Power & Energy Ratings Optimization in A Fast-Charging Station For PHEV Batteries
Power & Energy Ratings Optimization in A Fast-Charging Station For PHEV Batteries
I. INTRODUCTION
A. Needed Characteristics
The study begins by plotting the previous parameters as a
function of the grid power PGrid, and the proportion of energy
provided by the supercapacitor, nScap. The figures of the
various parameters versus PGrid and nScap are provided in
Figures 3-6.
parameters in the fast charging station (displayed in red in Fig. 3. Battery Charging Time Characteristic. A higher value indicates a
Figure 2): higher battery charging time for that level of grid power and percentage of
• Battery charging time (min) supercapacitor in the charging station.
III. METHODOLOGY
487
Waiting Time (min) Supercapacitor Contribution (kWh)
40 12
10
30
8
20 6
4
10
X: 10
Y: 30 2
Z: 7.5 X: 10
0 Y: 30
0 Z: 1.125
40
40
35 100
80
35 100
30 60 80
30 60
25 40
20 25 40
20 0 20
Grid Power (kW) SC prop (%) 20 0
Grid Power (kW) SC prop (%)
Fig. 4. Waiting Time Characteristic. . A higher value indicates a higher Fig. 6. SC Energy Contribution Charging Characteristic. The height indicates
battery charging time for that level of grid power and percentage of the amount of energy that originates from the SC that is used to charge the
supercapacitor in the charging station. PHEV battery.
,
ΔtGrid =
FES Contribution (kWh)
-2
40
35 100
E. ESD Parameters Calculations
30 60
80 The ESD maximum currents (IFES, ISC) and durations of
25
20
40
operation (ΔtFES, ΔtSC) must satisfy constraints (1) to (4)
Grid Power (kW) 20 0
SC prop (%) mentioned below.
Fig. 5. FES Energy Contribution Characteristic. The height indicates the
amount of energy that originates from the FES that is used to charge the The time of operation of the ESD must be smaller than the
PHEV battery. minimum battery charging time, ΔtBat (found in Part A):
The sum of the grid and ESD currents must equal the
maximum PHEV battery charging current, IBat,max (that can be
found on the battery datasheet):
488
IV. APPLICATION The described methodology revealed to be successful to
find the power and energy ratings of a fast-charging station for
A. Charging Station Sources Ratings PHEV batteries that uses, in addition to the grid, one or more
stationary energy storage devices. The power drawn from the
The described methodology is now applied to find the ESD
grid is minimized, the battery charging process does not
and grid parameters of a fast charging station that charges
exceed 15 minutes, and the replenishment of the storage
PHEV batteries with maximum capacity of 15 kWh from a
devices takes no longer than 7.5 minutes. These charging and
minimum of 20% to a maximum of 95% SOC (therefore
full-cycle times of the charging station conform to the Level
EBat,max = 11.25 kWh), maximum charging current of 125 A III fast-charger standard, as outlined in the SAE J1772
(therefore, IBat,max = 125 A), and with a DC bus voltage of 600 standard.
V (therefore VDC = 600 V) to satisfy the SAE J1772 standard An advantage of a graphical representation of how the
[8]. various parameters are affected by other parameters in the
design of the fast-charging station can help one visualize the
Using the graphs obtained in Section III, the respective values dependency of the various design parameters. From this, it is
for PGrid, and nScap that yield the minimum total time duration easy to visualize the effects of changing the grid power or
of the fast-charging cycle is determined to be: composition of the charging station. Future work will involve
changing the technologies of the charging station, and
PGrid = 30 kW changing the capacities of the PHEV batteries to closer match
battery electric vehicle (BEV) capacities.
nScap = 10 %
The results are summarized in Table I. [1] S.G. Wirasingha, A. Emadi, “Pihef: Plug-in Hybrid electric factor,” in
Proc. 2009 IEEE VPPC’09 Conf., pp. 661-668.
TABLE I
GRID AND ESD PARAMETERS [2] M. de Freige, G. Joos, M. Dubois, “Design and Simulation of a Fast
Charging Station for PHEV/EV Batteries,” in Proc. 2010 IEEE
Grid FES SC
EPEC’10 Conf., pp 1-5.
Maximum Duration of 10 10 5
Operation (min)
[3] “Electric Vehicle Fast Chargers - Level 3” BTCPower. [Online].
Maximum Power (kW) 30 30.75 13.5
Available: http://www.btcpower.com/products-and
Maximum Energy (kWh) 5 5.125 1.125 applications/electric-vehicle-chargers-level-3/
Phase 1 Phase 2 Phase 3 Total [8] Electric Vehicle Conductive Charge Coupler, SAE J1772.
Duration (min) 10 3.125 3.125 16.25
Recommended Practice, Draft Document in progress 2009
V. CONCLUSIONS
489