HSP Daily Dashboard 20230809

The document provides a daily construction progress dashboard for a tennis ball manufacturing plant, including planned and actual accomplishments across various areas like concrete work, rebar installation, and steel fabrication. Metrics such as completion percentages and weather conditions are included. The dashboard outlines the plan for the current day across different areas and responsible managers.

Uploaded by

Noli Benongo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
136 views1 page

HSP Daily Dashboard 20230809

The document provides a daily construction progress dashboard for a tennis ball manufacturing plant, including planned and actual accomplishments across various areas like concrete work, rebar installation, and steel fabrication. Metrics such as completion percentages and weather conditions are included. The dashboard outlines the plan for the current day across different areas and responsible managers.

Uploaded by

Noli Benongo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

REPORT DATE: 2023 AUGUST 09 - WEDNESDAY

MANPOWER MANPOWER
HEAD SPORT PHILIPPINES TENNIS BALL MANUFACTURING PLANT MILESTONES WEATHER
CONDITION
DAILY CONSTRUCTION PROGRESS DASHBOARD AREAS PLAN ACTUAL STATUS
PROJECT MANAGER 1
IN
1 CONCRETE 96
IN
83
IN IN
ACCOMPLISHMENT PREVIOUS WORKDAY - 2023 AUG 08 PLAN FOR TODAY - 2023 AUG 09 Start Finish Start Finish OPERATIONS LEAD (CIVIL) 1 1 REBAR 10 9 7:00 PROJECT MANAGER 1 1 CONCRETE 96 83
Item Leader Status Activity Area Ref Activity Area Ref Main Production 12/01/22 05/31/24 12/08/22 52% OPERATIONS LEAD (MEPFS) 1 1 STEEL FAB 14 12 8:00 OPERATIONS LEAD (CIVIL) 1 1 REBAR 10 9
1 C/S 61% Application of soil cement (CLSM/ Holcim Mix) Main Prod Continue Utility and Workshop 06/01/23 12/15/23 06/01/23 9% SITE ENGINEER (CIVIL) 5 5 ERECTORS 37 31 9:00 OPERATIONS LEAD (MEPFS) 1 1 STEEL FAB 14 12
2 C/S 25% Construction Equipment Foundation Main Prod Rubber Processing Continue Power Center 1 06/09/23 12/15/23 05/09/23 27% SITE ENGINEER (MPF) 2 2 ELECTRICIAN 8 7 10:00 SITE ENGINEER (CIVIL) 5 5 ERECTORS 37 31
SITE ENGINEER (ES) 2 2 WELDER 19 15
3 C/S 49% Grouting under baseplates (65 of 157) Main Prod Continue Power Center 2 06/09/23 12/15/23 05/09/23 3% 11:00 SITE ENGINEER (MPF) 2 2 ELECTRICIAN 8 7
FOREMAN 5 5 PLUMBER 23 17
4 C/S 62% Construction of footings Main Prod Toilets HOLD Solvent Storage 08/08/23 05/25/24
SURVEYOR 3 3 FIRE PRO 23 21
12:00 SITE ENGINEER (ES) 2 2 WELDER 19 15
5 C/S 94% Backfilling Warehouse HOLD Warehouse 03/06/23 05/15/24 03/16/23 48% QA/QC 1 1 GEN LABORER 114 92 13:00 FOREMAN 5 5 PLUMBER 23 17
6 C/S 97% Excavation of footings Cup Lump Storage HOLD Cup Lump Storage 09/15/23 05/16/24 05/10/23 6% NURSE 1 1 EQPT OPERATORS 44 36 14:00 SURVEYOR 3 3 FIRE PRO 23 21
7 C/S 96% Lean concrete pouring Cup Lump Storage HOLD Cooling Pond 09/15/23 05/14/24 06/09/23 5% SAFETY OFFICERS 5 4 SURVEY CREW 6 4 15:00 QA/QC 1 1 GEN LABORER 114 92
8 C/S 55% Installation of rebars/ formworks (footing) Cup Lump Storage Continue WWT Building 07/01/23 04/29/24 ENVIRONMENTAL/ PCO 1 0 HOUSEKEEPER 6 5 16:00 NURSE 1 1 EQPT OPERATORS 44 36
9 C/S 50% Concrete pouring of footing Cup Lump Storage HOLD Pump House 08/25/23 04/17/24 06/15/23 DOCUMENT CONTROLLER 1 1 WAREHOUSEMAN 1 1 17:00 SAFETY OFFICERS 5 4 SURVEY CREW 6 4
33%
CAD OPERATOR 0 0 WAREHOUSE AIDE 9 9
10 C/S 50% Excavation of footings Cooling Pond Shelter HOLD Scrap Grinding House 08/29/23 05/06/24 18:00 ENVIRONMENTAL/ PCO 1 0 HOUSEKEEPER 6 5
TIMEKEEPER 3 3
11 C/S 50% Lean concrete pouring Cooling Pond Shelter HOLD Administration Building 08/01/23 05/11/24 06/22/23 14% SUBTOTAL 32 30 410 342
19:00 DOCUMENT CONTROLLER 1 1 WAREHOUSEMAN 1 1
12 C/S 50% Installation of rebar/fw 1st lift pedestals Cooling Pond Shelter HOLD Canteen 07/12/23 05/16/24 04/14/23 15% TOTAL 442 372 20:00 CAD OPERATOR 0 0 WAREHOUSE AIDE 9 9
13 C/S 50% Concrete Pouring of 1st lift Pedestal Cooling Pond Shelter HOLD Security and Staff 07/03/23 04/16/24 21:00 TIMEKEEPER 3 3
14 C/S 30% Backfilling Cooling Pond Shelter HOLD Ext Equipment Foundations 09/15/23 05/14/24 22:00 SUBTOTAL 32 30 410 342
15 C/S 90% Backfilling Pump House HOLD Fire Protection SDP 03/03/23 01/04/24 03/16/23 12% 23:00 TOTAL 442 372
16 C/S 80% Backfilling Power Center 1 HOLD Sewer System SDP 02/08/23 12/09/23 03/16/23 48% 0:00
17 C/S 100% Excavation of catch basins (46 of 46) Drainage Main Prod CLOSED Drainage System SDP 01/03/23 11/03/23 02/16/23 14% 1:00
18 C/S 95% Construction of catch basins (44 of 46) Drainage Main Prod Continue Water Supply SDP 02/14/23 12/15/23 05/03/23 10% 2:00
19 C/S 59% Excavation/Installation of RC Pipe for storm drain line Drainage Main Prod Continue Auxiliary SDP 03/20/23 02/13/24 05/10/23 5% 3:00
20 C/S 61% Construction of catch basins (11 of 18) Drainage Warehouse Continue Electrical SDP 08/01/23 01/12/24 7/06/2023 2% `
21 C/S 65% Excavation of storm drain line Drainage Warehouse HOLD (Coord w/ AUX) Grounding SDP 07/04/23 05/19/24 03/21/23 8% SUNNY
22 C/S 26% Construction of catch basins (11 of 14) Drainage Canteen HOLD Road / Walkways/ Parking 05/13/23 05/07/24 02/17/23 29% CLOUDY
23 C/S 35% Installation of MH rebars/ formworks Sewer (SDP) South side HOLD Cistern Tank Foundation 02/14/23 12/15/23 03/16/23 70% DRIZZLE
24 C/S 15% Subgrade preparation for CLSM subbase Road S Road HOLD Fire Tank Foundation 02/14/23 12/15/23 03/16/23 70% RAINY
25 C/S 49% Concrete pouring of road/ drainage manhole Road NE Road Continue Fence/ Riprap 05/29/23 03/25/23 01/19/23 18%
26 C/S 56% Excavation and installation of pedestal Fence North Side (CYF-2) HOLD
27 C/S 57% Installation of cyclone fence Fence North Side (CYF-2) HOLD 1 18 37
28 C/S 100% Reinforce steel grill fence Fence East Side CLOSED
29 C/S 88% Excavation of strip footing Utility & Workshop HOLD (GL 15 - Balance for Access)
30 C/S 42% Application of soil cement (CLSM/ Holcim Mix) Warehouse HOLD
31 C/S 90% Formwork/Rebar Installation 1st Lift Pedestal Utility & Workshop GL E HOLD
32 C/S 30% Formwork/Rebar Installation 1st Lift Pedestal Cup Lump Storage Continue
33 C/S 27% Concrete Pouring 1st Lift Pedestal Cup Lump Storage HOLD
34 C/S 34% Construction of Perimeter Fence Fence South side (CYF-1) Continue
35 C/S 88% Lean Concrete Pouring Utility & Workshop HOLD (GL 15 - Balance for Access)
36 C/S 58% RC Pipe Installation for Storm Drainage Canteen HOLD
37 C/S 61% Installation rebars/ formworks footings Utility & Workshop GL A Continue
38 C/S 100% Concrete pouring of footing Admin Bldg CLOSED
39 C/S 12% Backfilling Utility & Workshop Continue
40 C/S 20% Construction of sump pit/ trenches Main Prod RB Continue
41 C/S 100% Concrete pouring of footing Utility & Workshop GL 1 CLOSED
42 C/S 48% Concrete pouring of footing Utility & Workshop GL A HOLD 50
48 57
43 C/S NEW Construction of Storm Drainage Line West Side
44 S/A 40% Installation of column rebars/ formworks Admin HOLD
45 S/A 98% Installation of side girts Main Prod GL A HOLD
46 S/A 100% Installation of mezzanine frame Main Prod Mezzanine 2 CLOSED
47 S/A 32% Construction of CMU wall above grade Power Center 1 Continue
48 S/A 8% Construction CMU wall above grade Main Prod Mezzanine 2 HOLD
49 S/A 68% Construction of CMU wall beam grade level Main Prod Mezzanine 2 Continue
50 S/A 83% Construction of CMU wall bond beam Main Prod Area 1 HOLD
51 S/A 42% Construction of roof beam Pump House Continue
52 S/A 83% Installation of end wall girts Main Prod GL 23 HOLD
53 S/A 50% Construction of 2nd Lift Pedestal Cooling Pond Shelter HOLD
54 S/A 35% CMU Wall Construction below grade Utility & Workshop GL E Continue
55 S/A 70% Construction CMU wall below grade Main Prod Area 3 Continue
56 S/A 18% Construction of CMU Admin Continue
57 S/A 100% Installation of main frame Warehouse GL 9 CLOSED 61 67
58 S/A 100% Installation of main frame Warehouse GL 8 CLOSED
59 S/A 100% Installation of main frame Warehouse GL 7 CLOSED QA/QC
60 S/A 50% Installation of main frame Warehouse GL 6 Continue
61 S/A 50% Installation of main frame Warehouse GL 5 Continue
INSPECTION AREA LOCATION STATUS REMARKS
62 S/A 50% Installation of main frame Warehouse GL 4 Continue No.
63 S/A 37% Installation of main frame Warehouse GL 3 Continue 1 Pre-pouring Inspection of Bond Beam Main Prod Area 1 - GL 4' / A-C' PENDING Rebar to Steel Connection
64 S/A 37% Installation of Purlins Warehouse GL 8-9 HOLD 2 Pre-pouring Inspection of Bond Beam Main Prod Area 1 - GL 4' / C'-K APPROVED
65 S/A 12% Construction of CMU wall above grade Main Prod Area 1 HOLD 3 Inspection of Rebar/Formwork (Footing) Cup Lump Continue
66 S/A 40% Installation of purlins Warehouse GL 7-8 HOLD 4 Inspection of Rebar/Formwork (Footing) Utility & Workshop GL A/7-15 Continue
67 S/A 80% Construction CMU bond beam Main Prod Area 2 Continue 5 Inspection of Rebar/Formwork 1st Lift Pedestal Cup Lump Continue
68 S/A 40% Installation of Purlins Warehouse GL 6-7 HOLD 6 Inspection of Rebar/Formwork 1st Lift Pedestal Utility & Workshop GL E Continue
69 S/A 30% Concrete pouring of columns Admin Bldg HOLD 7 Inspection of Metal Decking Main Prod Mezzanine 1 Continue
70 S/A 5% Installation of metal decking Main Prod Mezzanine 1 Continue 8 Inspection of Equipment Foundation Main Prod Rubber Processing Continue
71 S/A 3% Installation of Main Frame Warehouse GL 2 Continue 9 Inspection of Rebar/Formwork or Roof Beam Pump House Continue
72 F/W/S 74% Preparation of BI pipe Fire Pro (SDP) Continue (AUGUST 20) (20 Aug 2023) QA/QC 10 Inspection of CMU Main Prod Area 1 Continue
73 F/W/S 33% Partial Leak Test (Pre-install) Fire Pro (SDP) Continue 10 Inspection of CMU Main Prod Area 2 Continue
74 F/W/S 22% Excavation Fire Pro/Water (SDP) Continue 10 Inspection of CMU Main Prod Area 3 Continue
INSPECTION AREA LOCATION STATUS REMARKS
75 F/W/S 34% Preparation HDPE pipes Water (SDP) Continue (SEPTEMBER 10) No. 10 Inspection of CMU Power Center Continue
76 F/W/S 42% Laying of BI pipe Fire Pro South side HOLD 1 Pre-pouring Inspection of Bond Beam Main Prod Are a 1 - GL 4' / A-C' PENDING Rebar to Steel Connection 11 Pre-pouring Inspection of Bond Beam Main Prod Area 3 Continue
77 F/W/S 25% Final Leak Test (Before Backfill) Fire Pro (SDP) South side HOLD 2 Pre-pouring Inspection of Bond Beam Main Prod Are a 1 - GL 4' / C'-K APPROVED 12 Pre-pouring Inspection of Bond Beam Main Prod Area 2 Continue
78 F/W/S 50% Laying of HDPE pipe Sewer (SDP) South side HOLD (check encasement) 3 Inspection of Rebar/Formwork (Footing) Cup Lump Continue 13 Cleaning / Patching pre lifting Warehouse Continue
79 F/W/S 42% Laying of HDPE water line Water (SDP) South side Continue 4 Inspection of Rebar/Formwork (Footing) Utility & Workshop GL A/7-15 Continue 14 Weld Check Warehouse Continue
81 F/W/S 25% Laying of BI pipe Fire Pro (SDP) West side Continue 5 Inspection of Rebar/Formwork 1st Lift Pedestal Cup Lump Continue RESULT
6 Inspection of Rebar/Formwork 1st Lift Pedestal Utility & Workshop GL E Continue No. TESTING AREA STATUS REMARKS
82 F/W/S 20% Laying of HDPE line Water (SDP) West side Continue Pass Fail
7 Inspection of Metal Decking Main Prod Me zza nine 1 Continue
83 F/W/S 2% Installation of HDPE water line Water (SDP) East side Continue 1 CHB Compressive Strength - Pending - - Waiting for the Result
8 Inspection of Equipment Foundation Main Prod Rubbe r P roces sing Continue
84 E/A 45% Excavation of auxiliary line Auxiliary (SDP) HOLD
9 Inspection of Rebar/Formwork or Roof Beam Pump House Continue
85 E/A 38% Laying of PVC pipe (FDAS/ PA/ CCTV) Auxiliary (SDP) Continue 10 Inspection of CMU Main Prod Area 1 Continue
86 E/A 12% Sandfilling/ encasement Auxiliary (SDP) Continue 10 Inspection of CMU Main Prod Area 2 Continue
87 E/A 10% Installation of grounding Electrical Main Prod HOLD (Roughing Ins Completed) 10 Inspection of CMU Main Prod Area 3 Continue
88 E/A 10% Installation of grounding (rough ins) Electrical Warehouse HOLD (Roughing Ins Completed) 10 Inspection of CMU Power Center Continue
89 E/A 10% Installation of grounding (rough ins) Electrical Canteen HOLD (Roughing Ins Completed) 11 Pre-pouring Inspection of Bond Beam Main Prod Area 3 Continue
90 E/A 12% Excavation of HV/ Electrical line Electrical (SDP) Continue 12 Pre-pouring Inspection of Bond Beam Main Prod Area 2 Continue
91 E/A 3% Laying of HV/ encasement conduits Electrical (SDP) Continue 13 Cleaning / Patching pre lifting Warehouse Continue
92 E/A 5% Installation of grounding (rough ins) Cooling Pond Shelter HOLD 14 Weld Check Warehouse Continue
93 E/A NEW Installation of grounding (rough ins) Cup Lump RESULT
No. TESTING AREA STATUS REMARKS
94 E/A NEW Installation of grounding (rough ins) Utility & Workshop Pass Fail
95 E/A NEW Sandfilling/ encasement electrical Electrical (SDP) 1 CHB Compressive Strength - Pending - - Waiting for the Result
ISSUES/ CONCERNS ACTIONS REQUIRED Date Opened Date Closed
1. Accumulation of water on excavated areas due to high water table Continuous dewatering using submersible pumps 8-Dec-22
2. Limited access due to accumulated and undisposed excavated soil Expedite soil disposal 8-Dec-22
3. The tapping point of sewer is different material (PVC) Find appropriate fittings to connect 3-Jun-23 5-Jun-23

4. Steel grill fence needs additional reinforcement to stabilize from sway Provide retrofit to prevent sway 7-Jun-23 [20 JUL]

5. TEMPORARY POWER not provided (availability of materials/ manpower) Provide ASAP [30 JUN]
6. POWER SUPPLY holding the welding works of BI pipe 4-Jul-23
7. Poor staffing of MEPFS 4-Jul-23
8. Pumpcrete malfunction 1-Aug-23
9. Power center offset by 8 cm