Project Management
Project Management
Crashing assignment
CRASHING ASSIGNMENT
2
Crashing assignment
Table of Contents
Question 1..................................................................................................................................3
Question 2................................................................................................................................12
Reference List..........................................................................................................................13
3
Crashing assignment
Question 1
Based on the given data, the activities that can be crashed are mentioned below table,
from the crash time and normal time maximum crash time is computed here. Thus, (Crash
time – normal time) is equal to the maximum crash time and the cost slope is calculated using
Cost slope = (Normal Time - Crash Time) / (Crash time – normal time)
Using this formula, the below table has calculated the maximum crash time and cost
Activity Normal Normal Crash Time Crash cost Cost slope Crash time
A 5 300 5 300 0 0
B 8 250 5 400 50 3
C 2 100 2 100 0 0
F 4 275 3 300 25 1
The critical path is also determined using the fastest route to the tasks available here.
The critical path determines what is the shortest way which can be used to complete the
project while maintaining the main activities, so the scope of the project stays intact even
Critical Path
8
E
3
C G
A
2 9
5
D 4
By following the critical paths only, 5 Run can be calculated for this activity. After
estimating the 5 runs, it can be determined that the crash timing can be achieved by 20 days
after complying new resources here. Also, the activities will have to be completed based on
the above mentioned four critical paths. In the below table, additional and cumulative cost is
calculated along with the project cost using the estimated critical path.
5
Crashing assignment
Path
Project duration 25 24 23 22 21 20
critical path
ABEG
($)
($)
Savings ($) - - - - - -
Project Cost ($) 2075 (2075 + 50) (2125 + 125) (2250 + 150) (2350 + (2650 + 250)
Above table has shown all the necessary calculation to compute the project cost for
each run and the maximum number of crash time achieved by this project.
Run 1
In table 3, 1 day will be deducted from activity B and after the implementation of Run 1 the
total cost will be $2125 and total time for completion of the project is 24 days
Run 1
time
6
Crashing assignment
1 2
7
E
3
C G
A
2 9
5
D 4
Run 2
In table 4, 1 day from activity B and 1 day from activity F will be deducted after the
implementation of Run 2 the total cost will be $2200 and total time for completion of the
project is 23 days.
7
Crashing assignment
Run 2
time
1 1
1 0
6
E
3
C G
A
2 9
5
D 3
Run 3
8
Crashing assignment
In table 5, 1 day from activity B and 1 day from activity D will be deducted after the
implementation of Run 3 the total cost will be $2350 and total time for completion of the
project is 22 days.
Run 3
time
1 0
1 2
5
E
3
C G
A
2 9
5
D 3
5
9
Crashing assignment
Run 4
In table 6, 1 day from activity B and 1 day from activity G will be deducted after the
implementation of Run 4 the total cost will be $2650 and total time for completion of the
project is 21 days.
Run 4
time
1 1
1 0
5
E
3
C G
A
Figure
2 8
5
D 3
Run 5
In table 7, 1 day from activity D and 1 day from activity E will be deducted after the
implementation of Run 5 the total cost will be $2900 and total time for completion of the
project is 20 days.
Run 5
time
1 0
1 0
11
Crashing assignment
5
E
2
C G
A
2 8
5
D 3
Therefore, the activities cannot be crashed anymore after 20 days of completion time
of this project. The total cost for completing this project by 20 days of time and following the
Question 2
By given bonus per activity of $125, here the bonus for each activity may not be
needed since the activity changed in critical path will be used to spend. Crashed activities that
needs bonus are B > B, F > B, D > G, D > E, D. Thus, here bonus is added based on the
activities and the previous bonus activities as well. The total cost is calculated based on the
Duration of Crashing Crash cost Direct cost Bonus Total cost ($) (Direct
(days)
25 - - 2075 - 2075
Thus, the above table has indicated that total 20 days of time can be considered as the
highest crashed time achieved in this project and the required resource for 20 days
completion time will be $2275 if a bonus of $125 is given in each activity crashed here.
13
Crashing assignment
Reference List
Mahdiraji, H. A., Sedigh, M., Hajiagha, S. H. R., Garza-Reyes, J. A., Jafari-Sadeghi, V., &
Dana, L. P. (2021). A novel time, cost, quality and risk tradeoff model with a
https://www.sciencedirect.com/science/article/pii/S004016252100500X
Zandebasiri, M., Vacik, H., Etongo, D., Dorfstetter, Y., Soosani, J., & Pourhashemi, M.
type=article&id=65_2019-JFS