Factory Building

The document outlines technical specifications for pre-engineered steel building work. It includes sections on scope of work, site details, design considerations, structural members, connections, physical specifications, general guidelines, essential site conditions, machinery requirements, safety, and warranties. The supplier is responsible for design, fabrication, supply and erection of the building system according to the specifications and approved drawings. Structural members must meet minimum thickness requirements and be welded according to specifications.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
402 views19 pages

Factory Building

The document outlines technical specifications for pre-engineered steel building work. It includes sections on scope of work, site details, design considerations, structural members, connections, physical specifications, general guidelines, essential site conditions, machinery requirements, safety, and warranties. The supplier is responsible for design, fabrication, supply and erection of the building system according to the specifications and approved drawings. Structural members must meet minimum thickness requirements and be welded according to specifications.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

TECHNICAL SPECIFICATIONS

FOR
PRE ENGINEERED STEEL BUILDING WORK
(DOC. NO. – GCPL/ FBT/ 723/ TS/ PEB – 01)
(DATE – 08.04.2019, REV. – A)

PROJECT
FACTORY BUILDING
TARAPUR (MH)

CLIENT

GSR CHEMICALS PVT. LTD.


TARAPUR (MH)

CONSULTANT

307, MALOO-01, Plot No. 26-C/CA,


Sch. No. 94-C, Near Velocity Multiplex,
Ring Road, Indore-452010, M.P., INDIA
E-mail : [email protected]
Web: www.gcpl.net.in
Mob : +91-97520-95286 Tel : + 91-731-2555407
CONTENTS
SECTION A- TECHNICAL SPECIFICATIONS Page No.

1. SCOPE OF WORK 2
2. SITE DETAILS AND BUILDING DISCRIPTION 2
3. DESIGN & PREPARATION OF DRAWINGS 2
4. STRUCTURAL CONSIDERATION 3
4.1. STRUCTURAL MEMBERS 3
4.2. CONNECTIONS 4
4.3. PHYSICAL SPECIFICATIONS OF STRUCTURAL MEMBERS 4
4.4. GENERAL CONSIDERATION 5
4.5. STEEL WORK FINISH 5
5. SHEETING AND ACCESSORIES 6
6. GENERAL GUIDELINES TO FOLLOW 9
7. ESSENTIAL CONDITIONS FOR SITE 10
8. WATER AND POWER FOR CONSTRUCTION WORK 10
9. MACHINERY, MANPOWER ETC 10
10. ELEVATED WORKING 11
11. SUPPLY AND ERECTION SCHEDULE 11
12. HOUSE KEEPING 11
13. SAFETY 11
14. PERFORMANCE WARRANTIES 12

SECTION B- PRICE SCHEDULE

1. PREAMBLE TO PRICE SCHEDULE 14

APPENDICES
APPENDIX A. DEVIATION SCHEDULE 16
APPENDIX B. LIST OF DRAWING 17
1 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

SECTION - A

TECHNICAL SPECIFICATIONS

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 1 of 17


2 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

1. SCOPE OF WORKS
1.1. DESIGN, MANUFACTURE AND SUPPLY
1.1.1. Design, manufacture and supply of Pre-Engineered steel building system includes
builtup column & rafter, jack beams, mono rail, eave runner, portal/ angle bracing, tie
member, sag roads, rafter bracing, cleats, anchor bolts, templates, connection bolts etc.
complete as per design and drawings supplied by consultant/ client and as per
specifications and roof sheeting, side sheeting, gable sheeting, canopy sheeting (top &
bottom),deck sheet, flashing, trims, gutter, ridge panel, poly carbonate transparent
sheet, turbo-ventilator, stitching screw including all accessories as required for the
successful and satisfactory completion of the Pre- Engineered steel building system.
Application of paint including touch up paints as per specifications.
1.1.2. Design, manufacture & supply of galvanized Purlin, side girts & gable girts as per
specification.
1.2. ERECTION
1.2.1. Erection of Pre-Engineered steel building system as specified in item no. 1.1.1 & 1.1.2
including erection tools & plants complete accordance with the approved Design &
Drawing to relevant standard, codal provisions and contract conditions to the entire
satisfaction of client.

2. DESIGN & PREPARATION OF DRAWINGS


2.1. PEB supplier shall design & prepare all fabrication and erection drawings for entire work. All
the drawings & document shall be prepared in English language and in metric units. The
drawings shall be of one standard size and the details shown there in shall be clear and
legible.
2.2. PEB supplier shall submit the structural Design Criteria, Calculations, STAAD file 3D
analysis, General Arrangement (G.A)/ Design Drawing (with specifying the member size and
connection details) of the Building along with required explanatory sketches/drawings and
get the same reviewed & approved by Consultant before starting the final shop fabrication
drawings. The supplier shall also furnish the foundation loading, base reaction and all other
relevant data for the structure to client/ consultant (DWG format) both in soft and hard copy (3
sets).
2.3. Client/ consultant reserve the right to review/ approve any/all or none of the designs and
drawings. Review / approve by client/ consultant shall not relieve the Supplier of his
responsibility for correct design and execution of the works.

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 2 of 17


3 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

2.4. Fabrication of the structure shall not be taken up at shop till all the G.A/ design drawings are
reviewed & approved by the client/ consultant and comments/ suggestions given by client/
consultant are incorporated by Supplier.
2.5. The Shop Fabrication Drawings shall adhere to the approved design and general arrangement
drawings by the client/ consultant and shall be developed after incorporating all the
comments/ suggestions given by client/ consultant without any extra cost to and any
implication on time schedule for completion of work.
2.6. The shop drawings shall be provided to the representative deputed for stage inspections
during fabrication and of the material prior to dispatch.
2.7. Supplier shall submit following final drawings/ documents to the client/ consultant in 3 set of
hard copy along with soft copy in DWG format.
2.7.1. Anchor bolt setting plans.
2.7.2. Building column reaction drawings/ documents.
2.7.3. Structural erection drawings with connection detailing.
2.7.4. Supplier erection manual.
2.8. Supplier shall submit detailed overall work programme and a bar chart indicating the duration
and timing of all major activities showing the desired milestones.
2.9. Supplier shall submit the quality assurance plan duly signed by the corporate head or any
other authorized person.
2.10. Supplier shall submit list of work completed in last 3 years along certificate from customers/
end users for satisfactory performance of the work.

3. STRUCTURAL CONSIDERATION
3.1. LOADING ON STRUCTURE
3.1.1. Dead load should be considered as per actual.
3.1.2. Imposed load on mezzanine floor shall be 500 kg/ sq.m.
3.1.3. False ceiling & Exhaust system load 50 kg/ sq.m at blender & mixing station area.
3.1.4. Monorail of capacity 0.5 T as per tender drawing.
3.2. STRUCTURAL MEMBERS
3.2.1. Structural members shall be designed as per American code.
3.2.2. All T and I type built-up members of mezzanine columns, beams and jack beam shall
be welded from both side (continuous welding) and rafter, gable columns shall have
continuous weld at one side and chain weld at other side.

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 3 of 17


4 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

3.2.3. Welded splice joint shall be provided in web & flange at proper length (not less than
6m)
3.2.4. Minimum thickness of primary members shall not be less than 5 mm.
3.2.5. Minimum thickness of secondary members (Purlin/ Side Girts) shall not be less than
1.6 mm (base material).
3.2.6. Any butt joints shall be with 100% ultrasonic quality weld to ensure full strength of the
parent plate / section. At least 10% butt weld joints shall be tested by ultra-sonic
method (test report shall be submitted).
3.2.7. All edges of plates & sections shall be smooth, free from rough cut edges.
3.2.8. Deck sheet shall be design to take dead load of deck slab plus imposed load.

3.3. PHYSICAL SPECIFICATIONS OF STRUCTURAL MEMBERS


3.3.1. Members fabricated from plate shall have flanges and webs joined will conform to the
physical specifications of ASTM A570 (Grade 50) and having a minimum yield
strength of 50,000 P.S.I. (345 MPa) or IS 2062 grade E350 and having a minimum
yield strength of 350 Mpa.
3.3.2. Members fabricated by cold forming process shall conform to the physical
specifications of ASTM A570 (Grade 50) or equivalent and having a minimum yield
strength of 50,000 P.S.I (345 MPa).
3.3.3. Members fabricated from hot rolled structural shapes shall conform to the physical
specifications of ASTM A572 (Grade 36) or equivalent and having a minimum yield
strength of 36,000 P.S.I.(250 MPa).
3.3.4. Rod and angle bracing shall conform to the physical specifications of ASTM A36 (or
Equivalent) and having a minimum yield strength of 36,000 P.S.I. (250 MPa).
3.3.5. All other misc. secondary members shall have minimum yield strength of 36,000 P.S.I.
(250 MPa).

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 4 of 17


5 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

3.4. GENERAL CONSIDERATION


3.4.1. Knee bracing angle shall be provided from both side of column and roof rafter to side
runners/ purlins.
3.4.2. Approaches for gantry girder and roof shall be provided as per assignment drawing.
3.4.3. Proper rain water drainage system shall be provided with gutter and down takes up to
FGL (-) 0.20 M.
3.4.4. Supply of foundation bolts including 3 nuts, 1 washers & templates should be arranged
in advance, in accordance with progress of civil construction work at site.
3.4.5. Nuts, Bolts & washers shall be supplied 3% in excess than the actual requirement to be
supplied for foundation bolts.
3.4.6. In the bolted connection H.T. & H.S. nut & bolts for permanent connection, specific
torque is to be provided as per design. The torque wrench in sufficient numbers will be
brought at site for erection purpose.
3.4.7. Foundation Bolts shall be supplied with minimum 10 nos. templates for each type of base
plate. The alignment and levels shall be checked and certified by the PEB Supplier’s
engineer.
3.4.8. Stage inspections shall be carried out by client/ consultants during shop
fabrication and prior to dispatch of the materials. Any discrepancy shall be to the
Suppliers account.
3.4.9. No welding shall be permitted at site unless otherwise cleared by client/ consultants.
3.4.10. Supplier shall submit the separate quantity of structural steel, purlin/ girts, color
coated sheet, pvdf coated sheet, bare galvalume sheet, transparent sheet, turbo
vent etc. Along with price bid.

3.5. STEEL WORK FINISH


3.5.1. Primary steel
3.5.1.1. All primary steel member will be thoroughly cleaned of all loose mill scale, rust,
grease, dirt & other foreign matter and painted with the paint system described
below.
3.5.1.2. All paint delivered to the fabrication shop shall be ready mixed in original sealed
containers as packed by the paint manufacturer. No painting shall be done in frosty/
foggy weather or when the humidity is high enough to cause condensation on the
surface to be pained.
3.5.2. Secondary steel
Roof Purlin & wall girts shall be cold formed from galvanized steel coils (min.
180 gsm) and shall remain unpainted.
GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 5 of 17
6 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

3.5.3. Paint system


All primary & secondary steel member will be Airless Spray Coated in factory
with the following painting system.
3.5.3.1. One Primer coat of Zinc- cromate primer 25 microns DFT.
3.5.3.2. One under Coats of approved enamel paint 50 microns DFT.
3.5.3.3. One finish Coat of approved enamel paint of 25 microns DFT.

4. SHEETING AND ACCESSORIES


4.1.1. Roof sheeting shall be of min.0.47mm thick profiled bare galvalume sheeting.
4.1.2. Wall panel shall be of min.0.50mm thick profiled color coated sheeting.
4.1.3. Blender & Mixing area wall panel shall be 0.5mm thick pvdf coated sheeting.
4.1.4. For illumination 2 mm thick Polycarbonate transparent sheets shall be provided on side
walls and roof as per the assignment drawings and arrangement pattern shall be
approved by client/ consultant.
4.1.5. Sheeting Fasteners:
Standard fasteners shall be No. 14, Type A, self drilling sheet metal screws with metal
and neoprene washers. All screws shall be color coated to match roof and wall
sheeting and made of zinc plated steel.
4.1.6. Closures / Filler Strips:
Solid or closed cell E.T.P. (Ethylene Polypropylene Terpolymer) closures matching
the profile of the panel shall be installed along the eaves, rake and other locations
unless specified on drawings.
4.1.7. Ridge Cap:
A formed panel matching the material color, slope and profile of adjoining Rib roof
panels.(NOT APPLICABLE)
4.1.8. Flashing And Trim:
Flashing and/or trim shall be furnished at the rake, corners, eaves framed openings and
wherever necessary to provide weather tightness and finished appearance. Material
shall be 26 G thick conforming to the physical specifications of ASTM 446 Grade C or
equivalent and having minimum yield strength of 40,000 P.S.I. (275 MPa).
4.1.9. Eave Gutters And Downspouts:
Eave gutters shall be box shaped, color coated, 2 mm nominal thickness galvanized
steel.
4.1.10. The outside face of the gutter shall be supported with galvanized straps to the eave
member at a maximum spacing of 1.2 m. Downspouts shall be color coated 0.5 mm
nominal thickness (26 gauge) galvanized steel. Downspouts shall have a 45 degree
GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 6 of 17
7 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

elbow at the bottom and shall be supported by attachment to the wall covering at 3.0 m
maximum spacing.
4.1.11. Sheeting material shall be considered as following and all other accessories including
trim, closure, bolts, fixtures etc shall be suitably considered accordingly.

Sr. No Description Specification

1. Base Metal CR Sheets As Per JIS 3141


2. Coating Zincalume
a) Inside of Shed : To be confirm
3. from client.
Color Shed
b) Outside of Shed: To be confirm
from client.

4. Profile Details Profile MP980 or MP1020 or MP


Shape Wave 1220 For roof.
a) Thickness 0.50 mm thk. for side cladding .
0.47 mm thk. For roof.

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 7 of 17


8 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

SPECIFICATIONS FOR POLYCARBONATE TRANSLUCENT SHEETS FOR ROOFING -


Ultra-strong UV stabilized poly-carbonate profiling match to suit zincalume colour sheets.
Sr. No Description Specification

1. Physical
Density 1.2 g/cm3
2. Optical
a) Light transmission clear 90%
b) Haze ≤2%
3. Mechanical
a) Tensile stress at yield ≥60 N / mm2
b) Elongation at break 80%
c) Dart impact ‘A’ (1.5mm) >25J
d) Thickness 2 mm
e) Colour transparent clear
4. Thermal
a) Vicat VST/B >145-1500C
b) Heat deflection (DTUL) 135-1400C
c) Impact Strength >200 N/m
d) Flexural Modules 2500N/mm2
e) Izod notched 600-800 J/m
f) Coeff of liner thermal expansion 6.7 x 10-5 m/m 0C
g) Thermal conductivity 0.21 W/m 0C
h) Fire Rating Class-I
i) Oxygen index 25 (self, extinguishing &
non propagating)
j) K value (W/m2 K) 5.7%

Note : Poly carbonate sheets should have UV-protective coating for improved weather ability.

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 8 of 17


9 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

5. GENERAL GUIDLINES TO FOLLOW


5.1. Supplier shall depute his own Project Manager and Safety engineer at site during the
erection work.
5.2. The Supplier shall be deemed to have considered in his offer for providing maintenance and
final removal of all temporary works of whatsoever nature. No specific item of any or
particular temporary shed/work will be measured and paid for separately.
5.3. Supplier shall submit detailed overall work programme and a bar chart indicating the duration
and timing of all major activities showing the desired milestones.
5.4. Supplier shall submit the quality assurance plan duly signed by the corporate head or any
other authorized person.
5.5. Supplier shall submit list of work completed in last 3 years along certificate from customers/
end users for satisfactory performance of the work.
5.6. All materials supplied by supplier should satisfy the quality norms of respective Standards.
5.7. Well qualified and experienced agency shall be engaged by the Supplier at site for erection,
this agency shall be approved by the Owner prior to award of the contract to supplier.
5.8. The erection agency of Supplier must follow the safety rules & regulations strictly as shall
be prescribed by the client. The Supplier shall make available first aid for his labours,
skilled people, supervisors, engineers at site. The Supplier shall also maintain his own
mode of transport in case of emergencies and not to depend on Owner.
5.9. Supplier should visit and make themselves familiar with site working conditions.
5.10. Supplier should study the tender drawings carefully before quoting the price however it
should be noted that the tender drawings are for reference and quotation only.
5.11. Supplier shall attach the following along with their techno-commercial offer:
5.11.1. List of the similar projects executed by supplier during last three years from the date of
tender.
5.11.2. Detailed Time Schedule from date of LOI to handover of the PEB structure.
5.11.3. Detailed Fabrication and dispatch schedule, in line with the erection schedule.
5.11.4. Shop floor QA and QC system.
5.11.5. Erection manual.
5.11.6. List of plant and machineries/ facilities (with capacity) available with bidder.
5.12. Supplier/ seller shall provide/ arrange following documents duly verified & stamped by their
quality control department before/ during inspection.
5.12.1. Mill certificate for 100% steel plate & section.
5.12.2. Mill certificate for 100% fasteners, bolts, nuts & washers.
5.12.3. Detailed packing list, container wise clearly showing details of material with weight.

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 9 of 17


10 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

6. ESSENTIAL CONDITIONS FOR SITE


6.1. Vendor/ contractor will prepare on own site office and godown facilities.
6.2. The quoted rates shall include cost of preparation of all programs, bar charts, progress report
and other reports for execution and completion of the project.
6.3. Accommodation for vendor/ contractor staff and workers will be arranged by vendor/
contractor . The hygienic condition to be maintained as specified by client.
6.4. Vendor/ contractor should provide at the site appropriate technical and supporting staff as
required for erection and supervision of the project.
6.5. Safety officer and supervisor.
6.6. Complete responsibility about correctness of the structures as per drawings. Details and
specifications provided will ultimately rest with you.

7. WATER AND POWER FOR ERECTION


7.1. Single point free supply of water and power shall be provided each for erection site and
vendor/ contractor labour colony area at a convenient location. Further distribution will be to
vendor or contractor account. Illumination of working is in contractor’s scope and Area
illumination will be done by client.
7.2. Vendor/ contractor will be given only open land free of charge for vendor or contractor site
office, store and assembly yard. You shall construct your own site office and go down
facilities.
7.3. For labour camp and staff quarters only open land will be given to vendor or contractor as
may be necessary. Vendor/ contractor are required to dismantle the hutments/ quarters when
the work is completed.
7.4. Power connection related safety
7.5. Authorized electrician only will be allowed to operate electrical equipments. Proper care to
be taken for cable laying & power distribution.

8. MACHINERY, MANPOWER ETC.


8.1. Vendor/ contractor will deploy equipment, labour, technical and supporting staff in
consultation with client/ consultants for smooth and efficient progress of work. Deployment
of manpower shall meet planned project schedule.

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 10 of 17


11 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

8.2. All vendor/ contractor machinery, tools equipment etc will be listed in duplicate and endorsed
by client security while entering the work premises. This document should be produced for
obtaining gate pass while taking out any items outside the work premises.

9. ELEVATED WORKING CRANES


9.1. Depending upon the site condition suitable cranes are to be deployed. Only workers with
relevant experience of working at height and medically fit should only work for activities at
height. Proper safety equipment's with all PPE and with safety belt, life line, and fall arrestor
should be used. Prior inspection and tested of slings and D sackles, crane wire ropes etc
should be used before lifting assemblies at higher level.
9.2. All required cranes shall be arranged by the supplier/contractor for erection with in targeted
schedule and deployment of cranes should be approved by client/ consultants.

10. SUPPLY AND ERECTION SCHEDULE


Supplier shall submit supply and erection schedule along with offer.

11. HOUSE KEEPING


It is the responsibility of the contractor to keep storage yard of structural steel clean and properly
stored.

12. SAFETY
12.1. Device appropriate safety methodologies for follow up by all concerned with regard to
national codes/ statutory regulations.
12.2. To ensure that the agencies are aware of the appropriate provisions to be made by them.
12.3. Necessary cordoning of areas where critical tests/ erection activity etc is in progress.
Erection methods shall prepare by the contractor before lifting of critical items.
12.4. Periodically checking of all mechanisms and auxiliaries for performance etc.
12.5. Proper storage of gas cylinders from source of heat, correct handling of cylinders both during
and after use, use goggles during welding, provision of incombustible screen.
12.6. Vendor/ contractor will depute safety officer to take care of safety aspect of daily activities.
All the personal protective equipment's like helmet, safety belt, shoes, will be of ISO
approved and also approved by client/ consultants.
12.7. Vendor/ contractor will be responsible for safety of all workers working under vendor/
contractor scope of work.
12.8. Worker prior to start working at site should undergo safety training at our safety department,
and medical test.

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 11 of 17


12 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

12.9. Gas cylinder, diesel should be properly stored in a ventilated area.


12.10. Ignoring safety case, penalty will be imposed as per client’s safety norms.
12.11. All safety PPEs are as per client’s standard to be supplied by the contractor to their
workmen.

13. PERFORMANCE WARRANTIES


13.1. WEATHER TIGHTNESS
Supplier shall submit written weather tightness warranty for one (1) year against leaks in
roof and side cladding arising out of or caused by ordinary wear and tear under normal
weather and atmospheric conditions..
13.2. PAINTING & SURFACE FINISH
Supplier’s shall undertake paint film written warranty for five (5) year against
crackling, peeling, chalking and fading of the coating on painted wall panels, painted
roof panels and soffit panels.
13.3. STRUCTURAL STABILITY
Supplier shall issue a certificate towards Structural Stability warranty for a period of (50)
years as taken into design considerations.

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 12 of 17


13 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

SECTION - B

PRICE SCHEDULE

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 13 of 17


14 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

1. PREAMBLE TO PRICE SCHEDULE


1.1. The tenderer shall carefully go through the tender specification, site conditions, price schedule
and drawings and shall include in his price any sum he may consider necessary to cover the
fulfillment of the various clauses contained therin. The price stated in the price schedule
inclusive of everything necessary to complete the said item of work within the contemplation
of the contract and beyond the price no extra payment will be allowed for any incidental or
contingent work, labour, material and plant.
1.2. Unless otherwise specified, all measurement shall be in SI units.
1.3. The price in the price schedule shall also include the cost of following:
1.3.1. Storage of material and hoisting and lowering to all levels.
1.3.2. Supplying, protecting, handling and installation of material in accordance with the
tender specification.
1.3.3. Transport & accommodation of contractors supervisory staff and labour.
1.3.4. All fright up to site and all taxes, duties, levies etc. Out side.
1.3.5. Necessary care and protection against damage to equipment, if any supplied by the
owner or other contractor.
1.3.6. All waste and scrape.
1.3.7. The actual quantity of structural steel supplied should not be less than 3% as given in
price bid.

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 14 of 17


15 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

APPENDIX

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 15 of 17


16 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

APPENDIX-A, Deviation Schedule

We have examined the enquiry document and understood the technical requirement. We hereby
confirm that the scope of supply and other details of our offer confirm to all specification other
than deviations listed below. Purchaser will not entertain any deviations other than those specified
below. The deviations listed below are subject to Purchaser acceptance in writing.

Sr. No. Clause No. Description Deviation

DEVIATIONS :- (Use additional sheet if, required)

We hereby confirm, our acceptance to all the Terms and Conditions of purchase including all
documents enclosed with the inquiry which will form part of the Purchase Order, if awarded to us.

Name of the Company

Signature

Designation

Company’s seal

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 16 of 17


17 TECHNICAL SPECIFICATION OF PEB BUILDING

DOC. NO.- GCPL/ FBT/723/TS/PEB-01


PROJECT : CLIENT :
FACTORY BUILDING, M/S GSR CHEMICALS
TARAPUR (MH) PVT. LTD. TARAPUR (MH) REV. A DATE - 08.04.2019

APPENDIX-B, List Of Drawings

Following Drawings to be referred

Sr. No. Description Drawing No. Sheet Rev.


1. GCPL-723-PEB-01 1OF2 B
2. Tender/ Assignment Drawing For PEB GCPL-723-PEB-01 1OF2 B
3.
4.

GCPL/FBT/723/TS/PEB-01 GEOSTRUCT CONSULTANTS PVT. LTD., INDORE, INDIA Page 17 of 17