IWMP IDC - Inception Report - ENG - Clean - V4 - FINAL - 20230630 Eb
IWMP IDC - Inception Report - ENG - Clean - V4 - FINAL - 20230630 Eb
Management Project -
Institutional Development and
Capacity Building Consulting
Inception report
Ref : IWMP/QCBS/SC-21/002
DOCUMENT CONTROL
GENERAL INFORMATION1
..
RECIPIENT
■
VERSIONS
March 10th-13th 2023 V1 - draft for comment CA, GG, MB, AJ, BM
1 This Report is strictly confidential and is addressed only to the recipient indicated above, who may share it with its advisors on
a non-reliance basis. No other person may rely on it for any purpose whatsoever. This report shall be confidential and become
and remain the absolute property of the Client {in compliance with articles 22 and 27 of the IDC main contract for the IWMP
project).
This Report has been prepared solely on the basis of (i) the data and documents referenced therein and {ii) the investigations and
analysis described within. Seureca cannot be held liable for incorrect or incomplete data made· available by third parties at the
time of the report that may materially impact the conclusions and recommendations. Seure application of
'g ·
the contents of this Report for any purpose other than for the purpose and objective
---�-
July 2023.
�r.-.-.3 1 45 72 92 93__.
Issyk Kul Wastewater management project - Institutional Development Consultant
Inception report of the Institutional Development and Capacity Building
TABLE OF CONTENTS
ACRONYMS
EM Electro-magnetic
VK Vodokanal
EXECUTIVE SUMMARY
In the frame of the IWMP, the IDC Consultant has started to gather information in order to perform a
transversal maturity assessment of the Karakol and Balykchy vodokanals. The first findings and
preliminary assessment are presented in this report, along with the IDC project objectives and revised
workplan designed to meet the objectives. The key points of this report are presented below:
WATER OPERATIONS
Thanks in particular to a high availability of resources, both Vodokanals are able to offer continuity of
service to their customers. Nevertheless, the culture of NRW reduction and preventive maintenance is
very slightly developed, and the tools, particularly in IT, are largely outdated. The project will therefore
endeavor to provide added value in the working methods and tools in order to improve the quality of
service and the operational performance of the Vodokanals.
The IDC Consultantproject team will propose solutions adapted to each Vodokanal, taking into account
their particular characteristics (production, metering, etc.) and a different organization in operations.
Both of the existing wastewater treatment plants are out of service in terms of biological treatment.
However, the use of primary settlement tanks, final oxidation ponds and mixing with river water should
allow the vodokanals to use wastewater for agriculture irrigation and to avoid output of contaminated
water in surrounding rivers and lake.
Upcoming investments financed by ADB will include new primary sewers and a new Wastewater
treatment plants in both vodokanals.
The Operations could be improved to increase network maintenance with little additional resources
(main equipment investments needed would be a combined sewer cleaning truck in Karakol) .
The Septage management, which concerns approximately 62% of the population in Karakol and 56%
in Balykchy, is currently not controlled or financed in Karakol, while in Balykchy the vacuum trucks are
controlled (discharge point at the WWPS), and the population is charged for the service.
FINANCIAL SUSTAINABILITY
Today (per 2021 results), neither vodokanal covers their costs of operations (respectively 47.8 million
KGS in Karakol and 24.4 million KGS in Balykchy) nor their selling and administrative costs from the
tariffs. As a result, we observe that Balykchy vodokanal relies on subsidies (11.7 million KGS in 2021)
to maintain a positive net profit (3.5 million KGS), while Karakol suffers a persistent loss (6.7 million KGS
in 2021).
Although some operational costs efficiencies are reflected in the financial results (e.g. operational costs
have decreased by ~4 millions between 2020 and 2021 in Balykchy), the upcoming increase in
operational expenses with the works on water and wastewater networks and the development of
wastewater treatment plants pose a further threat to the financial sustainability of the vodokanals unless
tariffs can be increased to compensate for these higher costs, or subsidies are increased.
The preliminary findings have shown that metering is unequal between the two vodokanals (almost
nonexistent in Karakol, covering half of the population in Balykchy) and that the vodokanals still rely
heavily on the application of the tariff norms per person, which could induce some errors in billing.
Additionally, it appears that both vodokanals are struggling to update tariffs regularly either due to
difficulties in calculating and applying for the tariff increase, or due to lack of approval by the relevant
authorities. The last tariff increase on water for domestic customers was in 2022 in Balykchy and 2021
for Karakol.
1.1 IWMP
The Issyk-Kul Lake and surrounding region, located in the east of the Kyrgyz Republic, represents a
nationally valuable environmental, economic and cultural asset. The lake, world’s second largest high-
altitude lake and a well-known tourist destination, has over 100 rivers and streams feeding it and is part
of UNESCO's Issyk-Kul Biosphere Reserve.
Project scope
The Issyk-Kul Wastewater Management Project (IWMP) is a part of a long-term initiative of the Asian
Development Bank (ADB) to support environmental management and improve the provision of urban
services in the Issyk-Kul oblast. Its main objective is to improve access to drinking water and safe
sanitation for the cities of Balykchy and Karakol with 3 main outcomes:
1. Improvement of wastewater disposal and treatment
2. strengthening the institutional and service-oriented capacity of Vodokanal Enterprise
3. Improvement of septage management and increasing awareness of the consequences for
public health
The total budget of the IWMP project (loan and grant) is 41.82 million USD, where investments are
mainly focused on the Output 1 of the project.
This project of Institutional Development & Capacity Building aims at developing the outputs 2 and 3.
The Consultant understands that the Vodokanals are not liable to the reimbursement of the ADB
loan (versus financial obligations in the frames of EBRD Project). Indeed,
● There is nothing in the loan agreement suggesting the liability for servicing the loan was passed
from the Ministry of Finance (on behalf of the government) to any other party including the
Vodokanals.
● The PMO head confirmed orally that the vodokanals have not entered into any other agreement
regarding the reimbursement of the loan.
However, the investments (new facilities and equipment) will increase operational costs (OPEX) related
to the operation of the new facilities and general improvement of services and performance of the
utilities.
Project area
The IWM Project is financed by the ADB and managed by the Executing Agency (EA): the Department
of Construction and Engineer Infrastructure (DCEI). The DCEI is under the State Agency for
Architecture, Construction, Housing and Communal Services, itself under the Cabinet of Ministers of the
Kyrgyz Republic.
The Beneficiaries of the IWM Project are the Vodokanals of Karakol and Balykchy, also called
Implementing Agencies (IA) according to the Loan Agreement between Kyrgyz Republic and Asian
Development Bank, Section 1.02. (c), (s), (j).
The Institutional Development and Capacity Building (IDC or the Consultant) reports to the Executing
Agency and works under the guidance of the IWMP Project Management Office (PMO). The IWMP PMO
includes the PMO Director, the Gender and Institutional Development Specialist, the Financial Manager,
the Procurement specialist.
In Balykchy and Karakol, the IDC works with the Project Implementation Offices (PIO) representing
Implementing Agency.
In Balykchy the IDC office is established on the premises of the Vodokanal in accordance with the ToR.
In Karakol the IDC Consultant office was opened at the address city of Karakol, 21 Tynystanova str.,
office 24
Consultant team
As soon as the Contract was signed, Seureca started mobilizing its team and experts in order to start
the Project early and meet the Project deadlines.
From the 20th to the 24th of February, a team composed of the key experts accompanied by non key
experts visited both Vodokanals, among them:
● The Area Manager and Contract Authorized Representative: Camille Hennequin
● The Team Leader (KE1): Bertrand Masure
● The Engineer in operation (KE2): Matthew Bullock
Prior to the inception mission, the IDC Consultant provided a data request table to the PMO, to be
provided to the Vodokanals. During the inception mission, the IDC Consultant team proceeded to the
collection of available documents and information.
Based on the first exchanges with the Vodokanals, a revised data request with priority documents has
been assembled and is presented in Appendix 2.
The Consultant highlights the importance of collecting the documents presented in the revised data
request sheet. These documents include (but not limited to) :
● Information on networks, equipments, meters available or planned in the investments;
● Reporting on operations and maintenance activities ;
● Information on quantities of water billed to help design the NRW action plan and calculate the
water balance ;
● Information on the structuration of the Vodokanal (organisation, number of staff, etc.) ;
● Further information on procurements planned as part of the ADB and EBRD projects ;
● etc.
Important point
Map of Karakol and the sites visited during the inception mission
It shall be noted that legal issues were discussed with the HR specialist who is coordinating legal issues
as the company does not have a position of legal specialist,. The position of a lawyer is foreseen in the
staffing of the enterprise, but there is no specialist.
During the meeting with the administrative staff of Karakol Vodokanal, it was revealed that it is necessary
to conduct an inventory of internal local documents and develop missing ones, as well as adjust existing
ones that do not comply with the current regulations and the goals and policies of the Company.
The initial visit allowed to identify some key points to be analyzed further and which will require
assistance of the Consultant:
● the organizational structure of the Company was developed in 2015, and needs to be updated,
● implementing the HR policy at the Company,
● review of the Company Charter and its amendment, if necessary,
● development of job descriptions for each position,
● review of the existing Public Service Agreement (PSA) - the PSA was developed and signed by
the Mayor's office and the Vodokanal, but the Company requested to review and provide
recommendations if required,
● water use regulations to update,
Considering all the collected documents, the Consultant will analyze in detail the work done by the
Company during the last years, analyzing all the existing positive and negative aspects, and will develop
an Action plan for institutional development within the framework of the current ADB financed Project.
The Consultant will review all available legal information obtained both from public sources and provided
by the vodokanals, as well as independently collected by the Consultant's staff. The Consultant will also
analyze Kyrgyz legislation in terms of national programs in the Kyrgyz Republic for development of
drinking water supply and sanitation systems in settlements, construction of water pipelines and
rehabilitation of centralized water supply and sanitation systems in settlements, as well as available
materials of legal topics in the field of attracting investments during 2015 - 2022 in the field of water
supply and sanitation prepared by international financial institutions.
All improvements in the institutional and legal environment in water supply and sanitation will be
developed in cooperation with representatives of Karakol vodokanal and PMO, taking into account the
best international experience and practices in the field of water supply and septage.
Normative legal acts regulating the work of the Municipal Enterprises of the Karakol Vodokanal
№ RLA Description
№ RLA Description
The Law regulates the financial and economic relations of local self-
Law of the government bodies of the city with state bodies, other local self-government
Kyrgyz bodies, legal entities and individuals, and also determines the procedure
Republic dated and principles formation and execution of the local budget and off-budget
September 25, funds of local governments:
2003 No. 215 Article 22 fixes the rights of local self-government bodies to create
3 “On the municipal enterprises;
financial and Article 23. regulates the relationship between the local self-
economic government body and the municipal enterprise or joint-stock company
foundations of established by it;
local self- Article 25 regulates the municipal order, which can be executed by a
government” municipal enterprise. The transfer of execution of the municipal order
is carried out under the contract.
Regulations on
setting prices
(tariffs) for
goods (works,
services) for the
entities
regulated by the This Regulations set the tariff setting procedures and agreement of the
5
state - tariffs calculations with the antimonopoly bodies
approved by the
Decree of the
Government of
the Kyrgyz
Republic No 83
of 18.02.2013.
Law of the
Kyrgyz
The Law defines the basic requirements of relations in the field of domestic
Republic, dated
6 drinking water supply to the population and ensuring the quality of drinking
March 25, 1999
water;
No. 33 “On
Drinking Water”
№ RLA Description
The Law of the Article 22-1, establishes the norms of sanitary and epidemiological welfare
Kyrgyz of the population.
8
Republic "On
Public Health"
Law of the The Law defines the main provisions of technical regulation in the field of
Kyrgyz environmental safety and establishes general requirements for ensuring
Republic environmental safety in the design and implementation of activities at
“General economic and other activities for the processes of production, storage,
Technical transportation and disposal of products. According to clause 4, Appendix 2,
10 Regulations for a definition of the hazard category is given for economic and other activities
Ensuring that discharge wastewater.
Environmental
Safety in the
Kyrgyz
Republic”,
№ RLA Description
dated May 8,
2009 No. 151
The Law of the The Law aims implementation of the rights of citizens to an ecological
Kyrgyz environment favorable for life and health, maintaining a unified ecological
Republic “On system biosphere territory "Ysyk-Kol" ("Issyk-Kul"), the importance of
water disposal protecting and preserving flora and fauna, as well as reducing the adverse
and treatment impact of wastewater on the environment, preventing pollution of the
facilities of the ecosystem of Lake Issyk-Kul, as a result of economic, commercial,
11
Ysyk-Kol” recreational and other activities related to the direct discharge of domestic
(“Issyk-Kul”) and other household wastewater into the Issyk-Kul lake, the entry and
biosphere seepage of a significant amount of polluted (not treated) domestic
territory, dated wastewater into surface, groundwater and Issyk-Kul lake.
August 17,
2020 No. 133
Decree of the
Government of
the Kyrgyz
Republic No.
The Decree regulates the protection of surface waters from pollution,
128 “On
clogging and depletion, when water users carry out various types of
Approval of the
economic activities that have or may have an adverse impact on the state
12 Rules for the
of surface waters, regardless of their organizational and legal form, and also
Protection of
regulate the procedure for implementing measures to protect surface
Surface Waters
waters.
of the Kyrgyz
Republic”,
dated March
14, 2016
Among other things, the activities of the municipal companies (Balykchy and Karakol Vodokanals) are
regulated by other legal regulatory acts of the Kyrgyz Republic, as well as the Company Charters that
fix the main aims and objectives of the municipal company providing the water and wastewater services.
Public relations
All the public awareness activities at the Company are coordinated by the Head of PIU of the Vodokanal.
There is a public relations specialist (Khomenko Alyona), who is hired on a contractual basis.
Within the framework of the EBRD CDP component, the Karakol Vodokanal is implementing a public
information program. The PIU of the Vodokanal informed that there is an approved program for media
and public awareness and the activities are planned for 2023.
The Consultant has requested the Karakol Vodokanal to provide a public information program to plan
the public awareness program within the objectives of ADB assignment.
2.2.1 INFRASTRUCTURE
Production:
In addition to the surface water sources, there are groundwater sources which are used primarily to
substitute the main surface sources when network pressure is low or there is a deficit of water at the
network extremities. The boreholes are exploited using Russian submersible pumps and pump to local
reservoirs. Second lift pump stations are then used to pump to the network. It is not clear what
contribution these boreholes make to overall water production as there are no water meters installed.
The condition of the boreholes and infrastructure (fencing, power supply) appears adequate but second
lift pump stations are generally in poor condition.
The pumps characteristics of the boreholes are presented in the following table:
The plant capacity is designed to be 18,000 m3/d with a daily maximum of 20,000 m3/d. At the time of
visit the inflow showing on the main SCADA was 688 m3/h (16,510 m3/d) with an outflow from the
reservoirs of 585 m3/hr. meter (turbidity was different in the SCADA and on the turbidimeter).
On entering the station, water enters a very small contact chamber where a dose of Alum and Chlorine
should be added. Immediately after this chamber the water enters a 3 train conventional rapid gravity
filter unit. The filtered water is discharged to 2 tanks from where water is distributed under gravity. There
is no secondary chlorination.
It is reported that backwashing takes place currently every 72 hours, which is quite long. The operator
explained that he can switch to the manual mode when the turbidity increases and performs the
backwashing each 10 to 15 hours.
Distribution system:
The system has 2 main reservoirs: the 2 tanks at the WTP and the Hippodrome one. There is a third
reservoir in Parkavaia but it is currently bypassed.
The network is 130 km long according to the initial version of the GIS. Nevertheless it looks
underestimated, the GIS will be updated during the project.
2.2.2 OPERATIONS
Operations:
The dispatch department is staffed by 3 people who ensure during 12 working hours daily operation of
phones to receive reports of problems (such as low pressure, no water, water quality problems) from
consumers. The report is detailed in a log book and then communicated to the maintenance teams (one
main team, another dedicated to the blocks/multi-storeyed buildings). The requested team will then visit
and either fix the problem or call back to the office for further support / equipment /materials, etc. The
log books indicated most problems are solved within 1 day. There are a significant number of leaks
reported, as well as lack of water as detailed below (figures for January 2023):
● 28 leaks,
● 11 bursts,
● 69 interventions for no delivered service (mostly due to a frozen connection).
Maintenance:
There appears to be low levels of preventive maintenance other than the removal of silt from the Karakol
river pond. Most maintenance is reactionary based on reporting of problems by consumers. These
reports are communicated to the dispatch department.
The Vodokanal has a functioning GIS system based on an old Postgre database and QGIS front end
which has been customized to prevent access to many GIS features. The GIS is installed on a local
server (in the production manager office) which does not appear to be backed up to a remote location.
GIS presentation
Network modeling was reportedly carried out by SECO. The former ADB financed project did not carry
out modeling activities. There is no record of the SECO model at the vodokanal.
Update:
The GIS of the Vodokanal has finally been exported successfully. It will be updated with the missing
projects of extension and verified by the IDC GIS expert (checking the topology, filling the missing
information as diameter, etc.).
The updated GIS will be the base to build the hydraulic model. The calibration will be basic due to the
lack of flow metering (Kaska Suu, boreholes pumping stations, customers, etc.) and pressure
measurements in the network. The software used for the modeling is Epanet, as suggested in the terms
of reference. It is internationally recognized, free and quite simple to use (important for the handover to
the vodokanals).
Non-revenue water:
There is no existing system for the calculation of non-revenue water. The lack of customer meters means
that actual consumption is impossible to determine and therefore estimated consumption is derived
using local norms (number of people, floor area, car ownership etc). Actual water supplied is recorded
using the surface water meters but any contribution by the groundwater pumps cannot be measured
and is difficult to estimate.
The network in the city suffers from poor pressure control, leakage and high levels of wastage due to
taps being left open in the belief this prevents freezing in winter. In summer, there is a high level of water
use for gardens and irrigation which is not currently served by the separate irrigation system. The lack
of domestic meters means there is no incentive to either close taps in winter or reduce irrigation water
use in summer.
There is no active leakage control although some support for leak detection and localization was
provided in the previous SECO project.
2.3.1 INFRASTRUCTURE
The current Karakol city wastewater network was built around 1980, in ceramic, asbestos-cement and
cast-iron materials. It covers the apartment block in the city, with a 110 km network. It works by gravity,
and ends with a 700 mm diameter pipe to the WWTP located in the valley of the Karakol river,
downstream of the city.
The WWTP is currently out of service, except one of the 3 primary settlement tanks (PST) and its sludge
extraction to one drying bed. The wastewater flows through the rest of the plant without any treatment.
It goes through a further radial settlement tank, then an outlet pond (1 out of 4), and then flows to a large
pond (1,5 Mm3) 3 km downstream where the wastewater is mixed with river water and stored during
winter to be used for irrigation during spring and summer. This way, there is no wastewater discharge
to the river, except a leak at the by-pass valve in the inlet chamber, but probably discharging to the 1st
outlet pond.
Another part of the Karakol wastewater system covers the Pristan network (apartment block in Pristan),
the wastewater being pumped to the WWTP through 3 WWPS in series (WWPS n°1 nearby the lake,
WWPS n°2 & n°3 on the way to the WWTP nearby the road access to Pristan). There is a 4th WWPS
at Prjevalsk quays (East side of Pristan) where an old industrial compound stands. This WWPS was
pumping the wastewater from the industrial compound and the local houses to the WWPS n°2. It is no
longer working and the residual flow is rather small (35 m3/day). The Karakol VK is working on a project
(ADB financed Project output 1(iii)) to install a receiving tank of 50 m3 to collect the houses' wastewater.
This tank will be emptied by vacuum trucks (also part of the ADB financed Project) which will deposit
the wastewater to WWPS n°2.
Pristan village is located on the shore of the Issyk Kul lake, with a risk of direct pollution in case
of WWPS n°1 malfunctioning, and with a part of the village without any wastewater system.
SECONDARY NETWORK
The ADB financed project (output 1 (ii)) as shown by the vodokanal and the Karakol PIO doesn’t
include a secondary network. This secondary network can’t be at the cost of the consumers (only
the final connections). It will be at the cost of vodokanal/municipality, but this has to be planned
quickly, if not the current extensions (primary network) will bring only a little additional income.
2.3.2 OPERATIONS
Utility van
The second brigade is run using 2 teams on shifts: The first team works
one week from 8am to 8pm, and then rests for a week, while the 2nd
team is on shift. This 2nd brigade operates with their vacuum truck.
Vacuum truck
The wastewater team does not have any high pressure devices. They only use sucking (vacuum truck)
and manual sewer cleaning rods. This equipment doesn’t provide an efficient service and rags are not
collected, which means that downstream blockages can occur. In fact, the number of blockages is very
high, between 5 and 6 per day, 150 to 200 per month, around 2.000 per year. For 110 km of sewer, the
blockage ratio is 18 blockages/km/year, while the industry best practices levels in Europe are between
0.5 and 3 blockages/km/year. There is no preventive cleaning of the sewage network, because of lack
of equipment. These very limited equipment lead to sewer “repair”, involving digging out the pipe, when
the team does not succeed to unblock the sewer. They perform 3 to 5 “damage repairs” per month.
When the problem is large, the 2 brigades join their forces, and can be mobilized also at night if required.
SEWERS CLEANING
We advise the Karakol vodokanal to purchase a combined sewer cleaning truck, to be able to
deal faster with blockages, and reduce their number by collecting the rags during unblocking. A
preventive cleaning plan should also be formed. International Best Practices (Veolia worldwide
and french water industry) stand that 20% preventive cleaning of the network should be sufficient
on average if well prioritized (using GIS). The Vodokanal told us that the purchase of the
equipment and trucks was planned.
The wastewater team leader each year produces a list of small investments required for the
following year, which is validated by the director. The 2023 list includes 10 operations (~40
manholes repairs, and ~600 meters replaced), which is quite a good level of pipe replacement and
a good practice, all being executed by the own wastewater team with the support of the excavator.
The operation of the Pristan wastewater system is delivered by the local manager which was not met
during the inception mission.
Septage management: One manhole on the network has been identified for septic sludge discharges
by the approx. 4 private trucks operating on septage, and for Vodokanal's vacuum truck. We have not
seen any trace of activities on that manhole. There is no Vodokanal control on that manhole, and
probably the trucks discharge elsewhere, hopefully on the sewage network and not in nature. There is
currently no contract between Vodokanal and the private companies, and neither any payment.
Negotiations are underway to conclude contracts with private individuals pumping septic sludge in
Karakol for the 2023 season.
2.4.1 CUSTOMERS
Water service
The Karakol vodokanal currently serves 19,368 domestic customers for water services, covering 48,165
inhabitants according to the database (2.48 inhabitants/household on average). The majority of
domestic customers have individual connections (only ~50 street taps, see detail below).
In addition to domestic customers, the Vodokanal serves 1,044 legal entities (or organizations).
Table : Split of customers from Karakol Vodokanal by category of water service (Source : Database
extraction “ВОДА 31.12.2022г. инв”.)
Households with connections to the water, wastewater and district heating networks 8%
Street standpipes 2%
Yard standpipes 0%
Wastewater service
7,427 customers are provided with wastewater services, accounting for 15,149 inhabitants according to
the database. We assume all these customers are also serviced in Water and included in the above
19,368 domestic water customers, but this should be confirmed by the Vodokanal as it does not appear
to be the case in the database extraction.
NB : The number of inhabitants registered in the database appears to be low (2 inhabitants/household
on average according to the database) compared to the national average of 4.4 inhabitants/household
(According to the National Statistical Committee of the Kyrgyz Republic).
Table: Estimation of the population potentially depending on septage management in Karakol (Source
: Extraction of the system : “СТОКИ 31.12.2022г”. инв.)
Percentage of
Number of customers
population
Access to [Water +
7,427 38%
Wastewater] service
Access to [Water]
11,941 62%
service
Total customers
19,368 100%
(Serviced with water)
Meters
The majority of customers do not have water meters. According to the Vodokanal, there are 400 to 600
meters currently deployed but the metering does not appear to be controlled or systematic. Indeed,
meter readings rely mostly on a declarative basis (customers providing meter reading by mobile phone
messaging or through a visit with limited control over the frequency and accuracy of these readings).
The company does not have a reliable map of the location of the meters nor monitor their condition on
a regular basis.
Tariff applied
As a result of the status on metering deployment, most customers are billed according to the norm
(estimation of water consumption per inhabitant) and the number of inhabitants per household. The main
usage norms in operation are as follows:
Consumption
Tariff (KGS/year/person)
(m3/year/person)
Karakol
Water Wastewater Water Wastewater Total
‘New’ apartment
without District 60.23 60.23 352.95 117.08 470.03
heating
Individual house
36.5 NA 213.89 NA 213.89
without WW service
According to the database, the average household is composed of 2 to 2.5 inhabitants (respectively
from water and wastewater data) which is lower than the average for Kyrgyzstan (4,4
inhabitants/household according to the National Statistical Committee of the Kyrgyz Republic) bringing
into question the accuracy of the database.
It is also surprising to see that the customer database presents only 48,165 inhabitants supplied with
water when the population of Karakol city is 87,000 and when the water coverage area is reported to be
very good.
Norms provide a better basis of estimation than no norms at all but are no substitute for the metered
measurement of actual water consumption. Reliance on norms when alternatives are available supports
(conceals) operational inefficiency and potentially the misuse of natural resources.
Collection
The cash collection rate calculated from the 2022 billing system extraction is 95.7% for domestic
customers and 100% for legal entities (detail below). However, this collection rate does not not reflect
accurately the proportion of bills settled in the same period as it also includes customers’ advance
payments and amounts to pay off debts from previous periods.
Overview
The financial management function is headed by a Chief Accountant and Chief Economist. The Chief
Accountant is responsible for the production of financial reports from the accounting system including
annual financial statements. He is also responsible for finalizing the sales figures for the month. The
Economist performs various management accounting tasks including forecasting and internal reporting
on costs. Revenues tend not to be combined with costs in regular reporting although they are compared
for tariff computations.
The current accounting and billing platform is the software system “BIS” (software name to be confirmed)
but such is the dissatisfaction with this system’s functionality that the company is in the process of
switching to the widely supported and more configurable “1C” platform.
The ADB financed the production of IFRS-compliant audited financial statements for the years 2019 -
2021. The statements for 2020 were presented as comparatives for the 2021 financial statements. The
2019 financial statements received an adverse audit opinion and the 2020 and 2021 statements were
qualified by the auditors in respect of a number of issues.
Financial performance
The financial results of the company for the period 2019 - 2021 based on the audited financial statements
prepared in accordance with IFRS are as follows:
From these results it is evident that revenues increased in 2021 following a 60% rise in tariffs for water
and wastewater for domestic customers only. Gross production costs were better managed in 2021 and
the subsidy from the municipality was increased in that year. Nevertheless, even with that higher cash
subsidy the tariff increase was insufficient to avoid an overall net loss for the year 2021. It should be
emphasized that the municipality had planned for the tariff increase to be insufficient to cover all relevant
operating costs being reluctant to increase tariffs beyond the percentage rise required under the EBRD
loan and grant agreements preceding the current ADB investment project.
The company does not have any long-term debt in its balance sheet and therefore does not currently
incur financing costs. Neither is it intended that the company will be required to service the debt received
from ADB under the current project.
Management letter
The auditors of the financial statements also set out their concerns about the company’s accounting
processes and internal controls in the form of a Management Letter. Management Letters are prepared
for those charged with governance to consider ways in which the processes and procedures behind the
production of financial statements can be improved.
The Management Letters drafted by the auditors Marka Audit contain numerous points of a technical
accounting nature, including examples of incorrect allocations of expenses in the accounting system or
miscalculations of transaction amounts. Most of the points found in the Management Letter for Karakol
vodokanal are more usually found in the audit working papers for resolution by the audit managers prior
to the signing off of the financial statements. The auditor’s recommendations based on the points raised
and the response of the company are recorded in tabular format as an attachment to the management
letter. Unusually, the auditor appears to advocate in the management letter accounting for water
resources extracted by the company as a commodity. Such a treatment would be inconsistent with
current international accounting practice.
It was highlighted by ADB that the Management Letter points may not have been fully understood by
the Company since they appear not to have been heeded and is considering engaging another advisory
firm to explain to the Company how they should respond to the issues raised in Letter. However, it is
not axiomatic that all of the advice given in that letter is appropriate. In particular, it is not correct to
recommend to a water operating company to account for water resources as a commodity and to qualify
financial statements on the basis of incorrect accounting for cost of sales as is the case in the audit
opinion accompanying the 2021 audited financial statements.
Budgetary controls
The company’s economist does not produce a full income and expenditure budget nor issue updated
surplus or deficit forecasts on a regular basis.
Internal controls
The billing is managed by the Chief accountant (both the Water and Wastewater service are on the
same bill). The Chief Accountant is also responsible for preparing the company’s financial statements.
While the Economist should be in a position to provide an independent view of the company’s finances
in this case she takes her cost and revenue data from the financial accounting system managed by the
Chief Accountant. Therefore, according to current arrangements there is insufficient segregation of
duties between the accounts and sales staff which could undermine management control over the
quality and accuracy of sales accounting and reporting.
Water Wastewater
Water and wastewater tariffs have been raised only twice in just over a decade: in 2012 and in 2021.
The municipal authorities have in the past imposed ceilings on domestic tariff increases (e.g. 60% in
2021). According to the 2021 financial statements the municipality paid a subsidy to the water company
to partially offset the deficit from operations.
The company’s cash flows related to its operation are not systematically forecast. The pervasive lack of
cash flow management renders the company blind to the consequences of failing to bill all users or, in
some periods, failing to collect cash from consumers when payments fall due. The company may rely
on help from the municipality to cover operational expenses in cases where the cash flow does not allow
to cover all expenses. Old thinking and practices from the past remain ingrained in current day practice.
The existing method of calculating the tariff borrows mostly from traditional practices focusing on the
main costs of supplying the service according to historical records flexed for the volume and price
changes anticipated in the following year in which the tariff will come into force. A margin is applied on
top of the total forecast cost base to arrive at a tariff per unit (m3) per type of customer. Where applicable
the tariff per customer type is adjusted to partially compensate for shortfalls in forecast revenue
occasioned by the ceilings imposed on domestic tariffs.
Balance sheet and cash flow items such as capital asset acquisitions, debt repayments and provisions
for expenses are not included in the company’s tariff computation. The 2017 relevant regulation on water
tariff computations (“On the procedure for pricing (tariffs) for water and wastewater utilities providing
population with drinking water and wastewater collection services”, No. 83) envisages the inclusion in
the normative profit gross revenue of costs for development and modernisation of the utility (such as
capital equipment), other obligations such as reimbursement of a loan and other expenses not related
to the main activity (such as contingencies and provisions for future expenses including bad debt write
offs and exchange rate losses). None of these are currently considered for inclusion in the tariff
computation.
Balykchy is a city located at the western end of Lake Issyk-Kul. It has a population of approximately
51,500 inhabitants.
In conformity with the staff list the Comapny is composed of 84 employees. In fact, as of March 10,
2023 Vodokanal has 76 employees.
The Vodokanal operates about 175 km of water network and 64 km of wastewater network.
Map of Balyckhy and the sites visited during the inception mission
Considering the collected documents, the Consultant will review in detail the Company performance for
the last years, focusing on the existing positive and negative aspects, and will develop an Action plan
for institutional development within the framework of the current ADB financed Project.
The Consultant will analyze all available legal information obtained both from public sources and
provided by the Company, as well as independently collected by the Consultant's staff. The Consultant
will also review Kyrgyz legislation in terms of national programs for development of drinking water supply
and sanitation systems in settlements of the Kyrgyz Republic, construction of water pipelines and
rehabilitation of centralized water supply and sanitation systems in settlements of the Kyrgyz Republic,
as well as available materials of legal topics in the field of attracting investments in the Kyrgyz Republic
during 2015 - 2022 in the field of water supply and sanitation prepared by international financial
institutions.
All improvements in the institutional and legal environment in water supply and sanitation will be
developed in cooperation with representatives of water companies of Balykchy city and PMO, taking
into account the best international experience and practices in the field of water supply and sanitation.
Normative legal acts regulating the work of the Municipal Enterprises of the Balykchy and
Karakol Vodokanals
№ RLA Description
№ RLA Description
The Law regulates the financial and economic relations of local self-
government bodies of the city with state bodies, other local self-
government bodies, legal entities and individuals, and also
Law of the Kyrgyz determines the procedure and principles formation and execution of
Republic dated the local budget and off-budget funds of local governments:
September 25, 2003
Article 22 fixes the rights of local self-government bodies to
No. 215 “On the
3 create municipal enterprises;
financial and
Article 23. regulates the relationship between the local self-
economic foundations
government body and the municipal enterprise or joint-stock
of local self-
company established by it;
government”
Article 25 regulates the municipal order, which can be
executed by a municipal enterprise. The transfer of execution
of the municipal order is carried out under the contract.
Regulations on setting
prices (tariffs) for
goods (works,
services) for the
entities regulated by This Regulations set the tariff setting procedures and agreement of
5
the state - approved the tariffs calculations with the antimonopoly bodies
by the Decree of the
Government of the
Kyrgyz Republic No
83 of 18.02.2013.
№ RLA Description
№ RLA Description
Decree of the
Government of the
The Decree regulates the protection of surface waters from pollution,
Kyrgyz Republic No.
clogging and depletion, when water users carry out various types of
128 “On Approval of
economic activities that have or may have an adverse impact on the
12 the Rules for the
state of surface waters, regardless of their organizational and legal
Protection of Surface
form, and also regulate the procedure for implementing measures to
Waters of the Kyrgyz
protect surface waters.
Republic”, dated
March 14, 2016
Among other things, the activities of the municipal companies (Balykchy and Karakol Vodokanals) are
regulated by other legal regulatory acts of the Kyrgyz Republic, as well as the Company Charters that
fix the main aims and objectives of the municipal company providing the water and wastewater services.
Public relations:
There is no PR specialist in the company. All the public awareness activities are coordinated by the
Head of the PIU of Balykchy Vodokanal.
Previously, under the EBRD Project the Company contracted “Grant Thornton” as a Consultant for CDP
(corporate development project). Grant Thornton's contract has been completed. Within the framework
of the CDP contract, Grant Thornton developed and implemented a public awareness program. However
Balykchy Vodokanal noted that the public awareness program results did not fully meet the Company's
initial expectations.
As part of the ADB assignment, the Consultant is going to review the plan of activities performed within
the framework of previously completed Projects in the Company and taking into account all pros and
cons previously encountered by the Company, the Consultant will develop a public awareness program
within the framework of the ADB assignment.
3.2.1 INFRASTRUCTURE
Production:
Water Supply in Balykchy is primarily from groundwater sources, with a small contribution from a surface
water source:
● The main intake comprises 7 boreholes which pump to a local reservoir (reservoir 1).
● 8 other boreholes across the city complete the underground production. 7 have been
rehabilitated by the ADB financed project and 1 new borehole was drilled. All the boreholes are
connected directly to the network and are reportedly used when there is a water deficit in the
network, likely indicated by low pressure.
● Finally, there is a surface water source to the North, at around 8 km from the city. This source
feeds directly the highest part of the city, and reservoir 3. The source is captured from a river
descending from the mountains and goes through 2 reservoirs, the first for primary settling and
the second for distribution. Before joining the distribution network and reservoir 3 there is a
break pressure tank.
There is virtually no treatment of any water entering the network. Some rehabilitated or replaced
boreholes have basic chlorination systems and / or bactericide systems using UV lamps. No chlorination
system was operational at the time of visit.
Distribution system:
From reservoir 1, a 2nd lift pump station pumps water to the main reservoir at the vodokanal main site
in the city (Reservoir 2), and 2 other smaller reservoirs (called 4 & 5). From reservoir 2, another pump
station can lift water to reservoir 3, which serves the higher areas of the city. Currently reservoir 3
receives surface water from the source.
At reservoir 3, there is a pumping station in construction, with the objective of lifting water to the areas
currently feeded by the source, and then being able to abandon this resource. The pertinence of
abandoning this resource will be checked.
3.2.2 OPERATIONS
Operations:
The dispatch department ensures 24/7 operation of phones to receive reports of problems (such as low
pressure, no water, water quality problems) from consumers. The report is not recorded but information
is communicated to the maintenance team. The team will then visit and either fix the problem or call
back to the office for further support / equipment /materials etc. Problems are summarized into a 6
monthly report.
The Vodokanal staff appear to be responsive to pressure data and switch on only those pumps which
are required to ensure continuity of service.
Maintenance:
There appears to be low levels of preventive maintenance. Most maintenance is reactionary based on
reporting of problems by consumers. These reports are communicated to the dispatch department.
The Vodokanal has a functioning GIS system based on an old Postgre database and QGIS front end
which has been customized to prevent access to many GIS features. The GIS is installed on a local
server (in the deputy director office) which does not appear to be backed up to a remote location.
The GIS is not updated to reflect changes in the network and no facility exists for network problem
reporting asset management analysis or similar ongoing overview of the network. A desire for the
dispatch department to have access to the GIS was mentioned by the deputy director.
Network modeling was carried out under the old ADB financed project but this was not institutionalized
and no local copy was found, no staff able to operate the model or software.
Update:
The GIS of the Vodokanal has finally been exported successfully, and the consultant confirms that it has
not been updated since its installation in the Vodokanal. It will be updated with the available information:
currently only the EBRD financed project of rehabilitation and extension (2020). The ADB financed
project (Kumtor Borehole and connection to the existing network) and the list of rehabilitations made
internally have been requested to the Vodokanal but not provided.
After this step, the GIS will be verified by the IDC GIS expert (checking the topology, filling the missing
information as diameter, etc.), but the GIS quality looks very good.
The updated GIS will be the base to build the hydraulic model. The calibration will be basic due to the
lack of flow metering (many flowmeters are not working anymore) and pressure measurements in the
network. The software used for the modeling is Epanet, as suggested in the terms of reference. It is
internationally recognized, free and quite simple to use (important for the handover to the vodokanals).
Non-revenue water:
● DMA:
A beginning of NRW strategy has been developed under the previous ADB financed project.
In fact, it is reported that at least the main network (feeded by reservoir 2) is operated as one pressure
zone and then there is no consistent pressure management of the network.
● Metering:
Water meters with data loggers have been installed. There is a mix of mechanical meters with digital
readouts (mostly at boreholes at reservoirs) and battery powered electromagnetic (EM) meters in the
network.
Nevertheless, most of the meters were running until at least 2019 and this may have provided sufficient
data to allow better network operations.
Most of the data loggers do not have the pressure transducer connected. The loggers are also likely to
have flat batteries. It was not possible to determine if data was captured as the download cable (to
connect loggers to a computer) could not be found.
Customer metering: Domestic water meters have been installed in over 50% of connections. Staff has
reported that water demand has significantly reduced following water meter installation (but without
figures to justify).
● Leak detection:
The Vodokanal has a full equipment for leak detection in its warehouse but they never used it
(acoustic - leak noise - correlator, ultrasonic flowmeter, pipe
detector, ground microphone / listening stick etc.). The staff who
received the training under the previous ADB financed project
left the company quickly after.
● NRW calculation:
There is an existing system for the calculation of non-revenue water although this is based on norms
and estimates and is not compliant with an internationally recognised method. For many consumers the
lack of meters means that actual consumption is impossible to determine and therefore estimated
consumption is derived using local norms (number people, floor area, car ownership etc). The method
currently used determines some form of loss value using the total production less allowances for fire
flow, meter inaccuracy and domestic usage. There is no reference to the actual amount of water sold
(volumetric or monetary). Given the lack of working meters, the production volumes should also be
treated with some caution.
There is no active leakage monitoring, detection or control in evidence although staff expressed their
understanding and willingness to improve these activities.
3.3.1 INFRASTRUCTURE
Network
The current Balykchy wastewater network was built around 1985. It covers the apartment blocks in the
city, with a 64 km network. It works by gravity down to a central WWPS nearby the lake, and then the
wastewater is pumped with two 500 mm diameter PEHD pipes to the WWTP located nearby the road to
Bishkek (5,7 km from WWPS n°1).
SEPTAGE MANAGEMENT
The 1st manhole inside the perimeter of the WWPS is equipped with a screening basket and is
used for septage truck discharge. There are currently 6 septic tank vacuum trucks (3 m3) operating
in the city (3 private, 2 vodokanal and 1 municipal). They all discharge at the WWPS through a
contract (except for the vodokanal’s truck). They buy vouchers at Vodokanal to be authorized by
the WWPS operator to discharge (around 75 to 80 KGS/truck). The contract specifies the obligation
to come and discharge at the WWPS. If there is discharge anywhere else, a fine is provided for in
the contract at 100 times the normal cost. It is dissuasive and non-authorized discharges are
reported to never happen.
The second manhole before the emergency tank is equipped with a screen from which rags are removed
manually. The entry at the wet well of the WWPS is equipped with another screen and a chewer. It is
not clear if the 2 equipments are in series or in parallel. The screen doesn’t seem to be used much.
The WWPS has 4 grundfos pumps installed in the dry well. Their flow is 250 m3/h with around 20 m
head. Only one pump works at a time. They are controlled by a level transmitter. The control levels are
1,25 m and 1,73 m. There is a possibility of reversed pressure water for mixing the well, but they don’t
seem to be used. We noticed some vibration and noise which could be a cavitation issue. This should
be investigated in order to avoid premature damage on the pumps.
WWPS SECURITY
In addition to the existence of the 2,000 m3 emergency tank, and of the redundancy of 4 pumps,
the WWPS is connected to 2 mains lines on the electrical network, and will soon have an
emergency generator ready to substitute for the electrical network.
Even if currently the “treated” wastewater is used for irrigation without a tariff, considering the
high quality of treated wastewater achieved with such a WWTP (full process including carbone,
nitrogen and phosphorus removal, and final disinfection), we could think about establishing a
price for the use of this water for irrigation.
● (ii) The construction of 11 km of new sewers. These new sewers are the primary network in the
West of the city (houses quarters).
● (iv) The desludging of oxidation ponds nearby the Tchou river.
● (v) The procurement of 3 sewage vacuum trucks.
MASTER PLAN
There is a Master Plan for the wastewater services in Balykchy, with the objective of achieving
80% of water customers connected to wastewater. In the frame of this master plan, it will be
important to develop further projects with the secondary network to bring significant additional
revenue to the Balykchy VK. If not, the ADB financed project will not bring sufficient additional
revenues. Be careful that 4.200 m3/day capacity of the new WWTP corresponds to around
30.000 inhabitants, which is slightly below 80% of the population, which is the overall objective
for wastewater services coverage.
3.3.2 OPERATIONS
Wastewater operations are managed directly by the chief engineer with one brigade of 4 people (1 driver
+ 3 workers) operating with the new high pressure jetting (300 bars) combined vacuum sewer cleaning
truck 6x4 (2022). The team works from 8 am to 5 pm Monday to Friday. If there is an emergency, they
are called.
The team deals with blockages and preventive cleaning. During summer (from March to November) they
perform around 15 to 20 unblockages a month (2 to 3/month during the 2 months of winter - December
to February), and between 200 and 300 meters/day of preventive cleaning. Their equipment allows a
high efficiency of unblockages (with rag removal). They carry out preventive cleaning upstream to
downstream systematically, with no prioritization.
The number of unblockages dropped down since they are operating with the new truck. In 2022, their
number was 611, and 448 in 2021. It seems to be less than 200 nowadays (with sewers preventive
cleaning), and at the level of best international practices (0,5 to 3 unclokages/km/year - 3 in Balykchy).
SEWER CLEANING
Considering the length of the network, the Vodokanal team could clean the whole sewage
network in less than 2 years. The international best practices stand around every 5 years on
average. There is some margin for optimization. They could sell services for septage, or for
external sewage networks (other vodokanals or non domestic customers).
The company seems to operate the 2 old vacuum trucks for septage services, but only occasionally for
public administrations. They could organize teams to exploit them in a more commercial way.
They also have a high pressure truck no longer used. This small truck could be sold to a smaller
vodokanal.
3.4.1 CUSTOMERS
Percentage of
Balykchy Number of customers
population
Access to Wastewater
4,658 44%
service
Total customers
10,644 100%
(serviced with water)
In addition to domestic customers, the vodokanal serves organizations (or legal entities, both private or
public) which amount for ~25% of the billed water (as shown in the table below).
Table : Split of the water billed in 2022
Metering
The deployment of meters has reached approximately 58% of domestic customers and the majority of
organizations. Out of the 7,200 meters deployed during the EBRD project (number to be confirmed),
6,127 meters are currently installed and registered in the database. Customers often have more than
one meter when living in apartments (one in the kitchen, one in the bathroom). In total, 3,908 customers
are currently billed based on meter readings and among them, 3,020 are served with both water and
wastewater service.
The controllers of the customer department read customer meters every month and provide them to the
head of the commercial department for billing computation. They perform a control check based on the
last meter reading to make sure that the meters are working properly.
Tariff applied
The tariff currently in operation are as follows:
Table : Tariff applied in Balykchy in 2022
4.53
Domestic 9.6
planned increased in 2023 to 9.06
Organizations 30 25.49
Collection
The 2021 audited financial statements showed that the debtor repayment period (one of the key financial
covenants listed by the ADB Loan Agreement) was 60 days compared to the target set by the financial
covenants in the ADB loan and grant agreements for that year of less than 90 days.
In the end of 2022, the total debts accumulated for domestic customers amounted to 5,107,238.64 KGS,
which represents approximately 35% of the annual billed amount for domestic customers (14,688,285
KGS billed in 2022 to domestic customers for the water and wastewater service, according to the
extraction of the billing system).
As with Karakol Vodokanal, the financial management function at Balykchy vodokanal is headed by a
Chief Accountant and Chief Economist. The Chief Accountant is responsible for the production of
financial reports from the accounting system including annual financial statements. The current
accounting and billing platform is the software system “1C”. Finance staff have a reasonable knowledge
of this programme but in general IT skills require improvement.
The ADB financed the production of IFRS-compliant audited financial statements for the years 2019 -
2021. The 2019 financial statements received an adverse audit opinion and the 2021 statements were
qualified by the auditors in respect of a number of issues. The basis for the audit qualification in 2021
was that water cost of sales was incorrectly calculated. This is, however, an invalid basis for an audit
qualification not least because it is based on the false premise that water resources should be
recognised as an asset in a water company’s balance sheet prepared under international financial
reporting standards.
Financial performance
The financial results of the company presented in accordance with IFRS are as follows:
Table : Main Financial figures of Balykchy vodokanal
Other income 80
The above table summarises the results shown in the audited IFRS financial statements prepared by
the audit firm ‘Marka Audit’. From these figures it is clear that revenues did not increase significantly
over the three year period. In fact, there was a slight decrease in revenue from operations between 2020
and 2021. The company nevertheless posted a net profit before tax in 2021 by virtue of improved
operating cost control, avoidance of fines and an increase in subsidies paid to the company by the
municipality.
Management letter
The auditors of the financial statements also set out their concerns about the accounting processes and
internal controls in the company in the form of a management letter. Management Letters are prepared
for those charged with governance to consider ways in which the processes and procedures behind the
production of financial statements can be improved.
The management letters drafted by the auditors Marka Audit contain numerous points of a technical
accounting nature, including examples of incorrect allocations of expenses in the accounting system or
miscalculations of transaction amounts, many of which are more usually found in the audit working
papers for resolution by the audit managers prior to the signing off of the financial statements. The
auditor’s recommendations based on the points raised and the response of the company are recorded
in tabular format as an attachment to the management letter. Unusually, the auditor appears to advocate
in the management letter accounting for water resources extracted by the company as a commodity.
Such a treatment would be inconsistent with current international accounting practice.
It was highlighted by ADB that the management letter points may not have been fully understood by the
company since they appear not to have been heeded and is considering engaging another advisory firm
to explain to the company how they should respond to the issues raised in the letter. However, it is not
axiomatic that all of the advice given in that letter is appropriate. In particular, it is not correct to
recommend to a water operating company to account for water resources as a commodity and to qualify
financial statements on the basis of incorrect accounting for cost of sales as is the case in the audit
opinion accompanying the 2021 audited financial statements.
Budgetary controls
The company’s economist does not produce a full income and expenditure budget nor issue updated
surplus or deficit forecasts on a regular basis.
Internal controls
Customer billing is effectively controlled by the Chief Accountant although the head of the commercial
department is responsible for printing and distributing the individual bills. The Chief Accountant is also
responsible for preparing the company’s financial statements. While the Economist should be in a
position to provide an independent view of the company’s finances in this case she takes her cost and
revenue data from the financial accounting system managed by the Chief Accountant. Therefore,
according to current arrangements there is insufficient segregation of duties between the accounts and
sales staff which could undermine management control over the quality and accuracy of sales
accounting and reporting.
Water and wastewater tariffs have been raised several times in just over a decade. The municipality
pays a regular cash subsidy to the water company to partially plug any funding gap. As with Karakol,
Balykchy water company does not systematically forecast the cash flows related to its operations. The
pervasive lack of cash flow management renders the company blind to the consequences of failing to
bill all users or, in some periods, failing to collect cash from subscribers when payments fall due. An
agreement on the provision of public services has been drawn up with the Mayor's Office of Balykchy.
APS. Where it is said, the Contractor (Vodokanal) has the right to apply to the Customer (Mayor's Office)
with a claim for compensation for losses in the amount of expenses incurred. I.e. if the tariff does not
correspond to the prime cost. At the same time, the mayor's office partially covers the difference in the
tariff. The received funds the BME "Vodokanal” uses strictly for its intended purposes, i.e. to pay current
bills for the used electric energy and to pay credit obligations. The enterprise's own funds are used for
the salary and other operating costs..
The existing method of calculating the tariff borrows mostly from traditional practices focusing on the
main costs of supplying the service according to historical records flexed for the volume and price
changes anticipated in the following year in which the tariff will come into force. A margin is applied on
top of the total forecast cost base to arrive at a tariff per unit (m3) per type of customer. Where applicable
the tariff per customer type is adjusted to partially compensate for shortfalls in forecast revenue
occasioned by the ceilings imposed on domestic tariffs. It is not clear whether fully accrued financing
costs (such as interest payments on foreign debt which does exist in the company’s balance sheet) are
also included in the cost-plus tariff calculation.
Balance sheet and cash flow items such as capital asset acquisitions, debt repayments and provisions
for expenses are not included in the company’s tariff computation. The 2017 draft of the relevant
regulation on water tariff computations (“On the procedure for pricing (tariffs) for water and wastewater
utilities providing population with drinking water and wastewater collection services”, No. 83) envisages
the inclusion in the normative profit gross revenue of costs for development and modernisation of the
utility (such as capital equipment), other obligations such as reimbursement of a loan and other
expenses not related to the main activity (such as contingencies and provisions for future expenses
including bad debt write offs and exchange rate losses). None of these are currently considered for
inclusion in the tariff computation.
NB : Balykchy staff informed that from April 1, 2023, the tariff for the population to receive wastewater
will be applied to increase by 100%.
Reference to the Terms of Reference : 2. B. Scope of work, Section 5 items i) xv) xviii) xix) xx)
Experts responsible: Team leader (Bertrand Masure), Financial expert (Adrian Joliffe), NRW expert
(Matthew Bullock)
ADB pointed out that the Institutional Development Consultant (IDC) must work with a holistic approach
to support Vodokanals in their overall development.
The Corporate Business plan will be delivered in the form of an action plan separated into priority actions
on which the Consultant will provide support for the duration of the Project and suggests medium term
actions to be implemented by the Company outside of the IDC support.
The objective of the Corporate business plan is to provide the utilities with a tailored strategy, adapted
to the specificities of each utility and based on an assessment of knowledge, technical capacity,
structuration of staff and processes, performance, and geographic context.
The Corporate business plan explains where the overall business should be headed by identifying the
main issues to address for each main activity of the company and how to address them.
The program will include transversal actions including actions on the update of the commercial database
(item xv).
IDC will provide a time-bound action plan in improvement of the financial indicators of Vodokanals
related to the loan agreement including quantitative impact of each action to the particular financial
indicator and cost estimate, when it is possible to estimate for the implementation of each action (item
xviii).
Although the preliminary financial implications of the suggested actions will be presented in this first
Report (R1) the validation of the suggested action plan will be required before the submission of the
finalized financial projections which will be provided in Report 3. (item xix)
The financial projections will be accompanied by the calculation of financial and economic internal rate
of return of the project (item xx, provided in Report 6) and subsequent training sessions on financial and
economic assessment/reevaluation.
The Consultant has suggested to postpone the submission of Report #3 (containing the financial
projections) to allow time for review and validation of the Action Plan before the finalization of the
Financial Model.
Additionally, IDC will provide an assessment of the needs of Vodokanals in additional equipment, special
machinery, etc. to support operation and maintenance unit, as well as to prepare technical specifications
for them for the tender (item xvii).
Reference to the Terms of Reference : 2. B. Scope of work, Section 5 items ii) iii)
Experts responsible : Financial expert (Adrian Joliffe) and Local financial expert (Radion Diukov)
The Consultant will develop a tariff roadmap for both Vodokanals designed to identify a transition path
towards greater financial self-sufficiency. The roadmap will be linked to the recommended tariff
computation methodology which itself will be based on best practice and the relevant legislative
framework. The recommended measures in the tariff roadmap, including the timing and rate of tariff
changes per customer type, will be fully aligned with the companies’ long-term financial projections that
are also a requirement of the ToR of this Project
The approval of the tariff roadmap by the municipalities and the preparation and approval of related tariff
increases will depend on the Vodokanals. The Consultant will not be held liable should the municipalities
decide not to approve the roadmap.
The tariff roadmap will be implemented through a continuous support of the Vodokanals aiming at
facilitating the approval of the 2024 tariffs in line with the tariff roadmap. If successful, the companies
would use the lessons learned from the 2024 increase to independently implement the tariff roadmap
outside the period of consultancy support.
According to the Terms of Reference, the Consultant will start determining an initial water balance with
the available data, fitting as much as possible with internationally recognized methods. It will be a base
to analyze the level of water losses, physical and commercial. The Consultant will continue building a
program of NRW reduction adapted to the situation and equipment of each Vodokanal.
In parallel, the Consultant will build a hydraulic model, calibrated with the available data, creating an
additional tool to help the Operations team to make good decisions, particularly in pressure
management.
A first division of the network in several district metered areas will also be proposed by the Consultant.
The process will involve training and assistance all along the Project to ensure the good implementation
of the proposed Actions Plan.
During the inception mission, the Consultant has reviewed the organization of septage sludge collection
and discharge.
Holistic septage management also covers septic tanks construction controls (including specifications),
and periodic controls of existing septage tanks. It can also include compliance works campaigns of
septic tanks with public grants, managed by the Vodokanal.
Revision of the existing legislation will be the 1st step of this septage program elaboration.
Reference to the Terms of Reference : 2. B. Scope of work, Section 5 items vii) viii) xi) xii)
Experts responsible: All experts
The Consultant will develop a training plan in accordance with the Corporate Business plan actions. The
main objective of the training plan is to develop the human capacity of Vodokanals’ staff working on
water, sanitation, customer services, support and cross-functional processes.
Following the diagnosis phase and the missions of the IDC experts, training needs will emerge for the
short term (to ensure effective usage and operation of the new assets to be procured or built) and for
the long term (make the Vodokanals able to develop a training policy to ensure future continuous
improvement). These training programs will be detailed in a Training needs assessment (item vii) in
Report 2. The training plan will be conducted between validation of the training plan (i.e.June 2023) and
December 2023.
All training deployment techniques will be considered and proposed based upon the expected output:
Theoretical training as well as On-the-job training.
● Theoretical training : Theoretical knowledge serves as a basis before doing anything practically.
Some of the training will be performed by the international and national experts, and some
others will be directly provided by an international training centre (OiEau).
● On-the-job training : On-the-job training is a practical approach to acquire new competencies
and skills needed for a job in real training experience. Rather than showing employees
theoretical presentations, they learn about the job they are doing by cooperating (working side
by side) with the international counterparts.
Additionally, IDC will propose an international approach on the training plan through :
● A twinning agreement with a utility within the framework of Veolia operations;
● An International training in collaboration with the International Office for Water (OiEau). The
certified courses will be provided either in Kyrgyzstan or OiEau Training Centre. OiEau core-
activities deal with the development of skills for better water management in France, in Europe
and worldwide. In the field of water and its related activities, OiEau facilitates exchanges
between the various decision-makers, designers, managers, industrialists, trainers, researchers
and users concerned, in order to better face together their problems, coordinate their actions
and disseminate their information. The minimum number of employees within international
training per each city is 6 people, half of whom shall be women.
Reference to the Terms of Reference : 2. B. Scope of work, Section 5 items xiii) xvi) and xxi)
Experts responsible : Institutional expert (Azamat Kasymov) and PR experts (Local team)
IDC will support in organizing public awareness and outreach programs through mass media on themes
agreed with the IAs; media coverage on hygiene, environmental sanitation and other relevant areas
based on a Gender Action Plan (GAP) and a Program to Ensure Public or Local Community Participation
with Stakeholders (PECPSH) (item xiii).
As part of item xvi) and in connection with the targeted measures of the Corporate business plan , IDC
will work with the Vodokanals and the relevant stakeholders (municipalities, legal entities, etc.) to
prepare/update legal acts with the aim of clarifying the corporate relations, empowerments, roles and
responsibilities for a smooth and efficient implementation of water supply services to the population and
other final customers. The legal acts considered in the frame of the project will include only those that
already exist and that shall be in the Vodokanals by local legislation, i.e.: Company Charter if it needs
to be updated, Public Service Agreement (PSA) with municipality, standard contracts with legal entities.
● The legal acts should provide the appropriate incentives for the Vodokanals and their
management to achieve the objectives set out in the legal act and hence include the following:
● Definition of tasks and responsibilities between the parties to the Agreement;
● Basis for the right of the Service Provider to use the physical infrastructure and their obligations
and responsibilities regarding its use, as well as maintenance and replacement of assets;
● Technical actions and corresponding Key Performance Indicators (KPIs) to improve water
supply/Wastewater services;
● Tariff implication.
● IDC will also identify appropriate monitoring mechanisms and tools for performance review and
contract monitoring by the City of Karakol and Balykchy.
IDC will provide support to the relevant body in circulating draft RLA with government bodies and
approving them by the Cabinet of Ministers of the Kyrgyz Republic (if necessary).
Additionnally, IDC will focus on exchanging with the involved organizations (EBRD consultants, etc.)
with the support of the PMO team in order to harmonize and not duplicate the consulting services
provided to vodokanals (item xxi).
The Action plan (according to the submitted form) of the IDC with regards to the GAP will be provided
in Report n°1 and reporting on GPA activities in accordance with the Work Plan. .
Inclusivity is critical to the success of all the tasks of this project from a gender perspective. arly in the
process, a gender approach will be initiated for the development of the Capacity Building Program, and
of the Public Awareness and Outreach Program.
4.2 WORKPLAN
In the following, the consultant will suggest a review of the Work Plan and schedule of deliverables,
based on the comments above.
In the Technical offer, the Consultant has phased the Work Plan in 3 phases :
● Inception phase with mobilization and first introduction to the Vodokanals ;
● Actions plan development phase for deeper assessment of the Vodokanal maturity,
identification of priority actions and evaluation of their financial implications ;
● Implementation phase with implementation of the training plan and transversal action plan
through continuous support to the Vodokanals.
Ph 1 Ph 2 Ph 3
Mobilisation &
Kick Off Corporate Business Plan Assistance on Program /Action Plan
Data Collection &
Implementation
Tariff and Financial indicators
Review GAP
Non-revenue Water Reduction
Initial Situation
Analysis Septage Management
Inception
Workshop
Preparation of
Capacity Building & Training
After having visited both Vodokanals, discussed with their teams, reviewed the initial data and carefully
reviewed the Terms of Reference, the Consultant proposes to adapt the initial workplan in order to best
fit the Project's needs, to best serve the Vodokanals interests and to improve the efficiency of the action
plans and capacity building throughout the 2 years of the Project.
The paragraph below details the content of each Project deliverable and the proposed adjustment of the
timeline. The main reasons for these changes are:
● Leaving time for the discussion and approval of the action plans before starting their
implementation,
● Adjusting the training delivery to the Vodokanals availability and the evolution of the Vodokanals
all along the project,
● Spreading the Consultant inputs on the 2 years duration of the Contract so that the support to
the Vodokanals can be provided through time and not one shot.
The graphs below present a summary of the Project timeline as initially planned in the ToR and the
optimized timeline proposed by the Consultant (highlighting the changes in red).
Table of Deliverables
ToRs Amendments
Report №2
No later than 120 days from the
3 Documents to be submitted – para 7 (vi), 7(vii), 7(viii): contract signing date 02/06/2023
Report №3
Documents to be submitted – para 7(ix), 7(x), 7(xi), part of No later than 120 days from the Submission date is postponed to allow time for the review
4 7(xii), part of 7(iv): contract signing date of the action plans suggested in Reports 1 and 2. 25/08/2023
Report №5
No later than 210 days from the Submission date is postponed to give time for validation
6 Documents to be submitted contract signing date and implementation of the action plan 07/12/2023
No later than 270 days from the Changes : Progress report 1 moved postponed to give time
7 1. Progress Report 1 contract signing date of validation and implementation of the action plan 23/11/2023
*: the text in red in this table highlight the changes proposed compared to the ToR
This inception Report presents the first findings observed by the Consultant and the resulting update of
Project workplan, scope and timeline proposed to best suit the Vodokanals needs and reach a
successful project delivery.
Following the Inception Report submission, the Consultant will immediately continue with the preparation
of the next assignments, and particularly Reports 1 and 2, which contain the following tasks:
● Report 1:
○ a Corporate business plan for each Vodokanal
○ a program on reduction of non-revenue water (NRW), including the water balance, a
GIS update, a network modeling, and recommendations (action plan),
○ a technical capacity enhancement assessment,
○ A robust timebound action plan agreed with the Vodokanals to achieve financial
covenants by IA.
○ Gender Action Plan (GAP) - plan and schedule in conformity with the provided format.
● Report 2:
○ a tariff Road Maps for each Vodokanal,
○ a septage Program (in Kyrgyz, Russian and English);
○ a training needs assessment.
The Consultant will complete the data collection in collaboration with the Vodokanals and the PMO,
and mobilize the local partner to achieve this task through on site visits as much as necessary. Indeed,
as described in the introduction of the Report, the Consultant is awaiting additional documents (in digital
format) in order to perform a complete holistic assessment of the Vodokanals. As previously presented,
the Consultant prepared a data collection table (see Appendix 2). A strong support is expected from the
Vodokanals and the PMO team in order to collect all information. One of the key data for improving the
IDC performance and usefulness are the reports from other Consultants and programs, among which
the ERBD CDP Consultants reports and the WWTP related studies.
The IDC Team Leader and Local Project Coordinator will visit Karakol Vodokanal and PIU on the
16 and 17th of March, and Balykchy Vodokanal and PIU on the 22nd and 23rd of March to ensure
the requested progress of the Project.
6 APPENDIX
R2 - Report No2
Financial a) Amendment : Development of Tariff roadmap
General b) Training needs assessment
Technical c) Septage Program
R3 - Report No3
General a) Training materials endorsed by IAs, EA and ADB.
b) Septage Management Regulation and Septage Management
Technical Operations Manual
Financial c) Financial projections for each Vodokanal for YY2023-2026;
d) Assessment in RLAs development with the timeline for
Institutional/Legal circulation and approval.
Draft Agreement on operational management of core funds
between municipalities and Vodokanal agreed with IAs and
Institutional/Legal municipalities;
e) Technical specifications for special machinery/ equipment (if it is
Technical required)
R4 - Report No4
P1 - Progress report 1
Financial b) Tariff Road Maps implementation - 20%
c) Public Awarness-raising and Outreach Program implementation -
Institutional / Legal 20%
Institutional/Legal d) RLA circulated to ministries
Technical e) Program on non-revenue water reduction implementation - 50%
f) Action plan on achieving financial indicators by IA
Financial implementation - 50%
R6 - Report No6
Financial a) Tariff Road Maps implementation -50%
b) Septage Management Unit is operational according to the
Technical regulation
c) Public Awarness-raising and Outreach Program implementation -
Institutional / Legal 50%
Institutional / Legal d) RLA circulated to the Ministries and some of them approved
e) Reevaluated EIRR and IRR with respected spreadsheet
Financial calculation.
Addition (Contract negotiations MoM) : Financial model and revised
Financial Analysis agreed with Vodokanals
General f) Corporate business plans implementation
Addition : Support for implementation and monitoring of GAP
g) Action plan on achieving financial indicators by IA
Financial implementation - 100%
Technical h) Program on non-revenue water reduction implementation - 100%
P2 - Progress Report 2
P3 - Progress Report 3
R7 - Report No7
Financial a) Tariff Road Maps implementation -100%
b) Public Awarness-raising and Outreach Program implementation -
Institutional / Legal 100%
c) Septage Management Unit providing services as per project
Technical output and GAP indicators
d) RLAs approved and used by Vodokanals in financial accounting
Institutional / Legal and operations
General e) Corporate business plans implementation
Addition :Support for implementation and monitoring of GAP
activities
General f) Trainings conducted on Reevaluated EIRR and IRR
FR - Final report
Draft Final Report as part of the Consultant’s Terms of
Reference with presentations of round tables in Karakol
including comments from EA, IA – within 2 weeks after
receiving the comment.
SEURECA
Mailing address
seureca.veolia.com