TCO - CAL-036-07-H-0012 - CAL-036-07-H-0012 (Rev U00-Construction or Use)
TCO - CAL-036-07-H-0012 - CAL-036-07-H-0012 (Rev U00-Construction or Use)
ТЕНГИЗШЕВРОЙЛ
CALCULATIONS
РАСЧЁТЫ
0 01-03-2013 AFC FF FF FF
B 10-11-2010 IFA LK MT PP
A 26-04-2010 IFRC LK MT VO
Page 2 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
TABLE OF CONTENTS
Page 3 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
TECHNICAL DESCRIPTION
1. INTRODUCTION
The documentation includes the Technical Documentation of the active fire protection
system of the Tengiz – Wastewater Treatment Facility.
The fire protection design is based on applicable RoK and TCO standards. The Project
Specific Hazard Studies should be used as further reference to assure that the final
design is appropriately protected against potential and specific hazards that may arise in
the facility.
3. ABBREVIATIONS-
BMS Building Management System
CMG Caspimunaigas
ESD Emergency Shutdown
FDS Fire Detection System
GDS Gas Detection System
GOST Gosudarstvennye standard (State Standard)
GRP Fiberglas Reinforced Plastic
HDPE High-Density Polyethylene
HMI Human Machine Interface
HVAC Heating, ventilation and air conditioning
LLS Last Lift Station
MCC Motor Control Center
Page 4 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Page 5 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Item Value
Minimum average wind speed 3.9 m/sec.
Ice storms frequency periodically
Glaze storm region II
Wind region region III
5. GENERAL DATA
During wastewater treatment process neither any flammable nor explosive materials are
applied except for:
Therefore, the main other process facilities and equipment do not represent any hazard.
All other process zone buildings and facilities relate to grade II of fire resistance.
The material of the internal piping in the Production Building, Fire Fighting Pump Station,
etc will be a combination of stainless steel AISI316 (150PF01) and HDPE PE100 SDR11
(150PE2) because of the high concentration of chloride (350 ppm).
The following main factors have been considered while selecting fire fighting appliances
and techniques:
5.1 GENERAL
Based on the parameters of the facility under design and RoK regulations, Tengiz WTF
will be equipped with two combined fire extinguishing system:
Page 6 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Part of the facility is formed by the firewater tank and the closely connected pump house.
It is the place where the firewater to the built-in fire fighting equipment is supplied from.
The system will be directly connected to the firewater distribution system and is to be
used for fire fighting purposes only.
Within the Production and Operation Buildings, hydrant cabinets of wet system are
installed. The hydrant cabinets are connected through shut-off devices of size DN50 to
the firewater network. The hydrant cabinets are provided with shut-off devices, reversible
hose drums, 25 mm hoses and nozzles. In each hydrant cabinet, a 6-kg portable fire
extinguisher will be installed.
In the Fire Fighting Pump Station (FFPS), an automatic fire fighting system (sprinkler) for
protection of pumps will be established.
Fire extinguishers with INERGEN gas content are to be installed in rooms containing
electrical appliances, switch boards and cables.
In rooms containing electrical equipment, switch boards and cables, fire extinguishers
with INERGEN gas content are to be installed.
Page 7 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The requirements for the fire extinguishing system have been derived from the
requirements for internal fire fighting and from the requirements for external fire fighting:
General
The combined pump station is category “I” because it is supplying fire water
directly to the fire extinguishing system
Fire fighting water will be supplied from the fire fighting tanks by the fire
extinguishing system.
External fire fighting
The standardized duration of fire extinguishing is 3 hours (item 2.24 SNiP RoK
4.01-02-2001 Water Supply External systems and facilities);
The required water flow rate for external fire extinguishing is 40 l/sec (Table 8
SNiP RoK 4.01-02-2001);
Internal fire fighting
The duration time for internal fire extinguishing is 3 hours;
According to Table 2 RoK SNiP 4.01-41-2006 «Building Internal Water Supply
and Sewage», internal fire extinguishing within the production buildings with area of 5 to
50.000 m3 will be 2 jets, each 5.0 l/s;
Water flow for internal fire extinguishing in the operation building is also provided
for. The internal fire extinguishing water supply for the operation building will be 1 jet at
2.5 l/s. According to cl. 2.20 SNIP RoK 4.01-02-2001 this rate is not considered when
calculating the total required water volume.
Table 6.1.1
Internal External Combined
Operation Production Operation Production Total
building building building building
Number of [-] 0 2 1 1
jets(pcs)
Water [l/s] 2.5 5 10 30
consumption
per jet
Water [m³/h 0 36 36 108 180
consumption ]
Extinguishing [h] 3 3 3 3
time
Total [m³] 0 (*) 108 108 324 540
required
water volume
*) Remark: The required water volume for internal fire extinguishing in the operation
building has been already included.
Total volume of the water required for external and internal fire extinguishing will be 540
m³. Two fire fighting tanks will be built to store the fire extinguishing water of 540 m3.
Page 8 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Based on the hydraulic calculations, the pressure demand of the firewater network is 6
bar.
The water supply to the firewater network is planned by using one firewater pump of
electric drive and another firewater pump of Diesel drive as a 100% redundance.
Page 9 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Curves:
Diesel pump:
- Capacity: 180 m3/h
- Total head: 85 Mwc
- Speed: 2300 rpm
- Power shaft: 76 kW
- Power max: 88 kW
-
Diesel engine:
- Power / Speed: 95 kW / 2300 rpm
- Air consumption: 7,5 m3/min
- Fuel consumption: 18,5 ltr./h
Page 10 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Curves:
Total volume of the water required for external and internal fire extinguishing will be 540
m³.
Two fire fighting tanks have the following capacity: 2 x 276 m3.
The planned capacity exceeds the specified minimum one, therefore, it is acceptable.
Page 11 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The pressure in the firewater system is maintained by means of 2 Jockey pumps (one in
service and another in 100% standby).
Jockey Pumps are designed to compensate minor pressure variations due to variations
e.g. in temperature. In the case that any of the hydrants is activated, the pump is unable
to fulfil the water demand and one of the firewater pumps is started.
Page 12 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Curves:
The material of the internal piping in the Production Building, Fire Fighting Pump House,
etc will be a combination of stainless steel AISI316 (150PF01) and HDPE PE100 SDR11
(150PE2) because of the high concentration of chloride (350 ppm).
Page 13 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The structural materials for the systems were determined with the specification L-ST-
2003 taken into account.
During pre-fabrication in the manufacturing plant, the provisions of L-ST-2004 shall
apply.
The delivery requirements of the individual components and fittings for pipelines are laid
down in the specifications L-ST-2009 and L-ST-2011.
The marking system of fittings to be delivered shall be designed according to the
specification L-ST-2006.
During the establishment of underground pipeline system the requirements of
specification L-ST-2001 shall be fulfilled.
During the establishment of overground pipeline system, the specification L-ST-2007
shall apply.
In the design of pipe supports, the provisions of specification L-ST-2010 shall be
observed.
Other provisions are detailed in the individual chapters.
According to the data supply the useful volume of fire fighting tanks is 276 m 3/tank. The
total stored volume is 552 m3.
This tank will be filled with treated effluent of the WTF.
The two basins built next to each other is made of reinforced concrete with partial earth
covering. They are provided with manhole at the top and a sump inside to pump out the
firewater.
Page 14 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The fire fighting tanks will be provided with float valves to prevent the tanks overfilling.
These fire fighting tanks will always be filled with the required water volume. In case of
maintenance the fire fighting tanks will be filled up fully before water is pumped towards
the evaporation ponds.
The distance from the fire fighting tanks to the building is according to the SNIP
requirements (10 -200 m).
The firewater pump house is accommodated in the building integrated with the water
storage tanks. Its ground floor surface is 12.2 x 7.7 m with height between 5.5 and 4.6
m.
The fire protection of the pump house is ensured by a sprinkler system according to
clause 7.4 and a built-in indoor hydrant cabinet. The design of the system meets the
provisions of Snip 2.04-01.
According to the provisions of SNIP 2.02.02 (2002), the pump house is provided with an
external entrance opening outdoors. Above the entrance, the legend “Pumping station”
shall be put up.
The fire extinguishing station will be equipped with a diesel pump and an electric pump.
Two jockey pumps will be installed to maintain the pressure on the ring pipe work around
the building.
Steel structure is painted with fire proofing paint to have 45 minutes resistance.
Firewater pumps will comply with capacity and generated head requirements identified in
the Fire Protection manual SNiP RoK2.02-05-2002.
The firewater pumps meet the requirements laid down in the specification L-ST-2005
and the standard NFPA 20.
The piping of the water supply system will be designed according to the TCO Standard
AGB-CVX-GN-SPC-FS-0225 provisions.
Page 15 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The firewater distribution system piping will be constructed of materials resistant to the
effects of corrosion by the water supply, and will be arranged and sized to maintain a
continuous supply of firewater to all user outlets.
The piping will be arranged in a loop so that the supply of water may be from two
different directions.
The fire extinguishing system with a dual feeder supplied from Operation Building
Electrical Room Low Voltage Motor Control Centre.
Pipes
Form: welded, stainless steel pipe
Material: ASTM A312 TP 316/316L
Size: ASME/ANSI B36.19 Schedule 10S
Certification: acc. to EN 10204 3.1.B
Material certificates for dual certified stainless steel materials shall indicate compliance
with the requirements of both grades of stainless steel as stated in the item code
description.
Fittings
Material: ASTM A743/A- 743M Grade CF-8M
Size: acc. to TYCO /Grinnell/ catalog
Certification: acc. to EN 10204 2.2
Page 16 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Armature
Form: with flanged ends
Material: GGG 50
Size: Class 150, acc. to ASME B16.34
Certification: acc. to EN 10204 3.1.B (all)
FM; UL listed (only gate valves)
Gaskets
Form: flat ring
Material: REINZ-AFM 34
Size: Class 150, acc. to ASME B16.34
Certification: acc. to EN 10204 2.2
7.1.7 Operation
The firewater system is of automatic operation; the pumps are activated by signals from
pressure switches depending on the pressure variations in the system.
Fire Pumps will be supplied c/w integrated control panels as per TCO Standard.
The jockey pumps will ensure that the firewater distribution system remains filled with
water and pressurized. They start automatically when pressure drops below a pre-set
value. One jockey pump will be in service and the standby jockey pump will start
automatically when pressure drops below set point.
The constant pressure in the system is ensured by the Jockey Pump G-4720-G-035.
The main pump is activated when one of the hydrants or sprinklers is opened and the
pressure drops. In case of electrical firewater pump failure the diesel pump will
automatically replace it. Each firewater pump should be designed and arranged so that it
can deliver the maximum fire water demand. If firewater pressure drops below set point,
due to more firewater flow is required, diesel pump should start automatically and run in
parallel with the main pump.
Page 17 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The operation of the pumps shall be stopped manually. Having these done, the fire
extinguishing equipment can be set to its standby state again.
The sprinkler equipment issues operating state signals on its functional ability and
operation as well as alarm signals to the Fire Alarm Control Panel and F&G HMI.
Alarm signals:
– Start of Electric pump. (G-4720-G-034)
– Start of Diesel pump. (G-4720-G-033)
In case of starting the own sprinkler system of the sprinkler machine house, the built-in
flow sensor issues an alarm signal.
The fire extinguishing station interfaces with the FACP. Signals made available from the
fire fighting station:
– level stock water in each tank.
– pressure in the pump discharge line
– general alarm fire fighting system
– pump status, running, stand-by, alarm
Page 18 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The firewater system is of automatic operation; the pumps are activated by signals from
pressure switches depending on the pressure variations in the system.
In the case that any of the hydrants is opened or the sprinkler heads are activated the
system pressure decreases. Should the Jockey Pump be able to restore the pressure,
further pressure reduction takes place. In case of pressure drop, the pressure switch
integrated in the system trips to start the electric firewater pump.
Should the electric pump fail to start, the Diesel-driven pump is activated at a pre-set
pressure.
During pressure test, the de-aeration and possibility of filling as well as drainage shall be
ensured. The necessary pipe stubs are implemented in the pump house.
During the pressure test, the pumps shall be excluded from the system; they must not be
subject to pressure test.
Test pressure: 16 bar.g; 24 hours.
Medium: water
Ambient temperature: +5÷+20 °C
Criteria of acceptance: during the test no pressure drop shall occur.
Page 19 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The closed-loop firewater pipeline will be established around the Production Building
and Operation building laid underground. The installation level is specified to be below
the frost-line.
Pipeline material: PE100; SDR11
Operating pressure: 8.5 bar.g
Rated pressure: 12 bar.g
Test pressure: 16 bar.g
Operating temperature range_ 4÷-40 °C
Rated temperature: +25 °C
Pipe:
Piping material class: 150PE (acc. to L-ST-2003)
Material: PE100
Schedule (pressure rating): SDR11 (16 bar.g)
Fittings (elbow, Tee):
Material: PE100
Schedule (pressure rating): SDR11 (16 bar)
Sectioning gate valves:
Form: API 600; RF flanged; wedge gate valve, hand wheel operator with extended stem
and protective outer sleeve and pedestal support.
Pressure rating: Class 150
Material: carbon steel for low temperature service to ASTM A352, grade LCB. All
materials to be suitable for operation at minimum temperature of -40°C.
Page 20 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Marker tape for buried underground firewater mains shall be black in colour, PVC
polyethylene mesh or ribbon at least 150 mm wide, incorporating a corrosion resistant
tracing system and to be placed a minimum of 300 mm above top of the pipe.
During pressure test, the de-aeration and possibility of filling as well as drainage shall be
ensured. The necessary pipe stubs are implemented in the pump house.
Prior to the pressure test, the pipeline shall be put under load and the earth shall be
refilled in a length of 2 to 3 m at the sections between welded and flanged joints,
respectively.
Test pressure: 16 bar.g; 24 hours.
Medium: water
Ambient temperature: +5÷+20 °C
Criteria of acceptance: during the test no pressure drop shall occur.
Page 21 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Within the building, hydrant cabinets of wet system are installed. According to the
provisions of SNiP standard, the hydrant cabinets shall be arranged in a manner that
each point of the building is accessible from two hydrant cabinets.
The planned hydrant cabinets are of DN50 connection. Each hydrant includes a shut-off
device, reversible hose drum, hose or 25 mm size, nozzle as well as additionally a CO2
fire extinguisher.
For the oil separating equipment a special foam hydrant cabinet is planned as an
additional protection.
Pipes
Form: welded, stainless steel pipe
Material: ASTM A312 TP 316/316L
Size: ASME/ANSI B36.19 Schedule 10S
Certification: acc. to EN 10204 3.1.B
Material certificates for dual certified stainless steel materials shall indicate compliance
with the requirements of both grades of stainless steel as stated in the item code
description.
Fittings
Form: with grooved ends
Material: ASTM A743/A- 743M Grade CF-8M
Size: acc. to TYCO /Grinnell/ catalog
Certification: acc. to EN 10204 2.2
The pipeline system is installed primarily by using welded joints. At certain places (e.g.
pipe stubs) welded joints are required.
For the pipelines, materials specified in clause 7.3.5 shall be used.
The installation of pipeline system shall be performed according to the layout plan of
clause 7.3.2 and the isometric plans of the pipeline section referred to there.
Page 22 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
During pressure test, the de-aeration and possibility of filling as well as drainage shall be
ensured. The necessary pipe stubs are implemented in the pump house.
During the pressure test, the hydrant cabinets shall be excluded from the system; they
must not be subject to pressure test.
Test pressure: 16 bar.g; 24 hours.
Medium: water
Ambient temperature: +5÷+20 °C
Criteria of acceptance: during the test no pressure drop shall occur.
In the Fire Fighting Pump Station – FFPS, an automatic fire fighting system (sprinkler)
for protection of pumps will be established.
Pipes
Form: welded, stainless steel pipe
Material: ASTM A312 TP 316/316L
Size: ASME/ANSI B36.19 Schedule 10S
Certification: acc. to EN 10204 3.1.B
Material certificates for dual certified stainless steel materials shall indicate compliance
with the requirements of both grades of stainless steel as stated in the item code
description.
Fittings
Material: ASTM A743/A- 743M Grade CF-8M
Size: acc. to TYCO /Grinnell/ catalog
Certification: acc. to EN 10204 2.2
The pipeline system is installed primarily by using welded joints. At certain places (e.g.
pipe stubs) welded joints are required.
For connection of sprinkler heads NPT threaded joint is used (ASME B1.20.2)
Page 23 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
During pressure test, the de-aeration and possibility of filling as well as drainage shall be
ensured. The necessary stubs are established.
Test pressure: 16 bar.g; 24 hours.
Medium: water
Ambient temperature: +5÷+20 °C
Criteria of acceptance: during the test no pressure drop shall occur.
The applied extinguishing equipment is filled with the INERGEN (IG 541) gas.
The system is controlled by the Extinguishing Control Panel which installed to the main
Fire Alarm Control Panels in Operators Room. The Operation Building, Production
Building, 10kV Switchgears Room and Containerized Diesel Generator (FUTURE)
loops/detectors connected to the Main Fire Alarm Panel in Operators Room.
Function
The INERGEN-gas-filled cylinders are part of the fixed, automatic, fire protection system.
It can be activated by the fire detectors or by the manual extinguishment start key. It
contains an adequate pressure and quantity of INERGEN extinguishing gas. For a
defined electrical signal the extinguishing gas runs through the distributing pipe system
to the area to be protected.
In the cylinders the extinguishing gas is in gas physical condition thus there is no mist at
expansion when it discharges to the area to be protected, so the escape routes stay
clearly visible.
The Operation Building, Production Building, 10kV Switchgears Room and
Containerized Diesel Generator (FUTURE) loops connected to Main Fire Alarm Control
Panel. (Will be located in Operators Room.)
Operation
The cylinders keep the INERGEN gas on 200 bar pressure. For the signal of the fire
alarming centre the solenoid of the control valve starts the discharge of the gas through
the nozzles.
The gas consists such inert gases which can be found in air:
Nitrogen N2 50%
Argon Ar 42%
Carbon dioxide CO2 8%
It’s extinguishing method based on the reduction of the normal , 21% oxygen content of
the air, up to below 15%. At this concentration the combustion process stops, and in this
environment the combustible materials cannot burn further. At the same time due to the
CO2 content the human body receives the sufficient quantity of oxygen. This process
Page 24 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
works as follows: the CO2 concentration of blood increases, so the brain notices it, and
involuntary one’s respiration gets faster. So even at lower oxygen concentration one will
receive sufficient oxygen. (The same process takes place in the human body during
running or doing other physical exercises etc.)
It means the area does not need to evacuate, and after the extinguishment air does not
need to be ventilated.
If someone accidentally cannot leave the area, he/she can stay in the room without any
harmful health effect.
The pressure in the cylinder is electronically monitored. When the pressure drop below a
defined level an error signal appears in the fire alarming centre.
The fire alarming centre controls the optical and acoustical signal inside the area,
activate the solenoid, thereby discharges the gas from the extinguishing cylinders,
activate he extinguishment, and switches the optical and acoustical signal placed
outside above the door.
Beside the door of the room there will be installed a manual extinguishment start key
and a manual inhibit extinguishment key.
For more details, see: CAL-036-07-L-0064
Automatic function
The smoke detectors of the fire detection system are installed on two independent loop.
Only the synchronic signal from both loops or the signal of the manual start key starts
the INERGEN gas.
When the fire alarming system has got synchronic signal it is activating the extinguishing
control cycle with a programmed delay (which is equal to 30 seconds between alarming
and discharge). During this period the premise should be left, and the building
surveillance system must implement the preparatory operations. (e.g. close the fire
doors, ventilation stop etc.)
After the delay period is over, the valves get the signal to discharge the INERGEN gas,
and through the pipe system and the nozzles it spreads evenly in the room.
Within the delay period the discharge of the gas can be cancelled by the manual inhibit
extinguishment key which is installed next to the exit (blue button). This only can happen
if the responsible person makes sure that the extinguishment is undoubtedly needless.
(e.g. there were a false alarms, or in the meantime the fire is manually extinguished)
There will be a Manual Call Station in Operators Room to initiate a direct fire alarm and
in case of fire the Extinguishing System can start by Extinguishing Operating Unit.
Ventilation
If necessary, after extinguishment the room can be ventilated trough the open door or
fan.
Hydraulic calculation
At the hydraulic calculations and the designing of the system it applied a manufacturer-
provided engineering software and are comply with the EN 15004-10 standard.
Mechanical data
The INERGEN is stored in 80 litre cylinders, on 200 bar pressure and it is discharges to
the room through the pipe network.
Page 25 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The pressure gauge shows the pressure in the cylinders, it’s indicator should exceed
200 bar.
The threads during transportation and installation are protected by caps from damages.
The solenoid should be the latest-installed unit. Unless specialist cannot carry out this
work.
A 24 VDC; 1A electric signal is required to activate the solenoid. It’s cable should be
resistant for fire as per IEC-331 (950°C / 3hrs).
The description of the fire alarm centre is in the fire alarm chapter.
The description of the optical smoke detector is in the fire alarm chapter.
Signals from both independent loops are needed to activate the extinguishment.
If O1 sends a signal, the fire alarming center starts the optical and acoustical signal.
If O2 also sends signal, the extinguishing process starts with the calibrated delay.
Also there are manual buttons to start and stop the extinguishment. Beside the door of
the room there will be installed a manual extinguishment start key and a manual inhibit
extinguishment key.
The precaution alarm and the alarm before the start of extinguishment are differ from
each other.
Required temperature equal to 20°C, and for the hydraulic calculation this was the initial
value. The temperature of the cylinder room are between +20 and +54°C.
Neither for system nor for cylinder there are no danger of explosion. The standard walls
are suitable. The hydraulic calculation considered 1000 Pa value for the wall.
The cylinders will be placed on the floor. The only function of the horizontal fastening is
just to prevent the tumbling.
Page 26 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The gas cylinders are placed in the production Building’s separated room. The number
of cylinders are determined in the following table:
Mechanical data
Operational pressure 20°C: 200 bar
Filling agent: INERGEN (IG 451)
Quantity of filling agent: 80 Litre
The accurate data can be seen on the data plate on the side of the cylinders.
Operation: - Automatic extinguishing system/ controlled by the fire alarm center
- Manual starter system
Position of fixing: vertical
Solenoid: 1A
The cylinders have the certificate by manufacturer standard TPED and π marked
according to the EN 1964-2.
Pipe:
Form: seamless LTCS pipe
Material: ASTM A333 GR.6
Size: ASME B36.19 Schedule 80
Thread: welded
Certification: acc. to EN 10204 3.1.B
Page 27 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Fittings
Form: with threaded ends
Material: ASTM A420 WPL6
Size: acc. to ASME B16.11
Certification: acc. to EN 10204 2.2
During pressure test, the de-aeration and possibility of filling as well as drainage shall be
ensured. The necessary stubs are established.
Prior to the pressure test, it is forbidden to connect the pipeline system to the gas
bottles.
Prior to the pressure test, the heads shall be removed and the openings closed by using
plugs of proper strength.
After pressure test, the pipelines shall by dryed, the heads installed and the pipeline
system shall be connected to the gas bottles after a successful pressure test.
The Electrical and Instrumentation Room will be equipped with 3 carbon dioxide
extinguishers.
One of them will be located at the entry and other two inside of the room.
The transformer substation will be equipped with one carbon dioxide extinguisher.
The guard house will be equipped with extinguisher, one powder and one carbon dioxide
extinguisher.
Page 28 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The workers shall have passed a medical suitability test specified for their field of
activity.
The workers shall be provided with working tools and protective means necessary for
work. Prior to the commencement of work, the workers shall inspect the condition of
tools, protective means to be used during their work whether they fulfil the conditions of
safe work. It is prohibited to use improper protective means and devices etc.
The contractor of this part of work shall be familiar with and use the most recent edition
of all the regulations relevant to the equipment to be implemented — with the current
building type taken into consideration — and shall also know the equipment to be
implemented by all the other lines.
The materials and technical solutions used in the sprinkler equipment shall meet the
provisions of the relevant standards in respect of both their production and installation.
The trade regulations and the exemplary solutions laid down therein shall have the
priority.
No chemical actions are expected during the operation of the planned fire fighting
system.
No noise affecting the health is expected during the operation of the planned fire fighting
system.
As a result of fire fighting technology, no hard manual work is required for the operation.
The daily- and weekly inspections shall be performed by the trained personnel of the
User. The monthly-, half-yearly and yearly inspections as well as the planned preventive
maintenance are allowed to be performed only by qualified personnel.
Page 29 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
The fire fighting equipment shall continuously be maintained in good working order. The
competent authorities shall be notified of putting the system out of service and into
service again, except the inspection and planned maintenance work.
Page 30 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
ОГЛАВЛЕНИЕ
1. ВВЕДЕНИЕ........................................................................................................... 32
2. НОРМЫ И СТАНДАРТЫ ...................................................................................... 32
3. СОКРАЩЕНИЯ .................................................................................................... 32
4. ОСНОВНЫЕ ТЕХНИЧЕСКИЕ ДАННЫЕ ПРОЕКТИРОВАНИЯ
(СОГЛАСНО A-ST-2008) ....................................................................................... 33
5. ОБЩИЕ ДАННЫЕ ................................................................................................ 34
6. РАСЧЕТ СИСТЕМЫ ТУШЕНИЯ ПОЖАРА ВОДОЙ ............................................ 36
7. СТРУКТУРА ВСТРОЕННОЙ СИСТЕМЫ ТУШЕНИЯ ПОЖАРА ВОДОЙ ........... 41
8. ГАЗОВЫЕ СИСТЕМЫ ПОЖАРОТУШЕНИЯ ....................................................... 53
9. ПОРТАТИВНЫЕ ОГНЕТУШИТЕЛИ..................................................................... 58
10. ПЕРВИЧНЫЕ СООРУЖЕНИЯ ПОЖАРОТУШЕНИЯ .......................................... 58
11. ПРЕДПИСАНИЯ ПО ВЫПОЛНЕНИЮ РАБОТ .................................................... 59
12. ОХРАНА ТРУДА, ОКРУЖАЮЩЕЙ СРЕДЫ И ЗДОРОВЬЯ ................................ 59
13. ПЕРИОДИЧЕСКАЯ ПРОВЕРКА, ТЕХОБСЛУЖИВАНИЕ ................................... 60
Page 31 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
ТЕХНИЧЕСКОЕ ОПИСАНИЕ
1. ВВЕДЕНИЕ
Документация содержит техническую документацию активной системы
противопожарной защиты водоочистного сооружения Тенгиз.
2. НОРМЫ И СТАНДАРТЫ
Мы исходили из того, что «основная проектная» документация принятая местными
властями содержит данные, предоставленные Заказчиком. «Основная проектная»
документация была выполнена согласно нижеследующим правилам:
3. СОКРАЩЕНИЯ
BMS Система управления строительством
CMG Каспимунайгаз
ESD Система аварийного отключения
FDS Система обнаружения пожара
GDS Система обнаружения газа
Page 32 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Температура и влажность
Температура проектирования при +40 °C, если охлаждение воздуха
сухом воздухе: считается важным
Температура проектирования при +36 °C, если охлаждение воздуха не
сухом воздухе считается важным
Температура проектирования при +29 oС
влажном воздухе
Максимальная температура +44 °C
окружающей среды:
Максимальная температура +60 °C для оборудования и системы
проектирования: трубопроводов, не подвергнутых
прямому солнечному излучению
Максимальная температура при +75 °C
солнечного излучении
Минимальная температура
проектирования:
- важно - 40 °C
- не важно - 30 °C
Климатический регион IVG
строительства
Максимальная температура +13°C
грунтовой воды
Минимальная температура +5°C
грунтовой воды
Среднесуточная температура: 125 дней
<0°C
Глубина промерзания на 1.25 м.
стройплощадке
Атмосферные условия
Атмосферное давление 1013 мбар
Относительная влажность 68 %
(среднегодовая величина)
Максимальная относительная 85 % (самый холодный месяц)
влажность
Page 33 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Позиция Значение
Минимальная относительная 33 % (самый жаркий месяц)
влажность
Штормы песка
Максимальная 43 дня/год
частота/продолжительность
Среднее количество твердых 26 мг/м3
частиц в воздухе
Максимальное количество твердых 240 мг/м3 твердых частиц на высоте 3 м.
частиц в воздухе 50 mg/m3 solids at 6 m
Данные ветра
Зарегистрированная максимальная 35 м/сек.
скорость ветра
Проектная скорость ветра (на 40 m/sec.
высоте 10 м 3 секундными
рывками)
Соответствует СНиП 2.0107 25 м\с (давление ветра 0,38 кПа,
Проектная скорость ветра регион III Карт 3).
Соответствует СНиП 2.0107 на интервал усреднения 10 минут
уровне 10 м выше превышен
степень один раз в течение 5 лет в среднем
Лето, господствующее W
направление ветра
Зима, господствующее SE
направление ветра
Максимальная средняя скорость 6.5 m/sec.
ветра
Минимальная средняя скорость 3.9 m/sec.
ветра
Частота ледяных дождей периодически
Ледяной дождь регион II
Регион ветра регион III
5. ОБЩИЕ ДАННЫЕ
В процесс очистки сточной воды не применяются огнеопасные или взрывчатые
материалы за исключением:
Page 34 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Page 35 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
В насосной станции (Fire Fighting Pump Station – FFPS) для защиты насосов
обустраивается автоматическая система пожаротушения (спринклер).
Page 36 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Таблица 6.1.1
Внутренний Наружный Объедине
нный
Здание Производ Здание Производ Общее
обслужи ственное обслужи ственное количеств
вания обслужив вания обслужив о
ания ания
Число [-] 0 2 1 1
брандспойтов
(шт.)
Расход воды на [л/сек] 2.5 5 10 30
брандспойт
Расход воды [м3/ча 0 36 36 108 180
с]
Время гашения [час] 3 3 3 3
Необходимый [м³] 0 (*) 108 108 324 540
полный объем
воды
*) Примечание: Объем воды, необходимый для тушения пожара внутри здания
обслуживания, уже был предусмотрен в расчетах.
По таблице 6.1.1.
- Одновременная потребность в воде внутренних пожарных гидрантов: 36
м3/час
- Одновременная потребность в воде наружных пожарных гидрантов: 144
м3/час
Page 37 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Характеристики:
Page 38 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Дизельный насос:
- Подача: 180 м3/час
- Полный напор: 85 м водяного столба
- Число оборотов: 2300 оборотов в минуту
- Приводной вал: 76 кВт
- Максимальная мощность: 88 кВт
-
Дизельный двигатель:
- Мощность/число оборотов: 95 кВт / 2300 оборотов в минуту
- Расход воздуха: 7,5м3/мин
- Потребление топлива: 18,5 л/час
Характеристики:
Page 39 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Page 40 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Характеристики:
Page 41 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Чертеж № Заголовок
G-4720-B-5047 Противопожарная насосная станция. План
расположения оборудования
Page 42 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Page 43 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Трубы
Форма: сварная труба из нержавеющей стали
Материал: ASTM A312 TP 316/316L
Размер: ASME/ANSI B36.19 Перечень 10S
Свидетельство: в соответствии с EN 10204 3.1. B
В сертификатах дважды заверенной нержавеющей стали следует указать
соответствие с требованиями к обоим классам нержавеющей стали, как это
приведено в описании нормы изделия.
Фитинги
Материал: ASTM A743/A- 743M Класс CF-8M
Размер: в соответствии с каталогом TYCO /Grinnell/
Свидетельство: в соответствии с EN 102042.2
Page 44 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Арматура
Форма: с фланцевыми концами
Материал: GGG 50
Размер: Класс 150, в соответствии с ASME B16.34
Свидетельство: в соответствии с EN 10204 3.1. B (все)
FM; на UL-списке (только задвижки)
Уплотнения
Форма: плоское кольцо
Материал: REINZ-AFM 34
Размер: Класс 150, в соответствии с ASME B16.34
Свидетельство: в соответствии с EN 102042.2
Болты и гайки
Форма: шпилька + шестигранные гайки
Материал: ASTM A193 Gr B8M и ASTM A194 Gr 8M
Размер: в соответствии с ANSI B18.2
Свидетельство: в соответствии с EN 102042.2
Page 45 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Выключение: вручную
Резервный насос: G-4720-G-033/ дизельный насос/
Включение: 4,5 бар
Выключение: вручную
Сигналы тревоги:
– Пуск электрического спринклерного насоса. /G-4720-G-033/
– Пуск дизельного насоса. /G-4720-G-033/
– В случае пуска собственной спринклерной системы спринклерной насосной
станции встроенный датчик потока передает сигнал тревоги.
Page 46 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
При испытании под давлением должна быть обеспечена возможность для отвода
воздуха из трубопровода, а также для его наполнения или опорожнения.
Необходимые патрубки предусмотрены в насосной станции.
Во время испытания трубопроводов под давлением насосы должны быть отсечены
от системы; нагружать их испытательным давлением не допускается.
Испытательное давление: 16 бар (изб.), 24 часа
Среда: вода.
Температура окружающей среды: +5÷+20 °C
Испытанная система подходит: если во время испытания падение давления не
обнаруживается:
Page 47 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Page 48 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Труба:
Класс материала системы трубопроводов: 150PE (в соответствии с L-ST-2003)
Материал: PE100
Перечень (номинальные значения давления): SDR11 (16 бар)
Фитинги (колено, разветвление «Т»):
Материал: PE100
Перечень (номинальные значения давления): SDR11 (16 бар)
Разъединительные задвижки:
Форма: API 600, RF фланцевой, клиновая задвижка, работающая штурвалом, с
удлиненным стержнем, наружной защитной втулкой и опорой.
Номинальная величина давления: Класс 150
Материал: Углеродистая сталь для применения при низкой температуре по
стандарту ASTM A352, класс LCB. Все материалы должны быть пригодными для
применения при минимальной температуре -40°С.
Page 49 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
При испытании под давлением должна быть обеспечена возможность для отвода
воздуха из трубопровода, а также для его наполнения или опорожнения.
Необходимые патрубки предусмотрены в насосной станции.
Перед испытанием под давлением трубопровод следует загрузить, а на 2-3
участках между сварными и фланцевыми соединениями грунт следует обратно
засыпать.
Испытательное давление: 16 бар изб., 24 часа
Среда: вода.
Температура окружающей среды: +5÷+20 °C
Испытанная система подходит: если во время испытания падение давления не
обнаруживается:
Page 50 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Трубы
Форма: сварная труба из нержавеющей стали
Материал: ASTM A312 TP 316/316L
Размер: ASME/ANSI B36.19 Перечень 10S
Свидетельство: в соответствии с EN 10204 3.1. B
В сертификатах дважды заверенной нержавеющей стали следует указать
соответствие с требованиями к обоим классам нержавеющей стали, как это
приведено в описании нормы изделия.
Фитинги
Форма: с гофрированными концами
Материал: ASTM A743/A- 743M Класс CF-8M
Размер: в соответствии с каталогом TYCO /Grinnell/
Свидетельство: в соответствии с EN 102042.2
Page 51 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
При испытании под давлением должна быть обеспечена возможность для отвода
воздуха из трубопровода, а также для его наполнения или опорожнения.
Необходимые патрубки предусмотрены в насосной станции.
Во время испытания под давлением пожарные шкафы должны быть отсечены от
системы; их нагружать испытательным давлением не допускается.
Испытательное давление: 16 бар (изб.), 24 часа
Среда: вода.
Температура окружающей среды: +5÷+20 °C
Испытанная система подходит: если во время испытания падение давления не
обнаруживается.
Чертеж № Заголовок
G-4720-L-5118 Противопожарная насосная станция. План
расположения оборудования
В насосной станции (Fire Fighting Pump Station – FFPS) для защиты насосов
обустраивается автоматическая система пожаротушения (спринклер).
Трубы
Форма: сварная труба из нержавеющей стали
Материал: ASTM A312 TP 316/316L
Размер: ASME/ANSI B36.19 Перечень 10S
Свидетельство: в соответствии с EN 10204 3.1. B
В сертификатах дважды заверенной нержавеющей стали следует указать
соответствие с требованиями к обоим классам нержавеющей стали, как это
приведено в описании нормы изделия.
Фитинги
Материал: ASTM A743/A- 743M Класс CF-8M
Размер: в соответствии с каталогом TYCO /Grinnell/
Свидетельство: в соответствии с EN 102042.2
Page 52 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
При испытании под давлением должна быть обеспечена возможность для отвода
воздуха из трубопровода, а также для его наполнения или опорожнения. Система
снабжена необходимыми патрубками.
Испытательное давление: 16 бар, 24 часа
Среда: вода.
Температура окружающей среды: +5÷+20 °C
Испытанная система подходит: если во время испытания падение давления не
обнаруживается:
Назначение
Баллоны, наполненные газом INERGEN, представляют собой часть неподвижной,
автоматической системы противопожарной защиты. Система может быть
активирована датчиками огня или вручную, с помощью пусковой кнопки. В
баллонах обеспечено соответствующее давление и количество газа INERGEN для
тушения пожара. Во время действия определенного электрического сигнала газ
для тушения пожара, проходя систему распределительных трубопроводов,
поступает к защищаемой зоне.
Page 53 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Функционирование
В баллонах обеспечивается постоянное давление газа INERGEN 200 бар. По
сигналу тревоги центра противопожарной защиты соленоид клапана управления
начинает подачу газа через сопла.
Газ состоят из таких инертных газов, которые имеются и в воздухе.
Азот N2 50%
Аргон Ar 42%
Углекислый газ CO2 8%
Этот метод тушения пожара основывается на сокращении нормального
содержания кислорода в воздухе 21% ниже 15%. При этой концентрации
останавливается процесс сгорания и в такой обстановке горючие материалы не
могут гореть далее. В то же время, благодаря содержанию CO2, человеческий
организм получает достаточное количество кислорода. Этот процесс
функционирует следующим образом: Концентрация CO2 в крови увеличивается.
Мозг, замечая это, выдает команду, и дыхание ненамеренно начинает ускоряться.
Поэтому даже при более низкой концентрации кислорода человек получит его в
достаточном количестве. (Тот же самый процесс имеет место в человеческом
организме во время выполнения физических упражнений и т.д.).
Это означает, что данную зону не нужно эвакуировать и после тушения пожара
помещение не нужно проветривать.
Если кто-то случайно не может покинуть данную зону, то он или она может
остаться в помещении без всякого вредного воздействие на здоровье.
Обеспечен постоянный электрический контроль давления в баллоне. При падении
давления ниже определенного уровня в центре пожарной тревоги появляется
сигнал ошибки.
Центр пожарной тревоги управляет оптическим и акустическим сигналами в
пределах данной зоны и активирует соленоид, выпуская, таким образом, газ из
баллонов, включает процесс тушения пожара и переключает оптический, а также
акустический сигнал, выведенные снаружи над дверью.
Около двери помещения будет установлена ручная кнопка для пуска, а другая
кнопка – для прекращения тушения пожара.
Дополнительную информацию см. в: CAL-036-07-L-0064
Автоматическая функция
Детекторы дыма системы обнаружения пожара установлены на двух независимых
петлях.
Подача газа INERGEN начинается только по синхронному сигналу из обеих петель
или сигналу от ручной кнопки.
Page 54 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Вентиляция
В случае необходимости в тушении пожара помещение можно проветривать через
открытую дверь или с помощью вентилятора.
Гидравлические расчеты
Во время составления гидравлических расчетов и проектирования системы было
применено техническое программное обеспечение, предоставленное
изготовителем, которое соответствует предписаниям стандарта EN 15004-10.
Механические данные
Хранение газа INERGEN осуществляется в баллонах, вместимостью по 80 л, при
давлении 200 бар; газ выпускается в помещение через систему трубопроводов.
Page 55 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Для пуска и останова гашения имеются и ручные кнопки. Около двери помещения
будет установлена ручная кнопка для пуска, а другая кнопка – для прекращения
тушения пожара.
Описание акустического сигнала тревоги
Установка баллонов
1. Электрощитовая 89 416 11
Page 56 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Механические данные
Рабочее давление при 20°C: 200 бар
Заполняющая среда: INERGEN (IG 451)
Количество заполняющей среды: 80 литр
Точные данные приведены на щитке данных, прикрепленной на баллонах.
Управление: Автоматическая система пожаротушения/управляемая от центра
пожарной тревоги
- Ручная система пуска
Позиция установки: вертикальная
Соленоид: 1A
Труба:
Форма: цельная гальванизированная резьбовая стальная труба из углеродистой
стали для низких температур
Материал: ASTM A333 GR.6
Размер: ASME B36.19 Перечень 80
Резьба в соответствии: сваренный
Свидетельство: в соответствии с EN 10204 3.1. B
Фитинги
Форма: с резьбовыми концами
Материал: ASTM A420 WPL6
Размер: в соответствии с ASME B16.11
Свидетельство: в соответствии с EN 102042.2
Page 57 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
При испытании под давлением должна быть обеспечена возможность для отвода
воздуха из трубопровода, а также для его наполнения или опорожнения. Система
снабжена необходимыми патрубками.
Подсоединить систему труб к газовым баллонам перед испытанием под
давлением запрещается!
Перед испытанием под давлением головки следует демонтировать, а отверстия
заделать пробками соответствующей прочности.
После испытания под давлением трубопровод следует высушить, головки
монтировать, а систему трубопроводов (после успешного испытания под
давлением) подсоединить к газовым баллонам.
9. ПОРТАТИВНЫЕ ОГНЕТУШИТЕЛИ
Портативные огнетушители будут установлены в производственном здании,
здании офиса и вахтерке, на рабочих местах и местах установки машин. Они будут
заполнены таким средством тушения, которое лучше всего соответствует
пожароопасность, ожидаемой в зоне, где тушитель расположен. Главная цель этих
огнетушителей – это принимать начальные или срочные меры по
противопожарной защите, чтобы сооружение смогло лучше реагировать на
аварийную ситуацию. Тип и место расположения огнетушителей будут
определяться в соответствии с предписаниями СНиП РоК 2.02-05-2002.
Page 58 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
12.2 ЗВУКОЗАЩИТА
Page 59 of 60
TENGIZCHEVROIL Calculations
ТЕНГИЗШЕВРОЙЛ Расчёты
WTF FIRE FIGHTING CALCULATIONS CAL-036-07-H-0012 Реv. 0
РАСЧЕТЫ ПО ПОЖАРОТУШЕНИЮ НА КОС
Page 60 of 60