C Continuouslyreinforcedpccp
C Continuouslyreinforcedpccp
Department of Transportation
This checklist has been prepared to provide the field inspector a summary of easy-to-read step-
by-step requirements relative to the proper construction of Continuously Reinforced PCC
Pavement (Section 421). The following questions are based on information found in the
Standard and Supplemental Specifications, Highway Standards, Construction Manual and
current policy memorandums and letters.
1. SUBBASE TRIMMING
When a slipform paver is used, is the trimming being done with a subgrade
machine (1103.09) prior to paving? (420.05) (301.06(b)) ____
2. PAVING FORMS
Are the forms: metal, not less than 3 m (10 feet) in length, equipped
with both pin locks and joint locks, within 2 mm (1/16 inch) along the
1
length of its upper edge, within 6 mm ( /4 inch) along the length of its
front face? (1103.05) ____
Is the height of form face not less than edge thickness of proposed
pavement, the base width equal to or greater than the height, and are
3 steel pins being used to secure each section? (1103.05) (420.06) ____
1
Are the forms being set on a hard and true grade, built up in /2-inch
maximum lifts of granular material in low areas (without using wooden
shims) set not less than required for at least one days paving in front
of the paver, and cleaned and oiled prior to the placing of concrete?
(420.06) ____
Sheet 1 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement
When wooden forms are allowed, are they full depth, smooth, free of
warp, not less than 50 mm (2 inches) thick when used on tangent,
and securely fastened to line and grade? (1103.05) ____
3. FORM ALIGNMENT
Is the contractor checking (eyeballing) the forms for line and grade and
making necessary adjustments prior to concrete placement? (420.06) ____
4. TEMPLATE
Is the surface of the subbase being tested for crown and elevation by means
of a heavy subgrade template? (301.06) ____
After trimming, is the thickness of the subbase being checked by any method
at every 75 m (250 ft.) location or less? (Documentation Section,
Construction Manual) ____
Are all these job control thickness tests being recorded and retained as part
of the job records? (Table 1 & 7, PPG) (311.07) ____
6. DRAINAGE
Is the subgrade being kept drained during all operations? Are all berms of
earth deposited adjacent to the grade being kept drained by cutting lateral
ditches through the berms? (301.08) ____
If wide flange beam joint anchorages are specified, are they staked and
checked for dimensions and rebar placement as shown in the plans? ____
Are you marking the beginning and ending stations where adjacent curb,
median, or pavement will necessitate the placement of epoxy coated
deformed steel tie bars in the edge of the proposed pavement? (420.10(b)) ____
Sheet 2 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement
9. SUPERELEVATION STAKING
Are you examining the plan curve data for all curves to determine where to
stake the beginning and ending stations for all super-elevation transitions? ____
Has the contractor notified you of his/her proposed sources of materials prior
to delivery? (106.01) ____
Has all material been inspected, tested and approved before incorporation in
the work? (106.03) ____
If so, are you reviewing the latest version of the QC/QA documents for
information regarding quality control procedures by the Contractor and
quality assurance by the department? ____
Is the outside air temp in the shade at least 2°C (35 °F) and ascending
before allowing the contractor to start mixing and placement operations? ____
Is the temp of the concrete between 10°C (50 °F) and 32°C (90 °F) at the
time of placement? ____
Are the locations and lengths of lap for bar or fabric reinforcement in
conformance with the details shown in Std. 421001? ____
Are all bar and fabric laps being tied? (421.06) ____
Sheet 3 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement
If the contractor plans to use previously placed pavement as a haul road, are
you checking trucking weights to assure compliance with maximum weights
as permitted by state law? See Form BT 753. (107.01) & (701.05(c)(6)) ____
Does the engineer approve the transverse tie bar reinforcement being
fastened to the longitudinal bars with wire, clips or other methods?
(421.06(a)) ____
Sheet 4 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement
d. Screeding (420.11(a))
or;
or;
or;
or;
Sheet 5 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement
When the contractor uses this optional method for the construction of the
pavement are the following sequences being properly followed:
b. Are you checking the vibrator frequency at the start of each day with
a contractor furnished reed tachometer? (1103.12) ____
Are you checking the thickness of the pavement at least at every 75 m (250
ft) location? (Documentation Section, Construction Manual) (Before and
after rod and level, before and after stringline, or direct probing
measurements are all acceptable.) Record and retain in job records.
(420.18) (407.10) ____
Are you testing the concrete for air (5 - 8%) at least every 75 m (250 foot) of
pavement? (Sampling Schedule 3, PPG or Special Provisions) Record and
retain in job records. ____
Are you testing the concrete for slump 20 mm to 40 mm (3/4 to 1 1/2 inch) at
least once each day? (Sampling Schedule 3, PPG or Special Provsions)
Record and retain in job records. ____
Sheet 6 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement
Are you periodically probing the concrete to check the vertical positioning of
the pavement reinforcement? Refer to Standard 421101 or 421106 for
reinforcement placement and Article 421.06(a) for tolerances. Record and
retain in job records. ____
Are test specimens being cast at the site of work at the following frequency: ____
or,
b. Are the smooth dowel bars (if required) positioned parallel to the
grade @ t/2 depth and @ 300 mm (12 inches) centers? ____
Sheet 7 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement
b. Are joints at least 1.1 m (3 1/2 feet) from nearest bar lap? ____
e. Is the concrete internally vibrated along the length of the joint both at
the end of the day’s operation and once again at the resumption on
the next day? ____
Where,
Sheet 8 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement
Are the pavement surface and edges being cured for 3 days (1020.13(a)) by
one of the following methods: ____
29. PROTECTION
Sheet 9 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement
Are all bumps being marked, ground down and sprayed with protective coat?
(420.12) ____
If for any reason the contractor is required to replace any of the pavement
prior to final acceptance, are the construction requirements of Article
442.05(a) being adhered to? ____
Sheet 10 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement
or;
Sheet 11 of 11