CME - Estimates
CME - Estimates
PROJECT AND
MANAGEMENT
PART 2: ESTIMATES
PRESENTED BY:
ENGR. HADJI PEEJAY ARANDA
INTRODUCTION
WHAT IS ESTIMATE?
● is an expression of opinion or the prediction of the
●
To determine the probable cost of the project as
realistic as possible
●
To determine the most probable time to complete
the project
TYPES OF ESTIMATES
APPROXIMATE ESTIMATE
●
are sufficiently accurate for the evaluation of design
alternatives, or the presentation of preliminary
construction estimates to the owner, but are not
sufficiently accurate for bid purposes.
●
a more liberal view of quantities and prices may be
taken.
TYPES OF ESTIMATES
DETAILED ESTIMATE
●
Sometimes called final or definitive estimate.
●
It is prepared by determining the cost of materials,
labor, equipment, overhead, profit, and VAT in
detail per items of work based on the approved
design/construction plans, specifications and
construction methods.
TYPES OF ESTIMATES
DETAILED ESTIMATE
Ex.
A rough estimate of for a 2-storey commercial
building is needed by a prospective client during an
exploratory meeting with a contractor. After
describing initially the requirements of the client the
contractor mentally notes the costs of similar projects
that he made before
A+ 4 B+C
UC=
6
PREPARING APPROXIMATE
ESTIMATE
PROJECT COST
1 PHP 5,645,956.00
2 PHP 4,376,467.00
3 PHP 8,325,325.00
4 PHP 6,345,214.00
5 PHP 7,349,219.00
From the given we have
A = 4,376,467.00
B = 6,408,436.20 C = 8,325,325.00
PREPARING APPROXIMATE
ESTIMATE
A+ 4 B+C
Using the equation UC=
6
4,376,467.00+4∗6,402,436.20 +8,325,325.00
We have UC= 6
UC = 6,389,256.13
PREPARING APPROXIMATE
ESTIMATE
Ex:
The material cost of a two storey building in 2014
was 6,500,000.00 as agreed upon by the contractor
and the client. In 2017, the same contractor was
asked by another client for the estimated cost of a
similar project to be done. What will be the rough
estimate using the construction price index
PREPARING APPROXIMATE
ESTIMATE
CPI current n
=(1+i)
CPI past
232.3 3
=(1+i)
227.3
PREPARING APPROXIMATE
ESTIMATE
√
3 232.3 3
227.3
= √(1+i)
3
1.007279=(1+i)
3
Estimated cost 2017 =6,500,000.00 (1.007279)
Estimated cost 2017 =6,642,976.20
The value may not seem much since the index used is
the overall item. It would be better if the price index for
EACH materials will be used in making the rought
estimate
PREPARING APPROXIMATE
ESTIMATE
Ex:
The cost of a two storey building in 2014 was
6,500,00.00 as agreed upon by the contractor and
the client. In 2017, the same contractor was asked by
another client for the estimated cost of a similar
project to be done. What will be the rough estimate
using the construction price index
PROGRAM OF WORK
• Cost of Materials
DIRECT COST • Cost of Labor
• Equipment Expenses
• Overhead Expenses
• Contingencies
INDIRECT COST • Miscellaneous Expenses
• Contractor’s Profit
• VAT
PRICING
Cost at source:
processing, crushing, stockpiling, loading,
royalties, local taxes, construction and/or
maintenance of haul roads, etc.
MATERIALS
Expenses for hauling to project site
COMPONENT
Handling expenses COST
Storage expenses CONSIDERATION
Allowance for waste and/or losses
(not to exceed 5% of materials
requirement)
PRICING
a. ESTIMATED TRAVEL SPEED, LOADING/ UNLOADING
& ALLOWANCE FOR DELAY
T = D÷R
Where :
T = Time, Time of Travel (hr.)
Heavy Equipment
3 1.50 736.50 19,210.38 306.88 1,600.86 1,208.70 237.50 100.00 22,664.31 868.92 108.61
Operator
Highly Skilled
4 1.50 736.50 19,210.38 306.88 1,600.86 1,208.70 237.50 100.00 22,664.31 868.92 108.61
Operator
5 Light Skilled Operator 1.40 687.40 17,929.68 286.42 1,494.14 1,208.70 212.50 100.00 21,231.44 813.98 101.75
6 Driver 1.30 638.30 16,648.99 265.96 1,387.42 1,208.70 200.00 100.00 19,811.07 759.53 94.94
7 Skilled Laborer 1.30 638.30 16,648.99 265.96 1,387.42 1,208.70 200.00 100.00 19,811.07 759.53 94.94
8 Semi-Skilled Laborer 1.20 589.20 15,368.30 245.50 1,280.69 1,171.80 187.50 100.00 18,353.79 703.66 87.96
9 Unskilled Laborer 1.00 491.00 12,806.92 204.58 1,067.24 967.70 150.00 100.00 15,296.44 586.45 73.31
PRICING
AND
DEMOBILIZATION In no case should mobilization and
demobilization exceed 1% of the
Estimated Direct Cost (EDC) of the civil
works items.
PRICING OF THE MATERIALS
CONTRACTOR’S
PROFIT
VAT
INDIRECT OCM
COSTS
Up to P5Million 15 10 25
Above P5M up to
P50M 12 8 20
Above P50M up to
P150M 10 8 18
Above P150M 8 8 16
FACTORS TO BE CONSIDERED
IN ESTIMATES
Fluctuation of
Materials Cost
Weather Condition Wastage Factor
DPWH (2016)
MANUAL ON COST ESTIMATION FOR SCHOOL BUILDINGS (BUREAU OF CONSTRUCTION)
ARANA, F (2017)
ESTIMATES (BUDGETARY)
MEPF PRESENTATION
CIRIA RP992
The SuDS Manual Update: Paper RP992/22
PRICING OF THE MATERIALS
FOR QUESTIONS OR FOR COPIES OF PRESENTATION
PLEASE EMAIL ME AT”
[email protected]
PRICING OF THE MATERIALS
FOR ANY QUERIES AND FOR LINKS OF THE
PRESENTATION MATERIALS