0% found this document useful (0 votes)
41 views11 pages

C Continuouslyreinforcedpccp

This document provides a checklist for inspectors to ensure the proper construction of continuously reinforced Portland cement concrete (PCC) pavement. It outlines 16 steps to check, including requirements for subbase preparation, forms, reinforcement, concrete mixing and placement, and finishing. Inspectors are to verify that the contractor is following specifications for materials, support of reinforcement, temperature controls during placement, and time limits for delivery and deposition of concrete.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views11 pages

C Continuouslyreinforcedpccp

This document provides a checklist for inspectors to ensure the proper construction of continuously reinforced Portland cement concrete (PCC) pavement. It outlines 16 steps to check, including requirements for subbase preparation, forms, reinforcement, concrete mixing and placement, and finishing. Inspectors are to verify that the contractor is following specifications for materials, support of reinforcement, temperature controls during placement, and time limits for delivery and deposition of concrete.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

State of Illinois

Department of Transportation

CONSTRUCTION INSPECTOR’S CHECKLIST


FOR
CONTINUOUSLY REINFORCED PCC PAVEMENT

This checklist has been prepared to provide the field inspector a summary of easy-to-read step-
by-step requirements relative to the proper construction of Continuously Reinforced PCC
Pavement (Section 421). The following questions are based on information found in the
Standard and Supplemental Specifications, Highway Standards, Construction Manual and
current policy memorandums and letters.

Have you checked the contract Special Provisions, Supplemental


Specifications and plans to see if any modifications have been made to the
requirements listed herein? ____

1. SUBBASE TRIMMING

Has the subbase been trimmed prior to paving? (420.05) ____

When a slipform paver is used, is the trimming being done with a subgrade
machine (1103.09) prior to paving? (420.05) (301.06(b)) ____

2. PAVING FORMS

If paving forms are used do they meet the following requirements?

Are the forms: metal, not less than 3 m (10 feet) in length, equipped
with both pin locks and joint locks, within 2 mm (1/16 inch) along the
1
length of its upper edge, within 6 mm ( /4 inch) along the length of its
front face? (1103.05) ____

Is the height of form face not less than edge thickness of proposed
pavement, the base width equal to or greater than the height, and are
3 steel pins being used to secure each section? (1103.05) (420.06) ____
1
Are the forms being set on a hard and true grade, built up in /2-inch
maximum lifts of granular material in low areas (without using wooden
shims) set not less than required for at least one days paving in front
of the paver, and cleaned and oiled prior to the placing of concrete?
(420.06) ____

Sheet 1 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement

When wooden forms are allowed, are they full depth, smooth, free of
warp, not less than 50 mm (2 inches) thick when used on tangent,
and securely fastened to line and grade? (1103.05) ____

Are curved forms of metal or wood being used on curves of 30 m


(100 foot) radius or less? (1103.05) ____

3. FORM ALIGNMENT

Is the contractor checking (eyeballing) the forms for line and grade and
making necessary adjustments prior to concrete placement? (420.06) ____

4. TEMPLATE

Is the surface of the subbase being tested for crown and elevation by means
of a heavy subgrade template? (301.06) ____

5. SUBBASE THICKNESS TEST

After trimming, is the thickness of the subbase being checked by any method
at every 75 m (250 ft.) location or less? (Documentation Section,
Construction Manual) ____

Are all these job control thickness tests being recorded and retained as part
of the job records? (Table 1 & 7, PPG) (311.07) ____

6. DRAINAGE

Is the subgrade being kept drained during all operations? Are all berms of
earth deposited adjacent to the grade being kept drained by cutting lateral
ditches through the berms? (301.08) ____

7. WIDE FLANGE BEAM JOINT

If wide flange beam joint anchorages are specified, are they staked and
checked for dimensions and rebar placement as shown in the plans? ____

Are they constructed of Class SI or PV Concrete at least 24 hours prior to


pavement construction? (421.07(d)) ____

8. LONGITUDINAL CONSTRUCTION JOINT

Are you marking the beginning and ending stations where adjacent curb,
median, or pavement will necessitate the placement of epoxy coated
deformed steel tie bars in the edge of the proposed pavement? (420.10(b)) ____

Sheet 2 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement

9. SUPERELEVATION STAKING

Are you examining the plan curve data for all curves to determine where to
stake the beginning and ending stations for all super-elevation transitions? ____

By giving the contractor these points and intermediate points, a smooth


transition from crown to super can be constructed.

10. PLANT & MATERIALS APPROVAL

Has the plant where the concrete is to be produced been approved?


(1103.02) ____

Has the contractor notified you of his/her proposed sources of materials prior
to delivery? (106.01) ____

Has all material been inspected, tested and approved before incorporation in
the work? (106.03) ____

Is this project set up as Quality Control/Quality Assurance (QC/QA)? ____

If so, are you reviewing the latest version of the QC/QA documents for
information regarding quality control procedures by the Contractor and
quality assurance by the department? ____

Most PCC paving projects will be QC/QA. The QC/QA requirements


will apply to both the PCC pavement and the CAM II Stabilized
subbase. Contact your Materials department for concrete testing
equipment and mixture design approval.

11. TEMPERATURE LIMITATIONS (1020.14(a))

Is the outside air temp in the shade at least 2°C (35 °F) and ascending
before allowing the contractor to start mixing and placement operations? ____

Are you discontinuing the contractor’s operations when a descending air


temp reaches 5°C (40 °F)? ____

Is the temp of the concrete between 10°C (50 °F) and 32°C (90 °F) at the
time of placement? ____

12. REINFORCEMENT LAPPING

Are the locations and lengths of lap for bar or fabric reinforcement in
conformance with the details shown in Std. 421001? ____

Are all bar and fabric laps being tied? (421.06) ____

Sheet 3 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement

13. MIXING CONCRETE (1020.11)

Is the contractor producing the concrete in conformance with one of the


following methods? Check each article for a review of requirements and
restrictions for each: ____

a. Stationary mixer. (1103.01(a)) & (1020.11(c)) ____

b. Transit mixed concrete. (1020.11(c)) ____

14. TRUCK REQUIREMENTS

Is all concrete which is mixed in a stationary mixer being deposited within 30


minutes when hauled in nonagitating trucks and within 60 minutes when
hauled in agitor trucks? (1020.11(d)(8)) ____

Is transit mixed concrete being delivered and deposited within 60 minutes


from the time stamped on the ticket? (1020.11(d)(8)) ____

If the contractor plans to use previously placed pavement as a haul road, are
you checking trucking weights to assure compliance with maximum weights
as permitted by state law? See Form BT 753. (107.01) & (701.05(c)(6)) ____

15. REINFORCEMENT PLACEMENT

Is the reinforcement being supported on the prepared subbase by plastic


coated chairs fabricated with sand plates? (421.06(a)) ____

Note: Epoxy coated chairs are not required. (420.02 Note 1)

Does the engineer approve the transverse tie bar reinforcement being
fastened to the longitudinal bars with wire, clips or other methods?
(421.06(a)) ____

16. SEQUENCES OF FORM TYPE PAVING

Is all of the required concrete finishing equipment on the job and in


acceptable working condition? Are the following sequences for form type
paving being properly followed:

a. Placing concrete (420.07). As little rehandling as possible. If


equipment used can cause segregation, is the concrete being
unloaded into an approved spreading device? (1103.12) ____

b. Strike-off (420.09). Is the concrete being struck full and to the


approximate cross section of the pavement? ____

Sheet 4 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement

c. Consolidation (421.08). Is one pass of an approved surface vibrator


(minimum of 3500 VPM) or internal vibrator (minimum of 7000 VPM)
(1103.12) being made? Are you checking the vibrator frequency at
the start of each day with a contractor furnished reed tachometer? ____

d. Screeding (420.11(a))

(1) Is the concrete being screeded by an approved finishing


machine? (1103.13(b)) ____

or;

(2) (When breakdowns occur) Hand methods will be permitted to


finish up deposited concrete. (420.11(a)(2)) ____

or;

(3) (When pavement width varies or is less than 3 m (10 ft.)).


Vibrating screed may be used for strike-off and consolidation.
(420.11(a)(3)) ____

e. Longitudinal floating (420.11(b))

(1) Is the form riding mechanical float (1103.15) making 2 passes


over all areas? (420.11(b)(1)) ____

or;

(2) Form riding finisher float suspended on rigid frame. (1103.14)


(420.11(b)(2)) ____

or;

(3) (In emergency or when specified) 3.5 m x 150 mm (12 ft. x 6


inches) hand operated longitudinal float (1103.17(e)) operated
from form riding foot bridges. (1103.17(d)) (420.11(b)(3)) ____

f. Straightedging (420.11(c)) - At least two 3 m (10 ft) long shoulder


operated surface trueness testers. (1103.17(h)) ____

g. Edging (420.11(d)) - At least two 6 mm (1/4 inch) radius edging tools.


(1103.17(j)) ____

Sheet 5 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement

17. SEQUENCES OF SLIPFORM PAVING

When the contractor uses this optional method for the construction of the
pavement are the following sequences being properly followed:

a. Is the formless paver (1103.16) capable of spreading, consolidating


internally, screeding and float finishing the newly placed concrete in
one pass to the required line and grade? (420.17) ____

b. Are you checking the vibrator frequency at the start of each day with
a contractor furnished reed tachometer? (1103.12) ____

c. Is the pavement being straightedged, edged and textured as required


in the previous question? (420.11) ____

d. Does the contractor have available at all times metal or wooden


sideforms and burlap or curing paper for the protection of the
pavement in case of rain? (420.17) ____

e. Is the contractor immediately repairing all slumping edges in excess


of 13 mm (1/2 inch)? (See 420.17(a) & (b) for repairing excessive
edge slump.) ____

18. THICKNESS TEST

Are you checking the thickness of the pavement at least at every 75 m (250
ft) location? (Documentation Section, Construction Manual) (Before and
after rod and level, before and after stringline, or direct probing
measurements are all acceptable.) Record and retain in job records.
(420.18) (407.10) ____

19. AIR CONTENT (1020.08)

Are you testing the concrete for air (5 - 8%) at least every 75 m (250 foot) of
pavement? (Sampling Schedule 3, PPG or Special Provisions) Record and
retain in job records. ____

20. SLUMP (1020.07)

Are you testing the concrete for slump 20 mm to 40 mm (3/4 to 1 1/2 inch) at
least once each day? (Sampling Schedule 3, PPG or Special Provsions)
Record and retain in job records. ____

Note: A maximum slump limit up to 75 mm (3 inches) is allowed provided


the mix is reproportioned. (1020.05(f))

Sheet 6 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement

21. REINFORCEMENT DEPTH CHECKS

Are you periodically probing the concrete to check the vertical positioning of
the pavement reinforcement? Refer to Standard 421101 or 421106 for
reinforcement placement and Article 421.06(a) for tolerances. Record and
retain in job records. ____

22. STRENGTH (701.05(c)(6))

Are test specimens being cast at the site of work at the following frequency: ____

a. Modulus of Rupture 150 mm x 150 mm x 750 mm (6” x 6” x 30”


beam) (Section 3C, Prop. Manual): 4 beams first day; 2 per day
thereafter. (Manual for Test Procedures for Matrials)

Break @ 3, 5, 7 and 14 days.

Strength requirement = 4.5 MPa (650 psi) in 14 days (701.05(c)(6))

Report on Form LW 3, “Field Record Book of Modulus of Rupture


Tests of Concrete Beams” ____

or,

b. Compressive Strength 150 mm dia. x 300 mm cylinder (6” dia. x 12”


cylinder). ( Manual for Test Procedures for Matrials)

Make 2 cylinders in lieu of each beam (Sampling Schedule 3, PPG or


Special Provisions)

Strength requirement = 24 MPa (3500 psi) in 14 days (701.05(c)(6)) ____

23. SAWED LONGITUDINAL JOINT (420.10(a))

a. Strengthened by 750 mm (30 inches) - #6 tie bars at 750 mm (30


inches) centers at t/2 depth perpendicular to the joint? (Std. 420001) ____

b. Sawing of the longitudinal joint may commence as soon as the


concrete has hardened sufficiently to permit sawing without excessive
raveling. The saw cut shall be made to a depth of t/3 of the pavement
thickness. (420.10(a)) (Std. 421101 & 421106) ____

24. TRANSVERSE EXPANSION JOINTS (420.10(c))

a. Is the 75 mm (3 inch) preformed joint filler continuous from form to


form, shaped to the subbase and to the keyway (if present) along the
form? (420.10(c)) ____

b. Are the smooth dowel bars (if required) positioned parallel to the
grade @ t/2 depth and @ 300 mm (12 inches) centers? ____

Sheet 7 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement

c. Are the capped ends of the bar greased? (420.10(e)) ____

25. TRANSVERSE CONSTRUCTION JOINTS (421.07(b))

a. Are transverse construction joints placed at the end of each day’s


operation or after an interruption in the concreting operation of 30
minutes or more? ____

b. Are joints at least 1.1 m (3 1/2 feet) from nearest bar lap? ____

c. Are joints strengthened by supplementary 1.8 m (6 inches) long No.


20 (No.6) bars placed between normal longitudinal steel? (Std.
421101) ____

d. Are the transverse construction joints formed by means of a clean


(not oiled) split header board conforming to the cross section of the
pavement? ____

e. Is the concrete internally vibrated along the length of the joint both at
the end of the day’s operation and once again at the resumption on
the next day? ____

26. SURPLUS - DEFICIENCY DETERMINATION

Is a daily check being made on the yield of produced concrete? A deficiency


computation is serious; it usually indicates thin pavement. ____

Required Volume - Volume Used


D or S = x 100
Required Volume

Where,

Required volume = Lmeter x W meter x Dmeter (L’ x W’ x D’ x 1/27)

Used volume = No. of batches x m3 (cy)/batch

27. PAVEMENT STATIONING

Is your construction office stamping stations in the pavement surface every


100 m (250 ft.) at the location specified? Are station equations being
stamped where they occur? ____

Sheet 8 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement

28. CURING (1020.13(a))

Are the pavement surface and edges being cured for 3 days (1020.13(a)) by
one of the following methods: ____

a. Waterproof Paper Method. Covered as soon as possible with


blankets of tear-free reinforced kraft paper (1022.03), with 300-mm
(12 inches) laps, properly weighted? Has the pavement been wetted
with a fine spray first? (1020.13(a)(1)) ____

b. Polyethylene Sheeting Method. Covered as soon as possible with 30-


m (100-ft) long sheets of white polyethylene (1022.03), with 300-mm
(12 inches) laps, properly weighted? Has the pavement been
sprayed with a fine mist of water first? (1020.13(a)(1)) ____

c. Wetted Burlap Method. Covered as soon as possible with 2 layers of


wet burlap (1022.02), with 150 mm (6 inch) laps? Kept saturated by
means of a mechanically operated sprinkling system or an
impermeable covering? (Alternate; one burlap and one burlene
(1022.05) blanket) (1020.13(a)(3)) ____

d. Membrane Curing Method. As soon as water sheen has


disappeared, are 2 separate applications, separated by at least one
minute, of agitated Type III (white) curing compound (1022.01) being
2
uniformly applied? 0.16 L/m (one gallon/250 sf) application?
(1020.13(a)(4)) Not allowed between November 1 & April 15
(1020.13Note 6). Not allowed if protective coat is to be applied
(1020.13(c)) ____

29. PROTECTION

Is the contractor providing protection of the pavement from low temperatures


as follows: (1020.13(c))

Min. Temp. Forecast Protection


4°C - 0°C (25°F. - 32° F) 1 layer of poly & 1 layer burlap, or
(or if drops below 0°C (32° F) 2 layers of polyethylene, or
during first 72 hours) 2 layers of waterproof paper ____

Below -4°C (25° F) 150 mm (6 inches) of straw


covered with 1 layer of poly
or waterproof paper ____

Sheet 9 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement

30. SURFACE VARIATIONS

At the end of the curing period, are you profilographing or straight-edging


each wheel lane for surface variations? ____

Are all bumps being marked, ground down and sprayed with protective coat?
(420.12) ____

31. OPENING TO TRAFFIC

Is the pavement being closed to traffic until:

a. The curing and protection period has elapsed? (701.05(c)(6)) ____

b. All joints have been sealed? (420.14) ____

c. The required strength has been achieved by test specimen?


(701.05(c)(6)) ____

If the contractor wishes to open the pavement to traffic prior to the


date of your first routine beam break, are additional specimens being
cast and then allowed to cure out in the open the same as the
pavement? (701.05(c)(6)) ____

32. PROTECTIVE COAT

a. Is a protective surface treatment being applied when pavement is


constructed after October 15, and will be opened to traffic prior to the
following April 15; or when directed by the Engineer? (420.21) ____
2
b. Are 2 coats at 11 m /L (50 sy/gal) coat being applied to 14 day old
minimum pavement? Air temperature above 10°C (50° F)? (420.21) ____

33. REMOVAL AND REPLACEMENT OF CR PCC PAVEMENT (442.05(a))

If for any reason the contractor is required to replace any of the pavement
prior to final acceptance, are the construction requirements of Article
442.05(a) being adhered to? ____

34. FIELD RECORDS

Are all tests, measurements, observations and computations required in the


foregoing being maintained in a hard back field book? ____

35. DOCUMENTATION OF FINAL CONTRACT QUANTITIES

CONTINUOUSLY REINFORCED PCC PAVT, m2 (SY)


2
PAVEMENT REINFORCEMENT, m (SY)
2
PROTECTIVE COAT, m (SY)

Sheet 10 of 11
Rev. 6/26/02 Continuously Reinforced
PCC Pavement

a. Measured Quantities: Computations based on measured lengths and


measured variable width segments. (421.10(b)) Use plan width for all
constant width pavement. (109.01) ____

or;

b. Contract Quantities: Jointly signed Form BC 981 required.


(420.22(a)) (202.07(a)) ____

Revised to conform with the


Standard Specifications for Road and Bridge Construction
Adopted January 1, 2002

Sheet 11 of 11

You might also like