ZXDU68 B451 V6.0R20M02 DC Power System Quick Installation Guide

This document provides installation instructions for the ZXDU68 B451 (V6.0R20M02) DC power system. It describes the internal structure, which supports two configurations: an embedded power supply or a distributor module and lithium-ion battery. The document also outlines safety precautions and instructions for installing cabinets, connecting batteries, and more.

Uploaded by

Victor Artica
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
309 views7 pages

ZXDU68 B451 V6.0R20M02 DC Power System Quick Installation Guide

This document provides installation instructions for the ZXDU68 B451 (V6.0R20M02) DC power system. It describes the internal structure, which supports two configurations: an embedded power supply or a distributor module and lithium-ion battery. The document also outlines safety precautions and instructions for installing cabinets, connecting batteries, and more.

Uploaded by

Victor Artica
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

ZXDU68 B451 (V6.

0R20M02) DC Power System Installation Guide

Danger: indicates an imminently hazardous situation. Failure to comply will result in death or Internal Structure
seriouspersonal injury.
Warning: indicates a potentially hazardous situation. Failure to comply can result in death or The indoor cabinet of the ZXDU68 B451 (V6.0R20M02) supports two types of internal
serious personal injury. configurations .
ZXDU68 B451 (V6.0R20M02) Caution: indicates a potentially hazardous situation. Failure to comply can result in moderate
or minor personal injury. Internal Structure 1 of the Indoor Cabinet
DC Power System
Quick Installation Guide Electricity: Failure to comply may result in electric shocks or equipment damage.

ZTE CORPORATION Tools


Address: NO. 55 Hi-tech Road South ShenZhen P.R.China
Post Code: 518057
Tel: +86-755-26770800 800-830-1118
Fax: +86-755-26770801 Document Number:SJ-20210125144415-002
Email: [email protected] Release Version: 2020-12-30 (R1.0)

Open-end Flat head Tape Crosshead


About This Manual wrench Rope Pliers screwdriver measure screwdriver

This guide is applicable to the installation of the ZXDU68 B451 (V6.0R20M02) DC


power system.

Document Acquisition
Insulating Percussion Vacuum
Ÿ ZXDU68 B451 (V6.0R20M02) DC Power System Quick Installation Guide Hacksaw Level ruler Hose gloves drill cleaner
Ÿ ZXDU CSU602A (V3.02.00.00) Centralized System Management Unit User Guide
Ÿ You can query and download related documents from http://support.zte.com.cn.
Ÿ If your username cannot be registered for document downloading, you can send
an email [email protected].
Ÿ You can follow ztedoc in Wechat to obtain document information and put forward
suggestions.
Socket Maintenance Crimping
wrench Pipe wrench Multimeter ladder pliers
Installation Instructions 1 . Embedded power supply
2 . Distributor module
To ensure personnel and equipment safety, read carefully and abide by the 3 . Lithium-ion battery
following rules before installation.
Installation Environment Product Overview
Ÿ It is prohibited to install the equipment in acidic and corrosive environments, Internal Structure 2 of the Indoor Cabinet
or in an environment with a large amount of conductive dust.
Ÿ Ensure that water, metals, and other debris do not fall into the equipment. External Dimensions
Ÿ Otherwise, the equipment may be damaged due to a short circuit. The ZXDU68 B451 (V6.0R20M02) DC Power System uses an embedded power supply.
Installation engineers must be strictly trained, know correct operations, and be The following figure shows its external dimensions.
familiar with the security precautions.
Electrical Connections
Ÿ Never connect or disconnect cables when the device is still powered on.
Ÿ Ensure that the live wire and neutral wire are correctly connected. Ensure that
the neutral wire is properly connected, without any circuit break.
Ÿ Ensure that the positive and negative poles of batteries are correctly
connected.
Ÿ Wear protective gloves and use insulated tools during electrical connection.
Ÿ Ensure that connection terminals and other unnecessary bare parts are
properly insulated.
Ÿ Ensure that cables are reliably connected and that there is no short circuit or
open circuit.
Cable Safety Requirements
Ÿ The insulation layer of cables must not be damaged.
Ÿ Ensure that the cross-sectional area of power cables meets the maximum-
load requirements of the device.
Ÿ If cables in non-standard colors are used, choose black cables and use heat
shrink tubes or insulation tapes in the proper colors for easy identification. If
the local regulations on cable colors are different from the regulations in this
manual, you must observe the local regulations.
Ÿ If a cable has to be bent, you must ensure that the bending radius is equal to or

Safety Signs 1 . Distributor module


2 . Lithium-ion battery
Note: Provides additional information about a topic.

Caution: indicates equipment or environment safety information. Failure to comply can


result in equipment damage, data loss, equipment performance degradation,
environmental contamination, or other unpredictable results. Failure to comply will not
result in personal injury.

1 2
ZXDU68 B451 (V6.0R20M02) DC Power System Installation Guide

Embedded Power Supply 1 . Installing a Cabinet 2 . Connecting a Battery Temperature Sensor


The following figure shows the configuration of the embedded power system.
Perform the following steps to install a battery temperature sensor for a battery pack.
Steps
The location of the CSU is fixed, and cannot be changed without permission. 1 . Mark the positions of installation holes at the cabinet installation location. Ÿ A two-core plug is already connected to the X4 interface, and does not need to
be connected on site.
Ÿ Before attaching the sensor, clean the corresponding position on the battery to
Embedded Power System Cabinet Bottom View prevent the sensor from falling off.
Ÿ A pack of batteries needs only one sensor.
Front side Ÿ Three battery temperature sensors are configured by default.If there are three
4-Ø16机柜前面 or less battery packs, battery temperature is detected directly. If there are more
m 640 mm than three battery packs, the temperature of the battery box or battery cabinet is
Installation m
4-Ø16
hole 0 detected.

500 mm
600 mm
安装孔 60

Battery temperature sensor


Installation hole
Two-core plug
4 Securely stick the battery temperature
540 mm sensor to the middle part of the wider side
1 Fix the cable. 3 Remove the
600 mm outer paper. of the battery pack, or place it in the battery
box (the upper or middle part of the battery
2 Clean the position on box).The temperature sensor can be seen
2 . Drill holes on the marked positions. Install expansion bolts, and remove the nuts, the battery surfac for through the observation hole,ensuring that
spring washers and flat washers for later use. adhesion. the adhesion is reliable.

Vacuum
cleaner

Percussion drill

1 . PDU Expansion Flat Spring


2 . UIB board bolt washer washer
3 . CSU
4 . Rectifier 3 . Connecting Signal Cables and Configuring
CSU Parameters
3 . Move the cabinet to the installation position, and fasten the expansion bolts Description of Signal Interfaces
PDUs
(M12x100). Signal interfaces provided for users are distributed on the CSU and signal
interface unit. Signal cables must be connected to the corresponding interfaces
based on the on-site requirements for alarms or monitoring.
If the cabinet is not level at the bottom, place a U-shaped shim between
the cabinet and the ground. CSU

FE interface Indicators

USB interface

Buttons

SIU

U-shaped shim UIB


UIB board

IRLY2

IRLY3
IRLY4
IRLY1

5VW
5VW
CO4
NO8

CO7
NO6

NO5

CO3
NO2

NO1
CO6

CO2
NO7

NO3
CO8

CO5

CO1
NO4

5VT

5VT

5VT
TB1

TB2

TB3
1
2
3
4
5
6
7
8

1
2
3
4
5
6
7
8

1
2
3
4
5
6

1
2

1
2

1
2
X1 X2 X3 X4 X5 X6
Output RLY5,6,7,8 Output RLY1,2,3,4 Input RLY1,2,3,4 TEMP1 TEMP2 TEMP3

U-shaped shim
UIB

5VWAT

12VW
AGW
AGW

HUM
Door
5VW

5VW

SMK
5VW
WAT

RB2
5VT

AT2
TB4

V+
V+
V2

V4
V3
B1

V1
A1
G
1
2
3

1
2
3
1
2

1
2
3
4

1
2

1
2

1
2
3
4
5
6
1
2
X7 X8 X9 X10 X11 X12 X13 X14
ENV TEMP Door Flood Humility Smoke RS232 RS485-1 Input RLY5,6,7,8
(RS485-2) (Mid-voltage)

3 4 5
ZXDU68 B451 (V6.0R20M02) DC Power System Installation Guide

Introduction of Signal Cables 3 . 2 Connecting Input Dry Contact Cables 3.4 Signal Line Cabling Path and Cable-Tie Points
This section describes the signal cables for the system with the maximum There are eight input dry contacts on the UIB board. The input dry contact cables After UIB board signal lines are connected, lead the lines to the right side of the
configuration. The installation should be subject to the actual configuration. between the components in the cabinets are already connected before subrack and then upwards, see the following figure.
equipment delivery. Input dry contacts can be connected on site as required. For
Cable End A Cable View End B a description of the input dry contact cables, refer to the following table.
Name

Network FE interface of FE interface of the site Interface Name Interface Label Description
lead the lines
cable the CSU networkquipment/ to the right
End A End B energy NMS server X3 INRLY1 Dry contact signal 1
X3-1 side of the
subrack
Serial RS485 RS485 interface of the
port interface of transparent transmission X3-2 INRLY2 Dry contact signal 2
cable 1 the UIB board End A End B equipment
X3-3 5VW Used for grounding
Serial RS232 RS232 interface of the
port interface of transparent transmission X3-4 INRLY3 Dry contact signal 3
cable 2 the UIB board End A End B equipment Tie up signal lines. The following figure shows the cable tie points.
X3-5 INRLY4 Dry contact signal 4
Environm Environment Environment detection
ent detection device (temperature
detection interface of the End A sensor and magnetic X3-6 5VW Used for grounding
End B
cable UIB door switch)
board X14 INRLY5 (V1) Dry contact signal 5(battery Mid-voltage
X14-1 detection 1)
Input and Dry contact of Dry contact of system
output the equipment INRLY6 (V2) Dry contact signal 6(battery Mid-voltage
X14-2 detection 2)
dry UIB board
contact INRLY7 (V3) Dry contact signal 7(battery Mid-voltage
cables End A End B X14-3
detection 3)

Some signal cables need to be produced on site. For the method of producing a X14-4 INRLY8 (V4) Dry contact signal 8(battery Mid-voltage
signal cable, see the following figures. detection 4)

V+ Used for grounding


Tie up 17
signal
X14-6 V+ Used for grounding lines.

Ÿ Input relays 5 to 8 can be used to detect the battery midpoint voltage.


Detection method: Connect V1, V2, V3, or V4 to the middle of the second
and third batteries, and V+ is connected to the positive (+) terminal of the
last battery.
3.5 Connecting Communication Cables and Configuring
3.1 Connecting Environment Detection Cables Ÿ For the settings of input relays, refer to the ZXDT CSU602A Network Parameters
(V3.02.00.00) CSU User Guide.
Various environment detection interfaces are available on the SPB and UIB. The system can communicate with the energy NMS through an FE interface or
Insert the environment detection cables that are connected to corresponding serial port (RS485/RS232).You need to select the connection mode and configure
sensors into the corresponding interfaces. For a description of the environment The following figures use dry contact signal 5 (midpoint voltage detection 1) and network parameters on the site according to the actual situation.
detection interfaces, refer to the following table. dry contact signal 6 (midpoint voltage detection 2) as an example to show how to
connect dry contacts. Either pin 5 or 6 can be connected to the positive terminal FE Interface Connection Mode
Interface Description
of a battery pack. This communications mode is used for remote communication and needs a network
X4 (battery temperature detection) Detects the battery temperature. One interface is Dry contact signal 6 cable for connection. The connection mode is shown in the following figure.
used to detect the temperature of one battery pack. Dry contact signal 5
X5 (battery temperature detection) (battery Mid-voltage detection 1) (battery Mid-voltage detection 2)
FE interface
Battery- Battery+ Battery- Battery+
X6 (battery temperature detection)

X7 (ambient temperature detection) Detects the ambient temperature.It can be set to

V+
V+
V2

V4
V3
V1
V+
V+
V2

V4
V3
V1

detect temperature for battery pack 4.

1
2
3
4
5
6
1
2
3
4
5
6
X8 (magnetic door switch alarm) Detects whether the cabinet door is open. Back-end monitoring
X14 X14
X9 (flooding alarm) Detects whether the cabinet is flooded with water. Input RLY5,6,7,8 6 RLY5,6,7,8
Input
(Mid-voltage) (Mid-voltage)
X10 (humidity) Detects the humidity of the environment. Ethernet

X11 (smoke alarm) Detects whether there is smoke in the environment.

3.3 Connecting Output Dry Contact Cables Router/switch

There are eight output dry contacts on the UIB board. The components in the
Ÿ In connecting the magnetic door switch cables for side-by-side cabinets are connected with the output dry contact cables before delivery. Other
cabinets, the magnetic door switches of the cabinets must be connected output dry contact cables can be connected on site as required. For a description Ethernet connection mode supports data transmission through TCP/IP or SNMP.
in series and inserted into the magnetic door switch alarm interface. of the output dry contact cables, refer to the following table. Configure network parameters in accordance with the network protocol.

Ÿ Environment detection cables can be inserted into the corresponding Output Relay Interface Software Code Alarm Definition
detection interfaces as needed.
X2-D01 A1 One output dry contact can be associated with Configuring Ethernet TCP/IP Network Parameters
multiple alarms.One alarm can be associated You need to configure TCP/IP-based Ethernet network parameters on the CSU
X2-D02 A2 with only one output dry contact. after the network cables are installed. The method is as follows.
For the alarms associated with output dry
X2-D03 A3
contacts by default,refer to the alarm list in the Steps
X2-D04 A4 Solution Description. The relationships 1 . Configure a wired network.
between output dry contacts and alarms can be
X1-D05 A5 modified through the CSU. Parameter Default Value Setting
X1-D06 A6 Network Mode Modem Set it to "wired network".
X1-D07 A7 Start-Stop of diesel generator 1

X1-D08 A8 -

7 8
ZXDU68 B451 (V6.0R20M02) DC Power System Installation Guide

RS232 and RS485 cannot be used at the same time. Whether RS232 or RS485 is used
2 . Configure the wired network parameters.
can be set with a DIP switch. The following figure shows the position of the DIP
4 . 2 Connecting AC Input Cables
switch.
Parameter Default Value Setting Cable Name End A Cable View End B

Local IP Dynamic Set it in accordance with the on-site networking AC power AC input L1 Output the circuit breaker
mode requirements. cable circuit breaker or screw terminal of the
of the cabinet L2 mains electricity/diesel
If this parameter is set to Dynamic, Local IP, Mask, and End A End B generator
Gateway are automatically obtained. L3/L
Local IP 192.168.1.2 If Local IP mode is set to Static, set it to the actual IP N
address.
Mask 255.255.255.0 If Local IP mode is set to Static, set it to the actual subnet
mask. Ÿ The capacity of the external AC power switch must be larger than that of the
AC input circuit breaker of the equipment.
Gateway 192.168.1.1 If Local IP mode is set to Static, set it to the actual Ÿ If a diesel generator purchased by the customer is used together with this
gateway IP address. system, refer to the user manual for the specific locations of the AC output
connection terminals.
3 . Configure the network communication parameters.
Steps
Parameter Default Value Setting 1 . Set the external power switch on the equipment (in the AC power distribution
TCP Mode Server The CSU acts as the server. Set it to “server”. unit) to the OFF position.
2 . Switch off all the circuit breakers in the cabinet.
4 . Remove the panel from the AC power distribution unit of the power subrack in
the cabinet.
Configuring Ethernet SNMP Network Parameters 5 . Connect the AC input cables by referring to the following figure.
You need to configure SNMP-based Ethernet network parameters on the CSU
after the network cables are installed. The method is as follows. AC Power Distribution Unit
Steps AC Input
1. Configure a wired network. L1 L2 L3
Configuring Serial Port Network Parameters
N
Parameter Default Value Setting
Network Mode Modem Set it to "wired network".
You need to configure serial port network parameters on the CSU after the
RS485/RS232 serial port cable is installed. The method is as follows.

2 . Configure the SNMP parameters. Steps

Parameter Default Value Setting Parameter Default Value Setting N L1 L2 L3


SNMP Trap IP 000.000.000.000 Ÿ If it is necessary to automatically send Device Addr.-1#/- 1 Set it as required.
alarms to the NMS, set this parameter to the 2#/-3#/-4#
actual NMS IP address.
Ÿ After the default values are restored, set Port Baudrate 9600 bps Set it to the required network
this parameter to the actual NMS IP address. baud rate.
N if this parameter is set to 000.000.000.000, 4.3 Connecting Battery Cables
alarms are not automatically sent to the NMS.

SNMP Read Comm public Ÿ Use the default settings or modify the
default settings as required.
4 . Connecting Power Cables Cable Name End A Cable View End B

SNMP Set Comm private Ÿ The default port number is recommended. DC power Battery input circuit Negative binding post of
cable breaker of the cabinet End A End B the battery pack
SNMPV3 User Level To change the port number, ensure that the port
Auth, Nopriv
is not occupied. 4.1 Connecting the Grounding cable Grounding busbar of End A End B Positive binding post of
SNMPV3 User Name zteuser the cabinet the battery pack
SNMPV3 Auth.Pass 12345678 Cable Name End A Cable View End B

SNMPV3 Priv.Pass 12345678 Ÿ The positive wire and negative wire must not be incorrectly connected.
Grounding Grounding bar of End A End B On-site PE grounding
cable the cabinet bar Ÿ Ensure that the cables are securely connected to avoid short circuits and
SNMP Trap Port 163 open circuits.
SNMP Agent Port 161
Connecting the indoor cabinet to On-site PE grounding bar Steps
1 . Switch the circuit breakers in the cabinet to the OFF position.
RS485/RS232 Serial Port Connection
2 . Connect the cathode cable to the battery circuit breaker.
This mode is used for short-distance communication. A serial port cable is needed
for connection. The connection method is shown in the following figure.

On-site PE grounding bar GND

DC PDU
RS232
(RS485-2) RS485-1 BATT1 BATT2
TA2
G
RB2

B1
A1

For descriptions of the serial ports on the UIB board, refer to the following table.

Interface Description

RS232 serial port It is used for RS232 communication, and cannot be used
simultaneously with the RS485_2 interface.

RS485-1 independent It is used to extend a functional board. +


serial port

RS485-2 combo serial It is used for the RS485 communication, and cannot be used -
port simultaneously with the RS232 interface.

Lithium-ion battery
9 10 11
ZXDU68 B451 (V6.0R20M02) DC Power System Installation Guide

4.4 Connecting DC Output Cables 5 . Performing Electrical Connection Tests 5.3 Checking the AC Input Voltage
Steps
Cable Name End A Cable View End B 1. Set the AC input circuit breaker of this equipment to the OFF position.
You must perform an electrical connection test after connecting the cables, so
thatany damage to the device due to a wrong connection can be effectively 2. Set the external power switch on the equipment (in the AC power distribution unit)
DC power LLVD1 and LLVD2/BLVD Load cathode
cable of the cabinet End A End B avoided. to the ON position.
3. Switch the multimeter to the AC voltage mode. Check the AC input voltage by
Grounding busbar of Load anode referring to the following table.
End A End B
the cabinet
5.1 Detecting a Short Circuit on the AC Input Circuit
AC Input Mode Contact Criteria
Ÿ The capacity of each load must not exceed the capacity limit of the DC
output circuit breaker. A capacity margin must be retained. To avoid damage to the multimeter, do not perform any live short circuit check. Three-phase N-PE Ÿ The neutral-to-ground voltage must be lower
than 5 V. If the criterion is not satisfied, the
Ÿ Before cable connection, ensure that the DC output circuit breaker and
L1-N, L2-N, L3-N electrical grid needs to be upgraded to reduce
battery air circuit breaker are in OFF status. the neutral-to-ground voltage difference.
Ÿ During cable connection, the existing red detection cable in the DC Steps Single-phase N-PE Ÿ The phase voltage is between 176 V and 295 V.
output circuit breaker must be fastened. If the criterion is not satisfied, it is
1 . Set the external power switch on the equipment (in the AC power distribution
unit) to the OFF position. L-N recommended to start the diesel generator to
supply power.
Steps 2. Set the AC input circuit breaker in the equipment to the ON position.
1 . Set the AC input circuit breaker of this equipment to the OFF position. 3 . Switch the multimeter to the buzzer mode. Detect whether any short circuit Example: Check the voltage between AC input terminal L1/L and N.
exists on the AC input circuit by referring to the following table. If the fault
2 . Remove the panel from the DC power distribution unit in the cabinet.
exists, solve it and check it again. AC PDU
3 .Connect DC output cables to the loads by referring to the following figure.
The major load refers to important communication electrical equipment, whose AC Input Mode Contact Criteria AC Input
power failure may cause significant losses. The minor load refers to the Multimeter
communication electrical equipment that is less important than the major load. L1 L2 L3
Three - phase L1-L2, L2-L3, L1-L3 Ÿ If the buzzer is silent, it means that NN
there is no short circuit fault. The
L1-N, L2-N, L3-N check result is a pass.
Minor load Major load L1-PE, L2-PE, L3-PE
Ÿ If the buzzer buzzes, it means that
there is a short circuit fault. Find out the
GND -48V GND - 48 V point where the short circuit fault occurs,
Single-phase L-N
and reconnect the cables.
AC voltage mode
L-PE

Red test lead


Example: Detect a short circuit between AC input terminal L1/L and N.
AC PDU
Blac k test lead
AC Input
GND
L1 L2 L3
NN Multimeter
5.4 Checking the Terminal Voltage of a Storage
Battery Pack
Steps
1 . Switch off the circuit breaker of the batteries in the cabinet.
2. Switch the multimeter to the DC voltage mode.
Buzzer mode
3. Use the multimeter to check the terminal voltage of each battery pack in the
Red test lead power cabinet, and record the values in the table.
Blac k test lead For the check criteria, refer to the following table.

Object Contact Terminal Check Criteria and Troubleshooting


5.2 Detecting a Short Circuit on the DC Output Circuit Voltage

Battery Black test lead: input Ÿ If the value is positive, it means that
Steps pack of the battery input the battery cable is connected
Switch the multimeter to buzzer mode. Detect whether any short circuit exists on circuit breaker correctly.
the DC output circuit by referring to the following table and figure. If any fault Ÿ If the value is negative, it means that
Red test lead: the battery cable is connected incorrectly.
working grounding In this case, the cable should be
红笔

Contact Criteria busbar (GND)


N
connected correctly.

Black test lead: load output Ÿ If the buzzer is silent, it means that there is no short
ACB circuit fault. The check result is a pass.
Ÿ If the buzzer buzzes, it means that there is a short
Red test lead: working circuit fault. Remove the redundant cables that caused
grounding the short circuit.
busbar (GND)
GND
Example: Detect a short circuit in the DC output circuit of a load.

DC PDU Multimeter
DC PDU
Red test lead
Multimeter BATT1 BATT2 BATT3 BATT4
GND

Red test lead DC voltage mode

Buzzer mode
Blac k test lead

Blac k test lead

12 13 14
ZXDU68 B451 (V6.0R20M02) DC Power System Installation Guide

6 . Powering On and Debugging the System Appendix


Multimeter
6.1 Commissioning a Rectifier A Installing or Removing a Rectifier
Ÿ Rectifiers should be debugged when the CSU is not started. GND -48V Installing a Rectifier
Ÿ Rectifiers must be installed in the corresponding slots in accordance with DC load
the following slot addresses. If rectifiers are not sequentially installed, they Ÿ Remove the film at the ventilation holes or other objects that prevent the
must be evenly distributed in the phases (L1, L2, and L3) to ensure balance Red test lead rectifier from cooling to avoid damage to the rectifier due to poor heat
between the three phases of the AC power supply. DC Voltage Mode dissipation.
Black test lead
Ÿ In hot plug of the rectifier, slow action is required to avoid sparking.
Steps Ÿ Poor contact of the rectifier can result in equipment damage and even fire due
to serious heat generation after the rectifier is powered on. Thus, the rectifier
1 . Switch off all the circuit breakers in the power subrack.
must be installed properly.
2 . Remove the CSU and all rectifiers in the power subrack. For the procedure of removing the
CSU, refer to the Appendix of this guide. 8. Site Configuration Guide Ÿ When you push a rectifier into a slot, it is prohibited to press the ventilation
holes of the fan, buttons, or indicators to avoid damage to the equipment.
3 . Check the rectifiers one by one. Ÿ Long-distance transportation may make the internal components of the
a . Insert rectifier 1 into slot 1. System parameters have already been preset before delivery. Some parameters equipment loose. If there is any unusual sound in the rectifier during the
b . Turn on the AC output circuit breaker in the mains electricity distribution box and the need to be set and checked in equipment commissioning based on the actual installation, contact the supplier to repair the rectifier or replace it.
AC input circuit breaker in the power cabinet. situation and customer requirements. If there is any question about parameter
settings, contact ZTE technical support for help.
c . Determine whether the rectifier is operating properly with reference to the following 2
3
detection criteria. If the rectifier is not operating properly, install another rectifier in
1
the current slot until it is operating properly. Parameter Default Update Setting
d . Switch off the AC input air circuit breaker in the power unit, and extract rectifier 1. Value Value
e . Test the rectifiers in other slots by repeating step a to step d.
Battery Capacity -1# 81 Set the value to the sum of the capacity of
each battery in the battery pack.
Battery Capacity -2# 0 Note: If a battery is not connected to the
storage battery, the corresponding batter
Battery Capacity -3# 0 capacity must be set to 0.
Range: 0–9990.
Battery Capacity -4# 0

Battery Capacity -5# 0

Battery Capacity -6# 0

Press the button to release Push the rectifier to the slot


Chg.Curr.Coeff. (C10) 0.15 Set the coefficient based on battery the ejector lever
Detection Criteria characteristics.
If the power indicator and operation indicator of the rectifier are on, but the alarm Value range: 0.051 – 0.6
indicator and fault indicator are off, this indicates that the rectifier is operating 3
properly. Battery Type Deep Options: VRLA Batt, Fast Charge Batt, Deep
Cycling Cycling Batt,FeLiPO4 Batt, High Temp Batt,
Batt TB Batt, and FB Batt.

6.2 Debugging the CSU Buzzer switch 1 Set the buzzer alarm. 0: disable; 1: enable

The CSU has no switch. When there is stable power output from the rectifiers, Language 0 Set the system language. 0: Chinese; 1.
install the CSU properly. The CSU is started immediately. English
Steps
1. Install the CSU in the corresponding slot.
2. Determine whether the CSU is operating properly by referring to the following
detection criteria.
Charge Coefficient Setting
Ÿ Yes,The debugging is passed.
Ÿ No,Debug the CSU again after troubleshooting. The risk of ACB tripping due to battery loop current always exists. To avoid this risk,
lithium-ion batteries is independently connected. In accordance with the battery ACB
Detection Criteria Press down the ejector lever
current-limiting solution, the configuration principles are as follows:
If the power indicator is on, the operation indicator flashes, and there is no alarm If the system is configured with two dual-polarity 125 A ACBs , the load current is 50 A.
in the CSU (except the primary power-off circuit break alarm, battery power-off
circuit break alarm, and battery circuit break alarm), this indicates that the CSU is
the maximum charge current of the lithium-ion battery is less than 137.5 A (2 x 125 x Removing a Rectifier
75% – 50).
If the total capacity of the lithium-ion battery is 300 AH:
If the rectifier is removed after the CSU is started, you need to perform CAN
The maximum charge coefficient of the lithium-ion battery is less than 0.4583 C3 device statistics.
7. Connecting the Load (137.5/300).
To sum up, you can set the charge coefficient to 0.450.
1 2
3
If the DC output voltage detected on the DC load equipment is a negative value,
the load cables are connected in reverse. You must connect the DC output
cables properly. Otherwise, the equipment may be damaged.

Steps
1. Set the power switch of the –48 V DC load device to the OFF position.
2. Switch on the corresponding DC output circuit breaker of the load.
3. Switch the multimeter to the DC voltage mode, and check the accessed DC
voltage on the load equipment side.
Ÿ Detection contacts: red test lead/grounding terminal, black test lead/–48 V
screw terminal.
Ÿ Detection criteria: If the measured value is a positive value between 42 V
and 58V, the DC voltage is normal.
4. After the check is finished, switch on the load power. Press the button to release
Pull out the rectifier
the ejector lever
15 17
ZXDU68 B451 (V6.0R20M02) DC Power System Installation Guide

B Installing and Removing the CSU D Shutdown


Installing the CSU
A shutdown breaks the power provided to load devices. Be careful when
Ÿ If the CSU is faulty, it must be replaced immediately. performing this operation.
Ÿ In hot plug of the CSU, slow action is required to avoid sparking.
Ÿ When you push the CSU into a slot, you must not press the LCD screen, buttons,
or indicators to avoid any damage to the device. Application Scenario
Ÿ The electrical connection test and debugging have been completed. The
system does not need to be started temporarily.
1 2 Ÿ If the system is faulty, it needs to be shut down for troubleshooting.

Steps
1. Switch to another power system to supply power to the load devices, or turn off
the load devices to remove load from the system.
2. Switch off the DC output circuit breaker on the DC power distribution unit.
3. Remove the plugs from the photovoltaic array.
4. Switch off the AC input circuit breaker on the AC input power distribution unit.
5. Switch off the battery input circuit breaker on the –48 V DC power distribution

E Startup
Because there is a strong leakage current when the device is operating, the
Press the button to release Push the CSU to the slot device must be well grounded before it is powered on.
the ejector lever
Application Scenario
3 Ÿ The electrical connection test and debugging have been completed, and the
system needs to be started.
Ÿ Due to the maintenance purpose, the system needs to be shut down and started
again.
Prerequisites
All the power switches in the DC power supply are disconnected.
Steps
1. Switch on the circuit breaker of the storage battery pack, and wait until the CSU
start and operate properly.
2. After the CSU operate properly, switch on the AC input circuit breaker in the
DC power supply, and wait until the rectifier start and operate properly.
3 . Insert the plugs of the photovoltaic array into the solar power unit.

Press down the ejector lever F Emergency Shutdown


A shutdown breaks the power provided to load devices. Be careful when
performing this operation.

Remove the CSU


Application Scenario
There is an emergency situation such as fire or flooding.

1 2 Steps
1. Turn off the mains electricity circuit breaker on the power distribution unit.
2. Disconnect the battery circuit breaker of the device.
3. Remove the power plug from the solar power module.
4. Turn off the DC output circuit breaker of the device.
5. Turn off the power switch of the load equipment.

Press the button to release Pull out the rectifier


the ejector lever

21 22 23