Permanent Way Handbook
Permanent Way Handbook
Permanent Way Handbook for Use on Heritage Railways Written by: HENDERSON, MARCYNIUK
Checked by: CRAPPER – U of E
Draft 1 – Version 15 – 30/03/11 Written under the supervision of the
University of Edinburgh for the HRA.
Permanent Way Handbook for
Use on Heritage Railways
Heritage Railway Association
University of Edinburgh
FOREWORD
Since the first platelayers installed the rails on the Middleton Railway in 1758, the permanent way
has evolved and developed to present day 200m lengths of Continuous Welded Rail (CWR) and
ballast-less High Speed Rail. The Heritage Railway (HR) movement aims to preserve railways
themselves as well as items of rolling stock and provide tourist services. Their railways have a wide
variety of permanent way and methods of maintenance and many include museums to the age of
steam or diesel. This handbook aims to produce a Permanent Way reference for use on Heritage
Railways to fill a current deficit in documentation.
Mainline railway maintenance in the UK is conducted by Network Rail (NR) and its contractors. In
order to maintain levels of quality and safety, Network Rail produce standards for maintenance and
repair. These standards are highly technical and detail the necessary tolerances and procedures
required to allow safe passage of trains travelling at up to 125mph. Heritage Railways, on the other
hand, are in effect subject to Light Railway Orders and so are restricted to maximum speeds of
25mph. This low speed, coupled with very low annual cumulative tonnage, means that Network
Rail standards are well beyond what is required for the safe running of heritage lines.
Despite the maturity of the heritage movement within the UK, no publication exists specifically
detailing the permanent way of Heritage Railways. Network Rail standards are thought to be too
technically detailed and not suitable for the working practices and resources of Heritage Railways.
Whilst a great deal of technical knowledge is held by senior members of Heritage Railways, younger
members- the future of these organisations- struggle to gain sufficient background knowledge to be
able and confident to engage in the planning and coordination of maintenance. This handbook
seeks to rectify this with the formation of a Permanent Way handbook for use on Heritage
Railways, which details specifically relevant technical information and methods of working.
1 th
Coombs. D.H / PWI. 1971. British Railway Track: design, construction and maintenance. 4 Edition. Permanent Way
Institution, London.
Permanent Way Handbook
Heritage Railway Association
University of Edinburgh
1. INTRODUCTION ............................................................................................................................ 1
5. INSPECTION................................................................................................................................. 18
6. MAINTENANCE ........................................................................................................................... 37
BIBLIOGRAPHY .................................................................................................................................... 77
GLOSSARY ........................................................................................................................................... 79
INDEX .................................................................................................................................................. 92
1. INTRODUCTION
1.1 Purpose
This ‘Handbook for the Maintenance of the Permanent Way of Heritage Railways’ is intended as
an introduction to the Permanent Way of Heritage Railways (HRs) for those with little or no initial
knowledge. It aims to give a broad background to the Permanent Way whilst detailing standards
specifically relevant to Heritage Railways. Its purpose is to afford an adequate level of knowledge
to new volunteers allowing them to become aware of the ways of inspection and maintenance for
HRs.
The handbook may also prove useful as a reference document for those with an existing general
knowledge of railways. The standards contained within this handbook are specific to Heritage
Railways and so may enable quick reference of relevant values.
Heritage Railways, in general, run infrequent services at speeds of no more than 25mph. Network
Rail’s mainline standards are therefore not applicable for use on Heritage Railways due to their
high speeds and high annual cumulative tonnage. Further, the detailed and technical nature of
the Network Rail standards means they are difficult to access and understand for those with no
prior knowledge of the Permanent Way. This handbook aims to provide an alternative source of
literature to that previously available and address a deficit in Permanent Way guidelines for the
Heritage Railway sector.
It is trusted this handbook shall prove to be useful for those new to the railway sector and shall
enable knowledge to be quickly and rapidly gained by those looking to help maintain the
Permanent Way.
1.2 Scope
The notes which follow are intended to assist in the undertaking of inspection and maintenance
by those with little or no knowledge or experience in this field. Individual railways differ greatly in
their circumstances and so certain notes or methods of working may not be applicable for all
railways. This is in no way intended as a definitive rulebook rather a selection of relevant
information specifically suitable for the Heritage Railway sector.
Due to the complex and wide ranging nature of railways in general, the scope of this handbook
focuses on the Permanent Way only. Due to time constraints on this project, off track structures
have not been covered and it is intended these shall be covered in a subsequent publication.
Heritage Railways employ fishplated joints as the predominant method of joining lengths of rail
track. There are few instances of continuous welded rail (CWR) track due to the specialist
equipment and skilled labour required for its installation. For this reason this handbook covers
only the maintenance requirements for jointed rail.
This handbook is no substitute for experience and hands on working and is not intended to be so.
Its aim is to be a useful document for those with little experience of the Permanent Way or those
looking to increase their knowledge in specific areas.
1.3 Disclaimer
The Authors have used their best endeavours to ensure that the content of this handbook is
accurate, complete and suitable for its stated purpose. However they make no warranties,
expressed or implied that compliance with the contents of this document shall be sufficient to
ensure safe systems of work or operation. Accordingly the Authors, The University of Edinburgh
and the Heritage Railway Association will not accept liability for its content or any subsequent use
to which this document may be put.
Further, this document is neither endorsed nor guaranteed by the University of Edinburgh or the
Heritage Railway Association.
1.4 Terminology
Throughout this handbook the following words have been used with the following specific
definitions:
2. SAFE WORKING
It should be noted that local, railway specific, forms of safe working and documentation exist and
that these should be consulted and followed in the first instance.
Individuals
It should be understood by all that each and every member of the permanent way team has a
responsibility to ensure safe working practices are maintained. Where unsafe methods are
observed, individuals should halt work since the result of not doing so could be the injury of
friends and fellow volunteers.
Before work starts workers should ensure they are made aware of the following:
Running lines which remain open.
Positions of lookouts and methods of warning.
Limits of safe working area.
Positions of safety.
Known traffic movements during working hours.
Workers should be aware of their own limitations and not over exert themselves since injury is
likely to cause more delay to works than an individual being unable to complete a task.
PICOW
Works should be supervised and managed by one person only, termed the “Person in Charge of
Works” (PICOW). This individual is responsible for the safety of those taking part in maintenance
works and should be listened to and their instructions followed immediately. Work on the line
should not take place unless there is a suitably experienced individual acting in the role of PICOW.
Those using machinery or even simple hand tools should be aware of those working around them
to prevent injury caused by the swing of excavators or picks.
2.2.2 Training
Individuals should not use equipment which they are not familiar with. Instruction should be
carried out on the safe usage of each item of equipment used during works and precautions to be
taken to avoid injury.
Stable Position
If it is not possible to get close to the object, try sliding it into a more accessible area. Before
lifting ensure feet are shoulder width apart with one slightly in front of the other to help
maintain balance.
Posture
Hips and knees should be bent with a slight bend in the back to pick up the item.
Do not allow back to bend further upon lifting the load.
Avoid twisting back or leaning sideways, turn by moving feet rather than shoulders.
Ensure a good, firm hold
Holding the load against the body is preferable to gripping since hands can easily tire under a
heavy weight.
Lifting aids
Trolleys, jacks, ratchets etc. can be used to minimise the manual effort required for lifting
and movement of items.
2.3 PPE
Personal Protective Equipment (PPE) should be worn as a last resort measure to prevent or
reduce injury caused by accidents. PPE should not be relied upon, methods of work should be
planned so as to minimise the risk of accidents occurring and the need for PPE.
All personnel on or around the railway must wear at all times:
Orange high visibility clothing: as a minimum this should consist of a high visibility vest
Protective footwear: as a minimum this should include a protective toe cap. Steel sole
plates and non-slip grips are also important.
The nature of work being carried out may demand further equipment as stated below:
Gloves: manual handling or when handling harmful chemicals (such as creosote
substitute).
Ear defence: when using vibrating hammers or other power-tools.
Eye protection: during use of cutting equipment, rail drills or sleeper drills.
Face masks: during use of cutting equipment, rail drills or sleeper drills.
Safety apron: during use of chain saw.
The personal protective equipment mentioned must be worn at all times during which workers
are exposed to risk – no matter how short the task.
3. PERMANENT WAY
3.1 Subgrade
The subgrade of the railway is the section beneath the ballast; it is out of sight but still plays an
important role in the Permanent Way. It acts as an intermediary between the ballast and the
natural subsoil carrying the loads transmitted by the ballast and also draining water away from
the track structure. In certain cases a blanket may be required between the Ballast and the
subgrade, this is detailed in section 5.4.4.
3.2 Ballast
Ballast is placed between the formation and the sleepers. It acts to support the sleepers laterally,
longitudinally and vertically. Ballast shoulders restrain lateral movement of track whilst ballast
between sleepers prevents longitudinal movement. The ballast also provides a free drainage
environment to remove water from the track bed, for this reason it should be ensured that there
are no fines present in the ballast. Any variety of crushed stone can be utilised as ballast as long as
it is free draining and resilient to the loading and unloading experienced from the passage of
trains, generally the deeper the ballast the better.
3.3 Sleepers
Sleepers carry out two tasks on a railway; to maintain the gauge of the rails and to transfer the
loads from the passing train to the ballast. In order for sleepers to evenly distribute the loads to
the ballast it is important that the ballast is correctly tamped beneath the sleepers.
3.3.1 Concrete
Pre-stressed concrete sleepers have become more prevalent than wooden sleepers on mainline
railways due to their longer life spans and ability to carry heavier loads. Sleepers are commonly
available pre fitted with fixings for flat bottom rail. Concrete sleepers are utilised on Heritage
Lines however timber sleepers are still more popular.
3.3.3 Steel
Steel sleepers consist of plate steel that is rolled to form a hollow sleeper shape with spade ends.
Steel sleepers are bought pre fitted with rail fixings and maintain accurate rail gauge throughout
their lifetime. The spade ends prevent lateral movement of the sleeper, however require
thorough tamping of the ballast. Without a tamping machine it can prove difficult to adequately
pack the ballast into the hollow of the sleeper and so steel sleepers can only be utilised where
there access to an automated tamping locomotive.
3.4 Rails
There are two possible types of rail to be found on Heritage Lines, ‘Flat Bottom’ and ‘Bullhead’. As
illustrated in figure 3 the two types of rail are distinguished by their different profiles.
3.4.1 Bullhead
Bullhead rail was the standard rail laid by British Rail (BR) up until the 1950’s, consequently there
was, and still is in sidings, large volumes of bullhead in use. When many Heritage Lines were first
laying or renovating their track, donations of Bullhead Rail were made by BR and so it is widely
used on Heritage Lines.
3.4.4 Fishplates
The traditional ‘clickety-clack’ noise of a train running on tracks arises from the joints between the
lengths of rail. Rail comes in a variety of lengths dependant on its weight and origin and can be
between 30ft up to 350ft for that currently being installed by Network Rail on the UK mainline.
The method Heritage Railways use to join lengths of rail together is called ‘Fish Plating’ and it
consists of shaped sections of steel that are bolted into pre drilled holes at the rail ends. This
method is the same that has been employed since the early days of the railways and is as suitable
for HRs now as it was for the early railway pioneers then. Figure 4 details a typical fish plate and
the bolts that hold it onto the rail. The holes in the fishplate are elliptical and the bolts
correspondingly shaped so that the nuts can be tightened from one side only.
3.5.1 Bullhead
Bullhead rail fixings consist of a chair in which the rail sits and is held in position by a sprung key
which is hammered in to place. The chairs are usually cast iron and have changed little in over 130
years; an example in use on a HR dates from 1881 and is still performing its intended function.
3.5.3 Concrete
Concrete sleepers usually have pre fitted baseplates or bolts to enable chairs to be attached, as
such they are accurate and quick to achieve the required gauge and also maintain the gauge well.
3.5.5 Timber
Timber sleepers are able to carry a variety of rail fixings and rail types. Either baseplates or chairs
are secured by coach screws, similar to that in figure 8, and require holes to be predrilled into the
timber sleeper. It is important that this is done accurately as it shall affect the rail gauge and is
difficult to adjust once fitted.
3.6 Checkrails
Checkrails are extra, short sections of rail that are placed between the running lines to help
prevent derailment. The checkrails act as a guide to ensure the wheel cannot come off the track
as it is restrained by the flange. Checkrails are found on switches and crossing where there is a
risk of the train wheels coming away from the running line and also on corners where the flange
could ‘climb’ the rail leading to derailment. Figure 9 details the configuration of a check rail, the
check block serves the purpose of maintaining the correct gauge between the running line and
the check rail.
3.8 Curves
Simple curves consist of straight sections of track meeting a corner of fixed radius to transport the
train around a bend. Simple curves are generally utilised within sidings, whereas for a running line
a transition curve is normally utilised.
3.10 Cant
Cant or Super Elevation, as illustrated in figure 12, is the difference in height of sleepers
longitudinally across the track. It is found on bends to compensate for the centrifugal force
experienced by the train as it traverses the corner. It allows trains to go around corners at greater
speeds and with greater comfort for the passengers as the centrifugal forces cancel out the tilting
experienced.
3.12 Mileposts
Mileposts are numbered posts beside the track at regular, usually quarter mile intervals. They
mark distance usually from the main station and their function is as a measuring and location tool.
If an issue is found to occur on the track during an inspection the number of rail lengths to the
nearest mile post is recorded and this is used to locate to issue.
Gauge Widening
(on Curves of less than 200m)
Radius of 200 – 140 m ¼ in 6 mm
Radius of 140 – 110 m 15/32 in 12 mm
Radius below 110 m ¾ in 19 mm
Horizontal Alignment
Cant Varies from curve to curve, see section 7.2.1
Cross Level Error 13/16 in 20 mm
Twist (over 3m length) 13/32 in 10 mm
5. INSPECTION
Critical to ensuring trains run smoothly and safely is the inspection of the Permanent Way. The
importance of a detailed, effective and suitably stringent inspection regime must not be
underestimated since the consequences of not addressing this issue could cost money,
reputations and lives.
Regular inspection allows the identification of faults before they pose a threat to the safe running
of trains. Through early identification, timely maintenance intervention can take place:
Minimising the risk of derailment.
Reducing correction costs.
Lengthening the life of the track.
Minimising track down-time.
Thorough and co-ordinated inspection allows cost-effective work implementation through
planning and prioritisation.
A base level of knowledge is required to undertake line inspections, once an individual possesses
this knowledge, practice and experience will improve the quality of inspections undertaken.
The following sub-sections guide the novice track worker through the preparation, process and
subsequent actions involved in inspection. It will assist the Patroller in the correct identification
of faults and course of action needed.
Where there is more than one line running parallel then the distance between the lines governs
the approach to be taken. Where the distance between adjacent rail running edges is greater than
3 metres or 10 feet the tracks shall be inspected individually.
If the distance is less than 3 metres then two plain line tracks may be inspected concurrently
during a single inspection however:
Where either of the lines goes through S&C, the lines shall be inspected separately.
The second track must be clearly visible.
Between successive inspections the track walked must be alternated.
Strict safety procedures must be adhered to when inspecting the line. Please refer to Section 2.1
Lineside Safety for further safety information.
The following sub sections give guidance on the types of defects to be observed during visual
inspection of the track. These points should be read and understood before a Patroller conducts
their first inspection and consulted during to ensure a full and detailed inspection takes place.
5.6.1 Rails
As the upper most section of the Permanent way it is logical to start an inspection examining the
running rails. Broken down into three sections, common defects are listed.
Note that where a broken or cracked rail is found in the running line, the first priority and duty of
the patroller is to protect traffic. Immediate actions are described in Annex C.1.
Structure of rail
Cracked Rails
A regular inspection regime would hope to catch the early stages of cracking before the rail
physically breaks in two. Where broken rails are found, inspection shall record the type of
fracture.
Defects should be categorised in the following way:
Transverse Break
Longitudinal Split
Joints
Expansion Gap
Joints should be expected to be open in mild weather; if gap is minimal, as shown in figure 15,
this should be reported for further investigation.
Faulty Bolts
Bolts should be checked to ensure they are tight and do not contain cracks; loose bolts allow
joints to dip. Bolts may also be oiled to prevent seizing of the connection.
Dipped Joints
Extent of dipped joint should be noted and compared with previous inspections. Dipped joints
of above 12mm are not permissible and shall require correction, until such time an emergency
speed restriction of 5mph should be placed on the section.
Chairs
Broken / cracked
If a chair is fractured in the vicinity of the holes for coachscrews or in the vertical segment in
contact with the rail then replacement will be required. Fractured corners, where the fracture
is not in contact with fastenings are acceptable.
Loose
Loose chairs should be reported for further attention as per maintenance schedule.
Keys
Missing
Missing keys allow movement of the rail and are therefore unacceptable, often train
movement dislodges keys and so missing keys should be replaced during inspection with
use of carried key hammer.
Elongated holes
Elongated holes can be identified through the presence of loose chairs or baseplates and will
allow movement of spikes and coachscrews spreading the gauge. Should be reported for
investigation and potential sleeper replacement.
Broken / cracked fastenings
Where a fastening is found to be defective it will not satisfactorily complete its role and must
therefore be replaced.
Incorrect type
Fastening systems should be used only with the correct corresponding chair / baseplate.
Only one type of fastener may be used per chair / baseplate. Types should not be mixed on the
same chair and should be reported for replacement if found.
Baseplates
Missing Coachscrews
Chairs should be attached to wooden sleepers through the use of three coachscrews.
5.6.3 Sleepers
During line walking, inspection of sleepers is limited to a visual examination of the exposed
surfaces. Visual examination is satisfactory for steel and concrete sleepers, however, wooden
sleepers are at risk of wet rot which can affect any surface of the sleeper; visually inspecting the
sleepers will not establish if there is decay on the underside or within a wooden sleeper.
Correspondingly, severe weathering of the top surface, indicating poor condition, may mask
timber which may be quite sound internally.
General
Positioning
Sleepers should be positioned perpendicular to rails. Out-of-square sleepers increase the
distance between sleepers, resulting in undue stress being exerted on the support system.
Voids under sleepers
Voids can be detected by watching the vertical movement of the sleeper under traffic and in
the case of timber sleepers by sounding, near the chair or baseplate, with a hammer or
accurately measured using void meters.
Voids under concrete sleepers are indicated through the presence of white rounded ground
ballast and should be noted for maintenance.
Derailment damage
Derailments can cause significant damage to sleepers, irrespective of type. Careful and
detailed inspection should take place after such incidents. Any sleepers which experience
major damage should be replaced to prevent gauge spread and ensure the rigidity of the track.
Timber
Wet rot
Particularly prevalent in forested areas where leaf mulch allows water to gather on sleepers
and encourages decomposition, waterlogged ground also aids decomposition.
Hollow / rotten sleepers can be detected by the dull sound emitted when they are trod upon;
the sound being most apparent when the ends of the sleepers are struck.
Steel
Cracks in rail seat housing
Cracks within the surround of the rail seat must be investigated to ensure their presence does
not result in loose, unsecured rails which would weaken the track system.
Broken housing / fastening
The rail fastening for a steel sleeper is pictured in figure 22 below. Missing clips or rail pads
should be reported.
Concrete
Loose cast-in housing
The housing to allow rails to be attached to concrete sleepers is predominantly cast-in during
manufacture. Sleepers - particularly older units - should be checked to ensure the housings are
still adequately secured within the main body of the concrete sleeper.
Cracking
Sleepers should be inspected for cracks, particularly around fastenings and the rail seat, and
transverse cracks in the four-foot.
Erosion
Erosion resulting in reinforcement becoming exposed will allow corrosion, weakening the
structural integrity of the sleeper.
Rail pad
Rail pad should be centrally situated between sleeper and rail and should be in a suitable state
of repair, if not sleeper should be reported for maintenance.
5.6.4 Ballast
Contamination of ballast
Dirt, weeds, slurry can accumulate in the ballast and reduce drainage.
Quality / condition of ballast
The presence of crushed ballast will reduce the efficiency of the track system.
Ballast profile
Where the ballast shoulder profile and four foot level do not conform to the levels stated in
the specifications.
Permanent Way Handbook 29 of 93 pages
Heritage Railway Association
University of Edinburgh
Excess ballast obscuring clips
In severe cases of excess ballast it could interfere with traffic on the line and must therefore be
removed to the edges of the track.
Geometry
Basic visual inspection should involve assessing gauge and geometry by eye. It is outwith the
scope of such an inspection to accurately measure and assess conformance with the limits set in
the track standards. Where a minor issue is observed it should be noted for further investigation
during a gauge and geometry inspection. Major issues such as visible gauge widening should be
addressed immediately through the use of tie bars or similar.
Fastenings
Unbroken and tight
The following fastenings within S&C s should be checked to ensure they are tight and fully
serviceable.
o Heel Blocks
o Stock rail blocks
o Blocks and bolt in nose of crossing
o Chair / baseplate fastenings
o Fishbolts and fishplates
Stretcher rods
Rods should be straight, undamaged and securely fastened to rails.
Sleepers
Packing
Sleepers should be fully supported, compacted and restrained by ballast, particularly under
chairs, within the crib and at the ends of sleepers.
Condition
Sleepers should be inspected for faults as described in section 5.6.3.
Orientation
Sleepers should be perpendicular to the running rails by eye.
Operation
Switches should be inspected to ensure operation is smooth and unimpeded with clear and
lubricated slideplates and chairs. It is also important to observe S&C during the passage of trains
to ensure they remain rigid throughout and do not demonstrate any movement.
Movement
Evidence of movement of the rails or of the crossing being driven ahead or out of alignment,
should be checked for. Section 4.6.1 gives further details on common defects.
Wear
Due to the nature of switches and crossings, and their vulnerable position, they are subjected
to heavier wear than plain running line. In particular, the following areas should be inspected
for wear and damage:
o Switch blades
o Switch blade tips
o Crossing nose
Gauge
Gauge of switches and crossings should be checked when both open and closed.
Alignment
Rails
Lines should run straight and parallel. Passenger comfort and load safety is risked if this is not
the case.
Kinks and buckles can be identified by observing down the length of the track and recording
any irregularities seen.
Check rail clearances
Faulty or damaged check rails can affect the distance between the check rail and the running
rail, potentially obstructing passage of trains. For this reason it should be ensured that the void
between the rails is clear and free from obstruction and check blocks are fully tightened.
Longitudinal Level
Cross levels
On straight track, rails must be level on the vertical plane to ensure even distribution of loads
down to the sub layer and prevent eccentric loading increasing the possibility of derailment.
Settlement of sub layer over several track panels could result in an extended area of cross level
error and so evidence of settlement should be investigated.
Cant
Cant, where applied, should be measured to ensure it conforms to the designed level. The cant
and its run-out must be checked for divergence from the prescribed specification since in some
circumstances it can lead to derailment.
Cant should be checked with and without loading to ensure it is maintained under traffic.
Gauge Spread
If measurements demonstrate that the distance between the rails is increasing this could be a
case of “gauge spread”. The following should be looked to as an indication of the cause of the
problem.
Twist
Slips / subsidence
Unsupported or abnormally supported sleepers resulting from slips or subsidence can no
longer support rails and therefore twist can occur under the force of a passing train.
Incorrect tamping
Poorly supported sleepers allow them to move which may result in twist under loading.
Settlement
Differential track settlement or heave can result in twist occurring.
Sleepers
Out of square sleepers
Sleepers must be positioned perpendicular to the rail to provide ideal support conditions.
Correctly spaced
Sleepers should be evenly spaced, 24 per 60ft panel, along the length of the track.
Track Buckling
Measurements may indicate a rapid, tight bend in the rail. If this is the case the following should
be investigated as a possible root of the problem.
Over-tightened fishbolts
Fishbolts and fishplates are designed to hold the joint of rails firm but allow expansion and
contraction of rails with changes in temperature (i.e. summer heat waves). If fishbolts are
over-tightened the contraction and expansion movement is prevented, thereby causing
buckling.
Voided sleepers
If sleepers do not rest on firm ballast, vertical movement can occur. If the void beneath the
sleeper is large, enough vertical movement will be sufficient to cause buckling.
Horizontal buckling may also occur if there is insufficient ballast preventing lateral movement
of the sleepers.
Fixed point
Points at which rails are fixed (such as longitudinal timber bridge or level crossing) prevent
expansion and contraction and therefore, if not designed with this in mind, can buckle.
Expansion Gaps
To allow expansion of the rail due to raised temperatures the gaps between rails should conform
to the levels detailed in the standards sheet depending upon the atmospheric temperature during
measurement.
Inspection should take place in spring to allow correction before summer hot spells.
Rail Depth
Rail depth reductions may result after a particularly heavy running season. It may be prudent to
measure the extent of the reduction in rail depth during Gauge and Geometry Inspection.
Sidewear
Curves should be examined for evidence of sidewear. Where found a sidewear gauge should be
used to measure and record the extent and rate of change.
Clearly marking defects allows subsequent inspections to establish the rate of growth of existing
faults and also establish which faults have not previously been identified. It should also prevent
defective rails from being reused.
6. MAINTENANCE
Maintenance of the Permanent Way is an essential part of any working railway. Without it the safe
running of trains would be in doubt and derailment could become a possibility. Due to the
volunteer nature of the majority of those undertaking maintenance activities, efficient planning and
preparation should be adopted to make the most of the volunteer labour that is available.
Volunteer numbers for the Permanent Way are often far lower than those working in the engine
sheds or on the running of the trains. Therefore, large maintenance works need to be planned in
advance in order to assemble the required number of volunteers to satisfactorily and safely
undertake the works.
6.1.1 Routine
Routine maintenance will be conducted to a schedule which shall differ for individual railways
dependant on the regularity of use and weight of trains using the line.
The maintenance section in this handbook provides details of the routine works which should be
undertaken to ensure continual operation of the line.
6.1.2 Non-routine
Non routine maintenance, such as the upgrading or renewal of track or the rectification of
unexpected incidents requires an individual approach for each problem. Section 7 details the
standards such work should adhere to, including details of measurements for the relaying of track
and other works.
Non-routine planned maintenance shall usually be timetabled over the course of several years to
be completed in the off season of the railway. As a section of sleepers are nearing the end of their
life-span, for instance, they shall be added into the scheme of works to be completed several
years in the future. This planning allows business plans and expected cash flows to be drawn up
and the long term maintenance of the railway to be managed and planned for.
6.2.3 Ballast
Ballast acts to support and restrain the sleepers and to drain water away from the track, it should
therefore be maintained to allow it do both jobs it is intended to do. Autumn leaf litter and other
debris should ideally be removed from the line and not allowed to form a layer of mulch over the
ballast. This acts to prevent water from draining through the ballast and further deposits fines
within the ballast leading to ballast contamination.
Ballast can be lost from the ballast shoulders into the cess drain or down the side of an
embankment. Over time this may act to reduce the capability of the ballast to restrain the track
and so sections of track shoulder should be re-ballasted over an interval period.
6.2.4 Sleepers
Attention must be paid to sleepers once they cease to fulfil the role they were intended for.
The 1 in 4 method is applied to sleepers when maintaining a stretch of track. If 1 sleeper out of 4
in a row no longer maintains the gauge or supports the rails then this may be allowed to remain in
place as long as the remaining 3 sleepers are structurally sound.
Maintenance for timber and concrete demands different actions as detailed below.
TIMBER
As timber sleepers age and water starts to penetrate into the sleeper body, rot will occur. This can
exhibit itself in several ways as discussed in section 5.6.3. Generally once a sleeper starts to show
these symptoms there is little that can be done to correct them and replacement is the only
option.
If the sleeper cannot be replaced immediately a tie bar may be installed to maintain the gauge. If
found on a running day or perhaps before replacement of a stretch of sleepers, tie bars can be an
appropriate solution. Tie bars are a temporary solution and should be in place for no more than
six months.
To replace a sleeper, the ballast shoulders at either end of the sleeper first need to be dug away
and the ballast in between the sleepers loosened and removed. Particular attention should be
given to loosening the ballast in contact with the sleeper - with a pick axe - down to the sleeper
base as suction can occur and make removing the sleeper difficult.
If using second hand timber sleepers it is important to fill old screw holes. The holes collect water
and so allow rot to develop within the body of the sleeper. To address this, short sections of
wooden dowel of the correct diameter can be forced into the holes displacing the water and
preventing any further ingress of moisture.
CONCRETE
Concrete sleepers are similar to timber in as much as once serious cracking of the concrete occurs
there is little that can be done to remedy the situation. Small cracks and chips around the edge of
the surface pose no problem as long as the internal reinforcement bar is not exposed.
The process of replacing concrete sleepers is similar to timber however the increased weight of
concrete sleepers requires up to six men to drag and replace the sleeper safely. As a general rule
6.2.5 Chairs
Track bed failure
The maintenance of chairs is predominantly focussed on the replacement of those that are
cracked and/or damaged. Commonly manufactured from cast-iron they can crack easily and
cannot be repaired.
Cracks triggering the need for replacement of chairs are located in the upper vertical restraints
and in the vicinity of the fastening holes. Indicated in figure 27 below by a cross is a chair in
need of replacement due to the horizontal crack through the vertical restraint. The tick
demonstrates a damaged chair which does not require to be replaced; a corner has been
removed but since it does not affect the fastening of the chair to a sleeper it does not require
replacement.
Derailment
Derailment and the following rerailing process can cause significant damage to chairs, sleepers
and fastenings. After such an event chairs should be examined thoroughly for cracks and
where present should be replaced to maintain the structural integrity of the track system.
Loose chair
Maintenance at the first instance is retightening of the coachscrews or other fixings fastening
the chair to sleeper.
Keys
Should it become apparent that certain keys are repeatedly coming loose then inspection
should identify this and maintenance may involve the replacement of the keys in question.
With the passage of trains, keys can move out from between the rail and chair. If this occurs
the rail is no longer fully supported since movement can occur. Before the keys loosen
completely they should be returned to the correct position using a rail hammer.
Such issues are easily solved. Due to the easy nature of the work, it can often be carried out
during inspection of the line.
In figure 29 below the top picture is a chair requiring maintenance, in the form of reinstallation
of the rail key. The bottom picture is acceptable since the entire key is between the chair and
the rail.
BASEPLATES
Cracks
Similar to chairs, baseplates must be removed if cracks occur in the vicinity of fixing points.
Fixing holes
Upon removal of fixings the baseplate fixing should appear square and not exhibit any wear or
divergence from the standard shape, otherwise the plate must be replaced.
Pad movement
Where baseplate pads are found to have moved from beneath the plate, they must be
replaced to ensure the energy absorption role they play is maintained.
Loose baseplate
As per guidance given for loose chairs.
COACHSCREWS
Coachscrews must attach chairs / baseplates tightly to sleepers if the track system is to be rigid
and efficiently transfer loads. Maintenance must therefore include the tightening / tensioning of
all coachscrews.
Before the initiation of tamping or rail alignment works all screws should be checked.
Where coach screws are found to be damaged in any way (head or thread) they shall be replaced.
Permanent Way Handbook 43 of 93 pages
Heritage Railway Association
University of Edinburgh
Where new holes must be drilled for the installation of coachscrews they should be drilled at the
correct size (for the screw to be used), centrally within the plate/chair hole and vertically. If the
guidance holes are not drilled vertically straight downwards, upon installation of the screw, the
chair will be pulled out of position causing a change in the track gauge.
Coachscrews should NOT be driven into the sleeper using any type of hammer but should be
tightened using an impact wrench or T-spanner. During fastening it should be ensured that:
The screw is installed vertically.
The ferrule is not deformed.
The top of the chair and the underside of the coachscrew head do not touch.
The exposed nature of coachscrews means there is the potential for them to be significantly
damaged during a derailment (see figure 30). If the baseplate/chair continues to be held firmly
then there is no need for urgent replacement. However, where the chair has cracked, or the
screw is loose, as a result of the force, both the screw and chair should be replaced.
FERRULES
Ferrules should be present in all connections between chairs (or baseplates) and coachscrews to
absorb vibrations produced by movement of trains on the line and reduce any impact or resulting
damage.
Ferrules shall be positioned in the screw hole in a chair before the coachscrew is inserted. The
coachscrew is then tightened until there is full contact with the ferrule and approximately 6mm
(1/4”) is visible between the top of the chair and the bottom of the coachscrew head.
If a ferrule has been deformed from the standard shape (see figure 31) in any way then it must be
discarded and a new piece used.
Screws have been over tightened if there is any less than 6mm of the ferrule visible and must
therefore be removed, ferrule replaced and screw fixed with less torque.
If a new ferrule is found to drop entirely into the fastening hole present in a chair then
deformation of the chair has occurred and it must be replaced.
6.2.6 Joints
There are a number of causes which can act individually or in unison to cause a dipped joint
between two lengths of rail. Natural flexing, slack sleepers, loose fishbolts and worn fishplates all
allow a joint to lower.
Eliminating dipped joints improves ride and removes the main cause of wear on rail ends, thereby
reducing the chance of rail end failures. If dipped joints are not resolved, rapid development of
further defects can occur; including pumping of formation, broken fishplates and broken or
cracked rail ends.
POSITION
The position of rail joints should be carefully considered during replacement of rails, particularly
on curves, to ensure that joints in parallel rails are opposite each other. Curves must be given
special consideration because the inner rail travels a shorter distance than the outer rail.
FISHPLATES
Cracks
Fishplates are forged, therefore cannot be repaired when cracked. Where cracks are identified,
fishplates must be replaced with urgency,
The extent of damage to the fishplate will determine the urgency and approach to be taken
upon discovery of such a fault. Annex C.2 displays required reactions.
If repeated failure of fishplates occurs in the same location then a wide skirted fishplate may
be installed which can restrain the joint under greater loading.
Oiling
Oiling of fishplates takes place to facilitate and ease thermal expansion of rails preventing
seized joints which can lead to track buckling.
1. Removal of fishbolts
2. Removal of fishplate from rail web.
3. Existing grease and debris should be cleaned from the surface of the fishplate and the
web of the rail. A wire brush should be used to ensure the removal of stubborn dirt.
4. The fishplate should be inspected for crack or signs of weakening and, where found,
replaced
5. Grease should be liberally applied to the inner surface of the fishplate and to the web.
6. Position of plates should be reversed (sides swapped) to prevent continual repeated
wear.
7. Bolts refastened
Specialist fishplates
Where rails of different type or weight must be connected at a joint, specialist or bespoke
fishplates must be used. Dropped forged fishplates must be used between rail of different
sections or weights. Figure 32 shows the connection plate used between flat bottom rail and
bullhead rail and figure 33 displays the connection between two types of flat bottom rail of
different weights.
FISHBOLTS
Fishbolts should be kept sufficiently tight if the joint is to remain strong and increased component
wear is not to occur. However, it should be noted that if tightened too much the bolts will restrict
the capacity of the joint to accommodate thermal movement of rails.
Fishbolts should be tightened to the appropriate torque values displayed in the table below,
however note that compliance with these values is markedly less important than ensuring all
fishbolts are tight.
Efficient maintenance practices should involve the oiling of exposed threads of fishbolts during
the fishplate oiling process to allow easy removal of fishplates for maintenance and prolong
component life.
Upon removal of bolts during fishplate oiling the opportunity should be taken to inspect them for
signs of cracking or bending and where appropriate replace them.
FISHBOLT HOLES
Position of holes
Accuracy is vital in the drilling of fishbolt holes. Therefore marking of positions should be
carried out carefully using the dimensions detailed in table 3.
Note: the table below gives dimensions assuming a 6mm gap at the joint between rails.
Drill Bit ∅ 30 mm 30 mm 30 mm 30 mm
Drilling of holes
The process of drilling fishbolt holes in rail ends must be carefully controlled to ensure the
quality of work and an adequate fit upon installation of the rail.
The joint will not fit unless the hole is drilled perpendicular to the longitudinal length of the
rail. Rails must be firmly supported at both ends and around the area to be drilled to prevent
movement or vibration of the rail. The finished holes should present a smooth void through
which fishbolts can be easily fed.
Rails should not be drilled if temperatures are below 10 degrees Celsius.
Any error or defect resulting from drilling will cause overstressing of the bolts, plate and joint
and therefore must be avoided to prevent future maintenance problems.
SHIMMING
Where fishplates are found to be worn, such that they no longer give sufficient support to the rail
joint, they should either be replaced or shimmed.
EXPANSION GAPS
Expansion gaps should be left between rails to allow for the natural expansion of metal in hot
weather. For this reason expansion gaps should be checked in the Spring before the onset of
Summer.
If more than 5 consecutive joints are found to have no expansion gap (i.e. are closed) movement
of the rails should be considered.
See section 7.9 for details of expansion gap sizes.
Note that expansion size gap does not increase with the length of rail. It remains constant due to
the tolerances between the fishplate holes and the bolts.
SLEEPERS
The joint between rails marks the weak point of the track system and was one of the reasons for
the widespread adoption of CWR on the mainline network.
The sleepers bordering a joint must be firmly packed to limit movement of the joint since
movement can accelerate component wear. Handheld tampers should be used routinely as part
of the maintenance regime to ensure firm packing.
Rail joints should be centrally located between supporting sleepers to ensure even distribution of
the loads. During renewal this should strive to be achieved, however, it is not a critical area to be
changed urgently. It will lead to accelerated deterioration of the joint relative to normal wear
rates but this alone is not safety critical.
Sleepers on each side of the joint should be of the same type to ensure uniform reaction around
the joint to loading. If different sleepers were used, for example a concrete and timber sleeper
were combined, the timber sleeper would flex under loading whereas the concrete sleeper would
remain rigid resulting in undue strain being carried.
6.2.7 Rails
With Heritage Railways using both bullhead and flat bottom rail the maintenance of both are
considered in this handbook. Maintenance requirements are similar for both types of rail and
therefore the measures detailed below are, unless otherwise stated, applicable to both flat
bottom and bullhead rail.
Due to low order quantities which typify heritage railways requirements it can be difficult and
costly to obtain new rail. For this reason, Heritage Railways should investigate sources of second-
hand rail, including:
Ministry of Defence Establishments
The MOD uses railways extensively for the movement of ammunition within its armament
depots and docks. With the consolidation of resources in recent years depots have been
closed and rail with low wear has been available.
Former Ports / docks
Network Rail
Formerly an important source of second-hand permanent way components, however,
with the growth in asset management, donations of components are now more limited.
When obtaining rails from different sources, it must be ensured that the parallel rails making up
the running track are of the same type and weight.
MOVEMENT OF RAILS
During the movement of rails it is critical to ensure they are fully supported throughout. For this
reason the use of fork lift trucks should be avoided since the narrow support they offer allows
bowing and thus deformation of the rails.
A lifting boom, figure 35, may be used in to widen the distance between supports therefore
supporting a longer length of the rail. Otherwise strops spread wide apart may provide sufficient
support.
Particular care must be taken when loading and unloading rails to avoid damage, particularly to
rail ends.
STORAGE
Where rails are to be stockpiled they should be supported on a level base (such as a concrete
hard standing or compacted earth) or on regularly spaced level sleepers. Spacing should be small
enough to prevent obvious bowing between supports. Storage and support arrangement must
be considered carefully since rails easily deform if their entire length is not supported.
If rails are to be stacked the following should be observed:
Heavier, longer rails should occupy the lower levels.
Support should be capable of carrying load with minimal deflection.
Ends of rails should be kept above one another.
Stacking should not exceed hip height.
Placement of rails should be performed slowly to prevent damage.
Flanges of rails should not overlap, particularly on the bottom layer.
Rail ends should be positioned so as to avoid damage from vehicle movements.
Stockpile should be positioned to prevent gathering of water around base since this can
result in corrosion.
During maintenance work rails can be stored in the four foot of the running line as long as the
maximum height of the rail does not exceed the level of the running track by any more than
25mm.
The loads exerted on Heritage Railways are typically low and therefore wear rates are far lower
when compared with the main network. If chosen carefully second hand material can have an
extensive asset life.
For this reason it is critical that the rail chosen for the line, when second hand, is thoroughly
examined and inspected to ensure there are no flaws present caused by previous heavy usage.
Inspection has two main stages:
1. Establishment of extent of wear
2. Identification of common defects.
Extent of wear
The head of the rail experiences the most wear, therefore the overall height and width of the
rail head are the critical dimensions when assessing rails for reuse.
Due to the different types of rail used across the Heritage Railway network the permissible
wear of used rails is expressed, below, as a percentage reduction in the height of the rail or
width of the foot. Limit for reuse of partly worn rail:
o In heavily trafficked depot track 5%
o In sidings / occasionally used running lines 9%
If obtaining curved rail side wear should also be taken into account. See limits detailed in
section 7.7.
Assessment of the extent of wear on a rail can be carried out using an appropriate gauge
(similar to callipers) or where possible by weighing a sample of rail and comparing readings to
technical literature.
Common defects
Detailed visual inspection of used rails should identify any defects present in the rail. Defects
which automatically class the rail as unsatisfactory would include buckling, cracks and severe
corrosion.
Where defects and damage are limited to the fishing surfaces of a rail the rail may be used
after removal of the ends.
The same remedy may be applied to rail with worn / dipped ends or cracked fishbolt holes.
Wheel burns indicate locations where repeated slips of loco wheels have occurred and are a
possible source of rail fracture so should be carefully examined to determine the extent of the
defect.
Rails with chipped edges can be reused by reversing the rail as long as one edge is in good
condition.
Note: Re-rolled track should not be used for standard gauge running line.
RAIL GRINDING
Removal of faults and optimisation of the rail profile can, in some instances, be resolved through
the accurate and careful application of rail grinding. Short lengths of RCF can be removed and the
rate of return reduced through grinding.
Hand grinding may also be used to maintain rails in S&C.
SIDEWEAR
Sidewear is monitored since excessive reduction in the width of the rail head could allow the
flange of rolling stock to strike a fishplate.
However, on Heritage Railways the number and weight of trains is low enough that sidewear is
unlikely to be a problem unless:
1. Rolling stock axles are poorly adjusted and cause excessive wear with long fixed axle
vehicle.
2. Sub-standard rail used – possible if second hand, since records are non-existent.
RAIL LUBRICATION
Rail lubricators may be installed on curves with a radius of less than 200m to reduce friction and
wear between wheel flanges and the rail head.
If a tight curve is found to exhibit signs of excessive wear the installation of a rail lubricator should
be considered.
With wear on Heritage Railway lines being predominantly low it is unlikely that lubrication will be
widely required, however, in areas of high traffic flow such as entry to the main sidings or depot
lubrication may have its advantages.
Note that it must be ensured that the running surface of the track is not contaminated by their
installation.
CUTTING OF RAILS
Where a replacement rail must be cut to length or damaged rail ends removed the following
guidance should be considered:
Care should be taken to ensure accuracy when measuring and marking the position for the cut.
During operation the saw must not be pressured or forced through the cut but allowed to cut
at the designed speed.
Sawing must be done in a controlled environment, with the saw operator wearing appropriate
personal protective clothing. Only those involved in the cutting process should be in the close
vicinity whilst the saw is in operation.
As the saw blade approaches the tip of the rail foot it is important to ensure that the rail end
will not sag, twist or trap the saw blade under the weight of the rail being removed.
Disk cutter
As above, but also should be noted that it may be necessary to partially cut the rail from one
side and then cut the remainder of the rail from the opposite side due to the limited size of the
blade. If this is the case care should be taken to ensure the rail is fully supported and that it
does not bend and trap the cutting blade.
REPLACEMENT OF RAILS
When a rail requires replacement its replacement is likely to have a different profile to the
bordering rails. Where this is the case, any step in the gauge profile, must be blended with the
existing rails through rail grinding.
Hand-grinding should start and finish approximately 1.5 metres on each side of the rail joint to
ensure a sufficiently gradual change.
Note that hand grinding is unlikely to produce the required gradual change in rail head profile so
the grinder should be fully supported.
Lengths of rail removed from the track should be clearly marked to indicate such, however,
lengths should not be discarded since sections may be of sufficient quality to be able to be cut to
length for areas where bespoke length track is required.
RAIL CREEP
Rails have a tendency to creep in the following situations:
Downhill sections.
Direction of predominant traffic flow.
Areas of intense, repeated braking by trains.
Flat bottomed track creeping towards bullhead track.
These areas must be regularly examined to determine the extent of creep.
Minor creep can be prevented from worsening through the installation of rail anchors. Otherwise,
creep requires correction when it results in the closure of more than five consecutive expansion
joints or where initial signs of buckling occur.
SLEWING
Slewing of railway line is a maintenance method used to remove kinks in the line or reduce the
sharpness of curves.
The slewing process involves the removal of restraining ballast (ballast positioned in the direction
the track is to be moved, as shown in figure 36) from the ends of sleepers. Crow bars and jim
crows can then be used as levers against the underlying ballast to push the full track system
outwards.
Where the track fails to move the following steps should be attempted. After each, leverage
should be retried. If movement is still not forthcoming the next item listed should be carried out:
Ballast surrounding sleepers should be loosened with the use of picks and spades.
Track and sleepers should be jacked and lowered to break the surface tension between
ballast and underside of sleepers.
On curves where the track is being moved away from the centre point the keys of the
inner rail may be removed and slewing attempted.
It should be noted that this process will be more difficult if the ballast surrounding the sleepers in
question is contaminated, since moisture and fines will allow stronger surface friction to hold the
sleepers in place.
Where the above steps do not work, ratchets and chains can be used as long as there is a firm
anchor point or failing that, the track will have to be lifted and re-laid.
ADJUSTMENT OF LEVEL
The line must remain level to prevent increased component wear. The only point at which parallel
rails are at different levels is where cant is applied to curves.
BOLTS
Critical to the maintenance and continued smooth operation of switches and crossings is the
maintenance of the rigid track system through the checking of fastenings. Crossing bolts and heel
block bolts should be kept tight to prevent movement of the rails under loading which can
increase component wear, or in more serious instances result in derailment. Where possible bolts
should be tightened using a torque wrench to the levels indicated in section 6.2.5 for fishbolts.
When unfastened, bolts should be inspected for cracks and to ensure they remain true and
straight with the thread undamaged. Where faults are found they should be immediately
replaced.
As part of the railway maintenance regime the exposed threads of bolts should be greased to
prevent corrosion seizing joints.
REPLACING SWITCHES
Where a switch requires replacement due to wear or damage it should be noted that only
complete half sets of switches should be laid. Changing of just one rail in a half set is likely to lead
to differences in gauge and clearances during operation of the switch.
Installation should follow the steps listed below:
1. Placement of switch.
2. Fixing to timbers.
3. Adjustment for line and level.
4. Slide baseplate bolts tightened.
5. Timbers packed.
7. Track Standards
The following standards assume the use of standard, non inclined, base plates or chairs and are
suitable for both Bullhead and Flat Bottom rail (unless otherwise stated).
7.1.1 Standard
The standard gauge is 1435mm (4’ 8 ½“)
Track gauge should be maintained on straight plain line within the following limits:
Tight Gauge: 1429 mm ( 4’ 8 3/10“)
Wide Gauge : 1450 mm (4’ 9 1/10“)
n.b. Switches and Crossings gauge limits see section 7.1.3
Transition curves
Transition curves should be maintained to provide a gradually tightening radius between the
straight track and fixed radius curve.
Vertical Curves
Minimum curve radius is reliant on type of rolling stock operated and extent to which rail can be
fitted.
Twist
Maximum twist permissible over 3m is 10mm (13/32”)
7.2.4 Subgrade
A blanket may be employed if issues exist with mud pumping from clay based soils. The blanket
can be either a layer of fine aggregate or a ‘Terram’ style matting to isolate the ballast from
subgrade. Geotextiles should be laid as per manufacturer’s instruction with special care taken to
ensure they are placed the correct way up.
The implementation of a blanket shall require increased depth of ballast as detailed in section
7.2.5.
7.2.5 Ballast
Ballast should consist of angular crushed stone of between 28 – 50mm (1 1/10 – 2”), it should be
free of fines to allow adequate drainage and should be sufficiently hardwearing.
Ballast depth should be a minimum of 150 mm or 6“ beneath sleepers, ballast should be kept
clear of sleeper tops, chairs and baseplates.
Above a blanket layer, ballast should be a minimum depth of 250mm or 9 8/10” to prevent
tamping damage to the blanket.
Ballast shoulders should be a minimum width of 300mm (12”) for Plain Track. If extra lateral
restraint is required ballast can be heaped on shoulders up to 125 mm (4 9/10”) in height.
The four foot should be sufficiently filled with ballast so that the vertical sleeper faces cannot be
seen.
7.2.6 Sleepers
Sleepers should be of sound material and able to support loads and maintain the gauge, they
should be fitted perpendicular to the rail and uniformly spaced. Standard of 24 sleepers per 60ft
track panel.
In areas of difficult formation or tight curves (<800m) sleeper spacing’s of 650mm (2’2”) may be
used.
Replacement of sleepers must be of the same material, width and depth over the whole length of
one track panel.
Fine adjustment of cross level error can be achieved through the use of pea ballast as a packing
material.
Timber
Sleepers should be either preserved softwood or hardwood in material such as Douglas Fir, Scots
Fir, Baltic Redwood or Brazilian Hardwood.
Typical sleeper dimensions should be 250 mm (10”) x 125mm (5”) x 2600mm (8’6”).
Second-hand sleepers should be inspected to ensure they are true and straight and have no areas
of decay, hollow or unsound knots, splits or compression failures.
Concrete
Concrete should be prestressed, free from cracks, either transverse or longitudinal and no re-bar
should be exposed.
Current mainline standard F40 sleepers are over strengthened for use on HRs so where available
F27 may be preferred.
Steel
Steel sleepers where used should be to BS 500 design,
Sleeper spacing’s on jointed track should be at 750mm (2’6”) centres corresponding to 24
sleepers per 18.3 (60ft) rail length.
7.2.7 Rail
All rail should be to BS 9 - Bullhead, BS 11 - Flat Bottom, or equivalent for foreign imported rail.
Rails capable of carrying axle loads up to 25 tonnes include 98lb Bullhead and 113A Flat Bottom
rail to BS 11.
Sidewear should be within the limits stated below:
Extent of sidewear should not reach the bottom of the rail head.
7.2.9 Joints
Rail joints should be square on straight track and can be staggered by up to 60mm (2 3/8”) on
curved track.
Expansions Gaps
n.b.Length of rail has no effect on expansion gaps due to tolerances of fishplate hole/bolt
connection.
Fishplates
Fishplates should be greased before installation and secured by not less than 4 bolts per pair of
plates either side of rail ends. Cracked fishplates should be replaced due to risk of shattering.
Fishplates should be lubricated on a regular maintenance schedule using a high quality rail
lubricant to allow free thermal expansion and contraction.
Should repeated cracking of fishplates occur over time, deep skirted fishplates can be installed to
counteract the issue.
Connections between Flat Bottom and Bullhead rail utilise special fishplates which should be
fitted in the above described manner,
Remarks:
Type
EXAMPLE:
Panel 6 from milepost 1 ¾ BH Broken chair and ferrules missing – coach screws reusable
Type
Remarks:
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
BIBLIOGRAPHY
BRITISH STANDARDS
NR/L2/TRK/0053 Network Rail: Inspection and repair to reduce the risk of derailment at
switches.
ROGS 2006 The Railways and Other Guided Transport Systems (Safety)
Regulations 2006
ROGS 2006 Guide The Railways and Other Guided Transport Systems (Safety)
Regulations 2006 – A guide to ROGS
INDG 398 Are you making the best use of lifting and handling aids?
OTHER PUBLICATIONS
GLOSSARY
A
Adjustment Switch Switch allowing the expansion of continuous welded rail track. Installed
between CWR and jointed track it permits thermal movement of the CWR.
See also: expansion switch
Alignment Position of rail in both horizontal and vertical planes, relative to design.
position.
B
Ballast Layer of uniform sized stone placed on top of the sub-layer. The stone
(commonly limestone or granite) supports and restrains sleepers, and
provides good drainage for the track.
See also: bottom ballast and upper ballast.
Ballast Shoulder Ballast mounds placed at the ends of sleepers to prevent lateral movement.
Baseplate pad Square of rubber, or other resilient material positioned between sleeper and
baseplate to absorb vibrations and prevent indentation of the plate.
Blanketing Sand (or synthetic membrane) positioned between earthwork formation and
bottom ballast to improve drainage. Used particularly in situations where
mud pumping may occur, such as on clay soils.
Bottom Ballast Ballast beneath sleepers employed as vertical support. Placed, levelled and
compacted before track is laid.
Boxing in Term used to describe the placing of ballast to form typical ballast profile.
British Rail Operator of the entire railway network of the United Kingdom until
privatisation in 1995.
Buffer stop Found at the end of railway lines or sidings to stop vehicles.
C
Cant On curved track, the vertical elevation of the outer rail above inner rail to
counteract the centrifugal force of the train travelling around a curve. Also
can be referred to in terms of the cant of a rail; the angle of a rail relative to
vertical. Also known as superelevation.
Cant deficiency The height by which the outer rail on a curve would have to be lifted in order
to counteract the lateral cornering force. Dependant upon the typical running
speed of vehicles on individual curves.
Chair Fitting attached to timber or concrete sleepers which supports bullhead rail.
Predominantly superseded by bearing pads and flat-bottomed rail on the
main line network but still widely used on heritage railways.
Check Rail Rail set close to the inside running rail so as to make contact with the back of
the vehicle flange on traversing vehicles. On a sharp curve this contact
prevents the flange of the opposite wheel from impacting heavily with the
running rail. Check rails are also used at crossings to ensure the opposite
flange follows the correct route, avoiding derailment.
Crossing (1) A right of way across a railway line allowing pedestrians or vehicles to cross
the line safely.
(2) A piece of permanent way, the purpose of which is to allow one track to
cross another at an angle.
(3) Component of a turnout. Specifically the point where the tracks diverge
leading out of the turnout. Element forms a ‘V’.
Cross Level (1) Difference in the horizontal level of rails, relative to the centre line.
(2) Gauge used to measure the extent of this difference.
Cross over Rails allowing trains to move between two parallel tracks.
Cross-tie Sleeper
Cyclic top Can cause excessive vehicle sway resulting in passenger discomfort and
possibly derailment.
Depending upon the speed and loading of a vehicle, there is the potential for
it to cause a derailment. Cyclic top occurs predominantly on jointed track
where joints can dip every 30m (60ft). The regular dips can cause vehicles to
effectively bounce progressively more violently until the vehicle bounces out
of the four foot, derailing.
D
Design Speed Speed (in miles per hour) which the line has been designed to accommodate.
Diamond Track which allows one rail line to cross another. See also Crossing
Double Track Route in which a track is provided for travel in each direction.
Dual gauge Type of line designed to accommodate vehicles of different gauge through
the addition of a third rail between the existing rails.
Electric staff or token System of dispensing tokens from machines at either end of the operating
line which ensures only one token is in operation at once.
Embankment A section of the line built up to fill a depression in the terrain and reduce the
extent of the gradient of the line.
Expansion switch Switch allowing the expansion of continuous welded rail track. Installed
between CWR and jointed track it permits thermal movement of the CWR.
Also known as adjustment switch.
F
Facing Pointing in the direction from which trains predominantly approach.
Facing crossover Crossover which faces the predominant direction of travel on the lines.
Facing turnout A turnout which can select the path of a train (the way in which it will
diverge). Switches face the predominant direction of travel.
Facing point Point allowing trains to change track without changing direction of travel.
Fastening Device used to secure a rail. This can be through connecting the sleeper and
rail directly or indirectly connecting the rail to a chair fastened to the sleeper.
Fishplate Metal plate with four holes to allow the connection of two rails. In jointed
track. When fastened with four bolts a bolted butt connection is made.
Flangeway Area adjacent to rail which must be kept clear to allow free, unimpeded
passage of the wheel flange.
Ferrule Small hollow plastic hollow stopper placed between chair and coachscrew to
absorb vibrations from the track and reduced damage to sleepers caused by
such vibrations. Ferules act by absorbing some of the vibration caused by the
passing of trains to reduce the forces experienced by the sleepers. Therefore,
if they are found to be missing the sleepers experience the full vibratory
force, allowing movement of coachscrews thus widening holes and resulting
in a loss of grip, allowing the gauge to increase.
Flange Lip protruding from the inner edge of wheels to restrain the movement of
rolling stock and keep them on the rails.
Flangeway Gap through which the wheel flange passes between the check-rail and
running rail.
Flat Wheel defect in which the wheel is no longer round. Most commonly results
from the dragging of seized wheels caused by locked bearings or brakes
Flat bottom rail Type of rail with wide foot and flat bottom to allow direct fastening of the rail
to sleepers without the need for chairs.
Form of rail which superseded bullhead rail.
Flange Climbing During the traverse of a curve by a train the flange of the front outside wheel
pushes against the gauge face as it guides the vehicle around the curve. Due
to the rigid nature of the axles the outer wheel is directed outwards at an
angle resulting in the wheel impacting with the gauge face. The combination
of these forces causes sidewear but if the force of impact and pressure
against the outer rail are high enough then the wheel flange can climb up the
rail and derail.
Formation Level Marking the top the foundation level, level at which ballast is laid.
Fouling point Area around two or more converging tracks in which sufficient clearance is
unavailable for trains to pass each other.
Four foot The area of a track bordered by a pair of rails. Abbreviation for four foot,
eight and a half inches.
Frog Point in a crossover that allows the wheel flange of stock taking one route to
pass through the rail of the other.
Permanent Way Handbook 83 of 93 pages
Heritage Railway Association
University of Edinburgh
G
Gall Defect in which either the chair is damaged or eroded by the movement of
the rail or the rail is damaged by the chair.
Gauge face The inside or running edge of a rail from which the gauge is measured.
Geotextiles Permeable fabrics are those which have the capacity to filter, drain or protect
earthworks.
Gradient Post Post positioned beside the line to detail a change in gradient of the track.
Guard rail Extra rails positioned between the running rails to prevent a derailed vehicle
from going completely off the track.
H
Hallade Method used during permanent way works to survey design and set-out
curves. Named after Emile Hallade.
J
Jim Crow Tool used to bend or remove bends from track.
Joint Dip Situation where two ends of jointed track butted together have dipped below
the usual running line level. Can be due to a variety of causes but should be
addressed.
Jointed track Track in which track lengths are bolted together end-to-end using a fishplate.
Junction Point on the line at which two or more lines diverge from each other.
K
Kango Hammer A vibrating hammer with a special attachment which is sunk into ballast to
consolidate and so ‘tamp’ the ballast. User should only operate tool for short
periods due to risk of ‘white finger’.
L
Level crossing A crossing between road and rail.
Lookout Trackman whose duties involve observing for the approach of trains and
warning those working on the line.
Loading Gauge Height and width dimension limits which allow rolling stock to travel safely
and clear all lineside structures.
Longitudinal timbers Sleepers which run along instead of across the direction of travel. Used in
special circumstances on bridges etc.
M
Main line Primary running track (or artery) of railway, as contrasted with spurs, yard
lines, and sidings. Route connecting locations of importance.
Marker board Temporary notice placed to the side of the running track to draw attention to
a specific feature.
Mile post Post positioned beside the line to indicate the distance from that point to the
datum (usually start of the line). Aids recording and identification of faults
and defects.
N
Narrow gauge Track with a gauge less than 1435mm.
Network Rail Government created owner and operator of the majority of Great Britain’s
rail infrastructure.
Nose Point at which the running edges of two rails meet to form a crossing.
O
ORR Office of Rail Regulation.
Permanent Way Handbook 86 of 93 pages
Heritage Railway Association
University of Edinburgh
Economic and Safety regulator for the UK’s railway network. Replaced the
Rail Regulator in mid 2004.
P
PACT Paved Concrete Track.
From of ballastless track consisting of a continuous reinforced concrete slab
with baseplates attached to its surface.
Pad Material such as rubber which is non-conductive and resilient which is placed
between the baseplate and the rail to prevent galling.
Permanent Way The structure consisting of the rails, fasteners, sleepers and ballast plus the
underlying sub grade.
Permissible Speed Highest speed at which trains can traverse a curve when radius, cant, cant
gradient and rates of change of cant are considered.
Possession Occupation of the line (usually for engineering works) during which the line is
closed for normal services.
Pumping Defect where soft ground or voids results in sleepers being poorly supported
and allows movement under loading. Can result in fines being brought up
through the ballast and contaminating it.
Q
No Entries
R
Rail grinder Machine used to wear down irregularities on the surface of rails.
Rail seat Area on baseplate, sleepers or chair which supports the rail.
RCF Rolling contact fatigue - Damage that appears in rails due to overstressing
caused by wheel-rail contact. RCF describes a family of faults including:
spalling, flaking and squatting.
Refuge (1) Siding used by trains to allow overtaking by more important, faster trains. For
example passenger services overtaking goods trains.
(2) Indent in the wall of a tunnel or cutting in which a person or persons can
stand safely when a train is passing.
Rerailer Metal device used to guide derailed trains back onto the track.
Reverse Curve Curve formed by two circular curves on opposite sides of the track.
Running Line Track which makes up part of a continuous route rather than loops or sidings.
Running Rail Rails on which the wheels of trains run rather than, for example, check rails
which merely guide the rails.
Run-round the practice of releasing a locomotive from its train, moving it to the other
end of the train and re-attaching it, to make it ready for the return journey.
S
S&C Switches and crossings.
Covers all elements of crossings and turnouts.
Sand drag Length of track buried in sand to stop runaway vehicles safely without
derailing them.
Shim Slither of metal used to ensure worn fishplates fully fit into the rail profile
and adequately support the joint. Process of shiming.
Siding Track just off the main line used to store rolling stock.
Sleeper Hardwood, steel or concrete bars placed perpendicular (at 90 ) to the rails to
support them and transfer the load from trains down to the ballast and sub-
layer. Sleepers also maintain the position of the rails and therefore the
gauge.
Slewing Process of moving a section of track, including sleepers back into alignment
from a state of being out of alignment, possibly due to buckling.
Slide baseplate Baseplate which supports moving part of flathead rail in a turnout.
Slide chair Chair which supports moving part bullhead rail in a turnout.
Slippery Rail Condition resulting from leave litter and other detritus sticking to the track
causing wheel slippage.
Spalling A heat produced metal reaction when the wheel slides along the rail. Causes
dips to appear in either the wheel or on the rail surface.
Spot re-sleepering Replacement of sleepers on an individual basis when or just before failure
occurs.
Spur Stretch of line branching off from the main line. Often miles in length and
used to reach a facility, customer or industrial area.
Standard gauge Normal width between gauge faces used in the United Kingdom and across
Europe
Stock rail The fixed rail which the point of a switch rests against in a turnout.
Stretcher bar Connection between switches used to maintain gauge during operation.
Switch Track formation including moveable rails to allow diversion of trains from one
track to another.
T
Tamping The use of vibrating tongs to penetrate and repack ballast under sleepers.
Tongs can be vehicle mounted or a hand tool.
Timber Softwood or hardwood lengths used to connect and support the rails of
crossings or switches.
Token Object given to drivers of locomotives or others who wish to have full
possession of the line.
Top ballast Ballast placed on top of bottom ballast and above the level of the underside
of sleepers to restrain lateral movement of the track system. It is laid after
installation of the track components.
Track Formation The ground and soil structure beneath the ballast on which the track system
is laid.
Track Panel Term to describe the complete system of rails, chairs/fastenings and
sleepers. Typically considered in 30 or 60ft lengths.
Trailing crossover Crossover used by trains which are travelling against the normal flow of
traffic or are reversing. The crossover therefore faces in the opposite
direction to the predominant flow of traffic.
Transition Curve Where a straight track changes into a curve. The curve is of constantly
varying radius designed to reduce the effects of centrifugal force experienced
by users.
Turnout Another term for a set of points. Track involved in ‘turning out’ one line from
the main line.
Twist Track defect whereby there is a change in the cross level over a short length
of track. Where severe it can cause the wheels of a vehicle to lose contact
with the running surface of the rail.
Also known as the rate of change of cross level or cant gradient and can
therefore be detected through the measuring the cant of the track every
three metres.
Twist Rail A type of rail which merges together the inclined main line rail with the
vertical rail of a S&C component.
U
Up line Direction of travel towards the major city / London.
V
Permanent Way Handbook 90 of 93 pages
Heritage Railway Association
University of Edinburgh
Vertical Curves Second important transition element in the design of railway tracks allowing
gradual, smooth movement between terrains of different heights.
Viaduct Structure which carries the railway above ground level usually across rivers or
a valley.
W
Wet spot Area of track bed at which vertical movement of sleepers causes fines to
contaminate ballast and choke drainage.
Wheel base Distance between the front and rear axle of a vehicle (centre of axles).
X
No entries.
Y
No entries.
Z
No entries.
INDEX
BALLAST, 9, 31, 40, 66 INSPECTING THE LINE, 20
BASEPLATES, 45 INSPECTION KIT, 20
BUCKLING, 36 LEVELS OF INSPECTION, 20
PROCEDURE, 20
INSPECTION REPORTS AND RECORDS, 37
CANT, 17, 65
CHAIN, 3
CHAIRS, 43 JOINTS, 47, 68
CHECK RAILS, 68
CHECK RAILS IN S&C, 60
CHECKRAILS, 15 LEVEL CROSSINGS, 33
COACHSCREWS, 45 LEVELS OF INSPECTION, 20
COLD WEATHER, 62 LINESIDE SAFETY, 4
CONCRETE, 31, 67
CROSS LEVEL ERROR, 65
CURVES MAINTENANCE, 39
CANT, 17 MANUAL HANDLING
TRANSITION CURVES, 17 TECHNIQUE, 5
CUTTING OF RAILS, 56 MANUAL WORKING, 5
CUTTINGS & EMBANKMENTS, 40 MARKING DEFECTS, 37
CWR, 1 MILEPOSTS, 18
MOVEMENT OF TRAINS, 4
EXPANSION GAPS, 36
EXPANSION GAPS, 52 NARROW GAUGE, 2
EXPANSIONS GAPS, 68
OFF TRACK, 33
FERRULES, 46
FISHBOLTS, 49
FISHPLATES, 68 PATROLLER, 21
FISHPLATES, 47 DUTIES OF, 21
FIXED RADIUS CURVE, 65 PICOW, 5
FREQUENCY OF INSPECTION, 38 PLACE OF SAFETY, 4
PPE, 6