Notes POM Module 6
Notes POM Module 6
1. Aggregate planning
Determines the production requirements over a period of 6 months to 18 months
2. Master production scheduling
Converts production plan into specific material and capacity require nets. This is
the beginning of all short range planning
3. Material requirement planning
Converts MPS into what materials are required , how much and when.
4. Loading
Assignment of jobs to various work centers based on future processing, resource
utilization and sequence of operations
5. Sequencing
Determines what jobs are to be processed when on each work centre. This
depends on priorities of jobs and best utilization
6. Detailed scheduling
Determines start and finish dates and times for jobs on each machine.
7. Expediting
Actions to ensure scheduling is met by coordination for materials, tools,
availability of machines and manpower.
8. Production control
Information on status of plan and accruals. Information on problems that may be
faced in future period. This helps in taking decisions to meet the aim of
production planning and scheduling.
Objectives of MPS
• To schedule products to meet Delivery requirements
• To fully utilize capacity at lowest production cost
Detailed scheduling:
• Backward scheduling: Here the delivery dates is the starting point and the
loading date is determined by the lead time taken in each work center working
back wards
Facility loading
Facility loading is the process of determining which work centre receives which job
Loading depends on capacity determined by load schedules, priority sequencing and
work centre utilisation.
Finite loading – jobs are assigned to work centers based on required hours and hours
available.
Infinite loading- Jobs are assigned to work centers without regard to available capacity.
This requires decisions regarding overtime, subcontracting or delaying selected orders.
Load charts helps in visualizing loading and progress;
Milling
Grinding
Drilling
Priority sequencing
Question of sequencing arises when several jobs require same work centre for processing.
Priority indicates which is to be loaded first.
If the processing time is same on work centre 1 and 2 , arbitrarily assign either in the
beginning or last.
Sequence : C, D, E ,F , B , A
17 hours
Check Total operation time + total idle time = twice cycle time
28.5 + 5.5 = 2 x 17= 34 hrs.
Line Balancing
Line balancing deals with apportionment of sequential work activities to work stations in
order to gain high utilization of labour and equipment and therefore minimize idle time.
Grouping of tasks should be at or slightly less than the cycle time or multiples of cycle
times. If multiples are present more than one worker will be doing the same job.
• Balance efficiency = Out put of task time / cycle time x no. of work stations(
workers)
Balance efficiency = Theoretical no. of workers/ Actual no. of workers
Problem:
Precedence diagram . operation time in minutes.
D
0.20
A B C F G
0.65 0.40 0.30 0.400 0.30
E
0.45
Operation time = 7 hours per day
Output desired is 550 units per day
Theoretical minimum no. of workers= (0.65 + 0.40 + 0.3 + 0.2 0 + 0.45 0.4 + 0.3 )/0.76
= 2.7 / 0.76= 3.552
LOB is a technique used for production scheduling and control to ensure committed
delivery requirements.
Stage 1 – Preparation of operation program chart. This is based on lead times for each
activity. Delivery date is taken as 0 and worked back wards
Left part of chart indicates the week numbers and cumulative number of products to be
completed
Right side chart indicates the operations required
At any period line can be drawn from left hand chart and the quantity of products that
should have been completed at various operations can be easily read from the Right hand
chart
Cumulative completion
Quantity LOB
Q
T
Y
1 2 3 4
Week no.
Operation stages