Road Construction Method Statement - Method Statement HQ

This document provides a brief method statement for road construction work. It outlines the process from laying the sub-base of granular material to the final asphalt layers. Equipment needed includes paving equipment, rollers, cutting tools, and surveying equipment. Materials used are sand, crusher run stone, and various asphalt mixes. The work sequence is described as preparing the sub-base, laying crusher run road base, then applying asphalt binder and wearing courses. Project alignment must be approved before pavement work can begin.

Uploaded by

augustine samuel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
253 views

Road Construction Method Statement - Method Statement HQ

This document provides a brief method statement for road construction work. It outlines the process from laying the sub-base of granular material to the final asphalt layers. Equipment needed includes paving equipment, rollers, cutting tools, and surveying equipment. Materials used are sand, crusher run stone, and various asphalt mixes. The work sequence is described as preparing the sub-base, laying crusher run road base, then applying asphalt binder and wearing courses. Project alignment must be approved before pavement work can begin.

Uploaded by

augustine samuel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

Home Download Method Statements Civil SWMS Road Work Methods


PM Maintenance PQP HSE Plan Privacy Support Refund Policy


Cart

Method Statement HQ
Best Editable Construction QHSE Documentation Portal

Full Editable Document Catalog

Sign up on myMSC & Book Online


With our modern global fleet & local experts teams, we care for your agriculture Sign Up
shipments MSC 
https://methodstatementhq.com/road-construction-method-statement.html 1/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

Select Language
Powered by Translate

SEARCH

Subscribe
for New
Methodstatements
Enter your email
address to
subscribe and
receive
notifications when
new documents
are released.

Email Address

SUBSCR
IBE
Join 4,620 other
subscribers

Like & Follow on


Facebook


https://methodstatementhq.com/road-construction-method-statement.html 2/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

Methodst
3,606 follower

Road Construction
Follow Page
Method Statement

Below is very brief road construction work


method statement that outlines the
complete process from laying the sub base
to the laying of asphalt to achieve final
product or outcome. The scope for

Browse By pavement for the road construction consists


of sub-base of granular material, road base
Topics of crusher run, asphaltic concrete binder
 Aluminium & course and asphaltic concrete wearing
Glass Work course.
Methods (10)
 Building At the end of this article you shall find links
Management to download method statements samples
System (25)
for road works. Keep reading.
 Civil
Engineering This road construction method statement
Methods (161)
shall apply for all roadworks. The intention
 Civil SWMS
Downloads (36) of this work method statement is to give
general guideline for the roadwork
 Construction
Method construction. Details of the procedures
Statements contained herein may be modified based
(200) upon actual ground condition and project
 Download site requirements.
Method
Statement (154) Below is list of equipment and tools that are
 Duct Works mandatory for the construction work.
(14)
Paving Set
 Electrical Diamond Cutter
Downloads (45) Backhoe
 Electrical Back pusher
Method Tipper Lorries 
Total Station
https://methodstatementhq.com/road-construction-method-statement.html 3/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

Vibratory roller
Thermometer
Leveling Instrument

Below is the list of materials that we need


for the construction work of the road.
Sand
Crusher run
Asphaltic Concrete Binder Course ACBC 28
Asphaltic Concrete Wearing Course ACBC
20
Bituminous Prime Coat
Bituminous Tack Coat

Method of Road Construction


Before pavement construction can be
allowed it is necessary for both the
horizontal and vertical alignment to be joint
inspection and confirmed by the Consultant.

Make sure surveyor is using proper


instrument total station and dumping level.
Also ensure the mark on site is visible and
suitably protected during work construction.

Pavement construction works shall only be


allowed to commence on site upon the
approval and acceptance of the sub-grade
layer.

The Contractor shall counter check again the


alignment and all dipping pegs and confirm
with the Consultant prior to the permanent
work.

Road Works Sequence of Work

Below is typical sequence that can be 


followed for doing the site construction of
https://methodstatementhq.com/road-construction-method-statement.html 4/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

roads.
1. Preparing & laying 100mm granular
material sub-base
2. Laying 200mm crusher run road base
3. Preparing and laying 60mm Asphaltic
Concrete Binder Course
4. Laying 40mm Asphaltic Concrete Wearing
Course

Preparation of Formation To Receive


Road Pavement
Make sure that piped or box culvert services,
utilities and ducts (if any) or any other
drainage work that might affect the works,
are complete before the preparation of
formation. If this step is not complete such
preparation shall be carried out immediately
prior to the laying of the sub-base.

All the materials for sub base, road base,


ACBC and ACWC shall be sent to nominated
and approve laboratory to conduct
necessary testing and to be comply with
technical specification.

The surface of the formation shall be


substantially uniform in density throughout
its entire width and shall conform to the
density requirements for compaction. Trial
compaction to be conducted in order to
determine the designated degree of
compaction as required in the presence of
supervision consultant for the road
construction activities.

Other utilities crossing the road such as


water mains and cables shall be protected 
before proceed the road base works. For
https://methodstatementhq.com/road-construction-method-statement.html 5/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

example using lid for u-drain and G.I.


conduit for cables.

It shall be trimmed to conform to the lines,


camber, grades and typical cross sections
shown on the roadworks drawings or as
directed by road construction consultant.

The sample of earth to be sent to laboratory


for MDD test for comparison of degrees of
compaction.

To conduct trial compaction to determine


passes roller required.

Level pegging to be done at suitable


distance for inspection.

Earth Formation:  Where soft spots and


unsuitable materials found, it shall be
removed and back filled with approved
suitable material and compacted in
accordance to the agreed rolling pattern.

Sub Base Procedure

The sub base material shall be hard, durable


and clean. It shall be granular material and
shall be free from organic material, clay
balls, and any other deleterious substances.

The materials will be delivered to the site by


tipper lorries and spread and leveled by
means of a back pusher for the full width of
the pavement. The material shall be filled
and compacted to the required thickness as
specified in the approved drawing for the
road construction works. 
https://methodstatementhq.com/road-construction-method-statement.html 6/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

Compaction of the sub base layer shall be


carried out by using vibrating roller to
achieve relative dry density as per
specification.

Alignment, level and surface regularity will


be checked in accordance to Technical
Specification.

The final surface of granular sub base layer


shall be regulated and trimmed by back
pusher to the required level and cross fall
within the specified vertical tolerances.
Compaction work will be done using roller
compactor.

Field Density Test (FDT) or CBR Test on the


subgrade shall be carried out according to
the specification.

Laying Road Base Material


The crusher run road base to be placed on
top of the sub base shall consisting of
crushed aggregate laid in layers each of
thickness not exceeding 200mm and to give
the specified total compacted thickness and
width, correct line and levels shown in road
construction drawings.

The material shall be crushed rock of hard
https://methodstatementhq.com/road-construction-method-statement.html 7/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

durable particles or fragments of rock


crushed to the correct size, well graded and
lie within the following grading limits
specified in the specification.

Care shall be taken to prevent segregation


of the material into the coarse and fine
fractions.

Bituminous Prime Coat and Tack Coat


Procedure

An approve bituminous prime coat which is


submitted through material submission shall
be applied to the top of the completed
crusher run base course before laying the
asphaltic concrete binder course.

The surface shall be cleaned immediately


prior to the application of prime coat. The
bituminous shall be applied by means of a
distributor at suitable rates but not to be
less than 0.435 liters per sq meter. SS1K
using for prime coat while RS1K using for
tack coat.

The surface of the dense asphaltic concrete


binder course shall be cleaned immediately
prior to the application of an approve tack
coat. The bituminous shall be applied by 
means of a distributor at suitable rates but
https://methodstatementhq.com/road-construction-method-statement.html 8/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

not to be less than 0.35 liters per sq meter.

The prime coat shall be sprayed well in


advance and leave for 24 hours for curing.

Asphaltic Concrete Surfacing Method

The surfacing shall be two courses and shall


comprise of asphaltic concrete binder course
and Asphaltic concrete wearing course and
lay in accordance with BS 1621. The two
courses shall be constructed to the width
and thickness after compaction as shown in
the drawing.

Course Aggregate: Course aggregate shall


be hard un-weathered, durable, clean
crushed rock, angular in shape, free from
dust and tested in accordance with the
methods described in B.S. 812.

Fine aggregate: Fine aggregate shall be


approved clean natural bank, river, dune, pit
or quarry sand produced in a secondary
plant. They shall consist of hard, non-
absorbent sharp grains and shall be free
from clay, loam, loosely bounded
aggregations and other foreign matters.

Filler: Filler shall be either Portland Cement


complying with B.S. 12 or limestone, having
a bulk density in Toluene.

Asphaltic Concrete Binder Course, ACBC 28


ACBC 28 mix will follow the approved mix
design and trial mix. The aggregates shall be
surface dry and shall be mixed at an 
appropriate temperature The mixed
https://methodstatementhq.com/road-construction-method-statement.html 9/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ
appropriate temperature. The mixed
material as delivered to the laying site shall
be between 140 degrees Celsius to 160
degrees Celsius.

Laying Procedure for Road Construction


Work shall commence on site upon
approval and acceptance of the road base.
The surface to receive the asphaltic
concrete binder course shall be free of all
damage, loose materials and standing
water by sweeping.
Prime coat of approved bitumen emulsion
shall be applied as per Specifications on
the prepared surface prior to lay of the
asphaltic binder course.
The asphaltic concrete binder shall be
plant mixed with approved bitumen
content.
The approved asphaltic concrete binder
course shall be delivered to site by tipper
trucks. To prevent the loss of heat, the
mixture shall covered by tarpaulin.
The asphaltic concrete binder course shall
be laid by a paver in single layer.
Compaction shall be carried out using the
specified equivalent type of compactors.
Rolling shall always commence from the
lower to the higher side of the
carriageway. The minimum rolling
temperature shall be 80 degrees Celsius.
The surface of asphaltic concrete binder
course shall be finished to the line and
grade as required by the Drawings.

Asphaltic Concrete Wearing Course ACWC20


ACWC 20 mix will follow the approved
design mix and trial mix. The aggregates
shall be surface dry and shall be mixed at an
appropriate temperature. The mixed
material as delivered to the laying site shall

be between 140 degrees Celsius to 160
d
https://methodstatementhq.com/road-construction-method-statement.html C l i 10/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ
degrees Celsius.

Work shall commence on site upon approval


and acceptance of the asphaltic concrete
binder course. The surface to receive the
asphaltic concrete wearing course shall be
free of all damage, loose materials and
standing water by sweeping.

Tack coat of approved bitumen emulsion


shall be applied as per Specifications on the
prepared surface prior to lay of the asphaltic
wearing course. The asphaltic concrete
wearing shall be plant mixed with bitumen
content. The approved asphaltic wearing
course shall be delivered to site by tipper
trucks. To prevent the loss of heat, the
mixture shall covered by tarpaulin.

The asphaltic concrete wearing course shall


be laid by a paver in single
layer. Compaction shall be carried out using
the specified equivalent type of compactors.
Rolling shall always commence from the
lower to the higher side of the carriageway.
The minimum rolling temperature shall be
125 degrees Celsius. The surface of asphaltic
concrete wearing course shall be finished to
the line and grade as required by the
Drawings. 

Upon completion of laying and compaction,


joint survey shall be carried out to check for
compliance with the specified
requirement. After all the above works is
completed, the supervisor is to ensure that
the site is to be tidied up and all excess 
materials are to be discarded away from the
https://methodstatementhq.com/road-construction-method-statement.html 11/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

site.

Transportation of Bituminous materials


Bituminous materials shall be transported in
clean vehicles and shall be covered over
when in transit or awaiting tipping. Every
precaution is to be taken to avoid
segregation of mixed materials and to
ensure that they do not become
contaminated with foreign matter. In order
to maintain satisfactory temperatures of
materials in transit and to prevent undue
loss of heat adequate precautions are to be
taken to ensure that the materials are
properly protected.

Laying Method
Supply the mixed materials, as soon as
possible after arrival at the laying site,
continuously to the paver and lay without
delay.
Wherever practicable, road pavement
materials having bitumen as the binder
shall be spread, leveled and tamped by
approved self-propelled pavers capable of
laying to the required width, profile,
camber or cross fall.
Immediately after any course is placed 
and before rolling is started, the surface
https://methodstatementhq.com/road-construction-method-statement.html 12/19
8/31/23, 1:15 AM
g ,
Road Construction Method Statement – Method Statement HQ

shall be checked and all defects and


irregularities in alignment, grade or
texture corrected by the additional or
removal of mixture.

Compaction Procedure
The laid material shall be compacted as
soon as possible as rolling can be effected
without causing undue displacement of the
mixed material. The rollers shall be fitted
with beeper.

The materials shall be rolled in longitudinal


direction from the sides to the centre of the
carriageway.

For compaction, two times rolls pass by non-


vibrate compactor prior to two times rolls
pass by vibrate compactor. The roller shall
weigh not less than 12 tonnes.

Eight times rolls pass compaction shall be


carried out by Tyre roller.

The last compaction shall be done by non-


vibrate compactor.

Health Safety and Environment Compliance

Safety induction to be conducted to all new


workers that involved to this activity and
safety toll box meeting shall be conducted
every day to remind the workers about
concerning the safety. All workers
shall be provided with PPE (Personal
Protective Equipment) and shall be worn at
all time on site. Safety Manager / Safety

Supervisor shall ensure all the workers wear
ll th
https://methodstatementhq.com/road-construction-method-statement.html f t i t’ id d 13/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ
all the safety equipment’s provided.

All workers shall be advised to report any


accident or injury to supervisor. Proper and
adequate provision of temporary signage’s
and barricades at diversions and temporary
haul road as necessary (if applicable).

All workers shall educate on good


environmental management practices and
well disciplined to environment. The
garbage bin shall be provided at the
working area and Supervisor shall ensure its
must be collected regularly and disposed off
at the approved dumpsite. All workers shall
ensure that all tools and equipment
machinery are in good condition to avoid
any oil leakage that could harm to
environment.

Sample Road Works Method Statement


Download Links

Just right click below link and select Save


link as to save the files on your computer or
device.
1. Method of Statement for Road Works doc
file
2. Method Statement for Roadbase
Construction pdf file
3. Road Works Method Statement.pdf

Blank Dri

https://methodstatementhq.com/road-construction-method-statement.html 14/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

(95)
 Fire Fighting Previous Next
Downloads (9)
 Fire
Suppression
System (14)
 HVAC
Downloads (44)
 HVAC Method
Statements
(100)
 Method
Statement for
Civil Works
(120)
 Method
Statements
(374)
 Occupational
Health and
Safety (44)
 Piping
Method
Statements (30)
 Piping Works
(32)
 Plumbing
Downloads (26) 
https://methodstatementhq.com/road-construction-method-statement.html 15/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

 Plumbing
Method
Statements (63)
 Pressure
Testing (11)
 Preventive
Maintenance
(10)
 Project
Planning (12)
 Pump
Installation (4)
 Quality
Management
(44)
 Risk
Assessment (25)
 Roadworks
(19)
 Stainless
Steel Fabrication
(10)
 Technical
Articles (63)
 Technical
Calculations (3)
 Templates
(25)
 Test Reports
& Forms (13)
 Testing &
Commissioning
(102)


https://methodstatementhq.com/road-construction-method-statement.html 16/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

Plastering
Method
Statement

Method
Statement
for
Hydrostatic
Testing of
Metallic
Pipework

Construction
Safety
Procedure to
Keep
Children
Away from
Hazards

HVAC
System
Volume
Control &
Fire Damper
Installation
Method
Statement


https://methodstatementhq.com/road-construction-method-statement.html 17/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

Electrical
Installation
Method
Statement
for Central
Battery
Emergency
Lighting
System

Method
Statement
for
Condensate
Drain Piping
Installation
& Testing
(UPVC + GI)

Search prod

Design
Coordi 
https://methodstatementhq.com/road-construction-method-statement.html 18/19
8/31/23, 1:15 AM Road Construction Method Statement – Method Statement HQ

nation
Corpor
ate
Proced
ure
$2.99

Meta
 Log in
 Entries feed

 Comments
feed

WordPress.org