Client Name: Project Name:: Ezar For Engineering and Technical Services
Client Name: Project Name:: Ezar For Engineering and Technical Services
Project Name:
ID Task Task Name Duration September October November December January February March April May June July August September October
Mode W-2 W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42 W43 W44 W45 W46 W47 W48 W49 W50 W51 W52 W53 W54 W55 W56 W57 W58
1 COATING Of THE CRUD OIL STOREGE TANK FARWA (COT3P) 393 days
2 Contract Award 1 day
3 Kick Off Meeting 1 day
4 Engineering Phase 30 days
5 Detailed WMS 25 days
6 QA/QC Documentation 15 days
7 HSE Documentation 15 days
8 Detailed BOQ 30 days
9 Procurement Phase 75 days
10 Approval & Placing Orders For Project Consommable 3 days
11 Goods Preparation at supplier Factory 60 days
12 Transportation & Freight Forwarding 10 days
13 Reception at MOO Storage Area 2 days
14 Mobilization 19 days
15 Check & Control of Equipment Before Mobilization 10 days
16 Mobilization of Equipments 7 days
17 Mobilization of Project Staff 2 days
18 Mobilization of ManPower 7 days
19 Site Activities 283 days
20 Area Preparation 2 days
21 Equipement Preparation 1 day
22 Placement of Equipment as per Area Dispatching DWG 1 day?
23 Preparation of Waste Area Zone
24 Running of Compressed Air Duct and Flexibles
25 Inspection and Testing
26 Tank Opening 1 day
27 Opening of Tank Manhole 1 day?
28 H2S Testing
29 Installation of Ventillation System 3 days
30 Exhaust Installation
31 Duct Erection
32 Testing of Air Quality Circulating Inside The Tank
33 Installation of Lighting System 3 days
34 Installation of Explosion Proof Lamp 1 day?
35 Testing of Tank Liminosity 1 day?
36 Sefety Inspection & Area Controle 1 day
37 Tank Cleaning & Sludge Removal 6 days
38 Sludge Removal and Putting in Plastic Bags 6 days
39 Take off the Plastic Bags from the Tank and Conservation in MOO waste disposal Container
6 days
40 Scaffolding Installation 10 days
41 Preparation of Scaffolding Platform 1 day?
42 Preparation of Scaffolding Tubes
43 Scaffolding Fixing
44 Scaffolding Inspection
45 Tank Cleaning & Washing 15 days
46 Washing the Tank Surface Using Carsher 1 day?
47 Draining the Waste Water
48 Washing the Bottom Surface
49 Draining the Waste water used for Bottom washing
50 Tank Surface Inspection 1 day?
51 Visual Inspection
52 MT + UT for the Critical detected Points
53 Surface Preparation 170 days
54 Repair of Damaged Points in the Tank 170 days
55 Blasting Activity
56 Rigosity Measurement / Inspection & Surface Control
57 Painting Activities 170 days
58 Application of Paint System to the Surface
59 Application of Painting System to The Tank Accessories
60 Thickness Measurement / Inspection and Control
61 Replacement of Tank Anodes 25 days
62 Demolution of Old Anodes
63 Installation Of New Anodes
64 Commissionning and Startup the System
65 Testing & Reception 4 days
66 Handover of the Tank
67 Handover of the Documentation & QAQC Reports
68 Tank Area Rehabilitation 7 days
69 Cleaning the Area Around the Tank
70 Rehabilitation of the Area Around the Tank
71 Demobilization 17 days
72 Demobilization of Equipements 15 days
73 Demobilization of Manpower 2 days
Rev 02
P:D.BENALI