AM Forecast Models For Actual Construction Time and Cost
AM Forecast Models For Actual Construction Time and Cost
Research Repository
Published in:
Building and Environment
DOI:
10.1016/S0360-1323(03)00067-2
Licence:
CC BY-NC-ND
Recommended citation(APA):
Skitmore, R. M., & Ng, S. T. (2003). Forecast models for actual construction time and cost. Building and
Environment, 38(8), 1075-1083. https://doi.org/10.1016/S0360-1323(03)00067-2
General rights
Copyright and moral rights for the publications made accessible in the public portal are retained by the authors and/or other copyright owners
and it is a condition of accessing publications that users recognise and abide by the legal requirements associated with these rights.
For more information, or if you believe that this document breaches copyright, please contact the Bond University research repository
coordinator.
R. Martin Skitmore 1
S. Thomas Ng 2
1
School of Construction Management and Property, Queensland University of Technology,
GPO Box 2434, Brisbane Q4001, Australia.
2
Department of Civil Engineering, The University of Hong Kong,
Pokfulam Road, Hong Kong.
Please contact:
Dr. S Thomas Ng
Department of Civil Engineering
University of Hong Kong
Pokfulam Road, Hong Kong
1
FORECAST MODELS FOR ACTUAL CONSTRUCTION TIME AND COST
Abstract:
The actual construction time and cost of construction projects may be affected by the client,
project and contractual characteristics and in many cases can be very different from the
contract time and cost. In this paper, details of 93 Australian construction projects are used to
develop several models for actual construction time and cost prediction. A forward
crossvalidation regression analysis is used for the development of the model for actual
construction time forecast when client sector, contractor selection method, contractual
arrangement, project type, contract period and contract sum are known. The standard
deviation of the deleted residual indicates the best model for actual construction time
prediction to comprise the independent variables log contract time, lump sum procurement
and non-standard contractor selection. Regression models are also developed for forecasting
the actual construction time and cost when client sector, contractor selection method,
contractual arrangement and project type are known while contract period and contract sum
are estimated. Different forms of regression analyses, including the standard regression and
the crossvalidation regression, are used and the crossvalidation regression model with the
Since these models for time and cost are dependent on the contract period and contract sum
being known, it is necessary to investigate the effects in situations where these have to be
estimated. The results of the sensitivity analyses show that the errors in predicted actual
construction time become smaller as the contract period increases. In contrast, the errors in
predicted actual construction cost are virtually the same for large and small projects.
2
The effects of different project type, contractor selection method and contractual arrangement
are also examined. The results indicate that the actual construction time for industrial project
is the longest when compared with residential, educational and recreational projects and that
significant savings in actual construction time can be achieved when negotiated tender and
design and build contract are used instead of the traditional open tendering and lump sum
contract approaches.
Finally, some practical applications of the models are illustrated for predicting the actual
construction time and cost based on the risks and uncertainties of different client sector,
3
INTRODUCTION
An accurate forecast of construction time and cost is crucial to contract administration as the
predicted duration and cost forms a basis for budgeting, planning, monitoring and even
litigation purposes. In practice, there are two common methods for estimating construction
time and cost: (1) according to the client’s available budget and time constraints, i.e.
occupancy need, or (2) through a detailed analysis of work to be done and resources
available, using estimates of the time and cost requirements for each specific activity
(Telford, 1994). The detailed estimation of construction activities usually relies on the
estimators’ experience and judgement to correctly interpret project and site information and
model for predicting contract duration based on the estimated final cost of construction
project. The model, commonly known as Bromilow’s Time-Cost (BTC) model1, is used by
clients and contractors for estimating and benchmarking the contract period of construction
projects. Various research studies in Australia (Bromilow and Henderson, 1976; Bromilow et
al, 1980, 1988; Ireland, 1983; Mak, 1991; Ng et al, 2000; RAIA, 1989; Sidwell, 1984;
Walker, 1994, 1995), United Kingdom (Kaka and Price, 1991), Hong Kong (Chan, 1999;
Kumaraswamy and Chan, 1995) and Malaysia (Yeong, 1994) revealed that the time taken to
construct a project is highly correlated with the construction size as measured by cost.
Ireland (1983:137) concluded that the BTC model is “the best predictor of construction time”.
1
Detailed discussion of the BTC model can be found in Ng et al (2001)
4
Despite the development and use of the BTC model for construction time-cost estimation
(developed at the pre-contract stage), the actual construction time and cost (at the post-
contract stage) might be influenced by risks and uncertainties emanated from different client
sector, project type, contractor selection method and contract arrangement approach.
According to Walker (1994), one shortcoming of the BTC model is that it fails to consider
Several research studies (Ireland, 1983; Laptali et al, 1996) have been carried out to improve
the accuracy of the BTC model. Ireland (1983) developed a multiple regression model based
on the construction time, cost, area and number of storeys. Progress was halted by the
occurrence of unreasonably high standard errors. Walker (1994) also measured construction
time performance in terms of the gross floor area of a building. However, problems occurred
as the construction cost included a significant external works component, which present
This paper examines the relationships among the actual construction time/cost and other
contract details, such as the estimated construction time and cost, client sector, project type,
construction projects in Australia. The results indicate that relationships exist between the
actual construction time/cost and other contract details as mentioned. This leads to the
development of several regression models for actual construction time and cost prediction.
Analyses were conducted to examine the sensitivity of the regression models considering the
likely inaccuracy in the estimated contract time and cost. The results indicate that the
regression models could assist clients and contractors to predict the actual construction time
5
and cost pertinent to a particular client sector, project type, contractor selection method and
contractual arrangement when estimated contract time and cost become available.
DATA
questionnaire survey. Bromilow et al (1988) argued that attempts to obtain too much
which researchers (e.g. Bromilow, 1969; Bromilow and Henderson, 1976; Bromilow et al,
1980; Ireland, 1983; Laptali et al, 1991; Yeong, 1994; Mak, 1996; Walker, 1995; Chan,
were sought. The data requested included the company name, project name, project location,
client sector, project type, contractor selection method, contractual arrangement, original
contract period, actual contract period, original contract sum, and final contract sum.
The population was confined to projects having a contract value more than AUS$0.5 million
completed in the past eight years. Projects below AUS$0.5 million were considered to have
limited scope and complexity. For logistical reasons, the survey was limited to projects
Construction companies from two biggest cities of New South Wales, Australia, i.e. Sydney
and Newcastle, were considered in this study. Names and addresses of 100 construction
companies were obtained by random selection from the telephone directories under the
6
companies and 44 indicated that they were interested in the study and could provide the
required data.
A survey package containing a covering letter, survey instructions, six separate sets of survey
questionnaires and stamped self-addressed envelopes was distributed to each company. The
companies were asked to provide the details of up to six projects for analysis. Due to the
sensitivity of the data required, 12 companies dropped out from the study at this stage. The
The average time for construction was 237 working days, the longest and shortest times being
864 and 60 working days respectively. All costs were rebased to March 1998 prices using
the Building Price Index (BPI) in the price book (Rawlinsons, 1998). The average rebased
cost of projects in the sample was AUS$21.4 million, the lowest and highest costs being
ANALYSIS
The first analysis aims to develop a model for forecasting actual construction time when
client sector, contractor selection method, contractual arrangements, project type, contract
period and contract sum are known. This model is more relevant to the post-contract stage as
the contract period, contract sum, and other contract details are readily available during this
stage. The model will assist the client and contractor predicting the actual construction time
7
Forward Crossvalidation Regression
In this analysis, the dependent variable is the actual construction time (ATIME) to practical
completion. Various forms of ATIME were considered, including log and power
transformations. The choice of dependent variable is very much restricted due to the
(1969) and others (e.g. Chan, 1999; Ng et al, 2000) have shown log construction time to be
the generally most appropriate variable to analyse. This (LATIME) was then used as the
dependent variable. The form of the independent variables is less of a problem and various
forms can be examined and compared for their contribution. Dummy variables may be
created for the categorical factors of client sector, project type, contractor selection method
and contractual arrangements but, with only 93 cases to analyse, this cannot be done in any
nonarbitrary way. The method of analysis eventually chosen was to concentrate solely on the
various forms of contract time (CTIME) and contract cost (CCOST) as independent
variables, with the intention of checking the residuals for any significant sub-group (within
client sector, project type, contractor selection method and contractual arrangements) effects.
The regression model was built by a forward crossvalidation procedure. Each independent
variable was tested separately for inclusion by the standard deviation of the deleted residual.
As a result, the log contract time (LCTIME), with a deleted residual standard deviation of
0.179, was selected for inclusion in the model. The next stage was to repeat the test for
inclusion of further form of cost and time variables (Table 1). No improvement to the deleted
residual standard deviation was found and therefore the procedure stopped.
8
< Table 1 >
The deleted residuals of the final model were analysed for differences between the sub-
arrangements (CONTRACT) and project type (TYPE). Table 2 shows the results of the
ANOVA means tests and Levine variance homogeneity tests. The SELECTION and
residuals being higher than ‘other’ forms of contractor selection (mainly negotiated) and
lump sum being higher than design and construct contractual arrangements. This indicated
that at least one variable was missing from the regression equation. Dummy variables were
therefore created for the SELECTION sub-groups of selective tendering and ‘other’ and the
CONTRACT sub-groups of lump sum and D&C and entered into a forward stepwise
crossvalidation regression on LATIME along with LCTIME (Table 1). This showed the best
model to comprise the independent variables LCTIME and the ‘other’ and ‘lump sum’
dummies. Analysis of the subgroups showed that the significant differences had disappeared
(Table 2).
9
(R=0.96984455, R²=0.94059846, Adjusted R²=0.93859616, F(3,89)=469.76, p<0.0000, Std.
Error of Estimate=0.16382, see Table 3) where LATIME, LCTIME, LS and OT denote the
log-actual time, log-contract time, lump sum dummy variable and ‘other’ selection dummy
variable. D-W’s d=1.592, K-S d=0.104 (p>0.2) and the ANOVA on categorised LCOST is
F(3,89)=1.262 (p=0.292), suggesting the regression assumptions are not unduly violated.
crossvalidation was conducted. This involves simultaneously entering all the independent
where α0j , α1j, α2j, α3j , ..., αnj are the crossvalidation regression coefficients and x1j, x2j, x3j,
..., xnj are the values of the independent variables for the j=1, 2, ... , n cases (projects). The
β0, β1, β2, β3, ..., βn coefficients are computed to minimise the deleted residual sum of
squares (ssq) by means of a quasi-Newton algorithm. The α coefficients are then calculated
for all the (noncrossvalidation) data and the αβ products obtained. This method enables the
best crossvalidation model to be found, the β coefficients, once computed, being simply
multiplied by the α coefficients. Table 4 summarises the results (the columns ‘alpha’, ‘beta1’
and ‘ab1’ give the α , β and αβ coefficients and the last two rows give the residual ssq and
10
deleted residual ssq)2. This shows that the standard regression model (‘alpha’ column), as
expected produced a better residual ssq than the crossvalidation regression (‘ab1’ column)
with 2.11909 compared with 2.15984 but that the crossvalidation regression produced a better
deleted residual ssq than the standard regression with 2.43525 compared with 3.12966
improvement on the 0.168 of the forward method). As the ‘ab1’ coefficients show, the 16
independent variables plus the constant show seven to be redundant for crossvalidation
The column ‘beta2’ in Table 4 gives the results when β is unconstrained and ‘ab2’ provide
the consequent αβ coefficients. The ssq results show that the residual ssq values to be worse
than the ‘ab1’ model but the deleted residual ssq value is better at 1.77817. The last two
models, ‘beta3’ and ‘beta4’, are obtained by setting all α coefficients to unity, with the
‘beta3’ model for β≥0 and the ‘beta4’ model for unconstrained β. The ‘beta3’ model, with
10 zero coefficients is close to the model obtained earlier by forward crossvalidation, whilst
the ‘beta4’ model has a reduced deleted residual ssq of 2.09846 against 2.37386. However,
the ‘ab2’ model is preferred because of its smallest deleted residual ssq of 1.77817.
2
The raw CCOST, CCOST2 and CTIME2 could not be handled by the procedure, presumably due to scaling problems.
11
Table 4 also gives the results of the various models when applied to forecasting the actual
construction cost (forward crossvalidation regression was not used). This shows a similar
pattern of results to the time forecasts, with the ‘alpha’ (ordinary regression) model having a
good residual ssq (1.08674) but relatively poor deleted residual ssq (1.77806). The
crossvalidation model ab1 again has a worse residual ssq (1.15303) and better deleted
residual ssq (1.02433). Again, the ‘ab2’ model produces the best forecasts, with a deleted
residual ssq of only 0.56923, against 1.17982 and 1.08395 for the ‘beta3’ and ‘beta4’ models
SENSITIVITY ANALYSIS
All the models described to this point assume that the contract period and contract sum are
known. In practice, this is rarely the case, and contract period and contract sum are simply
estimated from whatever information is available at time of estimation. Therefore, since the
prediction of actual construction time and cost is based on the estimated contract period and
contract sum, it is necessary to examine how sensitive the prediction models are when the
Assume a contract sum of $10M and the other project particulars are public sector client,
residential building, open tendering and lump sum contract. The actual construction time for
a range of projects with an estimated contract period of 100 to 1000 days could be derived by
substituting all data into the prediction models ‘ab2’ for time. The actual construction time as
predicted by the model ranges from 122.51 days (CTIME=100) to 1056.93 days
(CTIME=1000) with zero percent estimate error (Table 5). This indicates that the actual
12
construction time is, on average, longer than the contract period by +22.51% for 100 day
The contract period estimate error was altered at ±5% intervals to examine the effects on the
actual construction time prediction. In the prediction model, the contract period is expressed
in several different forms, including CTIME, LCTIME, RCTIME, and INVCTIME. The
deviations (ie. +5% of the contract period) were applied to all different forms of contract
period when the calculating the revised actual construction time. Figure 1 shows the results
of the sensitivity analysis for contract period. At ±5% deviation level, the variations to the
actual construction time were between ±3.5% (CTIME=1000) to ±5.2% and (CTIME=100)
(Table 5). These indicate that the ‘ab2’ model for time is more sensitive at 100 days than
Similarly, the actual construction costs for projects between $1M to $10M were calculated
using the ‘ab2’ model for cost. The actual costs derived from the model ranged from $0.92M
Assuming a contract period of 100 days and the contract sum ranging from $1M to $10M, the
effects on the actual construction costs due to the deviations from the estimated contract sum
13
were examined by altering the contract sum at ±5% intervals. The deviations were reflected
in different forms of contract sum, including LCCOST, RCCOST, and INVCCOST. The
results of sensitivity analysis for ‘ab2’ model for cost is presented in Figure 2. The variations
of the ‘ab2’ model for cost are very constant throughout the $1M to $10M range. At ±5%
levels of deviation, the variations were approximately ±5% throughout the analysed contract
cost range.
The sensitivity of other factors, including project type, contractor selection method and
contractual arrangement approach, was also examined. Figure 3 depicts the sensitivity of the
‘ab2’ model for time to different project types, assuming that open tendering and lump sum
contract are used. The results as also shown in Table 5 indicate that the average actual
construction time for industrial, educational and recreational projects will take much longer
than that of the residential type. The differences in actual construction time between the
residential building and each of the industrial, educational and recreational buildings were
Figure 4 shows the sensitivity of the ‘ab2’ model for time to different contractor selection
methods and contractual arrangements, assuming a residential building. The results as shown
in Table 5 indicate that the actual construction time for negotiated tender and design and
construct contract is much less than open tender and lump sum contract. A saving of the
actual construction time of 16.67% can be achieved if negotiated tender instead of lump sum
14
tender is used. When a design and construct contract is used, a saving of 12.26% in the
actual construction time can be achieved over the lump sum contract (Table 5).
PRACTICAL APPLICATIONS
With the ‘ab2’ models, contract administrators could predict the actual time and cost for a
given project type, contractor selection method and contractual arrangement based on the
estimated contract time and cost. However, since the risk attitudes of clients may vary, it is
necessary to be able to cater for different risk perceptions. The effects on actual time and
cost due to the changes in risk attitudes can be represented diagrammatically by the actual
Figures 5 and 6 illustrates the actual time and cost curves of a typical project with an
estimated construction period of 237 days and contract sum of AUS$21.4 million. The
differences in risk attitudes are presented as the percentage deviations from the estimated
contract time and cost (±20% on x-axis), and the effects to the predictions are shown in the
actual time and cost curves. The actual time and cost curves facilitate a client to predict the
appropriate actual time and cost of a project based on his risk attitude. For instance, a risk-
seeking client is optimistic with the actual construction time and cost, and the predictions
along the left of the x-axis (-5% to -20%) could be referred to. A risk-averse client is
pessimistic with the actual construction time and cost. This type of client could refer to the
15
< Figure 5 >
The actual time and cost curves for different types of project, contractor selection and
contractual arrangement are presented in Figures 5 and 6. These curves can assist the client
during the pre-contract stage. Once the project type is identified, a client can compare the
actual time and cost curves for different contractor selection method and contractual
arrangement to determine which is the best option for a particular project. The contractor
selection method and contractual arrangement that would result in the shortest actual time
and least actual cost are preferred. In addition, the effects of risks on different contractor
selection and contractual arrangement options could be compared through the actual time and
cost curves.
CONCLUSIONS
A set of 93 Australian construction projects was used to develop several models for actual
construction time and cost prediction. A forward crossvalidation regression analysis was
adopted for the development of the model for actual construction time forecast when client
sector, contractor selection method, contractual arrangement, project type, contract period
and contract sum are known. The standard deviation of the deleted residual revealed that the
best model for actual construction time prediction comprises the independent variables ‘log
contract time’ (LCTIME), ‘lump sum’ (LS) in the CONTRACT sub-group, and ‘other’ (OT)
16
Regression models were also developed for forecasting the actual construction time and cost
when client sector, contractor selection method, contractual arrangement and project type are
known while contract period and contract sum are estimated. Different forms of regression
analyses, including the standard regression and the crossvalidation regression, were adopted.
However, the results of analyses show that the crossvalidation regression models ‘ab2’, with
the smallest deleted residual ssq of 1.77817 for time and 0.56923 for cost, are preferred.
Since the ‘ab2’ models for time and cost are dependent on the contract period and contract
sum being known, it is necessary to investigate the effects in situations where these have to
be estimated. The results of the sensitivity analyses on the ‘ab2’ models show that the errors
in predicted actual construction time become smaller as the contract period increases. In
contrast, the errors in predicted actual construction cost are virtually the same for large and
and small projects. The reliability of the actual construction time and cost prediction based
on ‘ab2’ models thus depends on the accuracy of the estimated contract period and contract
sum.
The effects of different project type, contractor selection method and contractual arrangement
were also examined. The results indicate that the actual construction time for industrial
project is the longest when compared with residential, educational and recreational projects.
A significant saving in actual construction time can be achieved when negotiated tender and
design and build contract are used instead of the traditional open tendering and lump sum
contract approaches.
17
Despite the ‘ab2’ models for time and cost being influenced by inaccurate contract period and
contract sum, the models provide practical tools for clients and contractors to predict the
actual construction time and cost based on the risks and uncertainties of different client
ACKNOWLEDGMENT
The authors would like to acknowledge the construction companies who participated in the
survey for providing the necessary project information to facilitate this research study, and
Michael Mak and Mark Varnam for collecting the project data.
18
REFERENCES
Bromilow, F.J, (1969) Contract Time Performance Expectations and the Reality, Building
Bromilow, F.J. and Henderson, J.A. (1976) Procedures for Reckoning and Valuing the
Performance of Building Contracts, The Chartered Builder, Vol. 10, No. 9, pp. 57.
Bromilow, F.J., Hinds M.F. and Moody, N.F. (1980) AIQS Survey of Building Contract
Bromilow, F.J., Hinds M.F. and Moody, N.F. (1988) The Time and Cost Performance of
Australia.
Chan, D.W.M. and Kumaraswamy, M.M. (1995) A Study of the Factors Affecting
Construction Durations in Hong Kong, Construction Management and Economics, Vol. 13,
19
Ireland, V. (1983) The Role of Managerial Actions in the Cost, Time and Quality
Performance of High Rise Commercial Building Projects, Unpublished Thesis Submitted for
Kaka, A.P. and Price, A.D.F. (1991) Relationship between value and duration of construction
Laptali E., Wild S. and Bouchlaghem N.M. (1996) Linear Programming for Time and Cost
Organisation and Management of Construction, 1996, D.A. Langford & A. Retik (eds),
Mak, M.Y. (1991) The measurement of time performance in major building construction
projects, Unpublished Thesis Submitted for the Fulfilment of Degree of Master of Project
Ng, S.T., Mak, M.M.Y., Skitmore, R.M., Lam, K.C. & Varnam, M. (2001) The predictive
ability of Bromilow’s time-cost model, Construction Management and Economics, Vol. 19,
RIRA (1989) Pre-Assessing Using Contract/Time Related Formula, The Royal Australian
20
Sidwell, A.C. (1984) The Time Performance of Construction Projects, Architectural Science
Walker, D.H.T. (1994) An Investigation into Factors that Determine Building Construction
Yeong, C.M. (1994) Time and cost performance of building contracts in Australian and
21
LIST OF CAPTIONS
Table 5: Sensitivity of contract time, project type, contractor selection and contractual
arrangements
22
1200
T -20 (ROL)
T -10 (ROL)
800 T -5 (ROL)
T 0 (ROL)
600
T +5 (ROL)
T +10 (ROL)
400
T +15 (ROL)
T +20 (ROL)
200
0
100 200 300 400 500 600 700 800 900 1000
Note: T -20 = -20% of contract time, ROL = residential + open tendering + lump sum
23
12
11
10 C -20 (ROL)
9 C -15 (ROL)
Actual Cost (AUS$)
8 C -10 (ROL)
7 C -5 (ROL)
C 0 (ROL)
6
C +5 (ROL)
5
C +10 (ROL)
4
C +15 (ROL)
3
C +20 (ROL)
2
0
1 2 3 4 5 6 7 8 9 10
Note: C -20 = -20% of contract cost, ROL = residential + open tendering + lump sum
24
1200
T -5 (ROL)
T 0 (ROL)
1000
T +5 (ROL)
Actual Time (Day)
800 T -5 (IOL)
T 0 (IOL)
600 T +5 (IOL)
T -5 (EOL)
400 T 0 (EOL)
T +5 (EOL)
200 T -5 (COL)
T 0 (COL)
0
T +5 (COL)
100 200 300 400 500 600 700 800 900 1000
Note: ROL = residential + open tendering + lump sum, IOL = industrial + open tendering + lump sum,
EOL = educational + open tendering + lump sum, COL = recreational + open tendering + lump sum
25
1200
1000 T -5 (ROL)
Actual Time (Day)
T 0 (ROL)
800
T +5 (ROL)
T -5 (RNL)
600
T 0 (RNL)
T +5 (RNL)
400
T -5 (ROD)
T 0 (ROD)
200
T +5 (ROD)
0
100 200 300 400 500 600 700 800 900 1000
Note: ROL = residential + open tendering + lump sum, RNL = residential + negotiated tender + lump sum,
ROD = residential + open tendering + design & contract
26
T-ROL
400
T-RNL
T-ROD
350 T-RND
T-IOL
Actual Time (Day)
T-INL
300
T-IOD
T-IND
250 T-EOL
T-ENL
T-EOD
200
T-END
T-COL
150 T-CNL
-20 -15 -10 -5 0 5 10 15 20
T-COD
Deviation From Contract Time (%) T-CND
(Contract time = 237 days, contract cost = AUS$21.4 million)
Note: T = time,
1st letter after hyphen represents project type: R = residential, I = industrial, E = educational, C = recreational
2nd letter after hyphen represents contractor selection method: O = open tendering, N = negotiated tender
3rd letter after hyphen represents contractual arrangement: L = lump sum, D = design & construct
27
C-ROL
26
C-RNL
C-ROD
24
Actual Cost (AUS$ million)
C-RND
C-IOL
22
C-INL
C-IOD
20
C-IND
C-EOL
18
C-ENL
C-EOD
16 C-END
C-COL
14 C-CNL
-20 -15 -10 -5 0 5 10 15 20
C-COD
Deviation From Contract Cost (%) C-CND
(Contract time = 237 days, contract cost = AUS$21.4 million)
Note: C = cost,
1st letter after hyphen represents project type: R = residential, I = industrial, E = educational, C = recreational
2nd letter after hyphen represents contractor selection method: O = open tendering, N = negotiated tender
3rd letter after hyphen represents contractual arrangement: L = lump sum, D = design & construct
28
Standard deviation
Variable
Step 1 Step 2 Step 3 Step 4
CTIME 0.332 0.184
CTIME2 0.735 0.454
√CTIME 0.231 0.180
lnCTIME 0.179 -
1/CTIME 0.270 0.179
Model 1
CCOST 0.701 0.186
CCOST2 0.759 1.264
√CCOST 0.619 0.193
lnCCOST 0.448 0.179
1/CCOST 0.518 0.181
lnCTIME 0.179 - -
Select - 0.173 0.169 na
Other - 0.172 0.168 -
Model 2
Lump sum - 0.170 - -
D&C - 0.175 0.171 0.169
Table 1: Results of forward crossvalidation procedure
29
Deleted residuals
Group Sub-group n ANOVA Levine’s
Mean Variance
(p) test (p)
public 31 0.022 0.031
Sector 0.404 0.830
private 62 -0.011 0.031
recreational 9 -0.048 0.032
industrial 26 0.010 0.030
Project type educational 15 0.001 0.722 0.018 0.651
residential 11 0.058 0.039
other 32 -0.015 0.039
Model 1 selective 59 0.035 0.035
Contractor
open 15 -0.010 0.012 0.021 0.064
selection
other 19 -0.102 0.018
lump sum 61 0.043 0.032
Contractual
D&C 16 -0.083 0.005 0.011 0.201
arrangements
other 16 -0.081 0.036
Total 93 0.000 0.032
30
Std. Err. Std. Err.
BETA B t(89) p-level
of BETA of B
Intercept .207638 .144462 1.43732 .154133
LCTIME .970507 .026231 .966737 .026129 36.99849 0.000000
Lc .070275 .028096 .097269 .038889 2.50122 .014206
OT -.051494 .027914 -.083980 .045524 -1.84476 068399
31
i Label alpha beta1 ab1 beta2 ab2 beta3 beta4
1 Constant -1.25943 0.85662 -1.07885 1.26350 -1.59130 0.06807 -11.44751
2 CTIME 0.00106 0.30771 0.00033 -0.00067 0.00000 0.00000 0.00752
3 LCTIME 1.48502 0.93565 1.38947 0.95108 1.41237 0.98254 4.50414
4 RCTIME -0.09797 0.67958 -0.06658 0.45174 -0.04426 0.00000 -0.64119
5 INVCTIME -0.18694 0.00000 0.00000 -83.29847 15.57190 0.00000 92.78079
6 LCCOST -0.00275 0.89772 -0.00247 1.05852 -0.00291 0.00000 0.00652
7 RCCOST -0.00001 0.00000 0.00000 0.16468 0.00000 0.00000 -0.00001
LATIME results
32
Contract time (days)
100 200 300 400 500 600 700 800 900 1000
-20% 97.39 199.61 302.10 401.33 496.09 585.98 670.94 751.06 826.51 897.50
-15% 103.61 212.52 321.01 425.46 524.71 618.42 706.58 789.35 866.98 939.70
-10% 109.88 225.41 339.79 449.31 552.85 650.16 741.30 826.51 906.07 980.31
-5% 116.18 238.29 358.42 472.85 580.51 681.22 775.13 862.55 943.84 1019.36
Accuracy 0% 122.51 251.13 376.91 496.09 607.68 711.59 808.07 897.50 980.31 1056.93
+5% 128.86 263.94 395.25 519.03 634.37 741.30 840.15 931.39 1015.53 1093.05
+10% 135.24 276.71 413.43 541.65 660.59 770.35 871.39 964.25 1049.53 1127.78
+15% 141.63 289.43 431.45 563.97 686.32 798.75 901.79 996.11 1082.36 1161.16
+20% 148.04 302.10 449.31 585.98 711.59 826.51 931.39 1026.99 1114.05 1193.26
Residential 122.51 251.13 376.91 496.09 607.68 711.59 808.07 897.50 980.31 1056.93
Industrial 136.06 278.92 418.61 550.98 674.91 790.32 897.47 996.79 1088.76 1173.86
Project type
Educational 128.30 262.99 394.72 519.52 636.38 745.20 846.24 939.89 1026.61 1106.85
Recreational 129.53 265.52 398.51 524.52 642.50 752.37 854.38 948.93 1036.48 1117.49
Contractor Open 122.51 251.13 376.91 496.09 607.68 711.59 808.07 897.50 980.31 1056.93
selection Negotiate 101.96 209.00 313.68 412.86 505.73 592.21 672.51 746.93 815.85 879.61
Lump sum 122.51 251.13 376.91 496.09 607.68 711.59 808.07 897.50 980.31 1056.93
Contractual
Design &
arrangement 107.49 220.34 330.70 435.26 533.17 624.33 708.98 787.45 860.10 927.32
build
Note: Base Contract cost = $10M, project type = residential, contractor selection method = open, contractual arrangement
= lump sum
Table 5: Sensitivity of contract time, project type, contractor selection and contractual
arrangements
33
Contract cost ($ million)
%
1 2 3 4 5 6 7 8 9 10
-20 0.73 1.48 2.23 2.99 3.74 4.50 5.26 6.02 6.79 7.55
-15 0.78 1.57 2.37 3.17 3.98 4.79 5.60 6.41 7.22 8.03
-10 0.83 1.67 2.51 3.36 4.22 5.07 5.93 6.79 7.65 8.51
-5 0.87 1.76 2.65 3.55 4.45 5.36 6.26 7.17 8.08 8.99
0 0.92 1.85 2.80 3.74 4.69 5.64 6.60 7.55 8.51 9.47
+5 0.97 1.95 2.94 3.93 4.93 5.93 6.93 7.94 8.94 9.95
+10 1.01 2.04 3.08 4.12 5.17 6.22 7.27 8.32 9.37 10.43
+15 1.06 2.14 3.22 4.31 5.41 6.50 7.60 8.70 9.80 10.91
+20 1.11 2.23 3.36 4.50 5.64 6.79 7.94 9.09 10.24 11.39
Note: Contract time = 100 days, project type = residential, contractor selection method = open, contractual arrangement =
lump sum
34