Contract Admin Manual 1 Goods May 2018
Contract Admin Manual 1 Goods May 2018
ACCRA, GHANA
MANUAL 1
PREPARED BY
FEBRUARY, 2018
Contract Administration Manual For Goods – Manual 1
FOREWORD
On 31st December 2003, the Government of Ghana enacted the Public Procurement Act, 2003 (Act
663) which became operational in August, 2004. The Act provided a framework for the conduct
of procurement in the Public Sector to guarantee best value for money in the context of poverty
reduction, private sector development, good governance and anti-corruption. The overriding aim
of Act 663 is to ensure judicious, economic and efficient use of Public Funds with procurement
being carried out in a fair, transparent and non-discriminatory manner. The Public Procurement
Authority (PPA) considers sustainable training a critical component of its efforts aimed at
strengthening the public procurement systems and achieving value for money.
The Public Procurement Authority, in 2007, developed twenty-five (25) Training Modules and
Manuals for training of various categories of Stakeholders on the provisions of the Public
Procurement Act, 2003 (Act 663). Over 20,000 Public and Private Operatives have since benefitted
from various training programmes on Public Procurement Act, 2003 (Act 663) using these
Modules. The Modules, however, were mainly on Procurement and did not cover Contract
Administration. To address this shortcoming, the PPA, in January 2015, commissioned the Ghana
Institute of Management and Public Administration (GIMPA) with funding from the African
Development Bank under the Ghana Institutional Support Project (GISP) to develop detailed
Contract Administration Modules and to review the existing Manuals on Goods, Works and
Services. These documents are to be used for the PPA’s capacity development activities. The
Contract Administration Modules and Manuals for Goods, Works, Consulting Services and
Technical Services have come at an opportune time, given that in Ghana and other developing
countries the procurement regime in the public sector has not been able to address most of the
challenges of managing contracts in line with international best practices and standards.
It is in the light of this that the Public Procurement Authority (PPA) of Ghana, with funds from
supporting Development Partners, has developed these important Contract Administration
Training Modules and Manuals which will go a long way to assist Procurement Entities in the
Public Sector to manage contracts after contract award. These Training Modules and Manuals will
also be useful for the Oversight Institutions like the Judiciary, Police, EOCO, Media and other
Anti-Corruption Agencies to monitor and manage Public Sector Contracts. It will also serve as
reference literature for Lecturers and Students teaching and pursuing courses in Public
Procurement Management and related courses.
These Modules and Manuals touch essentially on the following areas: Contract Principles; Basics
of Contract Administration; Forms of Standard Goods/Works/Technical/Consultancy Contract;
Contract Administration Processes Especially Post Award Preliminary Tasks; Monitoring of
Contract Performance and Reporting and Contract Modification. The remaining areas are Payment
and Cost Control using GIFMIS System; Claims and Settlement of Disputes; Contract
Termination; Contract Records Management; Contract Performance Evaluation and Post-
Implementation Tasks of Contract Administration.
ACKNOWLEDGEMENT
The Public Procurement Authority (PPA) extends profound gratitude and appreciation to the
Donors: Department for International Development (DFID), Deutsche Gesellschaft für
Internationale Zusammenarbeit (GIZ) who initially funded the preliminary development of the
Procurement Manuals and the Guidelines. Special appreciation goes to the African Development
Bank (AfDB) through its Ghana Institutional Support Project, which funded the development of
the current Contract Administration Training Modules and Manuals for Goods, Works, Consulting
Services and Technical Services together with the cost of facilitation and logistics involved in the
training of some Procurement Stakeholders across the country.
Special acknowledgement goes to the PPA Technical Working Group (TWG) that reviewed the
initial Manuals and Guidelines which were prepared by Crown Agents, UK. Special mention is
made of A. B. Adjei Chief Executive of PPA, Eric V. Appiah, Director, Benchmarking, Monitoring
& Evaluation (BM & E) of PPA, Lesley Dodoo, Director Legal, PPA, Carl Lokko, Director, Policy
& Strategy (P&S), Emelia Nortey, Director, MIS, Vidal Creppy, Director Capacity Development
and the External Consultants namely Messrs. Godfrey Ewool, Stephen Tackie, Nii Amasa Kotey
and. Jacqueline Angate.
Our special appreciation also goes to the PPA Team and the External Consultants that reviewed
the draft Contract Administration Manuals and Modules prepared by Ghana Institute of
Management and Public Administration (GIMPA), namely: Yvonne Quansah, Minawara Adams,
Andrew Baafi, Rhoda E. Appiah, Thomas K. Bondzi, Abraham Ablorh Mensah, Joseph Kuruk,
Faustina A. Okuadjo, Hilda A. Agyemang, Prince Agyemang-Badu, Edwina Safee-Boafo and.
Miriam Osei; and External Reviewer, John Benson. Additionally, the Authority wishes to
recognize the valuable contributions of participants of the Training of Trainers/Validation
Workshop which enhanced the final output of this document.
It is worthy to acknowledge the pioneering role of Hon. Samuel Sallas-Mensah, former Chief
Executive Officer of PPA and David Bennin, former Director, Capacity Development of PPA in
the development of these Manuals.
Finally, the Authority wishes to thank the GIMPA Consulting Team of Messrs. N.S.K. Appiah,
K. H. Osei-Asante, Michael Kofi Quashie and Paul Nartey, who eventually developed the final
Contract Administration Manuals and the accompanying Training Modules. Appreciation also
goes to the following personnel of the GIMPA Consultancy Services, who assisted in finalizing
the Manuals: Dr. Kofi Fred Asiedu, former Managing Consultant, Julius Hawkson-Aikins, Ag.
Managing Consultant, Fred Appiah and Asafo Adjei, both Consultants.
The Public Procurement Authority (PPA) wishes to record its appreciation for the time and effort
devoted by all the above-mentioned persons and organizations in the development of these
documents.
However, the ultimate responsibility for the form and content of the Manuals rest with PPA and
GIMPA.
TABLE OF CONTENTS
FOREWORD................................................................................................................................................ i
ACKNOWLEDGEMENT ......................................................................................................................... iii
TABLE OF CONTENTS ............................................................................................................................ i
LIST OF ABBREVIATIONS/ACRONYMS ............................................................................................. i
GLOSSARY OF TERMS ............................................................................................................................ i
INTRODUCTION....................................................................................................................................... 1
Background ............................................................................................................................................... 1
Purpose of the Manuals ............................................................................................................................ 1
Scope of Manual on Goods-1 .................................................................................................................... 1
Content/Structure of the Manual on Goods-1 ......................................................................................... 2
Exceptions to the Manual ......................................................................................................................... 2
Forms/Templates ...................................................................................................................................... 2
1.0 CONTRACT PRINCIPLES......................................................................................................... 3
1.1 Introduction .................................................................................................................................. 3
1.2 Contract – Definition ..................................................................................................................... 3
1.3 Essential Elements of a Valid Contract ......................................................................................... 3
1.4 Formation of a Contract ................................................................................................................ 4
1.5 The Law Applicable to a Contract ................................................................................................. 4
1.6 The Nature and Types of Goods ................................................................................................... 4
1.7 Types of Contracts for Goods Procurement ................................................................................. 5
1.8 Factors Affecting the Choice of Contract Type ............................................................................. 6
1.9 General Principles for Contracts ................................................................................................... 6
2.0 BASICS OF CONTRACT ADMINISTRATION ........................................................................ 7
2.1 Introduction .................................................................................................................................. 7
2.1.1 Nature of Contract Management and Administration ......................................................... 7
2.2 Objectives of Contract Administration ......................................................................................... 8
2.3 The Role of Contract Administration ............................................................................................ 8
2.4 The Benefits of Good Contract Administration ............................................................................ 9
2.5 Summary of Main Tasks of Contract Administration .................................................................... 9
2.5.1 Important Parties in a Goods Contract ................................................................................. 9
2.6 Organization for Contract Administration .................................................................................. 10
2.6.1 Legal and Institutional Arrangements for Contract Administration in Ghana .................... 10
2.6.2 Organization of Principal Procurement Bodies/Structures in Contract administration ..... 11
i Public Procurement Authority (PPA), Ghana
Contract Administration Manual For Goods – Manual 1
2.6.3 Contract Administration Organization for Supply of Goods ............................................... 13
2.7 Responsibilities of the Contract Administrator........................................................................... 13
2.8 Skills of the Contract Administrator ............................................................................................ 14
2.9 Poor and/or Fraudulent Contract Administration ...................................................................... 14
2.10 Fraud and Corruption in Contract Implementation .................................................................... 15
2.11 Conflicts of Interest ..................................................................................................................... 18
3.0 FORMS AND CONDITIONS OF STANDARD GOODS CONTRACTS ............................... 19
3.1 Introduction ................................................................................................................................. 19
3.2 Basic Documentation for Goods Contract .................................................................................. 19
3.2 Form of Goods Contract.............................................................................................................. 19
3.2.1 Standard Contract for Request for Price Quotation ........................................................... 19
3.2.2 Standard Contract Form for National Competitive Tendering ........................................... 22
3.2.3 Standard Contract Form for International Competitive Tendering .................................... 24
3.3 General Conditions of Contract (GCC) ........................................................................................ 26
3.3.1 Clauses under the GCC ........................................................................................................ 26
3.4 Summary List of Clauses in SCC for National Competitive Tendering ........................................ 30
3.5 General Conditions of Contract (GCC) & Special Conditions of Contract (SCC) for International
Competitive Tendering ........................................................................................................................... 30
4.0 CONTRACT ADMINISTRATION PROCESS: POST-AWARD PRELIMINARY TASKS 31
4.1 Introduction ................................................................................................................................ 31
4.2 Contract Administration Planning (Policies, Systems and Procedures) ...................................... 31
4.3 Contract Administration Plan (CAP) ............................................................................................ 31
4.3.1 Main Elements of a Contract Administration Plan ............................................................. 32
4.3.2 Key Milestones of a Contract for Supply of Goods ............................................................. 33
4.3.3 Monitoring Performance of Key Milestones....................................................................... 33
4.3.4 Contract Milestone Checklist for Each Contract ................................................................. 35
4.3.5 Managing the Contract Checklist ........................................................................................ 36
4.4 Commencement/Kick-off Meeting(s) ......................................................................................... 38
4.4.1 Critical issues to be established during the kick-off meeting ............................................. 38
4.5 Verification of Advance Payment Security and Performance Securities .................................... 38
4.6 Verification of Insurance Policies ................................................................................................ 39
4.7 Inspections .................................................................................................................................. 40
5.0 MONITORING CONTRACT PERFORMANCE & REPORTING ....................................... 42
5.1 Introduction ................................................................................................................................ 42
LIST OF FIGURES
Figure 1: Institutional Arrangements for Contract Administration in Ghana ............................... 11
Figure 2: Organization of Principal Procurement Bodies/Structures ........................................... 12
Figure 3: Process To Pay .............................................................................................................. 58
LIST OF TABLES
Table 1: Contract Milestone Checklist ......................................................................................... 36
Table 2: Description of INCOTERMS and Characteristics .......................................................... 92
LIST OF ABBREVIATIONS/ACRONYMS
Act 663 Public Procurement Act, 2003
ADR Alternative Dispute Resolution
CAGD Controller and Accountant General’s Department
CAP Contract Administration Plan
CoA Chart of Accounts
CFR Cost and Freight
CIF Cost, Insurance and Freight
CIP Carriage and Insurance Paid To
CPT Carriage Paid To
DANIDA Danish International Development Agency
DAF Delivered at Frontier
DAP Delivered at Place
DAT Delivered at Terminal
DDU Delivered Duty Paid
DEQ Delivered Ex Quay
DFID Department for International Development
ERMS Electronic Records Management Strategy
ERP Enterprise Resource Planning
EXW Ex Works
FAA Financial Administration Act (Legal and Regulatory Framework)
FAR Financial Administration Regulations (Legal and Regulatory Framework
Reform)
FAS Free Alongside Ship
FCA Free Carrier
FOB Free on Board
GCC General Conditions of Contract
GIFMIS Ghana Integrated Financial Management Information Systems
GoG Government of Ghana
ICT Information & Communication Technology
ICT International Competitive Tender
IFIs International Financial Institutions
IGF Internally Generated Funds
i Public Procurement Authority (PPA), Ghana
Contract Administration Manual For Goods – Manual 1
ISO International Standardization Organization
INCOTERMS International Commercial Terms
IPPD2 Integrated Personnel and Payroll Database
LPO Local Purchase Order
MDAs Ministries, Departments and Agencies
MMDAs Metropolitan, Municipal and District Assemblies
MoF Ministry of Finance
NCT National Competitive Tender
NITA National Information Technology Agency
PE Procurement Entity
PFM Public Financial Management
PO Purchase Order
PPA Public Procurement Authority
PRAAD Public Records and Archives Administration Department
P2P Procure to Pay
PUFMARP Public Financial Management Reform Programme
PV Payment Voucher
RFQ Request for Quotation
RM Records Management
SCC Special Conditions of Contract
SRA Store Receipt Advice
SRV Stores Receipt Voucher
SWIFT Society of Worldwide International Financial Telecommunication
TIN Tax Payer Identification Numbering
UK United Kingdom
GLOSSARY OF TERMS
TERM DEFINITION
Acceptance Refers to the acceptance of goods, works or services by the
Purchaser/Employer/Client.
Contract package The logical assembly of items within a contract that takes into
consideration timeliness, economies of scale, geographic
distribution, etc.
Economy Buying only what is needed for the project at the lowest evaluated
price.
Force Majeure An event that interferes with the performance of a contract which
an experienced supplier or contractor or consultant could not have
foreseen nor reasonably made provision for, e.g., war, riot, and
earthquake.
Indefinite Delivery Framework Contract for on-call specialized services for which the
Contract extent and timing cannot be defined in advance.
Parallel financing Co-financier agrees to finance specific contracts in a project and its
procurement procedures apply for the items it finances.
Plant Any integral part of the works that have a mechanical, electrical,
chemical, or biological function.
Post review A review by the funding agency of awarded contracts and related
procurement documentation below a stated contract threshold.
Procurement plan The document prepared by each procuring entity annually to plan
all procurement requirements necessary to perform the activity plan
of the procuring entity. The plan shall indicate:
(a) contract packages,
(b) estimated cost for each package,
(c) the procurement method, and
(d) processing steps and times.
Technical Services Services which are tendered and contracted on the basis of
performance of a measurable physical output such as drilling,
mapping, aerial photography, surveys, seismic investigations,
maintenance of facilities or plant and similar operations.
INTRODUCTION
Background
Since the establishment of the Public Procurement Authority (PPA) as a result of the promulgation
of the Public Procurement Act, 2003 (Act 663) Amended, it has instituted a number of pragmatic
and far-reaching initiatives aimed at ensuring maximum returns for the tax-payers’ money. Despite
these laudable efforts, the annual procurement assessment conducted by the PPA in the
procurement entities reveal several challenges relating to the administration of contracts awarded
by most entities.
These challenges can be attributed to the absence of credible arrangements for contract
administration. The observation has been that contract administration in most public procurement
entities usually involve disjointed processes unfortunately resulting in poor supervision of
contracts and compliance as well as missed opportunities for achieving value for money. As part
of the means to address the above challenges, the PPA commissioned a firm to develop separate
contract administration manuals for Goods, Works, Consulting Services and Technical Services.
There are four Manuals on contract administration. Manual 1 is on Goods, Manual 2 is on Works,
Manual 3 is on Consulting Services and Manual 4 is on Technical Services. To have full
knowledge of contract administration in Public Procurement, one will need to read all the four
Manuals. It is hoped that the manuals will prove to be useful as a handbook or resource material
for practitioners, facilitators and students.
Introduction
1.0: Contract Principles
2.0: Basics of Contract Administration
3.0: Forms and Conditions of Standard Contract for Goods
4.0: Contract Administration Process: Post-Award Preliminary Tasks
5.0: Monitoring Contract Performance & Reporting
6.0: Managing Contract Changes/Variations
7.0: Payments
8.0: Claims & Settlement of Disputes
9.0: Termination of Contract
10.0: Contract Records Management
11.0: Evaluation of Contract Performance
12.0: Post- Implementation Tasks
13.0: INCOTERMS
Forms/Templates
In some of the chapters, templates/formats deemed useful have been presented in Appendix 1.
1.1 Introduction
The award of a contract is essential to public procurement as it marks the starting point for contract
execution and administration. Some basic legal concepts relating to contracts are explained.
A contract may be oral or written. However, contracts financed with public funds are generally
made up in writing.
According to Public Procurement Act, 2003 (Act 663) as Amended, “a ‘procurement contract’
means a contract between the procurement entity and a supplier, contractor or consultant
resulting from procurement proceedings.”2
b) Certainty – The parties to the contract must be of the same mind about what is being
offered and accepted and thus the essential terms must be definite and agreed upon by
them.
c) Consideration – The parties to a contract must each give something of legal value to the
other or a third party in return for the benefit he/she receives.
d) Legality of Purpose/Object – The object of the contract must not be one of which the law
disapproves. The law will not enforce an illegal contract, or when it is against public policy.
1
Culled from Gosta Westring and George Jadoun (Rev.15th November 1996). Public Procurement Manual.
2
Refer to Section 98 of Public Procurement Act, 2003 (Act 663) as Amended.
Acceptance of an offer poses few legal problems so long as it is a “clean” acceptance, meaning
that no reservations are attached. Acceptance, thus, must be positive, unconditional, unequivocal
and unambiguous.
Attaching reservation to an acceptance generally constitutes a counter offer. In most legal systems,
a counter offer counts as a rejection of an offer, unless specifically permitted.
The importance of the applicable law, then, is first of all to regulate matters which the parties have
not addressed in their contract and, secondly, to hold the parties within limits drawn up by the
stringent provisions of the law. In addition, the applicable law is used by the judge or arbitrator to
interpret the contract and to fill gaps in the contract where no contractual provisions exist.
Under Public Procurement Act, 2003 (Act 663) as Amended, the Law Applicable to a Contract
is that of Ghana.
The standard forms of contract for goods procurement under the Public Procurement Act, 2003
(Act 663) as amended. are as follows:
i. Standard Contract for Request for Price Quotations
ii. Standard Contract for National Competitive Tendering & Restricted Tendering
iii. Standard Contract for International Competitive Tendering
iv. Framework Agreement
The standard forms of contract have terms and conditions. Most contracts for goods procurement
are of short-duration and therefore fixed price. Long duration contracts, usually exceeding
eighteen (18) months will have a provision for price adjustment in the terms and conditions.
It has to be noted that no contract exists until the procurement entity issues a Purchase Order (PO)
or “call-off” against the Framework Agreement.
2.1 Introduction
Contract administration is the management of contracts made with suppliers, contractors,
consultants or technical service providers to assure that all the parties comply with and fulfil
the terms and conditions of the contract.
It includes all dealings between parties to a contract from the time a contract is awarded until the
task has been completed and accepted or the contract terminated, payment has been made, disputes
have been resolved and the contract closed.
Contract Administration is the responsibility of the Procurement Entity and is distinguished from
physical performance of the contract which is the responsibility of the Supplier, Contractor,
Consultant or Technical Service Provider.
The stages of Contract Administration are intended to ensure that the parties work together to
achieve the objectives of the contract. Contract Administration is based on the idea that the contract
is an agreement, a partnership with rights and obligations that must be met by both sides to achieve
the goal. Contract Administration is aimed not at finding fault, but rather at identifying problems
and finding solutions together with all contracting parties involved.
Although the actual planning begins during the selection process, Contract Administration actually
starts upon the signing of the contract, which is the point at which the parties to the contract are
bound by its terms and conditions. As with contract management, contract administration ensures
that each party adheres to the contract and performs at or above the levels specified in the contract.
If we compare the nature or characteristics of the activities associated with both contract
management and contract administration (see below) then we can see that the differences are
fundamental, yet without efficient contract administration, then effective contract management
becomes very difficult, if not impossible.
3
UN Handbook on Procurement, 2006
7 Public Procurement Authority (PPA), Ghana
Contract Administration Manual For Goods – Manual 1
Contract Management Contract Administration
Relationship focus Operational focus
Strategic Tactical
Process development Process compliance
Longer term time frame Short-term/transactional
Holist view Narrow focus
Driven by added value Driven by key performance indicators
In the light of the above, most organizations/institutions use the two interchangeably.
However, in this Module, the Public Procurement Authority (PPA) has decided to use the term
‘Contract Administration’.
The two parties-Procurement Entity and Supplier- and their assigns are bound by the terms
and conditions of the contract.
Funding
Agency 2 Courts
Public Ministry of
Procurement Justice/AGD
Authority
Funding
Auditor-General
Agency 1
Controller &
Accountant General
Sources of
Information
Sources of
PROCUREMENT Information
ENTITY
The roles and responsibilities of the bodies that are involved in post contract activities are:
Finance/Accounts Department
The Department within the Procurement Entity responsible for the financial affairs of the Entity
and the control of the Entity’s budget.
The number of staff in the contract administration process will vary in number from one to many
depending on the nature, size, level of risk and complexity of the contract. Early in the procurement
process, there is the need to identify the contract administrator and those who are to assist him/her;
this will allow for roles and responsibilities to be assigned.
It is worth noting that in most simple supply of goods contracts, the Expeditor, acting as the
Contract Administrator can handle all responsibilities with the support of an Assistant.
Participating, as necessary, in developing the solicitation and writing the draft documents.
(Contract administration must be considered during this process.)
Monitoring the Supplier’s performance to ensure that delivery conforms to the contract
requirements.
Authorizing payments consistent with the contract terms.
Exercising remedies, as appropriate, where a Supplier’s performance is deficient.
Facilitating resolution of disputes in a timely manner.
Meeting with the Supplier when the need arises so as to review progress, discuss problems
and consider necessary changes.
Establishing control of correspondence, data and reports.
Identifying potential problems and solutions.
Managing any public property used in contract performance.
Documenting significant events.
Maintaining appropriate records.
The most frequent causes of badly managed contracts are often linked to:
(i) the capacity of the contract administration team
(ii) its willingness to act according to its mission and purpose, and/or
14 Public Procurement Authority (PPA), Ghana
Contract Administration Manual For Goods – Manual 1
Poor capacity, while dangerous for the contract implementation, can be remedied through
continuous and intensive training (both formal and on-the-job); hiring staff with the appropriate
expertise and experience; and through close supervision. Consequently, the negative effect of lack
of capacity can be successfully mitigated, especially if the issue of capacity is addressed at an early
stage during contract implementation.
Lack of willingness to act in the best interest of the contract can have two major causes, which are
radically different from an ethical perspective, but can be equally damaging to the success of
contract implementation:
i. The first cause (which is more benign and thus potentially less harmful) has to do with the
lack of motivation of the staff. This can also have many causes: dissatisfaction with the
level of remuneration; lack of professional challenges; eroding routine; lack of recognition
from the superiors; sense of futility etc. These symptoms must be identified early in the
implementation stage and properly addressed through appropriate management decisions
(incentives; motivation; correct allocation of tasks and responsibilities; correlation between
responsibilities and rewards; increased ownership of the process etc.)
ii. The second possible cause of staff inactivity has its roots in fraud and corruption and is
therefore the most dangerous risk during contract implementation. Whenever corruption is
involved, there is a high degree of certainty that the proper execution of the contract is
compromised in one way or another.
Delay in payment most often can be attributed to lack of funds from central government or
improper cash flow planning by the procurement entity. It is only in rare instances that it can be
due to deliberate unwillingness of the contract administration team to act.
As part of international best practices, guidelines and tender documents of international financing
institutions as well as national procurement systems have provisions which require Suppliers and
15 Public Procurement Authority (PPA), Ghana
Contract Administration Manual For Goods – Manual 1
their agents to observe the highest standard of ethics during execution of contracts. The following
forms of corrupt and fraudulent practices are defined here for the attention of Suppliers:
b) “Collusive practice” means a tacit or explicit agreement between two or more parties to
perform a coercive, corrupt, fraudulent, obstructive or prohibited practice, including any
such agreement designed to establish prices at artificial, noncompetitive levels or to
otherwise deprive the Employer of the benefits of free and open competition,
d) “Fraudulent practice” means any act or omission, including any misrepresentation, that
misleads or attempts to mislead a party in order to obtain a financial or other benefit in
connection with the implementation of any contract supported, in whole or in part,
including any act or omission designed to influence or attempt to influence the execution
of a contract, or to avoid or attempt to avoid an obligation.
e) “Obstructive practice” means any act taken in connection with the implementation of any
contract supported, in whole or in part:
i. That results in the destroying, falsifying, altering or concealing of evidence or making
false statement(s) to investigators or any official in order to impede an investigation
into allegations of a coercive, collusive, corrupt, fraudulent or prohibited practice,
ii. That threatens, harasses or intimidates any party to prevent him or her from either
disclosing his or her knowledge of matters relevant to an investigation or from pursuing
the investigation and/or
iii. Intended to impede the conduct of an inspection and/or the exercise of audit rights
provided under Act 663 as amended and related regulations, manual agreements and
standard tender documents, and
f) “Prohibited practice” means any action that violates Compliance with Anti-Corruption,
Anti-Money Laundering, Terrorist Financing, and Trafficking in Persons Statutes and
Other Restrictions of the United Nations.
Despite all efforts to prevent and fight these practices by International Financing Institutions and
Public Anti-Corruption Agencies, corruption still persists. The most frequent cases of fraud and
corruption involve:
Scope of the contract is not achieved as goods ordered are not delivered per the Purchase
order, although the money has been spent;
Unjustified variations and change requests granted by the Procurement Entity;
Products are substituted by inferior, less expensive and lower quality products than
specified in the contracts;
Delay in delivery/installation of Goods and Equipment.
However, all these precautionary measures should not be interpreted as instigations to abuse the
contract mechanisms and remedies against the Supplier. Overzealous and abusive Contract
administration is equally dangerous in terms of perceived fraud and corruption because any
obvious tendency to abuse the discretionary powers could be interpreted as an attempt to force the
Supplier into agreeing to kickbacks or other kinds of informal payment.
Without limitation on the generality of the foregoing, a Supplier, including all parties constituting
the Supplier and any agents or sub-suppliers for any part of the Contract, including related services,
and their respective personnel and affiliates may be considered to have a conflict of interest in
terms of Conflicting activities, Conflicting assignments and Conflicting relationships and in the
case of a Supplier, the Contract may be terminated.
A Supplier has an obligation to disclose any situation of actual or potential conflict of interest that
impacts their capacity to serve the best interest of the Procurement Entity or that may be reasonably
perceived as having this effect. Failure to disclose said situations may lead to the termination of
the Contract.
3.1 Introduction
This chapter identifies the set of documents that comprise a goods contract and explains the types
of PPA Standard Forms of Contract, including the General Conditions of Contract and the Special
Conditions of Contract.
WHEREAS the Purchaser invited bids for certain goods and ancillary services, viz.,
1. In this Agreement words and expressions shall have the same meanings as are respectively
assigned to them in the Conditions of Contract referred to.
2. The following documents shall be deemed to form and be read and construed as part of this
Agreement, viz.:
4. The Purchaser hereby covenants to pay the Supplier in consideration of the provision
of the goods and services and the remedying of defects therein, the Contract Price or such other
sum as may become payable under the provisions of the contract at the times and
in the manner prescribed by the Contract.
(b) authorization in the form of a Purchase Order (PO) generated from the Ghana
Integrated Financial Management Information Systems (GIFMIS) or in a form specified
by the Ministry of Finance (MoF) pursuant to the Applicable Law;
(c) the fulfillment of conditions precedent such as the submission of performance bond, if
any, that may be required on the part of either party under the Agreement or under the
Applicable law.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in
accordance with their respective laws the day and year first above written.
Name: Name:
Designation: Designation:
Sign: Sign:
Seal: Seal:
The Price Quotation Form of Contract is the simplest of the standard forms of contract of the PPA
and has one set of integrated Conditions of Contract with seventeen (17) clauses, ranging from
Definitions to Operations, Maintenance and Spare Parts Manual.
Contract Form
THIS AGREEMENT made the _____ day of ________[mm] 20_____ between [name of Purchaser] of
[country of Purchaser] (hereinafter called “the Purchaser”) of the one part and [name of Supplier] of [city
and country of Supplier] (hereinafter called “the Supplier”) of the other part:
WHEREAS the Purchaser invited Tenders for certain goods and ancillary services, viz., [brief description
of goods and services] and has accepted a Tender by the Supplier for the supply of those goods and services
in the sum of [contract price in words and figures in Cedis] (hereinafter called “the Contract Price”).
1. In this Agreement words and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract referred to.
2. The following documents shall be deemed to form and be read and construed as
part of this Agreement, viz.:
(a) the Tender Form and the Price Schedule submitted by the Tenderer;
(b) the Schedule of Requirements;
(c) the Technical Specifications;
(d) the General Conditions of Contract;
(e) the Special Conditions of Contract;
(f) the Purchaser’s Notification of Award; and
(g) Contract Data Sheet (to be used only when there are corrections to the original price schedule
submitted by the supplier).
4. The Purchaser hereby covenants to pay the Supplier in consideration of the provision of the goods and
services and the remedying of defects therein, the Contract Price or such other sum as may become payable
under the provisions of the contract at the times and in the manner prescribed by the Contract.
(b) authorization in the form of a Purchase Order (PO) generated from the Ghana Integrated Financial
Management Information Systems (GIFMIS) or in a form specified by the Ministry of Finance
(MoF) pursuant to the Applicable Law.
(c) the fulfillment of conditions precedent such as the submission of performance bond, if any, that
may be required on the part of either party under the Agreement or under the Applicable law.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in accordance
with their respective laws the day and year first above written.
Name: Name:
Signature: Signature:
Designation: Designation:
Seal: Seal:
Date: Date:
Name: Name:
Signature: Signature:
Designation: Designation:
Date: Date:
Contract
THIS AGREEMENT made the day of, _________ between _______________of (hereinafter
“the Purchaser”), of the one part, and of (hereinafter “the Supplier”), of the
other part:
WHEREAS the Purchaser invited Tenders for certain Goods and Related Services, viz., and has
accepted a Tender by the Supplier for the supply of those Goods and Related Services in the sum
of_____-_______ (hereinafter “the Contract Price”).
1. In this Agreement words and expressions shall have the same meanings as are respectively
assigned to them in the Contract referred to.
2. The following documents shall be deemed to form and be read and construed as part of this
Agreement, viz.:
4. The Purchaser hereby covenants to pay the Supplier in consideration of the provision of the Goods
and Related Services and the remedying of defects therein, the Contract Price or such other sum as
may become payable under the provisions of the Contract at the times and in the manner prescribed
by the Contract.
IN WITNESS whereof the parties hereto have caused this Agreement to be executed in
accordance with the laws of Ghana on the day, month and year indicated above.
Name
Signature
Witnessed by
Name
Signature
Witnessed by
ITT 36.4(b) requires that no agreement shall be valid unless a purchase is duly authorized in
the form of a Purchase Order (PO) generated from the Ghana Integrated Financial Management
Information Systems (GIFMIS) or in a form specified by the Ministry of Finance (MoF)
pursuant to the relevant laws on public expenditure under the Applicable Law. Until then any
written acceptance of the Tender/notification of award, shall not constitute a binding Contract
1. Definitions- The definitions are for the interpretation of terms used in the contract.
2. Application- These General Conditions shall apply to the extent that they are not
superseded by provisions in other parts of the Contract
3. Country of origin- All goods and services supplied under the contract shall have their
origin in Ghana or in eligible countries as specified in the Special Conditions of Contract.
For purposes of this clause “origin” means the place where the goods are mined, grown,
produced or manufactured, or from which Services are supplied. The origin of goods and
services is distinct from the nationality of the Supplier
4. Standards- Goods supplied under this Contract shall conform to the standards or codes
mentioned in the Technical Specifications, and, when no applicable standard is mentioned,
to the authoritative standards appropriate to the Goods’ country of origin. Where such
standards and codes are national or relate to a particular country or origin, other
authoritative standards that ensure substantial equivalence to the standards and codes
specified will be acceptable. Such standards shall be the latest issued by the concerned
institution unless otherwise expressly stated in the Contract.
5. Use of Contract Documents and Information- The Supplier shall not, without the
Purchaser’s prior written consent, disclose the contract, or any provision thereof, or any
specification, plan, drawing, pattern, sample, or information furnished by or on behalf of
the Purchaser in connection therewith, to any person other than a person employed by the
Supplier in the performance of the Contract. The Supplier shall make use of the said
information only for purposes of performing the Contract. Any other mentioned document
apart from the Contract shall remain the property of the Purchaser and shall be returned
by the Supplier to the Purchaser on completion of the Contract if so required.
6. Patent Rights- The Supplier shall indemnify the Purchaser against all third-party claims
of infringement of patent, trademark, or industrial design rights arising from use of the
Goods or any part thereof in the Purchaser’s country.
7. Performance Security- The Supplier shall furnish the Purchaser with a performance
security within fourteen (14) days after receipt of notification of award of contract. The
proceeds of the security shall be paid to the Purchaser by the Supplier as a compensation
for any loss in case of breach of contract or non-performance by the latter. The amount of
the performance security and the period of warranty shall be specified in the SCC. This is
normally 5% to 10% of the Contract price. The security shall be in the form provided for
in the Tender Document or any other form acceptable to the Purchaser. It will be
discharged by the Purchaser and returned to the Supplier not later than 28 days after the
expiration of the one year warranty period following the date of issue of the certificate of
final acceptance of equipment and after the installation and commissioning of the
equipment.
8. Inspections and Tests- The Purchaser has the right to inspect and/or to test the goods to
confirm their conformity to the Contract specifications. The specific scope and procedure
to be followed for the inspection and tests are specified in the SCC. The Purchaser may
reject the goods if it does not conform to the specification. The Supplier shall replace the
rejected goods or make alterations necessary to meet the specification at no extra cost to
the Purchaser.
9. Packing- This condition specifies that the Supplier shall provide such packing for the
Goods as is required to prevent their damage or deterioration during transit to their final
destination, as indicated in the Contract. The Supplier is also to adhere to any additional
packing requirement specified in the SCC or subsequently instructed by the Purchaser.
10. Delivery and Transfer of Risk- This requirement of the contract shall normally be in
accordance with the INCOTERMS governing the supply of the goods, otherwise it should
follow international practice or as specified in the SCC.
11. Insurance – The goods supplied under the Contract shall be fully insured in a freely
convertible currency against loss or damage incidental to manufacture or acquisition,
transportation, storage and delivery. This shall be in accordance with the stated
INCOTERMS in the Contract, otherwise it should be as specified in the SCC or must
follow international practice.
12. Transportation- Unless otherwise specified in the SCC, responsibility for arranging
transportation of the goods shall be in accordance with the stated INCOTERMS in the
Contract.
13. Incidental Services-Incidental services may be part of the Contract, to the extent that they
are specified elsewhere in the contract document, usually in the SCC. This may require the
Supplier to provide a supervision service on site for assembly/or start- up of the supplied
goods, furnishing of tools required for assembly, training of the Purchaser’s personnel at
the Supplier’s plant and also maintenance or repair of the goods for an agreed period of
time. This does not, however, relieve the Supplier of any warranty obligations under the
contract.
14. Spare Parts- Spare parts may be part of the Contract , to the extent that they are specified
elsewhere in the contract document , usually in the SCC
15. Warranty-The Supplier warrants that the quality of the goods meet the specification
requested for in the Tender document. This provision protects the Purchaser in case of poor
quality of the goods, during a certain period of delivery, which is to be specified in the
SCC. It shall remain valid for 12 months after the goods have been delivered to the final
destination indicated in the Contract, installed and commissioned to the satisfaction of the
Purchaser.
16. Payment- Payment terms and methods shall be in accordance with international
commercial practices applicable to the specific goods. General principles are specified in
the GCC, while specific terms and methods applicable to the Contract shall be specified in
the SCC. Letters of credit are normally used to pay for imports. The documentation required
is specified in the SCC
17. Prices-Prices charged by the Supplier for goods and services delivered and services
performed under the Contract shall not vary from the prices quoted by the Supplier in its
Tender, with the exception of any price adjustments authorized in the Special Conditions
of Contract. The price adjustment formula must be stated in the SCC.
18. Change Orders- The provisions and obligations of either party to the contract may have
to be changed within the general scope of the contract. This may include, for example
drawings, designs, method of shipment, packing, place of delivery and or services to be
provided. If any such change causes an increase or decrease in the cost of the time required
for the Supplier’s performance of any provisions under the contract, an equitable
adjustment may be made in the contract price or delivery schedule, or both, and the Contract
may accordingly be amended. Any claims by the Supplier for adjustment under this clause
must be assessed within twenty-eight (28) days from the date of the Supplier’s receipt of
the Purchaser’s change order. This has to be in writing.
19. Contract Amendments-Variations or modification of the terms of the Contract can only
be made in writing and needs to be signed by the Parties
20. Assignment –The Supplier shall not assign, in whole or in part, its obligations to perform
under the Contract, except with the Purchaser’s prior written consent.
21. Subcontracts- The Supplier shall notify the Purchaser in writing of all subcontracts
awarded under this Contract if not already specified in the Tender .Such notification, be it
in the original tender or later, shall not relieve the Supplier from any liability or obligation
under the Contract.
22. Delays in the Supplier’s Performance-Delivery of the goods and performance of services
shall be made by the Supplier in accordance with the time schedule specified by the
Purchaser in the Schedule of Requirements.
23. Liquidated Damages- Subject to GCC Clause 25,if the Supplier fails to deliver any or all
of the goods or to perform within the time period(s) specified in the Contact, the Purchaser
shall, without prejudice to its other remedies under the Contract, deduct from the Contract
Price, as liquidated damages, a sum equivalent to 0.5% of the Contract price of the delayed
goods for each week of delay until actual delivery, up to a maximum deduction of 10% of
the delayed goods Contract price as is stated in the SCC. Once the maximum is reached,
the Purchaser may consider termination of the Contract pursuant to GCC Clause 24.
24. Termination for Default- Purchaser may terminate the Contract for default on the part of
the Supplier. Some of the circumstances for termination by the Purchaser for default are
when the Supplier fails to deliver any or all the goods within the time period(s)specified in
the Contract or if in the judgment of the Purchaser the Supplier has engaged in corrupt or
fraudulent practices in competing for or in executing the Contract. The related clauses
specify all the circumstances, implication and procedure for the termination.
25. Force Majeure- It is normal practice that contracts include a clause of force majeure. This
protects both parties from certain risks in events such as natural disasters, which are beyond
the control of either party, and have major consequences for the Contract.
26. Termination for Insolvency- The Purchaser may at any time terminate the Contract by
giving written notice, without compensation to the Supplier due to insolvency on the part
of the Supplier, provided that such termination will not prejudice or affect any right of
action or remedy which has accrued or will accrue thereafter to the Purchaser.
27. Termination for Convenience- Purchaser may terminate the Contract for convenience.
The related clauses specify the circumstances, implication and procedure for the
termination.
28. Resolution of Disputes- Disputes may occur during contract execution resulting in claims
from either party. General provisions are specified on how to settle disputes either by direct
informal negotiations, mutual consultation and amicable resolution, or arbitration. The
provision for international arbitration may be considered when the Supplier is from a
foreign country as this is seen as contributing to fairness of treatment of tenderers. Specific
procedures to be followed in the event of disputes and arbitration are specified in the SCC.
It requires that the dispute shall be settled by arbitration in accordance with the provisions
of the United Nations Commission on International Trade Law (UNCITRAL)
29. Governing Language- The Contract shall be written in the language as specified in the
SCC. Subject to GCC Clause 30, the version of the Contract written in English shall govern
its interpretation. All correspondence and other documents pertaining to the Contract which
are exchanged by the parties shall be written in the English language. Act 663 specifies
English as the governing language.
30. Applicable Law- The applicable law prescribed in the GCC is the law of the Purchaser’s
country, Ghana. This provision may be modified in the SCC, if need be.
31. Notices-Any notice given by one party to the other pursuant to the Contract shall be sent
in writing to the other party’s address as specified for that purpose in the SCC.
32. Taxes and Duties- The Supplier shall be entirely responsible for all taxes, duties, license
fees, etc incurred until delivery of the goods to the Purchaser. The application of this
general provision is straightforward, when the Contract is limited to the delivery of the
goods. In the case of more complex contracts, where the scope includes provision of related
services within the Purchaser’s country, the problem of tax liabilities may become more
complicated. Usually, the Supplier is made liable for taxes on related services. In such a
case appropriate specific provision shall be specified in the SCC
4.1 Introduction
Post contract-Award Preliminary Tasks are essential for the eventual success of contract
performance monitoring and any follow-up actions. These involve all the preparatory activities
necessary to enable commencement of contract implementation. The chapter discusses
formation of the contract administration team and assigning roles and responsibilities; setting
up administrative, financial/payment, time control and inspection and quality assurance
procedures; determining communications and reporting requirements; preparation of contract
administration plan, including contract milestones; determining meeting procedures; and
devising verification procedures of securities and insurance policies.
The Contract Administration plan should aim at identifying the administrative and technical
tasks required for the successful performance of the contract and at putting in place “checks
and controls” to detect non-performance by either the Procurement Entity or the Supplier at
the appropriate time in order to reduce the risks to the delivery of the procurement package
caused by possible implementation problems.
Deliverables
Read your contract thoroughly and create checklists for all contract deliverables.
When you list the contract deliverables, make note of specific standards for acceptance
and allowances for substitutions.
Schedules
Contracts cover a specific period. The contract administration plan must include a
schedule for startup dates, deadlines for deliverables/requirements and the closing date
of the contract.
Take note of milestones that affect the production or submission of any deliverables,
and put them into the contract calendar.
The master schedule with milestones and deadlines is a planning tool that your
institution can use to monitor progress and adjust the contract administration plan.
Finances
Your institution must have a contract budget that details expenses to be incurred in the
performance of the contract. The person responsible for financial administration also
needs to reconcile projected expenses against actual expenses.
The person who manages the contract budget must know what documentation
accompanies every invoice and how payment will be made.
Expenditure on the contract will also be posted in the organization’s books in a manner
that lets you track contract accounts receivables and payments.
Work Plan
Create a work plan that allocates the personnel and financial resources required to meet
the terms of the contract.
Assign responsibilities for each deliverable to internal personnel or identify temporary
help and external experts you need to meet contract schedules.
Draft a reporting schedule that keeps you informed of resources required, resources
allocated and the cost burden of your resources
Contract Effectiveness
This is usually stated in the contract and the period usually starts from the date of contract
signature or as otherwise stated in the contract. Whatever definition is used in the contract is to
facilitate calculating the effective date of the contract. It should not be assumed that the
definition of effectiveness is the same between contracts. The date of effectiveness is usually
the date by which all else in the contract is calculated (i.e. delivery periods). Occasionally a
Supplier may require a further period following effectiveness before delivery of other contract
variables can be calculated. Such a period may be termed a Contract Commencement (or a
Contract Mobilization)
Payments Made in Respect of the Goods in Accordance with the Contract Payment
Terms
The Contract Administrator’s task in respect of payments is to initiate the payment process by
verifying that the request for payment is in order and confirm that the payment be made
accordingly. In doing this the Contract Administrator is guided by the contract terms applicable
to each contract and by the total amount of payments already made against the contract. This
is monitored by the maintenance of a payment record for each contract which compares the
total payments made against the contract total value (including any amendments to contract).
A Contract Milestone Checklist Form is shown in Table 1 and includes a number of typical
tasks that may be covered in a contract.
As can be seen in Table 1, a complete view of the likely timescale and all associated tasks that
must be completed prior to receiving the actual goods concerned, are fully apparent to the
Contract Administrator.
Contract commencement
Does the contract manager have the required level of skills and experience?
Does the contract manager have a satisfactory level of understanding of the contract
and of the relevant subject matter?
Have risks to the management of the contract been identified and risk treatments
identified?
Is it clear who is responsible for implementing any necessary risk treatments?
Has responsibility for all aspects of managing the contract been clearly assigned?
Do delegations exist for the approval of contracts, contract variations and the approval
of expenditure?
Have all stakeholders been identified and arrangements agreed to obtain feedback/input
throughout the life of the contract?
Have the benefits of flow charting internal processes, e.g. dispute escalation
arrangements, been considered?
Ongoing management
Are contract payments linked to satisfactory contract performance?
Are all invoices, and any supporting documents, checked to ensure they are in
accordance with contract requirements and are in order to be paid?
Is timely action taken when contract performance is unsatisfactory?
Are all variations to the contract agreed on value-for-money grounds?
Are all amendments to the contracts subjected to formal contract variations? Is a record
maintained of all contract variations?
Where the contract does not meet agreed levels of performance, are any actions taken
adequately documented? Where it is decided not to take action, is this decision properly
approved and documented?
For longer term contracts, is the contract subject to periodic review?
Are disputes addressed in a timely manner and satisfactory efforts made to resolve
them?
Is the contract being actively managed so that there is reasonable assurance that the
contract outcomes are being achieved?
Contract extension/renewal
Do systems/procedures enable the timely consideration of the need for contracts to be
extended or renewed?
Are all contract extensions justified on value for money grounds?
Are there arrangements in place designed to ensure that probity issues are identified
and addressed during contract extension and re-tender processes?
A special mention should be made regarding the requirement that the Supplier maintains a
(reduced) performance security during the warranty period. The Purchaser shall make sure that
the security is duly provided and is enforceable throughout the warranty period.
Purchaser’s staff should check if the policies have been contracted, paid and maintained
according to the conditions of the contract. Important aspects to consider:
Insured parties – does the Cargo Insurance and Installation “All Risks” Insurance
expressly name both the Purchaser and the Supplier as jointly insured? Policies where
only the Supplier is insured are not acceptable as they may leave the Purchaser liable
for certain risks.
Exclusions – events (risks) that are not covered by the insurance policy (i.e. if the goods
are damaged following the occurrence of an excluded event, the insurer does not pay
for the damage). There are many cases where the Supplier gets very cheap insurance
precisely because most events are excluded (usually through “silent” addenda to the
insurance policy). This is why the Purchaser should always check the exclusions of the
policies and should request directly from the insurance company confirmation about
the exact list of exclusions and their applicability.
Terms and conditions that may render the policies invalid under certain circumstances
or events – the Purchaser should check any conditions attached to the insurance policies
such as prior notification requirements and any other clauses that may affect its rights
4.7 Inspections
The reason for inspecting goods is to ensure their conformance to the specifications of the
Purchase Contract. This may be done by an outsourced inspection company at the country of
shipment, at the port of destination or by the Procurement Entity .The Procurement Entity’s
storekeepers and technical staff or the inspection committee/department may perform the
inspection function. It normally consists of quality inspection combined with checks of the
quantity or weight/volume of the goods, their marking and packing. Common methods of
inspection include visual inspection, performance, and safety testing.
Visual inspection is normally conducted by the inspection team, who would look at the
physical appearance of the item supplied so as to ascertain if it complies with the specification
provided by the Purchaser to the Supplier.
Performance testing is done by the inspector subjecting the item supplied to a strict test so as
to determine whether it complies with the performance specification or requirements
Safety test is conducted by subjecting the item supplied to a strict check to ensure that it would
not compromise the health and safety of the user department. For example, a sample of lime
hydrated supplied for water treatment would be tested by the Chemist/Bacteriologist to
ascertain if it is safe to be used for water treatment or not. His/her report will determine whether
the bulk consignment supplied should be accepted or rejected by the Procurement Entity.
The following activities need to be undertaken before goods can be received into the
Procurement Entity’s store:
Verification
Checking technical requirements
Certification
Verification
The receipt of non-technical items at the store requires that the verification procedures listed
below are followed by the Stores Unit
Check the number of cases or other packaging units against the delivery docket’s detail.
Sign for the number of cases or other units against the delivery docket details.
If a detailed check is not possible, write the word,’ unchecked’ on delivery document
before signing them
Check the quantity received against the packing or delivery note.
Notify the superior officer if the material is damaged or if there is a discrepancy in
quantity and prepare a ‘Claim Form’.
Checking
Certain items delivered to the store require checking by inspectors with the necessary technical
competency, from the Procurement Entity, before they are accepted. This is to ensure that the
items, delivered by the Supplier, comply with the specification on the Purchase Order (PO) and
the sample(s), if any.
Certification
This requires the exercise of engineering judgment where progress payment is to be made
before the contract is completed.
A typical contract such as the manufacture of a large steam boiler would allow for payment to
be made at the various stages of the work. At certain stages, judgment must be made of the
total value of the job, which has been completed. The user department or Consultant prepares
an engineer’s certificate stating that work to the invoiced value had been properly done (or
materials to the invoiced value had been delivered in good condition, on time, etc.) The
Contract Administrator may then initiate payment request on behalf of the Supplier.
Under GCC 8.2 the inspections and tests may be conducted on the premises of the Supplier or
its sub-Supplier(s) at point of delivery and/or at the Goods final destination. If conducted on
the premises of the Supplier or its sub-Supplier(s), all reasonable facilities and assistance,
including access to drawings and production data, shall be furnished to the inspectors at no
charge to the Purchaser.
GCC 8.3 stipulates that should any inspected or tested Goods fail to conform to the
Specifications, the Purchaser may reject the Goods, and the Supplier shall either replace the
rejected Goods or make alterations necessary to meet specification requirements free of cost to
the Purchaser.
GCC 8.4 states: “The Purchaser’s right to inspect, test and, where necessary, reject the goods
after the goods arrival in the Purchaser’s country shall in no way be limited or waived by reason
of the goods having previously been inspected, tested and passed by the Purchaser or its
representative prior to the goods’ shipment from the country of origin.”
5.1 Introduction
During contract performance, the contract administrator and his team must observe
performance, collect information, and measure actual contract progress and prepare reports.
These activities are essential to effective control. The purpose is to ensure that the consultant
is performing all duties in accordance with the contract and for the Procurement Entity to be
aware of and address any developing problems or issues.
The resources devoted to these tasks and the techniques used to perform them will depend on
the nature of the contract work, the size and complexity of the contract, and the resources
available.
Monitoring contract performance covers key areas of contract administration, namely: time
control, quality and quantity control, resolution of performance problems & contract remedies,
internal and external communication, processing payments, contract modifications/changes,
site visits, maintaining contract documentation, scheduling and holding meetings and
managing securities and insurance policies.
“The Purchaser or its Representative shall, at no extra cost, have the right to inspect and/or
to test the goods to confirm their conformity to the contract. The Special Conditions of Contract
and /or the Technical Specifications shall specify what inspections and tests the Purchaser
requires and where they are to be conducted. The Purchaser shall notify the Supplier in writing
of the identity of any representatives retained for these purposes within 21 days after award of
the contract.”
The above GCC Clause is to ensure that the Supplier does not deviate from delivering the
required specification. It is therefore seen as a means to achieve strict quality compliance with
the PO.
.
GCC Clause 15.1 addresses the issue of warranty. It requires that the Supplier warrants that
the Goods supplied under the Contract are new, unused, of the most recent or current models,
and that they incorporate all recent improvements in design and materials unless provided
otherwise in the Contract. The Supplier further warrants that all Goods supplied under this
Contract shall have no defect, arising from design, materials, or workmanship (except when
the design and/or materials is required by the Purchaser’s specifications) or from any act or
omission of the Supplier that may develop under normal use of the supplied Goods in the
conditions prevailing in the country of final destination.
Functional guarantee could also help to achieve quality control in Goods procurement. It may
be in the form of a need to have standard rating for the items to be supplied from a recognized
body, such as the International Organization for Standardization (ISO) or its equivalent. The
Supplier may also be required to issue warranty with respect to the items supplied.
Performance problems could affect timely delivery of supplies as well as result in delayed
payment to the Supplier.
The Contract Administrator must do well to tackle performance problems by taking the
following steps:
Interpret contract clauses related to the problem. Clause 22 of the GCC for example
addresses delays in Supplier’s performance.
Collect evidence from all parties
Establish facts
Determine cost/delivery impact related to the problem
Devise an optimum solution
Inform parties concerned of decision taken in writing
In order to avoid problems with communication between the Procurement Entity and the
Supplier, the following need to be observed:
Deadlines for communication must be adhered to
Any notice, consent approval or decision by any person required by the contract shall
be made in writing unless otherwise defined in the contract
The Contract Administrator must ensure that the established procedures are followed and that
payments are in compliance with contract provisions. The Contract Administrator must also
ensure that over payments are avoided and payment is made for accepted goods and associated
services only. Delays in processing payment requests may result in a Supplier raising claims
for interests on delayed payments.
5.10.4 Insurance
From the Supplier’s factory and or warehouse en route to the buyer’s place of delivery, goods
may often have to cover long distances by various modes of transport. The goods supplied
under the contract must be insured against loss or damage incidental to manufacture or
acquisition, transportation, storage and delivery in the manner specified in the conditions of
contract. Such insurance shall be arranged and paid for by the Supplier as indicated in SCC
11.1.
After the approval by the Entity Tender Committee, the Contract Administrator must ensure
that:
7.0 PAYMENTS
7.1 Introduction
It is the obligation of the Contract Administrator to initiate payment process following the
supply of goods by the Supplier. The Supplier is required to deliver the goods ordered by the
Procurement Entity to a designated point by a specified date. The Supplier’s delivery obligation
may be specified by the applicable INCOTERMS used in the contract (INCOTERMS are
covered in Chapter 13)
When this is done, the items are inspected by the inspection team/committee, which includes
the Procurement Officer, Storekeeper, User Department, etc. A pre-audit is undertaken by the
Internal Audit Unit and passed if there is no audit query of the items supplied. The goods are
accepted by the Storekeeper if there is strict compliance with the specification, amount and
quantity as contained in the GIFMIS generated Purchase Order, the invoice and waybill. The
Storekeeper then prepares a Stores Receipt Voucher (SRV). This is forwarded together with a
copy of the Purchase Order and invoice to the Accounts department/Controller and Accountant
General’s Department for payment to be made to the Supplier.
7.4.1 Introduction
It is Government decision to deploy GIFMIS for the management of all public funds
(Consolidated Funds (CF), Internally-Generated Funds (IGF), Statutory Funds (SF) and Donor
Funds (DF)) across MDAs and MMDAs in the country, as part of the broader PFM reforms
programme. The use of GIFMIS for processing financial transactions at MDAs and MMDAs
started in 2012. It is a legal requirement to use GIFMIS for processing public financial
transactions under section 25(6) of the new PFM Act, 2016 (Act 921). The objective is to
improve efficiency, comprehensiveness and transparency in Public Financial Management
through the GIFMIS platform (Objective II of the PFM Strategy, 2015- 2018).
GIFMIS is jointly funded by four development partners- the (i). World Bank (ii). DFID of
UK (iii). European Commission-EU (iv). Danish International Development Agency-
DANIDA.
‘’The Ministry of Finance has observed with concern the indiscriminate award of contract
by Ministries, Departments and Agencies without due regard to their budgetary allocation.
With effect from 1st January, 2014, the Ministry is determined to safeguard the integrity of
the budget by ensuring that all contract awards are informed by the budgetary allocation
and cash ceiling.
Thus, beginning from January, 2014, the general public is being informed that this Ministry
will recognize contracts as valid if only they are duly authorized by PURCHASE ORDER
(PO) generated from the GIFMIS SYSTEM. (Please refer to paragraph 937 of 2014 Budget
Statement and Economic Policy.)
By this announcement the general public especially contractors and suppliers should take
note and ensure their contracts follow the due process to be assured of prompt payment’’
From the above announcement, it can be concluded that procurement planning, budget
approval, purchase order/contract award and contract administration (in terms of payments and
reporting) must all be linked to the GIFMIS platform.
It means that if the particulars of a Contractor, Supplier, Consultant or any other identified
procurement service provider are not linked to the GIFMIS Platform from the time of contract
award and subsequent approval on GIFMIS, the service provider will not be recognized for
payment during contract administration.
What Is GIFMIS?
The Ghana Integrated Financial Management Information System (GIFMIS) is an
integrated computerized financial management system used in:
Budget preparation
Budget Execution
Accounting and Financial Reporting
Cash Management.
Assets management
Human resource and payroll management
Among others
Aims of GIFMIS
To establish an INTEGRATED ICT-based PFM Information Systems in Ghana at the MDAs
located at National, Regional and District levels and MMDAs to improve efficiency in
public financial management including Consolidated Fund, IGF, Statutory Funds and Donor
Funds.
Why GIFMIS?
Lack of timely, accurate and current information on budgetary allocations,
commitments and actual revenue and expenditures
Publish Annual Financial Reporting and reduce delays in the payment processing
Poor feedback mechanism for assessing Budgetary Performance
Lack of uniform chart of accounts (COA) which make the comparison of the
performance of various budgets difficult.
Strengthen Internal Controls and Auditing Capabilities.
Modernize the Technical Infrastructure
Interface Data from Existing Data Stores
Empower Local Government Units
Enhance and Modernize Revenue Collection Processes
Performance
51 Public Procurement Authority (PPA), Ghana
Contract Administration Manual For Goods – Manual 1
Lack of uniform chart of accounts (COA) which make the comparison of the
performance of various budgets difficult.
Strengthen Internal Controls and Auditing Capabilities
Budget Preparation
The budget preparation steps include:
1. Budget circular and instructions issued by MoF to all MDAs/MMDAs (FAR 152 &
153)
2. MDAs/MMDAs prepare and submit their budget proposals/estimates to MoF (FAR
156)
3. MoF holds budget hearing with MDAs/MMDAs (FAR 161)
4. MoF consolidates MDAs/MMDAs budgets into a National Budget Estimates and
submits/presents it to Parliament for approval
5. Parliament debates the Budget and approves it for execution
Demand Source
1. Standard Purchase Orders: You generally create standard purchase orders for one-
time purchase of various items. You create standard purchase orders when you
know the details of the goods or services you require, estimated costs, quantities,
delivery schedules, and accounting distributions. If you use encumbrance
accounting, the purchase order may be encumbered since the required information
is known.
Setting up of Suppliers
Supplier details to be submitted on Company Letter Head to the MDAs/MMDAs to
be forwarded to the GIFMIS Secretariat for setup, are as follows:
Company details
1. Supplier Name (Company Name)
2. Tax Identification Number (TIN) – Attach Certificate of Registration
3. VAT Registration Number (for VAT registered companies)
4. Complete Address (Including P.O. Box, City/Town, Country)
5. Telephone Numbers
6. E-mail Address
NB.
1. Without Certificate of Registration suppliers will not be registered.
2. Going forward TIN numbers will be verified via a portal from GRA
before setting them up.
Implementation Strategy
Categorization of Fixed Assets in 3 Categories
Main (Transport Equipment)
Major (Motor Vehicles)
Minor (Salon Cars)
Mapping of Fixed Assets Categories to Natural Accounts which are used to
prepare Appropriation Budget.
FA has been deployed to the following MDAs:
CAGD, MOF, MOH, MWRWH, MTR
7.4.5 GIFMIS Implementation Status
1. Systems Set-ups
Hardware and software have been procured, installed and operational for:
Budget component
Financial Accounting(FA) component
2. System Rollout
The Financial Accounting Modules (Oracle EBS) have been rolled-out as follows:
All MDAs subsisting on consolidated fund resources since 2012
250 national Spending Units (SUs) covered • 350 Regional SUs covered
7 MMDAs out 216
49 IGF Institutions out of 59 are live as at end of April, 2016
Fixed Assets module at 5 headquarters MDAs
The Budget Modules was rolled-out to all MDAs since 2014
HRMIS Modules rolled-out to 3 MDAs (PSC, GSS, GFS) as at Feb. 2016.
Payroll module has been operational since the 1990s
3. System Maintenance
Business Continuity strategy was developed
Disaster recovery site operational and being upgraded
Tools have been installed for system security monitoring, service desk,
messaging and collaboration
Capacity building for GoG staff is on-going for enhanced system and user
support
Next Steps
1. Bringing on board other public funds
IGFs
Donor funds
Statutory funds
2. Extend financial modules to the remaining 209 MMDAs
3. Extend PBB and budget module to all MMDAs
4. Extend HRMIS module to all MDAs.
5. Complete interface with all key PFM Systems under the new PFM Strategy
6. Complete implementation of fixed assets module.
Some Challenges
Inadequate ICT infrastructure in the public sector of Ghana, especially
Network connectivity. NITA must be supported for this.
59 Public Procurement Authority (PPA), Ghana
Contract Administration Manual For Goods – Manual 1
Relatively low computer literacy in the public sector
Change management- expectation by end-users that the system should
support old ways instead of current best practices.
People having the Mentality that the system has failed before and will still
fail when enough progress has been made.
8.1 Introduction
Claims and disputes are inevitable in contract administration. It is only logical that when they do
arise concrete measures are taken to resolve them before they escalate.
8.2 Claims
A claim is a request from either party for entitlement under the contract that is not being fulfilled.
Claims might result from:
unforeseen costs
disputes over the interpretation of contract clauses
disputes over what is included within the contract price
breaches of contract
adjustment of contract performance duration.
Claims may be genuine and will have to be assessed for their merits. Protracted disagreements
over settlement of claims usually lead to disputes. Either the Procurement Entity or the Supplier
may make a claim in respect of procurement of goods contract. However, the most common case
is that of a Supplier submitting a claim for the Procurement Entity to pay interest on an outstanding
amount of money for goods supplied thirty (30) days after the agreed due date. (GCC16.4)
8.3 Disputes
A dispute normally arises under a contract when there is a disagreement about:
Money due to either party;
Time for performance
Performance standards
Interpretation of contract terms and conditions
As a general rule, a disagreement becomes a dispute when it is not possible for the parties to resolve
it without resort to a formal resolution mechanism. Generally, what a dispute is and when it is
deemed to have occurred is defined in the contract, often in a dispute resolution clause.
A dispute is to be avoided if possible as any dispute arising either during the life of a contract or
at its termination can be expensive and time consuming. It can add substantially to the cost of a
contract as well as nullifying some or all of its perceived benefits or advantages. If there is dispute,
a fast, efficiently and cost-effective dispute resolution procedure is essential.
Where a dispute arises, the Contract Administrator is to protect the Procurement Entity’s and hence
public interest in all cases.
GCC Clause 28.1 states that: “The Purchaser and the Supplier shall make every effort to resolve
amicably by direct informal negotiation any disagreement or dispute arising between them under
or in connection with the Contract”.
GCC Clause 28.2 says that “If, after twenty-eight (28) days from the commencement of such
informal negotiations, the Purchaser and the Supplier have been unable to resolve amicably a
Contract dispute, either party may require that the dispute be referred for resolution to the formal
mechanisms specified in the Special Conditions of Contract. These mechanisms may include,
but are not restricted to, conciliation mediated by a third party, adjudication in an agreed national
or international forum, and/or national and international arbitration”.
This contract provision is the same for International Competitive Tendering (ICT) contract on
Settlement of Disputes (GCC Clause 10.1-10.2)
Negotiating between the Procurement Entity and the Supplier is the most common approach to
resolving disagreements and disputes. Direct negotiation should always be used and all possible
efforts made to reach an agreement before progressing to other dispute resolution procedures. At
this stage of the procurement cycle, the intention of the negotiations is to reach a mutually
acceptable solution, where both sides consider they have gained the best possible result in the
circumstances. It is important that one party does not consider they have been unduly pressured to
agree to a particular solution as a result of the negotiation, as this can lead to an escalation or
reappearance of the dispute at a later stage.
At the early stages of a potential dispute it is generally preferable to attempt to resolve the matter
by first discussing the issues with the Supplier. These discussions may take place in the course of
regular meetings between the parties or as separate discussions. Such an approach may mean that
it is possible to resolve any disagreements and prevent a formal dispute arising.
When these informal arrangements do not result in a resolution of the issue, invoking the dispute
resolution provisions of the contract will need to be considered. When this step is taken, careful
preparation and planning needs to be taken, including determining the need to obtain specialist
advice and assistance.
Irrespective of the approach adopted, negotiations should be undertaken by a person(s) who has
the appropriate authority and skills, and care needs to be exercised to ensure the outcome does
not contravene any legal or policy requirements. It is also important that the details of all
discussions and negotiations are recorded and a record maintained of all the agreements reached.
Advantages of Negotiation
It is free from any procedural formalities
The costs of any third-party involvement are usually avoided (except in the case of an
independent advisor)
A solution acceptable to all parties may be achieved on an amicable basis
Mediation
It is a private voluntary dispute resolution mechanism in which a neutral mediator (an
impartial third party) assists the parties in reaching a mutually acceptable solution to the
dispute.
It is a private voluntary dispute resolution in which a neutral mediator assists the parties in
reaching a mutually acceptable solution to the dispute.
Mediators have no authority to impose a judgment. They work with the parties jointly and
in private sessions, assessing strengths and weaknesses of the parties’ positions, areas of
common ground, and the possibility of creative forward-looking solutions
Mediations are conducted on a ‘’without prejudice’’ basis.
Private meeting between the mediator and each party are confidential to that party, unless
authority is given to the mediator for disclosure.
If there is a settlement as a result of the mediation, it is normal practice for the parties to
record the terms in writing. Parties may elect to have legal representation during
mediation.
About 90 per cent of cases that go to mediation/conciliation are settled (There are
insignificant technical differences between mediation and conciliation-in practice, the
name of the process is irrelevant provided all parties agree and understand the procedure
they wish to use).
Mediation is usually regarded as a faster, less formal and less costly process than court proceedings
or arbitration. There are a number of commercial organizations who maintain registers of
mediators, and who can be approached to appoint a mediator for a dispute. The outcome, however,
is not binding on the parties.
8.8.3 Arbitration
Arbitration is a formal dispute resolution process governed by legislation in which two or more
parties refer their dispute to an independent third person (the arbitrator) for determination. The aim
of arbitration is to obtain a final and enforceable result without the costs, delays and formalities of
litigation (i.e. court proceedings). Arbitration proceedings are private and can be held at a mutually
convenient time. The actual proceedings are less complex than litigation and the arbitrator can be
a person who is able to provide technical expertise relevant to the contract.
It is, nevertheless, an adversarial procedure with the possibility that neither party will be satisfied
with the outcome and it may be costly. Other possible drawbacks that should be considered before
entering into arbitration include: the difficulty in selecting an agreed arbitrator; the expertise of the
arbitrator for the particular case; uncertain appeal rights; and the lack of legal precedence.
Rules of Arbitration
After appointment, arbitrators are subject to any rules contained in the arbitration agreement and
to statutory provisions. Within these restrictions, they can determine their own procedures and
give any reasonable directions for the further conduct of the dispute resolution. Most major
arbitrations eventually come to a hearing that is similar to a court hearing before a judge but which
takes place in private. The arbitrator is bound by the same rules of evidence as a judge, unless the
parties agree to relax them. An interim award may be made concerning any part of the disputes,
with the final award being made at a later stage.
Jurisdiction of Arbitrator(s)
The arbitration agreement and the authority and jurisdiction of the arbitrator(s) that derive from it
are irrevocable by either party individually. Arbitration can only be terminated by agreement
between the parties or by order of a court. The arbitrator or arbitrators can only withdraw by
consent of both parties or with the permission of the court.
Rights of Appeal
Rights of appeal against arbitrator’s decisions are very limited and can only be made on a question
of law. Parties can, and often do, exclude the right of appeal from the arbitration agreement.
Recognizing the need for harmonization, the United Nations Commission on International Trade
Law (UNCITRAL) has issued arbitration rules that are a set of generally accepted principles for
conducting international arbitration. The rules constitute an ad hoc procedure, i.e. one that does
not refer to any one institution for its administration.
Place of Arbitration: In international commercial disputes, the parties should specify in the
arbitration agreement the place where the proceedings are to take place and where the arbitration
award is to be issued. When selecting a place, it must be one that guarantees that arbitration awards
are enforceable in the countries where the parties have their normal place of business. The place
of arbitration can also be an important factor in the costs of arbitration.
Merits of Arbitration
Carried out by experts
Specifically organized
Shorter time for decision
Demerits
Selection of experts could be a challenge
Expensive
8.8.4 Litigation
Litigation is the act or process of contesting a lawsuit or seeking redress through the law courts. It
can be an expensive and time-consuming procedure and is generally taken when other avenues of
dispute resolution have not been successful or are not available. Other approaches to resolving
disputes or Supplier’s defaults should therefore be considered prior to litigation. Appropriate legal
and other professional advice should be obtained prior to considering and commencing litigation.
Demerits
Slow and long process
Judges sometimes lack technical expertise of the subject matter of dispute
9.1 Introduction
Sometimes a decision is taken to terminate a contract prior to its conclusion and the completion of
the supply of goods. When a contract is terminated, the parties are relieved from further
unperformed obligations in accordance with the agreed terms and conditions. This may be for
various reasons, for example, political disturbances or natural disasters which are beyond the
control of the Supplier and the Procurement Entity. In some cases, termination is the optimal
choice; in others, it is detrimental to the overall intent of the procurement, which is generally to
support the implementation of an investment project. This implies a missed opportunity and a
waste of the funds already expended on the procurement. Termination of Contract needs to be
avoided if there is an opportunity to remedy the contract.
A contract may be terminated under distinct processes: Liquidated Damages, Termination for
Default, Termination for Corrupt or Fraudulent Practices, Force Majeure, Termination for
Insolvency and Termination for Convenience.
GCC Clauses 23, 24, 25, 26 and 27 of the Revised Draft Standard Tender Document for
Procurement of Goods (NCT) specify conditions under which contract termination can be effected.
Subject to GCC Clause 25, Force Majeure, if the Supplier fails to deliver any or all of the goods
or to perform within the time period(s) specified in the Contract, the Purchaser shall, without
prejudice to its other remedies under the Contract, deduct from the Contract Price, as liquidated
damages, a sum equivalent to (0.5%) of the contract price of the delayed goods for each week of
delay until actual delivery, up to a maximum deduction of (10%) percent of the delayed goods
Contract Price. Once the maximum is reached, the Purchaser may consider termination of
the Contract pursuant to GCC Clause 24(Termination for Default).
a. if the Supplier fails to deliver any or all of the goods within the time period(s) specified in
the Contract, or any extension thereof granted by the Purchaser pursuant to GCC Clause
22(Delays in the Supplier’s Performance); or
b. if the Supplier fails to perform any other obligation(s) under the Contract.
In the event the Purchaser terminates the Contract in whole or in part, pursuant to GCC paragraphs
24.1 and 24.3 (Termination for Corrupt or Fraudulent Practices), the Purchaser may procure, upon
such terms and in such manner as it deems appropriate, goods or services similar to those
undelivered, and the Supplier shall be liable to the Purchaser for any excess costs for such similar
goods or services. However, the Supplier shall continue performance of the Contract to the extent
not terminated.
The party which is unable to perform its obligations under the present Contract shall, within
fourteen (14) days of occurrence of the Force Majeure event, inform the other party with suitable
documentary evidence. Non-availability of raw materials from regular sources shall not be an
excuse for the Supplier for not performing its obligations under this clause.
Any waiver/extension of time in respect of the delivery/acceptance of any instalment or part of the
goods shall not be deemed to be a waiver/extension of time in respect of the remaining deliveries
If such inability to perform continues for a period of more than three (3) months, each party shall
have the right to be released from further performance of the Contract, in which case, neither party
shall have the right to claim damages from the other. All prior performance shall be subject to
Contract terms.
Notwithstanding the provisions of GCC Clauses 22, 23 and 24, the Supplier shall not be liable for
forfeiture of its performance security, liquidated damages or termination for default if, and to the
extent that it’s delay in performance or other failure to perform its obligations under the Contract
is the result of Force Majeure.
If a Force Majeure situation arises, the Supplier shall promptly notify the Purchaser in writing of
such condition and the cause thereof. Unless otherwise directed by the Purchaser in writing, the
Supplier shall continue to perform its obligations under the Contract as far as is reasonably
practical, and shall seek all reasonable alternative means for performance not prevented by the
Force Majeure event.
10.1 Introduction
The Public Procurement Act, 2003(Act 663) as amended in Section 28, statutorily requires all
procurement entities to keep records of procurement proceedings in a structured and systematic
manner and in accordance with national and international standards. The annual procurement
assessment conducted in the Procurement entities by the Public Procurement Authority (PPA)
reveal challenges relating to the management of procurement and contract management
documentation by most entities thus contravening the Public Procurement Act, 2003(Act 663) as
amended. The observation has been that procurement and contract records management in most
procurement entities usually involve disjointed processes which result in loss of vital procurement
and contract information, thus undermining accountability, transparency and good corporate
governance. Good records management is therefore essential for any corporate body to function
effectively.
A Procurement and Contract Records system promotes the efficient and systematic control of the
creation, receipt, maintenance, use and disposal of public procurement records.
Authentic
It must be possible to prove that records are what they purport to be and who created them,
by keeping a record of their management through time. Where information is later added
to an existing document within a record, the added information must be signed and dated.
With electronic records, changes and additions must be identifiable through audit trail.
Accurate
Records must accurately reflect the transactions that they document.
Accessible
Records must be readily available when needed.
Complete
Records must be sufficient in content, context and structure to reconstruct the relevant
activities and transactions that they document.
Comprehensive
Records must document the complete range of an organization’s business.
Effective
Records must be maintained for specific purposes and the information contained in them
must meet those purposes. Records will be identified and linked to the business process to
which they are related.
Secure
Records must be securely maintained to prevent unauthorized access, alteration, damage
or removal. They must be stored in a secure environment, the degree of security
reflecting the sensitivity and importance of the contents. Where records are migrated
across changes in technology, the evidence preserved must remain authentic and
accurate.
Current or active records are the open files that are in use for conducting the current business of
the organization. Current records and documents are constantly in use and should therefore be
maintained close to the users. They should be maintained and managed within a logical filing
system that facilitates their access. Current records are usually maintained in records offices (or
registries)
Semi-current records consist of the recently closed files. They are only infrequently used. They
should be entered in a closed record register and systematically transferred and organized in a
departmental records centre. The register acts as a retrieval tool.
Non-current or inactive records
These are documents that are hardly ever referred to for the conduct of business operations. Non-
current records should be reviewed and appraised in order to make judgment on their further
retention. Those that are selected as valuable records should be preserved in a departmental records
The disposal information indicates what is to be done with the file when it is closed. On the “related
files” space are indicted the titles and reference numbers of other files that are closely related with
the file.
A file is opened when an existing one matures for closing and the next volume is opened, when a
new subject or activity arises which cannot be accommodated in the existing files, or when an
existing file subdivides into new subjects. A file should be opened after adequate consultation with
the unit or officer responsible for records management. Consultation and care in file opening is
necessary to avoid opening files when similar or the same files are in existence, and which leads
to needless duplication of files.
This leads to uncertainty in filing of papers. The papers in the file should be neatly arranged in
chronological order, and on a specific subject.
The principal file movement control tool is the file movement register, where the file name,
reference number, name of the officer to whom the file is issued, and date of issue and return are
recorded.
A file movement register should have the following format:
Date out;
File title;
File reference number;
To whom issued and signature;
Date in; and
Signature of officer receiving file in registry.
The file’s return to the records office will be marked on the “date in” column. By regularly
checking the column the registry officers will be able to tell cases where files are overdue for return
and therefore to take necessary steps to have the files returned.
There should be an administrative guideline stipulating how long an officer should hold a file -
usually no officer should possess a file for more than four days. Borrowed files should be promptly
returned to the records office once an officer has completed consulting it.
The records staff must ensure that a requested file is promptly provided. Speedy provision of
requested documents and files is one way of cultivating and maintaining confidence in the users
of the registry services.
Closed files should be reviewed after every six (6) years to determine whether they warrant further
retention.
A contract file or folder should be opened by the Contract Administrator and the contract should
be carefully analyzed, taking note of the rights and obligations of each party. Any issues requiring
clarification or change of the contract should be fully documented in this file.
Although practice may vary among organizations, the following documents normally are part of
the contract administration file/folder:
10.3.3 E-mail
E-mails that are evidence of business transactions are official records and should be managed and
kept for as long as is required for functional purposes.
E-mails that approve or authorize an action, contain guidance, advice or direction, relate to project
activities or contain policy decisions should be managed as records and should be filed in a file
plan.
The documents to be digitized must be analyzed to determine their suitability for scanning. The
documents must be well organized and indexed. Priority for digitization should be accorded to
documents or files that are heavily consulted and whose digitization will facilitate multiple and
simultaneous access. Important documents and files in poor physical form and whose frequent use
may lead to their further physical deterioration can also be a priority for digitization.
It is important to select the right scanner, and this will depend on the volume of materials to be
scanned and the compatibility of the scanner with the existing hardware and software. The
digitized images should be stored in an appropriate and secure media such as hard drives, optical
disks and magnetic tapes.
A functional network will be necessary for staff to access the digitized images. The software used
should be able to handle multiple simultaneous access and permit only authorized staff to access
the digital images.
In spite of the challenges highlighted here automated records management and information has
immense benefits as observed elsewhere in this document. What is recommended is a hybrid or
dual system, meaning maintenance of paper records system parallel to the automated system.
11.1 Introduction
Contract evaluation encompasses the overall assessment of the performance of the contract and of
the Procurement Entity’s administration of the contract. The evaluation of the operation of the
contract and of contract outcomes can be very useful in understanding and improving overall
contract administration, improving Supplier performance and can assist in future stakeholder
decision-making.
An evaluation should be undertaken at the end of all contracts and should be planned for in
advance. This could be done periodically (quarterly, mid- term). When a transition from one
contract to another is to occur, it is better practice for an evaluation to be undertaken before the
contract ends so that any problems that might have occurred with aspects of the contractual
arrangement are identified and, where appropriate, improvements made in future contractual
arrangements.
Generally, Supplier performance evaluation is important for two reasons. First, it provides a means
of monitoring the quality of work done on a specific procurement task or project. Second, the
cumulative record of performance on previous projects is a key element in evaluation of the
Supplier’s qualifications for future work.
Factors, criteria or indicators to evaluate a Supplier’s performance will normally include, among
others, the following:
Price
Quality
Delivery(Milestones Timelines)
Service/Customer satisfaction (including supplier administrative effectiveness)
The factors are weighted in relation to their importance to the organisation.The result of a Supplier
evaluation or assessment is the ‘rating’ obtained by the supplier on the basis of the weighted
factors.A Supplier's declining standards can be highlighted and brought to their attention.
The feedback will enable the Supplier to improve upon their performance in future so as to be
more competitive and thus offer value for money in subsequent business dealings.
Supplier performace can form part of the criteria for evaluation of tenders in future procurements.
Potential sources of information that can be used to inform the evaluation include: notes from
meetings; performance data; interviews with management and the supplier; client and end-user
feedback; quality assurance reports; complaints data; and reports of any disputes.
Lessons Learnt
It is better practice that the findings of any evaluation be analyzed to provide lessons learnt to
underpin both continuing and future contracting activity. Lessons learnt should be documented
and provided to the appropriate parties. Any manuals, plans or policies should be reviewed and
updated as necessary.
Report to Stakeholders.
An evaluation report should be provided to relevant stakeholders, for example, senior management
of the Procurement Entity. The approach used to inform stakeholders about the evaluation findings
should be tailored to suit their particular role in the contract and may include both written and oral
briefings. This enables particular attention to be given to significant matters that need to be
considered by decision-makers.
After the review a report should be prepared and distributed as necessary. The report shall provide
good lessons for management of future contracts. Where there is need for action resulting from the
report the management of the Procurement Entity shall decide. Where the team has performed well
it should be commended and where it has not done very well it shall note for future improvement.
12.1 Introduction
Post-implementation tasks in goods contracts involve three main areas – Operational Acceptance,
Warranty and Contract Close-out. These post-implementation tasks are discussed within the
context of contract administration.
12.3 Warranty
Contracts for goods typically provide for a warranty clause. A warranty is normally a promise that
the goods will meet the required standard. Warranty for goods must be invoked during a specified
period from acceptance in accordance with contract requirements.
The contract file must be closed by the Contract Administrator on finalization of all administrative
matters related to the contract subsequent to its completion. The contract is complete when all the
goods ordered have been delivered by the Supplier and accepted by the Purchaser.
Activities involved in contract close out are:
Receipt of Supplier’s invoice
Processing of payment
Release of advance payment security
13.1 Introduction
International Commercial Terms, known as “INCOTERMS”, are internationally accepted terms
defining the responsibilities of exporters and importers in the arrangement of shipments and the
transfer of liability involved at various stages of the transaction.
INCOTERMS do not cover ownership or the transfer of title of goods. It is crucial to agree on an
INCOTERM at the start of a negotiation/quotation of a sale, as it will affect the costs and
responsibilities involved in shipping, insurance and tariffs.
The new INCOTERMS 2010 rules were revised by the International Chamber of Commerce and
became effective on January 1, 2011. Four terms were eliminated (DAF, DEQ, DES, DDU) and
two were added: Delivered at Place (DAP) and Delivered at Terminal (DAT).
The modifications affect obligations, risk transfer, and cost sharing for the Seller and Buyer,
resulting in better clarification and application of the eleven (11) INCOTERMS, and consistent
with the way global trade is actually conducted since the last update in 2000.
It should be noted that INCOTERMS are revised every ten (10) years.
ii. INCOTERMS (2010) Only Applicable for Sea and Inland Waterway Transport
FAS : free alongside ship
FOB : free on board
CFR : cost and freight
CIF : cost, insurance and freight
E Terms (EX-WORKS) - The only term where the seller makes the goods available to
the buyer at the seller’s own premises.
F Terms (FCA, FAS, FOB)- Under the F terms the seller is obliged to deliver the goods to a
carrier.
C Terms (CFR, CIF, CPT, CIP)- Under the C Terms the seller has to contract for carriage but
without assuming the risk of loss or damage to the goods or
additional cost, due to an event occurring after shipment and
dispatch.
D Terms (DAT, DAP, DDP)- The seller under the D Terms has to bear all costs and risks
needed to bring the goods to the country of destination.
A detailed description of INCOTERMS and their characteristics are presented in Table 2 below:
FCA Free Goods are cleared If buyer does not Any mode
Carrier(named for export and name precise
place) handed to the point, seller can
carrier at the choose within the
place named by range or place
the buyer stipulated. Seller
may be
responsible for
clearing the
goods for export.
Buyer bears cost
and risk from
when the goods
are handed to the
carrier.
FAS Free Alongside Goods are placed Buyer bears costs Sea or inland
Ship (named port alongside the and risks of loss waterway
of shipment) vessel at the or damage from
named port quayside. The
export clearance
obligation rests
with the seller.
FOB Free on Board Goods cleared for Buyer bears cost Sea or inland
(named point of export, passed and risks after waterway
shipment) over the ship’s goods have been
rail at named port delivered on
of shipment board the ship by
seller
CFR Cost and Freight Goods are cleared Risk of loss or Sea or inland
(named port of for export and damage and any waterway
destination) transported to the other cost is
transferred to the
CIF Cost, Insurance Cost, insurance Risk passes to the Sea or inland
and Freight and freight paid buyer when the waterway
(named port of to named port of goods are
destination) destination. The delivered on
marine insurance board the ship.
is against the
buyer’s risk of
loss or damage
during carriage
CPT Carriage paid to Goods are cleared Buyer bears risks Any mode
(place of for export and after the goods
destination) delivered into the have been
custody of the delivered to the
carrier carrier. However,
seller must pay
for carriage to the
named place of
destination
CIP Carriage and Same as CPT but Seller only Any mode
Insurance Paid To seller has to required to obtain
named place of contract and pay insurance on
destination. for cargo minimum
insurance against coverage. Risk
the buyer’s risk of shifts to buyer
loss or damage when seller
during carriage delivers goods to
carrier at an
agreed place.
DAT Delivered At Goods are made Seller bears all Any mode
terminal available at risks involved in
named terminal at bringing the
port or place of goods to and
destination unloading them at
the terminal at the
named port or
DDP Delivered Duty Goods are Seller bears all Any mode
Paid(named place transported and risks and costs
of destination) duty paid at including duties,
named place in taxes, etc. Buyer
country of is responsible for
importation unloading at
place of
destination.
INCOTERMS DO NOT…
Determine ownership or transfer title to the goods, nor evoke payment terms.
Apply to service contracts, nor define contractual rights or obligations (except for delivery)
or breach of contract remedies.
Protect parties from their own risk or loss, nor cover the goods before or after delivery.
Specify details of the transfer, transport, and delivery of the goods. Container loading is
NOT considered packaging, and must be addressed in the sales contract.
Remember, INCOTERMS are not law and there is NO default INCOTERM!
REFERENCES
7. The World Bank (2006) Consulting Services Manual 2006-A Comprehensive Guide to
the Selection of Consultants.
8. Gosta Westring and George Jadoun (Rev.15th November 1996). Public Procurement
Manual.
9. The World Bank (2011). Manual for Contract Management Procedures in World Bank-
Financed Projects in Europe and Central Asia Region.
12. International Training Centre (ILO) and World Bank, (July 2010). Equipment and
Works Procurement Management –Procurement Environment in World Bank –Financed
Projects: Module 1.
13. International Training Centre (ILO) and World Bank, (September 2009). Equipment
Procurement Management –The Standard Bidding Documents in World Bank –Financed
Projects: EPM Module 2.
14. International Training Centre (ILO) and World Bank, (September 2009). Equipment
Procurement Management –The Standard Bid Evaluation, Contract Award and
95 Public Procurement Authority (PPA), Ghana
Contract Administration Manual For Goods – Manual 1
Management: EPM Module 3.
15. International Training Centre (ILO) and World Bank, (May 2000). Works
Procurement Management –Bid Opening and Bid Evaluation: WPM Module 4.
16. International Training Centre (ILO) and World Bank, (April 2000). Works
Procurement Management –Bid Document: Types of Works Contract: WPM Module 2.
17. International Training Centre (ILO) and World Bank, (May 2000). Works
Procurement Management –The Bidding Process: Standard Bidding Documents: WPM
Module 3/1.
18. International Training Centre (ILO) and World Bank, (April 2000). Works
Procurement Management –The Bidding Process: Standard Bidding Documents: WPM
Module 3/2.
19. International Training Centre (ILO) and World Bank, (April 2000). Works
Procurement Management – Contract Implementation and Management: WPM Module 5.
20. Public Procurement Authority Accra, Ghana (Rev, January, 2015) Standard and
Sample Contract for Consultant’s Services -Small Assignments, Time-Based Payments.
22. Public Procurement Authority Accra, Ghana (Rev, January, 2015) Standard and
Sample Contract for Consultant’s Services -Small Assignments, Lump-Sum Payments.
24. Public Procurement Authority Accra, Ghana (Rev, January, 2015) Standard
Document for request of Expression of Interest
APPENDIX 1: TEMPLATES
Payments made
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
Invoice No 0.00
APPENDIX 2
1. Definitions......................................................................................................................... 82
2. Contract Documents.......................................................................................................... 83
3. Corrupt Practices............................................................................................................... 83
4. Interpretation ..................................................................................................................... 84
5. Language........................................................................................................................... 85
6. Joint Venture, Consortium or Association........................................................................ 87
7. Eligibility .......................................................................................................................... 87
8. Notices .............................................................................................................................. 87
9. Applicable Law ................................................................................................................. 87
10. Settlement of Disputes ...................................................................................................... 87
11. Scope of Supply ................................................................................................................ 88
12. Delivery and Documents................................................................................................... 88
13. Supplier’s Responsibilities ............................................................................................... 88
14. Contract Price.................................................................................................................... 88
15. Terms of Payment ............................................................................................................. 88
16. Taxes and Duties............................................................................................................... 89
17. Performance Security ........................................................................................................ 89
18. Copyright .......................................................................................................................... 90
19. Confidential Information .................................................................................................. 90
20. Subcontracting .................................................................................................................. 91
21. Specifications and Standards ............................................................................................ 91
22. Packing and Documents.................................................................................................... 91
23. Insurance ........................................................................................................................... 92
24. Transportation ................................................................................................................... 92
25. Inspections and Tests ........................................................................................................ 92
26. Liquidated Damages ......................................................................................................... 93
27. Warranty ........................................................................................................................... 94
28. Patent Indemnity ............................................................................................................... 94
29. Limitation of Liability....................................................................................................... 95
30. Change in Laws and Regulations...................................................................................... 96
31. Force Majeure ................................................................................................................... 96
2. Contract 2.1 Subject to the order of precedence set forth in the Agreement, all
Documents documents forming the Contract (and all parts thereof) are
intended to be correlative, complementary, and mutually
explanatory.
3. Corrupt 3.1 The Government of Ghana (GOG) requires that all Procurement
Practices Entities as well as Tenderers, Suppliers, Contractors and
Consultants participating in contracts financed from the public
funds of the Republic of Ghana, adhere to the highest ethical
standards, both during the tendering process and throughout the
execution of such contracts. The list of definitions set forth below
involves the most common types of corrupt practices, but is not
exhaustive. For this reason, the Public Procurement Authority
will also consider claims of similar nature involving alleged acts of
corruption, in accordance with the established procedure.
3.3 The Tenderer shall disclose any commissions or fees that may
have been paid or are to be paid to agents, representatives, or
commission agents with respect to the tendering process or
execution of the contract. The information disclosed must
include at the name and address of the agent, representative, or
commission agent, the amount and currency, and the purpose
of the commission or fee. The information must be included in
the Tender Submission Sheet. Furthermore, Tenderers shall be
aware of the provision stated in Sub-Clause 3.2 and Sub-
Clause 35.1 (c) of the General Conditions of Contract.
4. Interpretation 4.1 If the context so requires it, singular means plural and vice versa.
4.2 Incoterms
(a) Unless otherwise specified in the SCC, the meaning of
any trade term and the rights and obligations of parties
thereunder shall be as prescribed by Incoterms.
(b) The terms EXW, FOB, FCA, CIF, CIP, and other similar
terms, when used, shall be governed by the rules
prescribed in the current edition of Incoterms, published
by the International Chamber of Commerce at the date of
the Invitation for Tenders or as specified in the SCC.
4.4 Amendment
4.5 Non-waiver
(a) Subject to GCC Sub-Clause 4.5(b) below, no relaxation,
forbearance, delay, or indulgence by either party in
enforcing any of the terms and conditions of the Contract
or the granting of time by either party to the other shall
prejudice, affect, or restrict the rights of that party under
the Contract, neither shall any waiver by either party of
any breach of Contract operate as waiver of any
subsequent or continuing breach of Contract.
4.6 Severability
5.2 The Supplier shall bear all costs of translation to the governing
language and all risks of the accuracy of such translation.
6. Joint Venture, 6.1 If the Supplier is a joint venture, consortium, or association, all of
Consortium or the parties shall be jointly and severally liable to the Purchaser for
Association the fulfillment of the provisions of the Contract and shall
designate one party to act as a leader with authority to bind the
joint venture, consortium, or association. The composition or the
constitution of the joint venture, consortium, or association shall
not be altered without the prior consent of the Purchaser.
7. Eligibility 7.1 The Supplier and its Subcontractors shall have the nationality of an
eligible country, in accordance with Section V, Eligible Countries.
A Supplier o r Subcontractor shall be deemed to have the
nationality of a country if it is a citizen or constituted,
incorporated, or registered, and operates in conformity with the
provisions of the laws of that country.
7.2 All Goods and Related Services to be supplied under the Contract
and financed from the public funds of the Republic of Ghana shall
have their origin in Eligible Countries.
7.3 For the purpose of this Clause, origin means the country where the
goods have been grown, mined, cultivated, produced,
manufactured, or processed; or through manufacture, processing,
or assembly, another commercially recognized article results that
differs substantially in its basic characteristics from its imported
components
8. Notices 8.1 Any notice given by one party to the other pursuant to the
Contract shall be in writing to the address specified in the SCC. The
term “in writing” means communicated in written form with proof
of receipt.
9. Applicable Law 9.1 the Contract shall be governed by and interpreted in accordance
with the laws of Ghana, unless otherwise specified in the SCC.
10. Settlement of 10.1 The Purchaser and the Supplier shall make every effort to resolve
Disputes amicably by direct informal negotiation any disagreement or dispute
arising between them under or in connection with the Contract.
11. Scope of Supply 11.1 Subject to the SCC, the Goods and Related Services to be supplied
shall be as specified in the Schedule of Requirements.
12. Delivery and 12.1 Subject to GCC Sub-Clause 32.1, the Delivery of the Goods and
Documents Completion of the Related Services shall be in accordance with
the Delivery and Completion Schedule specified in the Schedule
of Requirements. The details of shipping and other documents to
be furnished by the Supplier are specified in the SCC.
13. Supplier’s 13.1 The Supplier shall supply all the Goods and Related Services
Responsibilities included in the Scope of Supply in accordance with GCC Clause
11, and the Delivery and Completion Schedule, as per GCC
Clause 12.
14. Contract Price 14.1 The Contract Price shall be as specified in the Agreement subject
to any additions and adjustments thereto, or deductions therefrom,
as may be made pursuant to the Contract.
14.2 Prices charged by the Supplier for the Goods delivered and the
Related Services performed under the Contract shall not vary
from the prices quoted by the Supplier in its Tender, with the
exception of any price adjustments authorized in the SCC.
15. Terms of 15.1 The Contract Price, including any Advance Payments, if
Payment applicable, shall be paid as specified in the SCC.
15.5 The Purchaser shall pay to the Supplier interest on any outstanding
amount at the prevailing interbank rate where the Purchaser has
received an accepted invoice or certificate from the Supplier but
has failed to make payment within the number of days stated in the
Data Sheet and where such period is not stated payment remains
outstanding for more than … days after the agreed due date
16. Taxes and 16.1 F o r goods supplied from outside Ghana, the Supplier shall be
Duties entirely responsible for all taxes, stamp duties, license fees, and
other such levies imposed outside Ghana.
16.2 For goods supplied from within Ghana, the Supplier shall be
entirely responsible for all taxes, duties, license fees, etc., incurred
until delivery of the contracted Goods to the Purchaser.
17. Performance 17.1 The Supplier shall, within twenty-eight (28) days of the
Security notification of contract award, provide a performance security for
the due performance of the Contract in the amount specified in the
SCC.
18. Copyright 18.1 The copyright in all drawings, documents, and other materials
containing data and information furnished to the Purchaser by the
Supplier herein shall remain vested in the Supplier, or, if they are
furnished to the Purchaser directly or through the Supplier by any
third party, including suppliers of materials, the copyright in such
materials shall remain vested in such third party
19. Confidential 19.1 The Purchaser and the Supplier shall keep confidential and shall not,
Information without the written consent of the other party hereto, divulge to any
third party any documents, data, or other information furnished
directly or indirectly by the other party hereto in connection with
the Contract, whether such information has been furnished prior to,
during or following completion or termination of the Contract.
Notwithstanding the above, the Supplier may furnish to its
Subcontractor such documents, data, and other information it
receives from the Purchaser to the extent required for the
Subcontractor to perform its work under the Contract, in which
event the Supplier shall obtain from such Subcontractor an
undertaking of confidentiality similar to that imposed on the
Supplier under GCC Clause 19.
19.2 The Purchaser shall not use such documents, data, and other
information received from the Supplier for any purposes unrelated
to the contract. Similarly, the Supplier shall not use such
documents, data, and other information received from the Purchaser
for any purpose other than the design, procurement, or other work
and services required for the performance of the Contract.
19.3 The obligation of a party under GCC Sub-Clauses 19.1 and 19.2
above, however, shall not apply to information that:
(a) the Purchaser or Supplier need to share with the Public
Procurement Authority of the Republic of Ghana or other
institutions participating in the financing of the Contract;
19.4 The above provisions of GCC Clause 19 shall not in any way modify
any undertaking of confidentiality given by either of the parties
hereto prior to the date of the Contract in respect of the Supply
or any part thereof.
20. Subcontracting 20.1 The Supplier shall notify the Purchaser in writing of all
subcontracts awarded under the Contract if not already specified
in the Tender. Subcontracting s h a l l in no event relieve the
Supplier from any of its obligations, duties, responsibilities, or
liability under the Contract.
22. Packing and 22.1 The Supplier shall provide such packing of the goods as is
22.2 The packing, marking, and documentation within and outside the
packages shall comply strictly with such special requirements as
shall be expressly provided for in the Contract, including
additional requirements, if any, specified in the SCC, and in any
other instructions ordered by the Purchaser.
23. Insurance 23.1 Unless otherwise specified in the SCC, the Goods supplied under
the Contract shall be fully insured—in a freely convertible currency
from an eligible country—against loss or damage incidental to
manufacture or acquisition, transportation, storage, and delivery, in
accordance with the applicable Incoterms or in the manner
specified in the SCC.
24. Transportation 24.1 Unless otherwise specified in the SCC, responsibility for
arranging transportation of the Goods shall be in accordance with
the Incoterms specified in the Schedule of Requirements.
25. Inspections and 25.1 The Supplier shall at its own expense and at no cost to the
Tests Purchaser carry out all such tests and/or inspections of the Goods
and Related Services as are specified in the Schedule of
Requirements.
25.4 Whenever the Supplier is ready to carry out any such test and
25.5 The Purchaser may require the Supplier to carry out any test
and/or inspection not required by the Contract but deemed
necessary to verify that the characteristics and performance of the
Goods comply with the technical specifications codes and standards
under the Contract, provided that the Supplier’s reasonable costs
and expenses incurred in the carrying out of such test and/or
inspection shall be added to the Contract Price. Further, if such
test and/or inspection impedes the progress of manufacturing and/or
the Supplier’s performance of its other obligations under the
Contract, due allowance will be made in respect of the Delivery
Dates and Completion Dates and the other obligations so affected.
25.6 The Supplier shall provide the Purchaser with a report of the
results of any such test and/or inspection.
25.7 The Purchaser may reject any Goods or any part thereof that fail
to pass any test and/or inspection or do not conform to the
specifications. The Supplier shall either rectify or replace such
rejected Goods or parts thereof or make alterations necessary to
meet the specifications at no cost to the Purchaser, and shall
repeat the test and/or inspection, at no cost to the Purchaser, upon
giving a notice pursuant to GCC Sub-Clause 25.4.
26. Liquidated 26.1 Except as provided under GCC Clause 31, if the Supplier fails to
Damages deliver any or all of the Goods or perform the Related Services
within the period specified in the Contract, the Purchaser may
without prejudice to all its other remedies under the Contract,
deduct from the Contract Price, as liquidated damages, a sum
equivalent to the percentage specified in the SCC of the Contract
Price for each week or part thereof of delay until actual delivery
or performance, up to a maximum deduction of the percentage
specified in those SCC. Once the maximum is reached, the
Purchaser may terminate the Contract pursuant to GCC Clause
34.
27. Warranty 27.1 The Supplier warrants that all the Goods are new, unused, and of
the most recent or current models, and that they incorporate all
recent improvements in design and materials, unless provided
otherwise in the Contract.
27.5 Upon receipt of such notice, the Supplier shall, within the period
specified in the SCC, expeditiously repair or replace the defective
Goods or parts thereof, at no cost to the Purchaser.
27.6 If having been notified, the Supplier fails to remedy the defect within
the period specified in the SCC, the Purchaser may proceed to
take within a reasonable period such remedial action as may be
necessary, at the Supplier’s risk and expense and without prejudice
to any other rights which the Purchaser may have against the
Supplier under the Contract.
28. Patent 28.1 The Supplier shall, subject to the Purchaser’s compliance with
Indemnity GCC Sub-Clause 28.2, indemnify and hold harmless the
Purchaser and its employees and officers from and against any
and all suits, actions or administrative proceedings, claims,
demands, losses, damages, costs, and expenses of any nature,
including attorney’s fees and expenses, which the Purchaser may
suffer as a result of any infringement or alleged infringement of
any patent, utility model, registered design, trademark, copyright,
or other intellectual property right registered or otherwise existing
at the date of the Contract by reason of:
(a) the installation of the Goods by the Supplier or the use of
Such indemnity shall not cover any use of the Goods or any
part thereof other than for the purpose indicated by or to be
reasonably inferred from the Contract, neither any infringement
resulting from the use of the Goods or any part thereof, or any
products produced thereby in association or combination with
any other equipment, plant, or materials not supplied by the
Supplier, pursuant to the Contract.
28.2 If any proceedings are brought or any claim is made against the
Purchaser arising out of the matters referred to in GCC Sub- Clause
28.1, the Purchaser shall promptly give the Supplier a notice
thereof, and the Supplier may at its own expense and in the
Purchaser’s name conduct such proceedings or claim and any
negotiations for the settlement of any such proceedings or claim.
28.3 If the Supplier fails to notify the Purchaser within twenty-eight
(28) days after receipt of such notice that it intends to conduct any
such proceedings or claim, then the Purchaser shall be free to
conduct the same on its own behalf.
28.4 The Purchaser shall, at the Supplier’s request, afford all available
assistance to the Supplier in conducting such proceedings or
claim, and shall be reimbursed by the Supplier for all reasonable
expenses incurred in so doing.
28.5 The Purchaser shall indemnify and hold harmless the Supplier
and its employees, officers, and Subcontractors from and against
any and all suits, actions or administrative proceedings, claims,
demands, losses, damages, costs, and expenses of any nature,
including attorney’s fees and expenses, which the Supplier may
suffer as a result of any infringement or alleged infringement of
any patent, utility model, registered design, trademark, copyright, or
other intellectual property right registered or otherwise existing at
the date of the Contract arising out of or in connection with any
design, data, drawing, specification, or other documents or
materials provided or designed by or on behalf of the Purchaser.
30. Change in Laws 30.1 Unless otherwise specified in the Contract, if after the date of the
and Regulations Invitation to Tender, any law, regulation, ordinance, order or by-
law having the force of law is enacted, promulgated, abrogated, or
changed in the particular area of Ghana where the Site is located
(which shall be deemed to include any change in interpretation or
application by the competent authorities) that subsequently affects
the Delivery Date and/or the Contract Price, then such Delivery
Date and/or Contract Price shall be correspondingly increased or
decreased, to the extent that the Supplier has thereby been
affected in the performance of any of its obligations under the
Contract. Notwithstanding t h e foregoing, su c h additional
or reduced cost shall not be separately paid or credited if the same
has already been accounted for in the price adjustment provisions
where applicable, in accordance with GCC Clause 14.
31. Force Majeure 31.1 The Supplier shall not be liable for forfeiture of its performance
security, liquidated damages, or termination for default if and to
the extent that its delay in performance or other failure to perform
its obligations under the Contract is the result of an event of Force
Majeure.
31.2 For purposes of this Clause, “Force Majeure” means an event or
situation beyond the control of the Supplier that is not
foreseeable, is unavoidable, and its origin is not due to negligence
or lack of care on the part of the Supplier. Such events may include,
but not be limited to, acts of the Purchaser in its sovereign
capacity, wars or revolutions, fires, floods, epidemics, quarantine
restrictions, and freight embargoes.
31.3 If a Force Majeure situation arises, the Supplier shall promptly notify
the Purchaser in writing of such condition and the cause thereof.
Unless otherwise directed by the Purchaser in writing, the
Supplier shall continue to perform its obligations under the Contract
as far as is reasonably practical, and shall seek all reasonable
alternative means for performance not prevented by the Force
Majeure event.
32. Change Orders 32.1 The Purchaser may at any time order the Supplier through notice
and Contract in accordance GCC Clause 8, to make changes within the general
Amendments scope of the Contract in any one or more of the following:
(a) drawings, designs, or specifications, where Goods to be
furnished under the Contract are to be specifically
manufactured for the Purchaser;
32.2 If any such change causes an increase or decrease in the cost of,
or the time required for, the Supplier’s performance of any
provisions under the Contract, an equitable adjustment shall be
made in the Contract Price or in the Delivery/Completion Schedule,
or both, and the Contract shall accordingly be amended. Any claims
by the Supplier for adjustment under this Clause must be asserted
within twenty-eight (28) days from the date of the Supplier’s receipt
of the Purchaser’s change order.
32.3 Prices to be charged by the Supplier for any Related Services that
might be needed but which were not included in the Contract
shall be agreed upon in advance by the parties and shall not
exceed the prevailing rates charged to other parties by the
Supplier for similar services.
33. Extensions of 33.1 If at any time during performance of the Contract, the Supplier or
Time its subcontractors should encounter conditions impeding timely
delivery of the Goods or completion of Related Services pursuant
to GCC Clause 12, the Supplier shall promptly notify the
Purchaser in writing of the delay, its likely duration, and its cause.
As soon as practicable after receipt of the Supplier’s notice, the
Purchaser shall evaluate the situation and may at its discretion
extend the Supplier’s time for performance, in which case the
extension shall be ratified by the parties by amendment of the
Contract.
(b) The Goods that are complete and ready for shipment
within twenty-eight (28) days after the Supplier’s receipt
of notice of termination shall be accepted by the
35. Assignment 35.1 Neither the Purchaser nor the Supplier shall assign, in whole or in
part, their obligations under this Contract, except with prior
written consent of the other party.
GCC 10.2 The formal mechanism for the resolution of disputes shall be as follows:
(a). For contracts entered into with Foreign Suppliers:
In case of a dispute between the Purchaser and the supplier, the dispute shall be
settled by arbitration in accordance with the provisions of the United Nations
Commission on International Trade Law (UNCITRAL) arbitration Rules.
GCC 11.1 The scope of supply for the Goods and Related Services to be supplied shall be as
specified in:
Upon shipment, the Supplier shall notify the Purchaser and the Insurance Company
by cable the full details of the shipment, including Contract number, description of
Goods, quantity, the vessel, the bill of lading number and date, port of loading, date
of shipment, port of discharge, etc. The Supplier shall mail the following documents
to the Purchaser, with a copy to the Insurance Company:
The above documents shall be received by the Purchaser at least one week before
arrival of the Goods at the port or place of arrival and, if not received, the Supplier will
be responsible for any consequent expenses.
[Other similar documents should be listed, depending upon the Incoterm retained.]
Upon delivery of the Goods to the transporter, the Supplier shall notify the Purchaser
and mail the following documents to the Purchaser:
(i) Copies of the Supplier’s invoice showing Goods’ description, quantity,
unit price, and total amount;
(ii) Delivery note acceptable to the Purchaser such as railway receipt, or truck
receipt;
(iii) Manufacturer’s or Supplier’s warranty certificate;
(iv) Inspection certificate issued by the nominated inspection agency, and the
Supplier’s factory inspection report; and
(v) Certificate of origin.
The above documents shall be received by the Purchaser before arrival of the Goods
and, if not received, the Supplier will be responsible for any consequent expenses.
GCC 14.2 The prices charged for the Goods delivered and the related Services performed
be adjustable.
If prices are adjustable, the method specified in the attachment to the SCC shall be
used to calculate the price adjustment.