Daily Report (18.03.2020 - 31.05.2020)

This daily site report summarizes construction work from March 18 to May 31, 2020 at a development site in Johor Bahru, Malaysia. [1] The site was inactive during this period due to a government-mandated lockdown in response to COVID-19. [2] Starting May 31, construction was allowed to resume with compliance to standard operating procedures. [3] No materials or machinery were delivered to the site during the lockdown period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
117 views1 page

Daily Report (18.03.2020 - 31.05.2020)

This daily site report summarizes construction work from March 18 to May 31, 2020 at a development site in Johor Bahru, Malaysia. [1] The site was inactive during this period due to a government-mandated lockdown in response to COVID-19. [2] Starting May 31, construction was allowed to resume with compliance to standard operating procedures. [3] No materials or machinery were delivered to the site during the lockdown period.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CHINA CONSTRUCTION YANGTZE RIVER SDN BHD MALAYSIA

DI ATAS LOT 32665,JALAN MEWAH RIA ,TAMAN BUKIT MEWAH ,MUKIM TEBRAU,DAERAH JOHOR BAHRU
SITE DAILY REPORT
Date 18/3/2020 - 31/05/2020

NSC = SYARIKAT ELEKTRIK WOON SDN BHD (ELECTRICAL SERVICES)

Manpower Plant and Machinery


No Trade Qty No Trade Qty No Trade Qty No Type Qty No Type Qty
1 Dep. Project Director 16 Surveyor 31 Electrical - Woon 0 1 Hydraulic Excavator 16 Poker Vibrator

2 Project Manager - Woon 0 17 Clerk / HR Admin 32 Earthing - Woon 2 Backhoe 17 Diesel Tank

3 Const. Manager 18 Machine Operator 33 Plumbing 3 Dumper Truck 18 Water Jet


4 Architecture Manager 19 Chainman 34 RC 4 Water Truck 19 Bobcat
5 M & E Manager 20 Site Supervisor 35 5 Mobile Crane 20 Rubbish Skip
6 Technical Manager 21 Carpenter 36 6 Compactor 21 Borepile Machine
7 HSE Manager 22 Barbender 37 7 Water Pump 22 Hydraulic Conc. Breaker
8 Site Manager 23 Concretor 38 8 Diesel Genset/Welding Set 23 Bar bending Machine
9 Asst QAQC Manager 24 General Worker 39 9 Air Compressor 24 Crawler Crane
10 Site Engineer 25 Supervisor (Subcon) 40 10 Backpusher / Bulldozer 25 Grabing Machine / M.G
11 Safety Officer 26 Earthwork 41 11 Tower Crane 26 Bentonite Plant
12 Safety Site Supervisor 27 RC 42 12 Concrete Mixer 27 Showel
13 M & E Engineer 28 RC 43 13 Concrete Pump 28 Rig Rag
14 QAQC Engineer 29 Plumbing 44 14 Rotary Drilling Rig 29 Mini Escavator
15 M & E Coordinator 30 Project Engineer-Woon 0 45 15 30

Total 0 Total 0
Summary of work done and activities :-

No Location Description of work Time

1) Site was inactive due to the implementation of Movement Control Order by


1 N/A Malaysian Government starts from 18/03/2020. Starting from 31/05/2020 and N/A
afterwards site are allowed to continue works with condition to follow SOP.

Material/Machineries delivered to site


No Material Remarks
1
2
3
4
5

Prepared by: Acknowledgement By:


Joenathan Ambross
(Site Engineer/ Authorised Personnel) (Client / Consultant)
CS-QR-02