Structure Monthly Report May 2023
Structure Monthly Report May 2023
Structure Monthly Report May 2023
25/May/23 25/May/23
Slab culvert No 25 25 25 0%
2
Date:________________________________ Date:______________________________
Signature:____________________________ Signature:__________________________
Project Construction Works of Jinka-Hana Road Design and Build Project
Contract I Jinka-Mendir 49.56km + Jinka Town Section 3.2 Km
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Authority (ERA)
Consultant Highway Engineers And Consultants /HEC/ PLC
Contractor Ethiopian Construction Works Corporation
Description Ditch With cover and Curb Stone Status Report For Payment
Station Office Date Err:509 - 25/May/21
18 15+100 15+275 0.18 LHS 13.01 46.19 - 12.26 12.20 83.66 0.15 Onprogress
19 15+275 15+425 0.15 LHS 13.01 46.19 - 12.26 - 71.46 0.11 Onprogress
20 15+425 15+620 0.20 LHS 13.01 46.19 - 12.26 12.20 83.66 0.16 Onprogress
21 15+720 15+940 0.22 LHS 13.01 46.19 - 12.26 12.20 83.66 0.18 Onprogress
22 15+940 16+400 0.46 LHS 13.01 46.19 - 12.26 12.20 83.66 0.38 Onprogress
23 16+400 17+070 0.67 LHS 13.01 46.19 - 9.54 9.49 78.22 0.52 Onprogress
24 17+070 17+270 0.20 LHS 13.01 32.33 - 9.54 - 54.88 0.11 Onprogress
0+00 ~ 1+00
01 0+240 0+740 0.50 RHS 13.01 46.19 - 12.26 12.20 83.66 0.418 Onprogress
02 0+240 0+740 0.50 LHS - - - 12.26 - 12.26 0.061 0.48 Km Onprogress
1+00 ~ 2+00
03 1+280 1+460 0.18 RHS 13.01 46.19 - - - 59.20 0.11 Onprogress
04 1+460 1+590 0.13 RHS 13.01 46.19 - - - 59.20 0.08 Onprogress
0.32 Km
05 1+590 1+780 0.19 RHS 13.01 23.09 - - - 36.11 0.07 Onprogress
06 1+880 2+000 0.12 RHS 13.01 46.19 - - - 59.20 0.07 Onprogress
2+000 - 3+000
07 2+000 2+205 0.21 RHS 13.01 46.19 - 12.26 - 71.46 0.15 Onprogress
08 2+800 2+880 0.08 RHS 13.01 46.19 - - - 59.20 0.05 Onprogress
09 2+780 2+870 0.09 LHS 13.01 46.19 - - - 59.20 0.05 0.32 Km Onprogress
10 2+900 2+960 0.06 RHS 13.01 46.19 - - - 59.20 0.04 Onprogress
11 2+895 2+960 0.07 LHS 13.01 46.19 - - - 59.20 0.04 Onprogress
Prepared By: Zerihun Mulugeta (Int. Structural Engineer) and Eleni H/Micheal (Structural Inspector )
09/09/2023
Signature:______________
Project Construction Works of KESSA GEMJABET AZENA AMBELLA ROAD PROJECT
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Administration (ERA)
Consultant Niche Infrastucture Consulting with HUB Engineering
Contractor China Civil Engineering Construction Corporation (CCECC)
Description Slab Cuvert Status Report For Payment
Station Office Date 26/Apr/23 - 25/May/23
Location of Excavatio Class C Deck slab
No Masonry Formwork Waterway Backfill Total Constructio
Slab Culvert n concrete casting Remark
n Status
Weightage 10.00% 5.00% 30.00% 2.00% 40.00% 3.00% 10.00% 100.00%
1 1+048 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
2 6+397 10.0% 5.0% 30.0% 2.0% 40.0% 3.0% 10.0% 100.0% Complete
3 7+130 10.0% 5.0% 30.0% 2.0% 35.0% 3.0% 8.0% 93.0% Onprogress
4 9+528 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
5 10+012 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
6 10+483 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
7 12+789 10.0% 5.0% 30.0% 2.0% 40.0% 3.0% 10.0% 100.0% Complete
8 17+683 10.0% 5.0% 30.0% 2.0% 40.0% 3.0% 10.0% 100.0% Complete
9 26+974 10.0% 5.0% 30.0% 2.0% 40.0% 3.0% 10.0% 100.0% Complete
10 38+071 10.0% 5.0% 30.0% 2.0% 0.0% 3.0% 0.0% 50.0% Onprogress
11 38+759 10.0% 5.0% 30.0% 2.0% 0.0% 3.0% 0.0% 50.0% Onprogress
12 38+980 10.0% 5.0% 30.0% 2.0% 0.0% 3.0% 10.0% 60.0% Onprogress
13 39+218 10.0% 5.0% 30.0% 2.0% 40.0% 3.0% 10.0% 100.0% Complete
14 41+229 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
15 46+332 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
16 48+931 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
17 49+917 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
18 55+249 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
19 58+589 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Not Started
Total 0.90 0.45 270% 0.18 2.35 0.27 0.68 7.53
Total Nomber of Completed 5
Total Nomber of Onprogress 4
Total Nomber of Not Started 10
Prepared By: Zerihun Mulugeta (Int. Structural Engineer) and Eleni H/Micheal (Structural Inspector )
09/09/2023
Signature:______________
Project Construction Works of KESSA GEMJABET AZENA AMBELLA ROAD PROJECT
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Administration (ERA)
Consultant Niche Infrastucture Consulting with HUB Engineering
Contractor China Civil Engineering Construction Corporation (CCECC)
Description Bridge Status Report For Payment
Station Office Date 26/Apr/23 - 25/May/23
Masonry
Location Class A Girder slab Construction
No Excavation Rock fill Handlaid Formwork Railing Backfill Total Remark
of Bridge concrete casting Status
Abutement Wing wall RepRap
Prepared By: Zerihun Mulugeta (Int. Structural Engineer) and Eleni H/Micheal (Structural Inspector )
09/09/2023 13
Signature:______________
Project Construction Works of Jinka-Hana Road Design and Build Project
Contract I Jinka-Mendir 49.56km + Jinka Town Section 3.2 Km
Federal Democratic Republic of Ethiopia
Employer
Ethiopian Roads Authority (ERA)
Consultant Highway Engineers And Consultants /HEC/ PLC
Contractor Ethiopian Construction Works Corporation
Description Retaining Wall Status Report For Payment
Station Office Date 26/Apr/23 - 25/May/21
Excavati Class A
Location of Ditch Bedding Masonry Pointing Total
on concrete Linear
Constructio
No Linear executed Remark
n Status
From To Meter in Side 20% 10% 25% 35% 10% 100% length
M
2 36+869 36+890 21.00 RHS 20% 10% 25% 35% 0% 90% 0.19 Onprogress
4 0% 0.00
4 0% 0.00
5 0% 0.00
6 0% 0.00
Total Length in km 0.19 Km 189.00 m
Total Nomber of Completed 0
Total Nomber of Onprogress 1
Total Nomber of Not Started 2
NB: RWWP = Retaining Wall With Pipe
Prepared By: Zerihun Mulugeta (Int. Structural Engineer) and Eleni H/Micheal (Structural Inspector )
09/09/2023
Signature:______________