Dar - Feb.8,2023

The daily activity report summarizes work activities on February 8, 2023 at the Sheridan Drive Center construction site. Weather was fair with clouds and some rain between 12-5pm. 27 workers were on site as planned, with activities including rebar works, formworks installation, concrete masonry, and backhoe operation. Progress photos were also taken to document the day's work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views16 pages

Dar - Feb.8,2023

The daily activity report summarizes work activities on February 8, 2023 at the Sheridan Drive Center construction site. Weather was fair with clouds and some rain between 12-5pm. 27 workers were on site as planned, with activities including rebar works, formworks installation, concrete masonry, and backhoe operation. Progress photos were also taken to document the day's work.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

SHERIDAN DRIVE CENTER

Sheridan Drive, Camp John Hay, Baguio City

221101SHB-DAR-00030

DAILY ACTIVITY REPORT (FEBRUARY 8, 2023)

ORDERED BY: CHECKED BY:

Engr. Simeon James D. Villacrusis


Engr. Alvin Bernal
PE/PA/PIC/PLANNING ENGR. PM/AREA ADMINISTRATOR
TABLE OF CONTENTS
Weather Report ........................................................................................................................................ 1

Manpower Report..................................................................................................................................... 2

Equipment And Vehicle Report................................................................................................................ 3

Site Activities ............................................................................................................................................ 4

Progress Photos....................................................................................................................................... 5

Page 1 of 15
WEATHER REPORT

DATE 8-Feb-23
WEATHER FAIR CLOUDY RAINY STORMY
TIME 7:30 – 5:00 12:00 – 5:00
CONTRACT START DATE January 9, 2023
CONTRACT END DATE July 6, 2024
CONTRACT DURATION 545
DAYS ELAPSED 30
DAYS "TO GO" 515

MANPOWER REPORT

DAILY
POSITION PLANNED MANPOWER ACTUAL MANPOWER TOTAL MANHOURS ON/OFF SITE
MANHOUR

Project Manager 8 1 1 8 On site


Operation Group
PIC Tower 1 8 1 1 8 On site
Rebar Engineer 8 1 1 8 On site
Formworks Engineer 8 1 1 8 On site
Concreting Engineer 8 1 1 8 On site
Precast Engineer 8 1 1 8 On site
Architectural Works
Site Architect 8 1 1 8 On site
Site Architect 8 1 1 8 Off Site
Survey group
Surveyor/Line & Grade Engineer 8 1 1 8 On site
Survey Aide 8 1 1 8 On site
Engineering Control and Administration
Office Supervisor 8 1 1 8 Off Site
Quantity Surveyor 8 1 1 8 Off Site
Document Controller 8 1 1 8 Off Site
Planning Engineer 8 1 1 8 Off Site
Project HR 8 1 1 8 Off Site
Autocad Operator 8 1 1 8 Off Site
Time Keeper 8 1 1 8 On site
Warehouse Man 8 2 2 16 On site
Warehouse Aid 8 1 1 8 On site
Site Driver 8 1 1 8 On site
Health, Safety and Environmental Control
Safety Officer 8 1 1 8 On site
First Aider 8 1 1 8 On site
MEPFS
MEPF Supervisor 8 1 1 8 On site
MEPF Engineer 8 1 1 8 On site
Quality Assurance and Control
QA/QC Structural and Architectural 8 1 1 8 On site
QA/QC Aide 8 1 1 8 On site
TOTAL 208 27 27 216

Page 2 of 15
DAILY PLANNED
POSITION
MANHOUR MANPOWER
ACTUAL MANPOWER TOTAL MANHOURS ON/OFF SITE

Structural Manpower
General Foreman 8 1 1 8 On - site
Rebar Works Manpower
Rebar Fabricator 8 1 1 8 On - site
Steel Man (Installer) 8 1 1 8 On - site
Leadman 8 1 1 8 On - site
Formworks Manpower
Formworks Fabricator 8 1 1 8 On - site
Formworks Installer 8 1 1 8 On - site
Helper 8 1 1 8 On - site
Leadman 8 1 1 8 On - site
Precast Manpower
Precast Installer 8 1 0 0 Off - site
Leadman 8 1 0 0 Off - site
Concreting Crew
Concreting Crew/Finisher 8 1 0 0 Off - site
Leadman 8 1 0 0 Off - site
Architectural Manpower
Rectification/Rubcon Works/Masonry
Mason 8 1 0 0 Off - site
Skim Coater 8 1 0 0 Off - site
Water Proofing Works
Applicator 8 1 0 0 Off - site
Concrete Topping Works
Mason 8 1 1 8 On - site
Helper 8 1 1 8 On - site
Tiling Works
Tile Setter 8 1 0 0 Off - site
Helper 8 1 0 0 Off - site
Sealant Application
Sealant Applicator 8 1 0 0 Off - site
Painting Works
Skim Coater/Painter (Interior) 8 1 0 0 Off - site
Skim Coater/Painter (Exterior) 8 1 0 0 Off - site
Door Installation
Finishing Carpenter 8 1 0 0 Off - site
Helper 8 1 0 0 Off - site
Safety Crew and Maintenance
House Keeper 8 1 0 0 Off - site
Equipment Operators
Backhoe
Backhoe Operator 8 1 1 8 On - site
Rigger 8 1 1 8 On - site
Tower Crane
Tower Crane Operator 8 1 0 0 Off - site
Rigger 8 1 0 0 Off - site
Telescopic Crane
Telescopic Crane Operator 8 1 0 0 Off - site
Rigger 8 1 0 0 Off - site
Boom Truck
Boom Truck Operator 8 1 0 0 Off - site
Rigger/Helper 8 1 0 0 Off - site
Alimak
Alimak Operator 8 1 0 0 Off - site
MEPF WORKS
Electrical 8 1 1 8 On - site
Mechanical 8 1 1 8 On - site
Plumbing 8 1 1 8 On - site
Sanitary 8 1 1 8 On - site
SUBCONTRACTORS
THOMFIX 8 11 8 64 On - site
CEB 8 18 18 144 On - site
LPQ 8 7 7 56 On - site
TOTAL 328 74 49 392

Page 3 of 15
EQUIPMENT & VEHICLE REPORT

PLANNE ACTUAL OPERATING


DESCRIPTION
D UNIT UNIT HOURS
Tractor Head w/ Trailer Bed Sets 1 0 8
Dumptruck (Tower) 4 2 8
Mini DT / Elf (Tower) 1 1 8
Tower Crane - 01 (Tower) 1 1 8
Mobile Crane (25 Tonner; Tower)
Transit Mixer (Tower) 11 0
Concrete Pump (Tower) 1 0
Backhoe 3 2 8
Tamper Hammer
Skid Loader
Plate Compactor
Motorized Gondola (Tower)
Bar Bender 2 2
Bar Cutter 2 2
Welding Machine 300A 4 2 8
Welding Machine 500A 4 2 8
Pressure Washer 4 4 8
Submersible Pump 6 6 8
Flood Light 30 30 8
Computer 15 15 8
Heater 6 6 8
Circular Saw 4 4 8
Grinder 4 4 8
Power Saw 4 4 8

Page 4 of 15
SITE ACTIVITIES

AHEAD

BEHIND
ON - TIME

DAILY PLANNED ACTUAL ACCOMPLISHMENT(%)


ACTIVITY AREA STATUS/REMARKS
PRODUCTIVITY START FINISH START FINISH PLANNED ACTUAL
Construction of Crane Footing AREA 5 10-Jan-23 17-Jan-23 10-Jan-23 24-Jan-23 100% 100% COMPLETED
Tower Crane Erection AREA 5
CONSTRUCTION OF TEMPORARY FACILITIES
Installation of Smart House Partition AREA 7 19-Jan-23 25-Jan-23 19-Jan-23 100% FOR COMPLETION
Installation of Ficem Board prior to partition of CR AREA 7

Construction of Staff House AREA 7

Construction of Warehouse AREA 7 15-Jan-23 26-Jan-23 100% FOR COMPLETION


Construction of Power House AREA 4 13-Jan-23 24-Jan-23 100% FOR COMPLETION
Clearing of mud at entrance gate Outside Perimeter

Page 5 of 15
SLOPE PROTECTION
AREA 1 9-Jan-23 16-Jan-23 10-Jan-23 100%
AREA 2 17-Jan-23 21-Jan-23 10-Jan-23 100%
AREA 3 23-Jan-23 25-Jan-23 3-Feb-23 100%
Excavation AREA 4 27-Jan-23 31-Jan-23 100%
AREA 5 27-Jan-23 31-Jan-23 100%
AREA 6 27-Jan-23 31-Jan-23 100%
AREA 7 27-Jan-23 16-Feb-23 100%
AREA 1
AREA 2
AREA 3
Hauling AREA 4
AREA 5
AREA 6
AREA 7
AREA 1 20-Jan-23 20-Jan-23 8-Feb-23 100%
AREA 2 28-Jan-23 7-Feb-23 2-Feb-23 4-Feb-23 100% COMPLETED
AREA 3 6-Feb-23 15-Feb-23 100%
Shotcrete / Primer AREA 4 10-Feb-23 15-Feb-23 100%
AREA 5 10-Feb-23 16-Feb-23 7-Feb-23 100%
AREA 6 10-Feb-23 14-Feb-23 100%
AREA 7 10-Feb-23 21-Feb-23 100%
AREA 1
AREA 2 8-Feb-23 6-Feb-23 COMPLETED
AREA 3
Wire Mesh Installation AREA 4
AREA 5
AREA 6
AREA 7
AREA 1
AREA 2
AREA 3
Soil Nailing AREA 4
AREA 5
AREA 6
AREA 7

Page 6 of 15
RETAINING WALL (FOUNDATION)
AREA 1 1.00 18-Feb-23 23-Feb-23 10-Jan-23 100%
AREA 2 29-Mar-23 6-Apr-23
AREA 3 4-Apr-23 25-Apr-23
Excavation AREA 4 30-Mar-23 8-Apr-23
AREA 5 29-Mar-23 5-Apr-23
AREA 6 27-Mar-23 4-Apr-23
AREA 7 27-Apr-23 8-May-23
AREA 1 18-Feb-23 23-Feb-23 23-Jan-23 100%
AREA 2 29-Mar-23 6-Apr-23
AREA 3 4-Apr-23 25-Apr-23
Hauling AREA 4 30-Mar-23 8-Apr-23
AREA 5 29-Mar-23 5-Apr-23
AREA 6 27-Mar-23 4-Apr-23
AREA 7 27-Apr-23 8-May-23
AREA 1 18-Feb-23 23-Feb-23 23-Jan-23 100%
AREA 2 29-Mar-23 6-Apr-23

AREA 3 4-Apr-23 25-Apr-23


Concrete Pouring
AREA 4 30-Mar-23 8-Apr-23
AREA 5 29-Mar-23 5-Apr-23
AREA 6 27-Mar-23 4-Apr-23
AREA 7 27-Apr-23 8-May-23

Page 7 of 15
COLUMN FOOTING / FOUNDATION
AREA 1 2.667 21-Jan-23 25-Jan-23 14-Jan-23
AREA 2 14-Feb-23 27-Feb-23
AREA 3 22-Feb-23 6-Mar-23
Excavation AREA 4 18-Feb-23 2-Mar-23
AREA 5 20-Feb-23 3-Mar-23
AREA 6 17-Feb-23 28-Feb-23
AREA 7 20-Mar-23 30-Mar-23
AREA 1 22-Jan-23 26-Jan-23
AREA 2 15-Feb-23 28-Feb-23
AREA 3 23-Feb-23 7-Mar-23
Hauling AREA 4 19-Feb-23 3-Mar-23
AREA 5 21-Feb-23 4-Mar-23
AREA 6 18-Feb-23 1-Mar-23
AREA 7 21-Mar-23 31-Mar-23
AREA 1
AREA 2
AREA 3
Concrete Pouring AREA 4
AREA 5
AREA 6
AREA 7

Page 8 of 15
FOOTING TIE BEAM
AREA 1 0.042 21-Jan-23 25-Jan-23 8-Feb-23
AREA 2 14-Feb-23 27-Feb-23
AREA 3 22-Feb-23 6-Mar-23
Excavation AREA 4 18-Feb-23 2-Mar-23
AREA 5 20-Feb-23 3-Mar-23
AREA 6 17-Feb-23 28-Feb-23
AREA 7 20-Mar-23 30-Mar-23
AREA 1 22-Jan-23 26-Jan-23
AREA 2 15-Feb-23 28-Feb-23
AREA 3 23-Feb-23 7-Mar-23
Hauling AREA 4 19-Feb-23 3-Mar-23
AREA 5 21-Feb-23 4-Mar-23
AREA 6 18-Feb-23 1-Mar-23
AREA 7 21-Mar-23 31-Mar-23
AREA 1
AREA 2
AREA 3
Concrete Pouring AREA 4
AREA 5
AREA 6
AREA 7

Page 9 of 15
PERSPECTIVE PHOTO

Perspective Photo (Feb. 7,2023)

Perspective Photo (Feb. 8,2023)

Perspective Photo (Feb. 7,2023)

Perspective Photo (Feb. 8,2023)

Page 10 of 15
PROGRESS PHOTO REFLECTED KEY PLAN

CONSTRUCTION OF TEMPORARY FACILITIES


(INSTALLATION OF STAFF HOUSE PARTITION) (Feb. 7,2023)

2/4/23 10:23AM

AREA 7

CONSTRUCTION OF TEMPORARY FACILITIES


(INSTALLATION OF CR PARTITION FOR STAFF HOUSE) (Feb. 8,2023)

Page 11 of 15
PROGRESS PHOTO REFLECTED KEY PLAN

LEARING OF MUD AT ENTRANCE GATE


(Feb.8,2023)

INSTALLATION OF FICEM BOARD PRIOR TO CR PARTITION INSTALLATION OF CR PVC DOOR


(Temporary Facilities) (Feb.7,2023) (Temporary Facilities) (Feb.8,2023)

Page 12 of 15
PROGRESS PHOTO REFLECTED KEY PLAN

CONTINUATION OF TOWER CRANE BOOM


INSTALLATION
(Feb. 8,2023)

FABRICATION OF REBAR FOR COLUMN FOOTING


& FOOTING TIE BEAM
(Feb. 8,2023)

Page 13 of 15
PROGRESS PHOTO REFLECTED KEY PLAN

SOIL TRIMMING
(SOIL NAIL) (Feb. 7,2023)

SOIL TRIMMING
(SOIL NAIL) (Feb. 8,2023)

Page 14 of 15
PROGRESS PHOTO REFLECTED KEY PLAN

SHOTCRETE
(SOIL NAIL) (Feb. 7,2023)

SHOTCRETE
(SOIL NAIL) (Feb. 7,2023)

Page 15 of 15