Dar - Feb.8,2023
Dar - Feb.8,2023
221101SHB-DAR-00030
Manpower Report..................................................................................................................................... 2
Progress Photos....................................................................................................................................... 5
Page 1 of 15
WEATHER REPORT
DATE 8-Feb-23
WEATHER FAIR CLOUDY RAINY STORMY
TIME 7:30 – 5:00 12:00 – 5:00
CONTRACT START DATE January 9, 2023
CONTRACT END DATE July 6, 2024
CONTRACT DURATION 545
DAYS ELAPSED 30
DAYS "TO GO" 515
MANPOWER REPORT
DAILY
POSITION PLANNED MANPOWER ACTUAL MANPOWER TOTAL MANHOURS ON/OFF SITE
MANHOUR
Page 2 of 15
DAILY PLANNED
POSITION
MANHOUR MANPOWER
ACTUAL MANPOWER TOTAL MANHOURS ON/OFF SITE
Structural Manpower
General Foreman 8 1 1 8 On - site
Rebar Works Manpower
Rebar Fabricator 8 1 1 8 On - site
Steel Man (Installer) 8 1 1 8 On - site
Leadman 8 1 1 8 On - site
Formworks Manpower
Formworks Fabricator 8 1 1 8 On - site
Formworks Installer 8 1 1 8 On - site
Helper 8 1 1 8 On - site
Leadman 8 1 1 8 On - site
Precast Manpower
Precast Installer 8 1 0 0 Off - site
Leadman 8 1 0 0 Off - site
Concreting Crew
Concreting Crew/Finisher 8 1 0 0 Off - site
Leadman 8 1 0 0 Off - site
Architectural Manpower
Rectification/Rubcon Works/Masonry
Mason 8 1 0 0 Off - site
Skim Coater 8 1 0 0 Off - site
Water Proofing Works
Applicator 8 1 0 0 Off - site
Concrete Topping Works
Mason 8 1 1 8 On - site
Helper 8 1 1 8 On - site
Tiling Works
Tile Setter 8 1 0 0 Off - site
Helper 8 1 0 0 Off - site
Sealant Application
Sealant Applicator 8 1 0 0 Off - site
Painting Works
Skim Coater/Painter (Interior) 8 1 0 0 Off - site
Skim Coater/Painter (Exterior) 8 1 0 0 Off - site
Door Installation
Finishing Carpenter 8 1 0 0 Off - site
Helper 8 1 0 0 Off - site
Safety Crew and Maintenance
House Keeper 8 1 0 0 Off - site
Equipment Operators
Backhoe
Backhoe Operator 8 1 1 8 On - site
Rigger 8 1 1 8 On - site
Tower Crane
Tower Crane Operator 8 1 0 0 Off - site
Rigger 8 1 0 0 Off - site
Telescopic Crane
Telescopic Crane Operator 8 1 0 0 Off - site
Rigger 8 1 0 0 Off - site
Boom Truck
Boom Truck Operator 8 1 0 0 Off - site
Rigger/Helper 8 1 0 0 Off - site
Alimak
Alimak Operator 8 1 0 0 Off - site
MEPF WORKS
Electrical 8 1 1 8 On - site
Mechanical 8 1 1 8 On - site
Plumbing 8 1 1 8 On - site
Sanitary 8 1 1 8 On - site
SUBCONTRACTORS
THOMFIX 8 11 8 64 On - site
CEB 8 18 18 144 On - site
LPQ 8 7 7 56 On - site
TOTAL 328 74 49 392
Page 3 of 15
EQUIPMENT & VEHICLE REPORT
Page 4 of 15
SITE ACTIVITIES
AHEAD
BEHIND
ON - TIME
Page 5 of 15
SLOPE PROTECTION
AREA 1 9-Jan-23 16-Jan-23 10-Jan-23 100%
AREA 2 17-Jan-23 21-Jan-23 10-Jan-23 100%
AREA 3 23-Jan-23 25-Jan-23 3-Feb-23 100%
Excavation AREA 4 27-Jan-23 31-Jan-23 100%
AREA 5 27-Jan-23 31-Jan-23 100%
AREA 6 27-Jan-23 31-Jan-23 100%
AREA 7 27-Jan-23 16-Feb-23 100%
AREA 1
AREA 2
AREA 3
Hauling AREA 4
AREA 5
AREA 6
AREA 7
AREA 1 20-Jan-23 20-Jan-23 8-Feb-23 100%
AREA 2 28-Jan-23 7-Feb-23 2-Feb-23 4-Feb-23 100% COMPLETED
AREA 3 6-Feb-23 15-Feb-23 100%
Shotcrete / Primer AREA 4 10-Feb-23 15-Feb-23 100%
AREA 5 10-Feb-23 16-Feb-23 7-Feb-23 100%
AREA 6 10-Feb-23 14-Feb-23 100%
AREA 7 10-Feb-23 21-Feb-23 100%
AREA 1
AREA 2 8-Feb-23 6-Feb-23 COMPLETED
AREA 3
Wire Mesh Installation AREA 4
AREA 5
AREA 6
AREA 7
AREA 1
AREA 2
AREA 3
Soil Nailing AREA 4
AREA 5
AREA 6
AREA 7
Page 6 of 15
RETAINING WALL (FOUNDATION)
AREA 1 1.00 18-Feb-23 23-Feb-23 10-Jan-23 100%
AREA 2 29-Mar-23 6-Apr-23
AREA 3 4-Apr-23 25-Apr-23
Excavation AREA 4 30-Mar-23 8-Apr-23
AREA 5 29-Mar-23 5-Apr-23
AREA 6 27-Mar-23 4-Apr-23
AREA 7 27-Apr-23 8-May-23
AREA 1 18-Feb-23 23-Feb-23 23-Jan-23 100%
AREA 2 29-Mar-23 6-Apr-23
AREA 3 4-Apr-23 25-Apr-23
Hauling AREA 4 30-Mar-23 8-Apr-23
AREA 5 29-Mar-23 5-Apr-23
AREA 6 27-Mar-23 4-Apr-23
AREA 7 27-Apr-23 8-May-23
AREA 1 18-Feb-23 23-Feb-23 23-Jan-23 100%
AREA 2 29-Mar-23 6-Apr-23
Page 7 of 15
COLUMN FOOTING / FOUNDATION
AREA 1 2.667 21-Jan-23 25-Jan-23 14-Jan-23
AREA 2 14-Feb-23 27-Feb-23
AREA 3 22-Feb-23 6-Mar-23
Excavation AREA 4 18-Feb-23 2-Mar-23
AREA 5 20-Feb-23 3-Mar-23
AREA 6 17-Feb-23 28-Feb-23
AREA 7 20-Mar-23 30-Mar-23
AREA 1 22-Jan-23 26-Jan-23
AREA 2 15-Feb-23 28-Feb-23
AREA 3 23-Feb-23 7-Mar-23
Hauling AREA 4 19-Feb-23 3-Mar-23
AREA 5 21-Feb-23 4-Mar-23
AREA 6 18-Feb-23 1-Mar-23
AREA 7 21-Mar-23 31-Mar-23
AREA 1
AREA 2
AREA 3
Concrete Pouring AREA 4
AREA 5
AREA 6
AREA 7
Page 8 of 15
FOOTING TIE BEAM
AREA 1 0.042 21-Jan-23 25-Jan-23 8-Feb-23
AREA 2 14-Feb-23 27-Feb-23
AREA 3 22-Feb-23 6-Mar-23
Excavation AREA 4 18-Feb-23 2-Mar-23
AREA 5 20-Feb-23 3-Mar-23
AREA 6 17-Feb-23 28-Feb-23
AREA 7 20-Mar-23 30-Mar-23
AREA 1 22-Jan-23 26-Jan-23
AREA 2 15-Feb-23 28-Feb-23
AREA 3 23-Feb-23 7-Mar-23
Hauling AREA 4 19-Feb-23 3-Mar-23
AREA 5 21-Feb-23 4-Mar-23
AREA 6 18-Feb-23 1-Mar-23
AREA 7 21-Mar-23 31-Mar-23
AREA 1
AREA 2
AREA 3
Concrete Pouring AREA 4
AREA 5
AREA 6
AREA 7
Page 9 of 15
PERSPECTIVE PHOTO
Page 10 of 15
PROGRESS PHOTO REFLECTED KEY PLAN
2/4/23 10:23AM
AREA 7
Page 11 of 15
PROGRESS PHOTO REFLECTED KEY PLAN
Page 12 of 15
PROGRESS PHOTO REFLECTED KEY PLAN
Page 13 of 15
PROGRESS PHOTO REFLECTED KEY PLAN
SOIL TRIMMING
(SOIL NAIL) (Feb. 7,2023)
SOIL TRIMMING
(SOIL NAIL) (Feb. 8,2023)
Page 14 of 15
PROGRESS PHOTO REFLECTED KEY PLAN
SHOTCRETE
(SOIL NAIL) (Feb. 7,2023)
SHOTCRETE
(SOIL NAIL) (Feb. 7,2023)
Page 15 of 15