Material Requirement Planning
Material Requirement Planning
Planning
Dependent Demand
• For any product for which a schedule can be established,
dependent demand techniques should be used
Benefit of MRP
1.Better response to customer orders
2.Faster response to market changes
3.Improved utilization of facilities and labor
4.Reduced inventory levels
Dependent Demand
§ The demand for one item is related to the demand for another
item
§ Given a quantity for the end item, the demand for all parts and
components can be calculated
§ In general, used whenever a schedule can be established for an
item
§ MRP is the common technique
Dependent Inventory Model
Requirements`
• Effective use of dependent demand inventory models requires
the following
1.Master production schedule
2.Specifications or bill of material
3.Inventory availability
4.Purchase orders outstanding
5.Lead times
Master Production Schedule (MPS)
Production
Figure 14.1
Marketing Finance
Capacity Customer demand Cash flow The Planning Process
Inventory
Master production
schedule
Change master
production
Material schedule?
requirements plan
Schedule and
execute plan
tion Weeks 1 2 3 4 5 6 7 8
240-watt amplifier 100 100 100 100
pe and
be 150-watt amplifier 500 500 450 450
75-watt amplifier 300 100
Start production of D
Must have D and E Figure 14.3
completed here so
production can Time-Phased Product
begin on B Structure
1 week
D 2 weeks to
produce
B
2 weeks
E
A
STUDENT TIP
2 weeks 1 week This is a product structure on
E its side, with lead times.
2 weeks 1 week
G C
3 weeks
F
1 week
D
1 2 3 4 5 6 7 8
Time in weeks
and we can illustrate a small one by hand. A master production schedule, a bill of material, Gross material requirements
inventory and purchase records, and lead times for each item are the ingredients of a material plan
requirements planning system (see Figure 14.4). A schedule that shows the total
Once these ingredients are available and accurate, the next step is to construct a gross mate- demand for an item (prior to sub-
MRP Structure
rial requirements plan. The gross material requirements plan is a schedule, as shown in Example 2.
It combines a master production schedule (that requires one unit of A in week 8) and the time-
phased schedule (Figure 14.3). It shows when an item must be ordered from suppliers if there
traction of on-hand inventory and
scheduled receipts) and (1) when
it must be ordered from suppliers,
or (2) when production must be
is no inventory on hand or when the production of an item must be started to satisfy demand started to meet its demand by a
for the finished product by a particular date. particular date.
MRP by
date report
Lead times
(Item master file) Planned order
STUDENT TIP
report MRP software programs are
popular because manual
Inventory data approaches are slow and error
Purchase advice
Material prone.
requirements
planning
programs
Exception reports
(computer and
Purchasing data software) Order early or late
or not needed