SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE: Civil
SAUDI ARAMCO TYPICAL INSPECTION PLAN
STRUCTURAL STEEL--Piperack, Steel Supports & Miscellaneous Steel
SATIP-M-001-01 25-May-05 MECHANICAL- Structural Steel
Structures
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
1.0 DOCUMENT REVIEW
Procedure for Tightening of High Strength
1.1
Bolted connections
SAIC-M-2001 RHI RH1
Procedure for Localized Heating for repair
1.2
of warpage
SAIC-M-2002 RH1 RH1
2.0 MATERIAL RECEIVING
2.1 Structural Steel Shapes and Plates SAIC-M-2003 SAIC-M-2003 H1 W2 S.ARAMCO shall be notified for the first batch of deliveries.
2.2 Bolts, Nuts and Washers SAIC-M-2021 SAIC-M-2021 H1 W2 S.ARAMCO shall be notified for the first batch of deliveries.
2.3 Fabricated Steel Structures SAIC-M-2004 SAIC-M-2004 H1 W2 S.ARAMCO shall be notified for the first batch of deliveries.
2.4 Storage, Handling & Preservation SAIC-M-2005 SAIC-M-2005 H1 S
3.0 INSTALLATION
Inspection of Support Foundation prior to
3.1 SAIC-M-2006 SAIC-M-2006 H1 W1
Structural or Equipment Installation
3.2 Field Weld connection inspection Refer to SATIP-M-001-04
SAIC-M-2007
3.3 Structural Alignment prior to Grouting SAIC-M-2007 W1 S
SATR-M-2001
3.4 Grouting Refer to SATIP-Q-010-01
3.5 Repair/Correction of Errors SAIC-M-2008 SAIC-M-2008 W1 W1
Pre-Installation Procedure Verification
3.6 Testing of Turn-of-Nut Method (ASTM SATR-M-2002 SATR-M-2002 H1 H1
A325 or ASTM A490 Bolts)
Pre-Installation Procedure Verification
Testing of DIRECT TENSIONING
3.7 SATR-M-2003 SATR-M-2003 H1 H1
INDICATOR (ASTM A325 or ASTM A490
Bolts)
Pre-Installation Procedure Verification
3.8 Testing of Calibration Wrench (ASTM SATR-M-2004 SATR-M-2004 H1 H1
A325 or ASTM A490 Bolts)
Page 1 of 2
SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)
SATIP No. APPROVED DATE DISCIPLINE: Civil
SAUDI ARAMCO TYPICAL INSPECTION PLAN
STRUCTURAL STEEL--Piperack, Steel Supports & Miscellaneous Steel
SATIP-M-001-01 25-May-05 MECHANICAL- Structural Steel
Structures
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
S.ARAMCO shall be notified for the INITIAL bolt tightening
3.9 Final bolt tightening inspection and testing SAIC-M-2009 SAIC-M-2009 W1 W2
activities.
3.10 Access Structures SAIC-M-2010 SAIC-M-2010 W1 W1
3.11 Painting/Coating and touch up Refer to applicable SATIP-H series
4.0 PRE-COMMISSIONING
Structural Re-Instatement/Final SAIC-M-2011
4.1 SAIC-M-2011 H1 S
Punchlisting SATR-A-2011
4.2 Mechanical Completion Punch listing SA-6133 H1
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels
1 of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
W1 100% Witness Inspection/Test H2 Sample Hold Point for QC Inspection or Test RH1 100% Review and Approval of Documents
W2 Sample Witness Inspection/Test R1 100% Review of Documents RH2 Sample Review and Approval of Documents
H1 100% Hold Point for QC Inspection or Test R2 sample Review of Documents S Surveillance
Page 2 of 2