Permit To Work Procedure
Permit To Work Procedure
Raghavendrakiran
Originated By
Deputy HSE Manager
William
Reviewed by
Technical Manager
Ahmed Nalouti
Approved by
Project Manager
Issue Status : For
Revision No. A Revision Date : 05 June 2023
Implementation
IMPORTANT: The master of this document is stored on an electronic document server “SharePoint”. Copies may be printed or downloaded
to your desktop; however, any hardcopy or softcopy of this document (other than the Master) is considered as uncontrolled document and
Document Title Issue Date
Permit to Work Procedure 05-Jun-23
used for reference only. It is the responsibility of the user to verify that this copy is of the latest revision.
REVISION RECORD
NOTE:
A vertical line on left hand side margin denotes revisions.
Document Title Issue Date
Permit to Work Procedure 05-Jun-23
TABLE OF CONTENTS
1.0 PURPOSE 4
2.0 SCOPE AND OBJECTIVES 4
3.0 REFERENCES 4
4.0 TERMS AND DEFINITIONS 5
5.0 ROLES AND RESPONSIBILITIES 6
5.1 PERFORMING AUTHORITY 6
5.2 ISSUING AUTHORITY 7
5.3 SITE/FACILITY MANAGER 7
5.4 SITE/FACILITY HSE IN-CHARGE 8
5.5 SUPERVISORS/LEADERS 8
5.6 EMPLOYEES 8
5.7 PERMIT TO WORK COORDINATOR (PTWC) 8
5.8 AUTHORIZED GAS TESTER (AGT) 9
6.0 PROCEDURE 9
6.1 REASONS FOR IMPLEMENTING PERMIT TO WORK 9
6.2 PERMIT TO WORK PROCESS 11
Specific Process for Radiography Certificate 12
Specific Process for Simultaneous Operation (SIMOPS) 13
6.3 SPECIFIC DETAILS – CONDITIONS 13
6.4 AUDITING 15
6.5 RECORDS 15
7.0 APPENDICES 16
7.1 APPENDIX 7 – PERMIT TO WORK FORM 16
Document Title Issue Date
Permit to Work Procedure 05-Jun-23
1.0 PURPOSE
This procedure describes the MIC Construct Permit to Work (PTW) system that is
used to provide the controls necessary in achieving the safe performance of a
specified range of potentially hazardous tasks, in our project laydowns (fenced area).
This PTW Procedure serves as a compulsory document to be observed and
complied with by all MIC Construct employees and Subcontractors.
As a guide, all non-routine, high risk and hazardous activities will require application
for and approval of a PTW from the relevant area authority, prior to commencement
of the activity.
Note: All personnel should be aware that the PTW system is not an absolute
safeguard in itself. It is the responsibility of each individual to be alert to hazardous
situations that may arise during the operation.
2.0 SCOPE AND OBJECTIVES
This procedure applies to all activities undertaken by MIC Construct and its
Subcontractors, and is valid within all MIC Construct facilities or any other workplace
that MIC Construct is involved, with below conditions:
● Where the task at hand is classified as non-routine, high risk, or hazardous
and requires control;
● Where the task at hand is among the list of activities defined in this document
as PTW required activities;
● Where relevant risk assessment dictates PTW implementation; and
● Unless it is superseded by a Client/Operator imposed PTW system.
MIC Construct is determined to achieve the following objectives, throughout the
execution phase, through implementation of this PTW procedure:
● Controlling potential hazards and risks associated with non-routine, high risk
and hazardous activities, through development and implementation of
effective mitigation measures;
● Preventing likely adverse interaction between two different activities held at
the same workplace, at the same time;
● Preventing the occurrence of incidents/accidents by ensuring compliance with
established HSE plans and procedures;
● Reducing and minimizing HSE impacts on, and disturbances to, the
surrounding environment and neighbouring residents/contractors/facilities.
3.0 REFERENCES
1. VI-ECP-PRC-005 Procedure Governing the Requirements for Consolidated
Permit to Work In Common Areas of MIC and RLC
2. OGO-OPS-OVR-001 Qatar Gas Permit to work system operating procedures.
from the team handling the task at hand, or can be the HSE officer in the
workplace. AGT training can be done in-house, or by a third party training
centre where necessary.
4.2 Confined Space
Any space that is large enough and so configured that an employee can
bodily enter and perform assigned work, which has limited or restricted
means of entry or exit, has limited or no natural ventilation, and is not
designed for continuous occupancy.
4.3 Critical Lifting
Critical lifting activities are lifting activities that are realized within one or more
of below circumstances:
● Complex shaped load, with at least one dimension exceeding 12
meters and the centre of gravity is difficult to ascertain;
● Load weight is exceeding 50 tons;
● Lift is exceeding 30 meters in height;
● Lift requires full boom extension or maximum radius;
● Lift requires use of more than one crane simultaneously;
● Load consists of thin/fragile members susceptible to deformation
during lifting;
● Lifts in which site facilities, buildings or machinery are within the line of
fire;
● Personnel lifts, lifts over pipelines, near overhead electric power lines,
where lifting operation can endanger the safety of the plant or crane.
● Lifts where safety of personnel and equipment are at risk, which is a
concern raised by any responsible authority.
Figure-1. Life-Saving Rule: Work with a valid work permit when required
List of Routine & Non Routine activities are listed as follows, but are not
limited to:
Routine Activities:
● General civil maintenance activity
● Housekeeping
● Material Shifting
● Diesel refiling
● Loading/ unloading of skips
● Sewage removal
Document Title Issue Date
Permit to Work Procedure 05-Jun-23
*Note: This applies only in MIC Construct facilities, when there is change in
work standard / step, PTW will be applicable.
Non-Routine Activities:
● Radiography works;
● Hydrostatic or pneumatic testing;
● Entry into confined spaces (vessels or pipes fabricated, septic tank,
etc.);
● Load testing of lifting equipment;
● Major overhaul activities;
● Any critical lifting activity;
● High pressure water jetting;
● Any modification of fire alarm system;
● Any modification of firefighting system;
● Any modification of electrical installation within the facility;
● Canteen LPG tank re-filling activities;
● Maintenance activities within facilities;
o Roof repair;
o Any facility maintenance that can affect fire alarm system
(including fire alarm maintenance activities);
o Firefighting equipment maintenance (hoses, pumps, water tank);
o Gas lines repair;
● Any non-routine activity that requires working above 2.5 m;
● Any task that requires electrical isolation;
● Any task that are considered as non-routine and high-risk; and
● Any task that are recorded in hazard and risk register to require permit
to work.
6.2 Permit to Work Process
Attachment 1 displays the flow chart of Permit to Work process. Details are
given below (note the actions in bold requires signature on the permits to
work):
1. As part of the work planning, the permits to work requirements are
assessed by Performing Authority (PA) and necessary permits are raised
by signing. PA ensures that permits raised are supported with certain
documents, as and where necessary:
● Relevant and applicable work certificates (Confined Space Entry,
Excavation, Radiography);
● Isolation certificate where applicable and necessary;
● Records of toolbox talks held with performing party;
● Method Statement and Job Safety Analysis, if any;
● In the absence of a Job Safety Analysis, Risk Assessments related
with the tasks undertaken or relevant clauses of HSE Risk Register
shall be utilized as an essential supporting document, where
available and applicable;
● Safety Data Sheets of chemicals used;
● Third party certificates and other inspection records of: lifting
equipment and gears used, pressure test equipment like
manifolds, etc.;
Document Title Issue Date
Permit to Work Procedure 05-Jun-23
These sessions have a validity period of Three (3) year; hence refresher
sessions are to be taken upon validity is due for the Authority.
Specific training module is available for Authorized Gas Testers (AGT), with
a validity period of Three (3) year, hence refresher sessions are to be taken
upon validity is due for the AGT. Performing Authorities can be nominated as
AGTs, or they may choose a candidate that has adequate skills to perform
gas tests, record on forms and interpret the results upon getting trained.
Workforce is provided with general Permit to Work awareness during
mandatory MIC Construct induction.
HSE In-Charge will be responsible to ensure that workforce reach the
adequate level of PTW awareness, through toolbox talks, posters, and other
tools as necessary.
6.4 Auditing
Permit to work system will be subject to regular audits by site HSE
organization. HSE In-Charge will ensure that site HSE team performs PTW
audits and records the findings.
Document Title Issue Date
Permit to Work Procedure 05-Jun-23
HSE In-Charge will further ensure that PTW records and implementation
process are ready for internal audits by QA team as per planned audit
schedule and any external audit (by certifying party, by Client, by relevant
local authorities, etc.).
HSE Form 091 is the Permit to Work Audit Form, which will be used for
recording PTW audits.
Issuing Authority, as part of his role, is required to inspect permits to work
under his authority and intervene with any deviation from process.
6.5 Records
Permits to work are signed for closure, when the validity period of the permit
is due or when the task subject to the permit is complete. Closed permits,
along with their supporting documents, are handed over to HSE department
for archiving purposes. Archiving duration for permit to work and its
supporting documents is one (1) year. It is to be noted that this condition is
set for internal PTW procedure only; and where Client PTW system is
followed, the recordkeeping conditions will be as per respective Client
procedure only.
Document Title Issue Date
Permit to Work Procedure 02-Jan-21
7.0 APPENDICES
7.1 Appendix 7 – Permit to Work Form
Document Title Issue Date
Permit to Work Procedure 02-Jan-21