METHOD STATEMENT OF
CONCRETE WORK
Table of content
1. Scope
2. Purpose
3. References
4. Responsibilities
5. Equipments
6. Material
7. Shop Drawings
8. Procedure
8.2. Formwork
9. Concrete Compaction
CONCRETE WORK
PT. GEMILANG KARYA MANDIRI
1. SCOPE
The scope of this method of statement is to cover concrete works activity which
includes (Formworks installation, rebars supply and installation, concrete supply and
placement, water proofing, etc) supply for cast in situ Concrete in the project. In
accordance with contract requirements and approved specification, project safety
procedure and approved issued for construction drawings.
2. PURPOSE
• The method statement shall address the precedence of physical operation
applicable for the supply and placing Structural / nonstructural Concrete on
the project.
• This Method Statement is to ensure that concrete works activiti will be
expedite in an efficient and safe manner in accordance with all relevant
contract documents, (Specification and Drawing) and international accepted
methods, utilizing proven methods and procedures, as detailed herein and
was implemented on previous projects.
• This Method Statement is for submittal to Consultant / Employer for their
concurrence.
• This Method Statement will, if deemed necessary, be revised as and when
required to accomodate circumstantial requirements that cannot be foreseen
at this page.
3. REFERENCES
3.1. Project Standard Specification for CONCRETE WORK
25457-0000-3PS-DB00-0001 Rev. 001 for Concrete Work
25457-0000-3PS-DB01-0001 Rev. 001 Furnishing and Delivering ready – Mix
Concrete
25457-0000-3PS-DG01-0001 Reinforced Steel, Embedded Item and
Mischellaneous Concrete Accessories.
3.2. EN 206-1 Concrete specification, performance, production and conformity
CONCRETE WORK
PT. GEMILANG KARYA MANDIRI
4. RESPONSIBILITIES
• Site Manager have the responsibilities for overall the project activities
including safety measures.
• Construction Supervisor (Civil), in charge shall be responsible for
coordination and supervision of construction works (activities) and
construction groups, ensuring that works is done as per project specification
and approved drawings, and all safety measures are implemented, of site
construction and report to construction manager civil.
• Site General Foreman, shall be supervising closely that activities designated
to them ensuring that all instruction are followed are strictly adhered to (this
may involve providing alternative access routes for moving Traffic with Traffic
Signs if necessary are in place prior to commencing the work, safety
procedures of the project are strictly followed).
• QC Inspector or his designee shall be responsible for review all relevant
documentation and test reports issued by parties involved (SE, Lab, Surveyor
and QC Inspectors) and submit record to client, Ensure that all discipline
activities that require to be inspected in the concreting operation has been
inspected and approved.
• Scafolding Supervisor, to ensure that all scaffolding system has been erected
accordingly to safety and requirements.
• Safety Officer, to ensure all safety precautions has been taken into
consideration before commencing the concrete works, inspection all
equipment and all heavy equipment operators such as excavators, cranes,
forklift, etc, should have third party licence.
CONCRETE WORK
PT. GEMILANG KARYA MANDIRI
5. EQUIPMENTS
5.1. Concrete Mixing and Transport equipment
5.2. Ready Mix Concrete batching Plant
5.3. Transport Mixer
5.4. Concrete Pump
5.5. Hoses / Concrete Shoots
5.6. Concrete Busckets
5.7. Air Compressor
5.8. Survey Equipment
5.9. Level
5.10. Total Station (Surveying instrument for checking level & distances)
5.11. Masonry Accessories
5.12. Wheel Barrows
5.13. Concrete vibrators
6. MATERIAL
6.1. Form Plywood
6.2. Timber
6.3. Scaffolding
7. SHOP DRAWINGS
Shop drawing approved / Issued for Construction drawing.
8. PROCEDURE
8.1. Excavation And Backfilling
• All the areas where excavation is required, the surveyor will give the
information to the excavation foreman to start the excavation to the levels
indicated in the IFC (issued for construction) drawings.
• After the excavation is completed, the surveyor will check the final grade
of the excavation and the grade will be adjusted accordingly.
CONCRETE WORK
PT. GEMILANG KARYA MANDIRI
8.2. Formwork
• Concrete placement will not commence before Client Approval of
Formwork and Rebar Installation.
• The design and construction of formwork shall take account of safety and
of the surface finish required. The formwork will be sufficiently rigid and
tight to prevent loss of grout or mortar from the fresh concrete and stand
concrete Vibration (Excreted Hydrostatic Pressure) without Movements.
Form work and its supports to maintain the correct position and to
maintain correct shape and profile.
• The formwork for foundation, beam connection, column neck and
manholes etc. Will be made of either traditional formwork (plywood and
timber and supported by tie rod and steel support ) or DOKA system
which a combination of DOKA wooden beams, plywood and DOKA steel
supports system with tie rod.
• Molds and formwork shall be prepared according to the IFC drawing.
• Formwork will be placed and aligned fixed to the required dimensions as
detailed in issued for construction drawings by the carpentry crew.
CONCRETE WORK
PT. GEMILANG KARYA MANDIRI
• Formwork shall be rigid / sturdy and fixed in such a way to retain the
structure members dimensions.
• QC Inspector will check the formwork installation and safety officer to
ensure safety of the work.
• Before placing the steel reinforcement, an approved form release
agent will be applied to the internal face of the formwork.
• For columns, walls shutter will not be closed before QC and
client/consultant releases.
temperature, slump air content and fresh concrete density and samples
taken asper specifications ). Then transit mixer Mixer released to
specified Concrete location.
• Place the approved mix concrete into layers 450 mm per layer maximum
using one of the above methods.
• Preparation forms, reinforcement, joints and mixing conveying.
• Concrete shall not be dropped from a height exceeding 1.8 meters.
• Expansion / Contraction joints shall be provided as per IFC drawings.
• If the air temperature is less than 30 deg C concrete shall be placed
within 90 minutes of the introduction of the mixing water to the cement
and aggregates, or cement to aggregates. If the air temperature is greater
than 30 deg C mixing time shall be reduced and concrete placed within
60 minutes except when a suitable set retarding mixture is used and
slump requirements can be met. The maximum time between batching
and placing shall not be exceed 120 minutes in all cases.
• Specific measures taken for minimum dimension of any casting is .80
merters or more.
• Where Kicker is used it shall be at least 70 mm high and carefully
constructed.
• Concrete in high temperature (ACI standard 305.1 for hot weather
concrete shall be complied with.
• The minimum concrete cover maintained as detailed in specification.
9. CONCRETE COMPACTION
• Full compaction of concrete shall be achieved throughout the entire depth of the
layer using mechanical vibrators.
• Vibration of concrete shall be thoroughly worked agains the formwork and
around the reinforecement, successive layers shall be thoroughly bonded
togheter during vibration.
• Ensure reinforcement or form is not disturbed.