10+483 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
7 12+789 10.0% 5.0% 30.0% 2.0% 40.0% 3.0% 10.0% 100.0% Complete
8 17+683 10.0% 5.0% 30.0% 2.0% 40.0% 3.0% 10.0% 100.0% Complete
9 26+974 10.0% 5.0% 30.0% 2.0% 40.0% 3.0% 10.0% 100.0% Complete
10 38+071 10.0% 5.0% 30.0% 2.0% 0.0% 3.0% 0.0% 50.0% Onprogress
11 38+759 10.0% 5.0% 30.0% 2.0% 0.0% 3.0% 0.0% 50.0% Onprogress
12 38+980 10.0% 5.0% 30.0% 2.0% 0.0% 3.0% 10.0% 60.0% Onprogress
13 39+218 10.0% 5.0% 30.0% 2.0% 40.0% 3.0% 10.0% 100.0% Complete
14 41+229 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
15 46+332 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
16 48+931 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
17 49+917 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
18 55+249 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
19 58+589 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
Total 0.90 0.45 270% 0.18 2.35 0.27 0.68 7.53
Total Nomber of Completed 5
Total Nomber of Onprogress 4
Total Nomber of Not Started 10

Prepared By: Zerihun Mulugeta (Int. Structural Engineer) and Eleni H/Micheal (Structural Inspector )
09/09/2023
Signature:______________
Project Construction Works of KESSA GEMJABET AZENA AMBELLA ROAD PROJECT
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Administration (ERA)
Consultant Niche Infrastucture Consulting with HUB Engineering
Contractor China Civil Engineering Construction Corporation (CCECC)
Description Bridge Status Report For Payment
Station Office Date 26/Apr/23 - 25/May/23

Masonry
Location Class A Girder slab Construction
No Excavation Rock fill Handlaid Formwork Railing Backfill Total Remark
of Bridge concrete casting Status
Abutement Wing wall RepRap

Weightage 5% 10% 5% 30% 5% 4% 1% 2% 30% 2% 5% 99%

1 3+864 5% 10% 5% 30% 5% 5% 1% 0% 0% 0% 0% 61% Onprogress

2 8+726 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% Not Started

3 24+980 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% Not Started


26+340 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
4 Not Started

5 39+107 5% 10% 5% 30% 5% 4% 1% 0% 0% 0% 0% 60% Onprogress

6 47+615 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% Not Started

Spur Road (Access to Lake Terba)


0+868 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
1 Not Started

Total Nomber of Completed 0

Total Nomber of Onprogress 2

Total Nomber of Not Started 5

Prepared By: Zerihun Mulugeta (Int. Structural Engineer) and Eleni H/Micheal (Structural Inspector )
09/09/2023 13
Signature:______________
Project Construction Works of Jinka-Hana Road Design and Build Project
Contract I Jinka-Mendir 49.56km + Jinka Town Section 3.2 Km
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Authority (ERA)
Consultant Highway Engineers And Consultants /HEC/ PLC
Contractor Ethiopian Construction Works Corporation
Description Retaining Wall Status Report For Payment
Station Office Date 26/Apr/23 - 25/May/21
Excavati Class A
Location of Ditch Bedding Masonry Pointing Total
on concrete Linear
Constructio
No Linear executed Remark
n Status
From To Meter in Side 20% 10% 25% 35% 10% 100% length
M

1 35+600 35+660 60.00 RHS 0% 0% 0% 0% 0% 0% 0.00 Not Started

2 36+869 36+890 21.00 RHS 20% 10% 25% 35% 0% 90% 0.19 Onprogress

3 42+000 42+040 40.00 RHS 0% 0% 0% 0% 0% 0% 0.00 Not Started

4 0% 0.00

4 0% 0.00

5 0% 0.00

6 0% 0.00
Total Length in km 0.19 Km 189.00 m
Total Nomber of Completed 0
Total Nomber of Onprogress 1
Total Nomber of Not Started 2
NB: RWWP = Retaining Wall With Pipe

Prepared By: Zerihun Mulugeta (Int. Structural Engineer) and Eleni H/Micheal (Structural Inspector )
09/09/2023
Signature:______________