Manhanttan Lift Installation

The document outlines an 18 task, 27 day project plan for installing a lift in Manhattan from August 8th to September 13th. Key tasks include erecting scaffolding on August 8th, installing counterweight guide rails from August 9th-11th, installing the platform from August 14th-15th, installing and tuning the traction machine and controller from August 16th-17th, installing the counterweight from August 18th-21st, roping from August 22nd-23rd, demolitions from August 25th-28th, installing landing doors from August 25th-31st, builders work from September 1st-4th, car door installation on September 5th, door auto tuning on September 6th

Uploaded by

Augus Mande
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views1 page

Manhanttan Lift Installation

The document outlines an 18 task, 27 day project plan for installing a lift in Manhattan from August 8th to September 13th. Key tasks include erecting scaffolding on August 8th, installing counterweight guide rails from August 9th-11th, installing the platform from August 14th-15th, installing and tuning the traction machine and controller from August 16th-17th, installing the counterweight from August 18th-21st, roping from August 22nd-23rd, demolitions from August 25th-28th, installing landing doors from August 25th-31st, builders work from September 1st-4th, car door installation on September 5th, door auto tuning on September 6th

Uploaded by

Augus Mande
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Manhattan Lift Installation

ID Task Task Name Duration Start Finish August 2023 September 2023
Mode 6 8 10 12 14 16 18 20 22 24 26 28 30 1 3 5 7 9 11 13 15 17 19
1 Manhattan Lift A Installation 27 days Tue 8/8/23 Wed 13/9/23 0%
2 Erection of Scaffolding 1 day Tue 8/8/23 Tue 8/8/23 0%
3 Counterweight Guide Rails 3 days Wed 9/8/23 Fri 11/8/23 0%
4 Car Guide Rails 3 days Wed 9/8/23 Fri 11/8/23 0%
5 Platform Installation 2 days Mon 14/8/23Tue 15/8/23 0%
6 Traction Machine Installation 2 days Wed 16/8/23Thu 17/8/23 0%
7 Controller Installation 2 days Wed 16/8/23Thu 17/8/23 0%
8 Counter Weight Installation 2 days Fri 18/8/23 Mon 21/8/23 0%
9 Roping 2 days Tue 22/8/23 Wed 23/8/23 0%
10 Machine Auto Tune 1 day Thu 24/8/23 Thu 24/8/23 0%
11 Demolitions 2 days Fri 25/8/23 Mon 28/8/23 0%
12 Landing Doors Installation 5 days Fri 25/8/23 Thu 31/8/23 0%
13 Builders Work 2 days Fri 1/9/23 Mon 4/9/23 0%
14 Car Door Installation 1 day Tue 5/9/23 Tue 5/9/23 0%
15 Doors Auto Tuning 1 day Wed 6/9/23 Wed 6/9/23 0%
16 Wiring 2 days Wed 6/9/23 Thu 7/9/23 0%
17 Speed Run and Testing 2 days Fri 8/9/23 Mon 11/9/23 0%
18 Inspection & Commissioning 2 days Tue 12/9/23 Wed 13/9/23 0%

Critical Manual Task Baseline Milestone External Tasks

Critical Split Start-only Milestone External Milestone

Critical Progress Finish-only Summary Progress Inactive Task

Task Duration-only Summary Inactive Milestone

Split Baseline Manual Summary Inactive Summary

Task Progress Baseline Split Project Summary Deadline