Sub Design2
Sub Design2
1 Designed the substation model, implemented the code and wrote the methodology
2 Supervised the research
3 Provided essential software knowledge
Abstract
Abstract
This methodology describes the basic design process to design a step-up substation which is
connected to a solar PV plant. The objective of this document is to present the main steps that
are necessary to determine the electrical characteristics of a substation.
There are many di�erent ways in which a substation can be designed. Each way would have
some advantages and disadvantages. The author of this methodology has decided on a structure
which follows the work of the substation’s experts during many decades:
• The circuit arrangement of the substation is selected and the number of transformer and
line bays are established.
• The insulation coordination is computed to operate the substation satisfactorily not only
under normal operating conditions but also in the presence of transient and temporary
overvoltages.
• The safety distances that will be maintained within the substation’s �eld are speci�ed.
• The main components of the substation are determined according to their standards. Power
transformers, surge arresters, instrument transformers, circuit breakers, disconnectors and
grounding devices, among others are studied in the methodology.
• For the double busbar substations, the following aspects are considered to size the busbars:
current-carrying requirements (continuous and short circuit), environmental considera-
tions (ice, wind, weight, etc.), physical constraints, future requirements of the substation
and corona interference.
Note: All the calculations that are presented in this methodology are carried out in accordance
with the latest IEC and IEEE standards.
Substation Methodology 1
Contents
Contents
Abstract 1
4 Insulation Coordination 21
4.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21
4.2 General procedure for insulation coordination . . . . . . . . . . . . . . . . . . . 22
4.2.1 Class I insulation coordination procedure . . . . . . . . . . . . . . . . . 23
4.2.2 Class II insulation coordination procedure . . . . . . . . . . . . . . . . . 24
4.3 Determination of the representative voltages and overvoltages . . . . . . . . . . 25
4.3.1 Temporary overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
4.3.2 Slow-front overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . 26
4.3.3 Fast-front overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
4.4 Determination of the coordination withstand voltages . . . . . . . . . . . . . . . 29
4.4.1 Temporary overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
4.4.2 Slow-front overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
4.4.3 Fast-front overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
4.5 Determination of the required withstand voltages . . . . . . . . . . . . . . . . . 31
4.6 Conversion to rated withstand voltages . . . . . . . . . . . . . . . . . . . . . . . 33
4.7 Selection of the rated insulation levels according to IEC . . . . . . . . . . . . . . 34
4.8 Selection of the clearance distances according to IEC . . . . . . . . . . . . . . . 37
Substation Methodology 2
Contents
4.9 Determination of the temporary, BIL and BSL voltages according to the IEEE . . 40
4.9.1 Determination of the temporary voltages: . . . . . . . . . . . . . . . . . 41
4.9.2 Determination of the basic lightening impulse voltage BIL: . . . . . . . . 41
4.9.3 Determination of the basic switching impulse voltage BSL: . . . . . . . . 42
4.10 Selection of the rated insulation levels according to IEEE . . . . . . . . . . . . . 44
4.11 Calculation of the clearance distances according to IEEE . . . . . . . . . . . . . 45
4.12 Selection of the clearance distances according to IEEE . . . . . . . . . . . . . . . 47
5 Safety Distances 50
5.1 Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
5.2 General procedure for the calculation of the safety distances . . . . . . . . . . . 51
5.2.1 Sta� movement factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
5.2.2 The basic value . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
5.2.3 Field height . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
5.2.4 Field length . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
5.2.5 Distance between buses . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
6 Substation Equipment 55
6.1 Power transformers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
6.1.1 Two winding transformers . . . . . . . . . . . . . . . . . . . . . . . . . . 55
6.1.2 Three winding transformers . . . . . . . . . . . . . . . . . . . . . . . . . 56
6.2 Grounding equipment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57
6.3 Surge arresters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
6.3.1 Selection of the surge arrester . . . . . . . . . . . . . . . . . . . . . . . . 58
6.4 Circuit breakers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
6.5 Disconnectors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
6.6 Current transformers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
6.7 Voltage transformers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
6.8 Cables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
Bibliography 83
Substation Methodology 3
Contents
C Insulation Coordination 93
C.1 General procedure for insulation coordination . . . . . . . . . . . . . . . . . . . 93
C.1.1 Class I insulation coordination procedure . . . . . . . . . . . . . . . . . 93
C.2 Determination of the representative voltages and overvoltages . . . . . . . . . . 94
C.2.1 Temporary overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . 94
C.2.2 Slow-front overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . 94
C.2.3 fast-front overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
C.3 Determination of the coordination withstand voltages . . . . . . . . . . . . . . . 95
C.3.1 Temporary overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
C.3.2 Slow-front overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
C.3.3 Fast-front overvoltages . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95
C.4 Determination of the required withstand voltages . . . . . . . . . . . . . . . . . 96
C.5 Selection of the rated insulation levels . . . . . . . . . . . . . . . . . . . . . . . . 97
C.6 Selection of the clearance distances . . . . . . . . . . . . . . . . . . . . . . . . . 97
D Safety Distances 98
D.1 General procedure for the calculation of the safety distances . . . . . . . . . . . 98
D.1.1 The basic value . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
D.1.2 Field height . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98
D.1.3 Field length . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
D.1.4 Distance between buses . . . . . . . . . . . . . . . . . . . . . . . . . . . 99
Substation Methodology 4
Contents
Substation Methodology 5
List of Figures
List of Figures
4.1 Range of 2% slow-front overvoltages at the receiving end due to line energization
and re-energization [11] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
4.2 Ratio between the 2% values of slow-front overvoltages phase-to-phase and phase-
to-earth. The upper part may be applied to three-phase re-energization, the lower
part to energization. [11] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
4.3 Evaluation of deterministic coordination factor : cd [11] . . . . . . . . . . . . . . 30
4.4 Dependence of exponent m on the coordination switching impulse withstand
voltage [11] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
5.1 The safety distance is made up of two values: basic value and safety zone for
sta�. Source: Own elaboration from the data provided by [15]. . . . . . . . . . . 51
5.2 The safety distance in the substation �eld. Source: Own elaboration. . . . . . . 52
7.1 The forces that a�ect the structure of a busbar. Source: Own elaboration . . . . 73
Substation Methodology 6
List of Tables
List of Tables
3.1 Short-circuit power and currents According to IEC. Source: Own elaboration . . 18
3.2 Short-circuit power and currents According to IEEE. Source: Own elaboration . 18
E.1 Technical data for surge arresters - 145 kV. [22], [25] and [26] . . . . . . . . . . 102
Substation Methodology 7
Chapter 1. Selecting Circuit Arrangements
Chapter 1
This chapter summarizes the possible electrical substations that the user will be able to obtain as
well as the conditions that every solution will satisfy.
1. A switching and breaking station is the solution that operates at a single voltage level,
meaning there is no power transformer. A switching station can be de�ned as a group of
cubicles that are protected by a switchgear, whose objective is to break or split a distribu-
tion power line into one or several output lines. An illustration of this type of substations
is represented in Figure 1.1
Figure 1.1: Switching and breaking station con�guration. Source: Own elaboration
2. A line to transformer substation is the type that consists of one transformer bay. In addi-
tion, a medium voltage cubicle will connect the photovoltaic plant with the power trans-
former. Figure 1.2 illustrates the line to transformer substation.
Substation Methodology 8
Chapter 1. Selecting Circuit Arrangements
3. A single busbar substation is the substation that consists of one or more transformer bays
and one or more outgoing circuits which are connected to each other by a rigid bus. The
connection between the photovoltaic plant and the power transformers is made through
one or more medium voltage cubicles. This type of substation is represented in Figure 1.3.
The generated solution will depend on the plant’s installed capacity, the medium voltage system,
and the number of power transformers.
In general, a switching and breaking station has some cubicles that are designed for a feeder
function and others that are designed for either measuring the voltage and the current (metering
function) or for protecting the station against over voltages or faults (circuit breaker or fuse
protection function).
The cubicles that are incorporated in the station are the following:
Feeder function
Substation Methodology 9
Chapter 1. Selecting Circuit Arrangements
A feeder cubicle enables the communication with the main busbar. In addition to the feeder
cubicle that connects the station to the grid, there will be as many feeder cubicles as medium
voltage power lines leaving the photovoltaic plant. A feeder cubicle is equipped with:
• A switch-disconnector. Its main parameters that are given are the rated current and the
short-circuit current.
• The cables coming from the photovoltaic plant or those that feed the station. Up to six
repetitions per cable can be connected to the feeder cubicles.
Metering function
A metering cubicle provides information about the operating voltage and the current that �ows
through the cubicle. It is equipped with:
• A current transformer.
• A voltage transformer.
It provides general protection for feeders or instrument transformers as well as providing con-
nection and disconnection operations. A protection cubicle is equipped with:
• A switch-disconnector.
• A vacuum circuit breaker.
It provides general protection for feeders or instrument transformers as well as providing con-
nection and disconnection operations. Furthermore, an auxiliary service line with a step down
transformer is connected to the fuse protection cubicle. The 100 kVA auxiliary transformer will
step down the voltage from the medium voltage level to a low voltage level that equals to 400 V.
A fuse protection cubicle is equipped with:
• A switch-disconnector.
• A fuse.
• A power transformer.
• A surge arrester that protects the secondary winding of the power transformer.
• A surge arrester that protects the primary winding of the power transformer.
• A grounding device for the secondary winding of the power transformer.
• A circuit breaker.
• An earthing disconnector.
Substation Methodology 10
Chapter 1. Selecting Circuit Arrangements
• A current transformer.
• A voltage transformer.
• A surge arrester that protects the end of the overhead line.
Transformer bay
• A power transformer.
• A surge arrester that protects the secondary winding of the power transformer.
• A surge arrester that protects the primary winding of the power transformer.
• A grounding device for the secondary winding of the power transformer.
• A circuit breaker.
• A disconnector.
• A current transformer.
Buses level
The buses are used to connect bays into an existing substation. The software will give all the
information about the dimensions of the buses such as material, external diameter, internal di-
ameter, and section while taking into account external conditions, loads, post insulators, etc... In
addition, a voltage transformer has been considered.
Transformer bay
• A power transformer.
• A surge arrester that protects the secondary winding of the power transformer.
Substation Methodology 11
Chapter 1. Selecting Circuit Arrangements
• A surge arrester that protects the primary winding of the power transformer.
• A grounding device for the secondary winding of the power transformer.
• A circuit breaker.
• Two disconnectors.
• A current transformer.
Buses level
The buses are used to connect bays into an existing substation. The software will give all the
information about the dimensions of the buses such as material, external diameter, internal di-
ameter, and section,while taking into account external conditions, loads, post insulators, etc...
In the bus level, a bus coupler has been included. The bus coupler allows the two busbars to
either run separately or to run with the bus coupler’s breaker closed or open. In addition, two
voltage transformers (one per each bus) have been considered.
The switching and breaking station must always ful�l that the total current is lower than 500 A.
t 1250 (1.1)
( pv 60 "+ (1.2)
Where:
The line to transformer substation ful�lls that the number of transformer bays is equal to one.
# bays = 1 (1.3)
Where:
Substation Methodology 12
Chapter 1. Selecting Circuit Arrangements
The single busbar substation ful�ls that the number of transformer bays is greater than one. It
also meets that the total operating current of the PV plant is lower than three times the maximum
admissible current per bay.
t 3· op-mv (1.4)
Where:
The double busbar substation ful�ls that the number of transformer bays is greater than one.
Moreover, it meets the criteria that the total operating current of the PV plant is greater than
three times the maximum admissible current per bay.
Where:
Substation Methodology 13
Chapter 2. Determination of the number of substation bays
Chapter 2
In this chapter, the main criteria to split the substation in di�erent bays will be presented. The
number of transformer bays will be determined automatically based on four criteria. The num-
ber of output bays will also be established automatically and this decision will be calculated in
accordance to one criterion.
As mentioned in Chapter 3, the operating short-circuit current that could a�ect the medium
voltage system shall be lower than the design short-circuit current that has been selected to size
the substation components.
So, the �rst criterion that a transformer bay must ful�ll is given in Equation 2.1.
op-sc sc (2.1)
Where:
• op-sc is the operating short-circuit current per bay at medium voltage level. [A]
• sc is the design short-circuit current at the substation input. [A]
In order to establish the number of transformer bays, one of the key parameters is the design
current that can �ow per bay in the medium voltage system. The design short-circuit current
limits this admissible current, which is calculated using Equation 2.2.
des = sc · I sc (2.2)
Where:
Substation Methodology 14
Chapter 2. Determination of the number of substation bays
• des is the maximum design current that can �ow through a transformer bay at medium
voltage level. [A]
• sc is the design short-circuit current at the substation input. [A]
• I sc is short-circuit impedance of the power transformer in parts per one.
The operating current that actually �ows per transformer bay is calculated using Equation 2.3.
%t
op-mv = p (2.3)
* 3
Where:
• op-mv is the current that �ows through the medium voltage level. [A]
• %t is the capacity of the power transformer. [VA]
• * is the medium voltage level. [V]
So, the second criterion that a transformer bay may ful�l is given in Equation 2.4.
Where:
• des is the maximum design current that can �ow through a transformer bay at medium
voltage level. [A]
• op-mv is the current that �ows through the medium voltage level. [A]
According to [1], to obtain a total load that is equal to the total installed power of the PV plant,
the power transformers must have the same short-circuit impedance. For that reason, the short-
circuit impedances of the power transformers per bay may be equal. The third criterion that a
transformer bay may ful�l is given in Equation 2.5.
Where:
The cables that connect the primary medium voltages with a power transformer should with-
stand the total current that they are carrying. These cables are calculated based on Section 6.8.
The last criterion that a transformer bay may ful�l is given in Equation 2.6.
Where:
Substation Methodology 15
Chapter 2. Determination of the number of substation bays
• ccc is the current-carrying capacity of the selected cable after applying the standard cor-
rection factors. [A]
• op-mv is the current that �ows through the medium voltage level. [A]
If the total current is strictly higher than 10000 A, a three-winding transformer will be designed
to step-up the voltage.
So, the criterion that an output bay may ful�l is given in Equation 2.7.
4000
op-hv (2.7)
5s
Where:
• op-hv is the current that �ows through the HV output bay. [A]
• 5s is a safety factor that equals 1.25.
Substation Methodology 16
Chapter 3. Calculation of the short-circuit currents
Chapter 3
The calculation of the short-circuit currents is key to correctly size the number of substation
bays and the electrical characteristics of the devices. In this section, four short-circuit currents
will be presented.
• The design short-circuit current for both high and medium voltage systems. Design short-
circuit currents are considered to size the substation switchgear.
• The operating short-circuit currents according to [2] and [3] following both the IEC and
the IEEE standards respectively.
• The peak short-circuit current for both the high and medium voltage systems, according
to [2].
• The thermal short-circuit current for both the high and medium voltage systems, according
to [2].
The �rst criterion that has to be ful�lled is that the operating short-circuit current that could
a�ect the the medium voltage system shall be lower than the design short-circuit current that
has been selected to size the substation components.
op-sc sc (3.1)
Where:
Substation Methodology 17
Chapter 3. Calculation of the short-circuit currents
Table 3.1: Short-circuit power and currents According to IEC. Source: Own elaboration
Table 3.2: Short-circuit power and currents According to IEEE. Source: Own elaboration
Due to the topology of the problem, that is, the photovoltaic plant is connected to the grid thanks
to a substation that is made by one or several power transformers, it can be simpli�ed if the
e�ects of two main elements: an ideal external network and one/several two-winding power
transformers are studied.
Substation Methodology 18
Chapter 3. Calculation of the short-circuit currents
This calculation method consists of de�ning several nodes in which the short-circuit current will
be studied. Between those nodes, the impedance of the di�erent elements that belong to the grid
will be obtained. The short-circuit current in a node is given by Equation 3.2.
2 ·*
op-sc = p (3.2)
/· 3
Where:
*2
/ network = (3.3)
( sc
Where:
* 2 I sc
/t = · (3.4)
( t 100
Where:
p
p = op-sc ·^ 2 (3.5)
Substation Methodology 19
Chapter 3. Calculation of the short-circuit currents
Where:
3'/- )
^ = 1.02 + 0.984 ( (3.6)
Where:
• ^ is a network factor.
'
• is the resistance-reactance ratio of the network that equals 0.07.
-
p
th = op-sc < += (3.7)
Where:
1
<= · {4 4·5 ·)k ·;= (^ 1)
1} (3.8)
2 · 5 · )k · ;=(^ 1)
Where:
Substation Methodology 20
Chapter 4. Insulation Coordination
Chapter 4
Insulation Coordination
In this chapter, the insulation levels and clearance distances for air insulated substations are
calculated based on [9], [10] and [11] in obedience with the IEC standard and based on [12] and
[13] in compliance with the IEEE standard . The objective is to specify the procedure for the
selection of the rated withstand voltages for the substation equipment’s insulation.
After selecting the rated withstand voltages, the associated clearance distances will be recom-
mended.
4.1 Introduction
This chapter calculates the insulation levels according to [9] for both class I (1 - 245 kV) and class
II (245 - 800 kV) substations following the international standard and to [12] for class I (15 - 242
kV) and class II (242 - 800 kV).
The process followed in accordance with the IEC standard is the following:
First, the representative values for the temporary, slow-front, and fast-front overvoltages are
calculated. Because the grid characteristics are unknown, some estimation will be made in the
study.
Afterwards, the coordination overvoltages are computed. In this case, a coordination factor will
be applied. Later, two correction factors are applied to obtain the required overvoltages. These
correction factors take into account the di�erences in the dielectric strength between service and
test conditions.
Once the required overvoltages are calculated, the assigned standard overvoltages are obtained.
These standard rated voltages are linked to the highest voltage for equipment.
On the other hand, the process followed to calculate the insulation coordination according to the
IEEE standard is the following:
First, the system voltage stresses for the overvoltage’s classes are determined: switching, light-
ening, and temporary and that is for the phase-to-phase and phase-to-ground con�gurations.
Substation Methodology 21
Chapter 4. Insulation Coordination
Finally, depending on the voltage, the assigned standard voltage stresses are obtained, which
depend on the maximum voltage of the equipment.
• Class I: From 1 kV to 245 kV (included). This range applies to both distribution and trans-
mission lines.
• Class II: For main transmission substation with high voltages above 245 kV.
• Class I: From 1 kV to 242 kV (included). This range applies to both distribution and trans-
mission lines.
• Class II: For main transmission substation with high voltages above 242 kV.
For class I substations, temporary and fast-front overvoltages,which are the temporary and the
basic lightening voltage or BIL in the IEEE standard, are calculated to obtain the standard rated
withstand voltages. The slow-front overvoltages are also computed following the IEC; and later,
converted to temporary and to fast-front overvoltages. In some cases, slow-front converted val-
ues are higher than temporary or fast-front voltages and for that reason, they have to be taken
into account.
For class II substations, the withstand voltages will depend on the slow-front, named the basic
switching voltage or BSL in the IEEE standard, and fast-front overvoltages or BIL. In addition, the
temporary overvoltages are computed, however, they are converted to slow-front overvoltages
when calculating in accordance to IEC. These overvoltages will have a signi�cant role if they are
greater than slow-front and fast-front overvoltages.
Moreover, the �rst step to obtain the standard rated withstand voltages is to select the highest
voltage for the equipment, given in Table 4.1 for the IEC standard and in Table 4.2 for the IEEE.
This value will be considered to choose the withstand voltages from the standard.
Finally, the results will be a set of withstand voltages for internal and external insulation and for
both phase-to-phase and phase-to-earth con�gurations. Once these standard rated withstand
voltages are de�ned, the clearance distances are directly obtained.
The lightning arresters that are installed in the substation are calculated to have a good estima-
tion of the insulation coordination. These devices will protect the substation equipment from
overvoltages; and the complete model to obtain their most important parameters is presented in
Subsection 6.3.1. The lightning and switching impulse protective levels play an important role
to determine the representative fast-front and slow-front overvoltages.
Substation Methodology 22
Chapter 4. Insulation Coordination
Table 4.1: Highest voltage for the equipment according to IEC [11]
Table 4.2: Highest voltage for the equipment according to IEEE [13]
Substation Methodology 23
Chapter 4. Insulation Coordination
3. Calculation of the required overvoltages by applying a security factor and the atmospheric
correction factors.
4. Conversion of the slow-front overvoltages to temporary and fast-front overvoltages by
applying conversion factors.
5. Identi�cation and selection of the standard rated withstand voltages in regards to the re-
quired overvoltages by referring to the highest voltages for the equipment.
6. If some required voltages are higher than the maximum standard rated withstand voltage
for a speci�c highest voltage for equipment, a greater value of the standard voltage is
selected even though the highest voltage is superior.
7. Selection of the minimum rod-structure and conductor-structure clearance distances for
the standard rated withstand voltages that have been selected.
8. Identi�cation of the phase-to-earth and phase-to-phase distances.
As for the IEEE standard, to determine the minimum recommended phase-to-phase and phase-
to-earth clearance distances, the following steps are required:
Substation Methodology 24
Chapter 4. Insulation Coordination
1. Determination of the Basic Lightening impulse level (BIL) and the Basic Switching Impulse
Insulation level (BSL) by applying protective margin and atmospheric correction factors.
2. Identi�cation and selection of the standard rated withstand voltages in regards to the BIL
and BSL by referring to the highest voltages for the equipment.
3. If some required voltages are higher than the maximum standard rated withstand voltage
for a speci�c highest voltage for equipment, a greater value of the standard voltage is
selected even though the highest voltage is superior.
4. Selection of the minimum rod-rod clearance distances for the standard rated withstand
voltages considering phase-to-earth and phase-to-phase con�gurations.
5. Identi�cation of the phase-to-earth and phase-to-phase distances.
• Earth faults.
• Load rejections.
• Resonance.
• Synchronization.
• A combination of the previous e�ects.
For voltage systems higher than 36 kV, earth faults and load rejections are the two main sources
that cause temporary overvoltages. The earth fault and the load rejection factors can be deter-
mined by grid studies. As the grid characteristics are unknown, these factors are estimated.
The maximum representative phase-to-earth and phase-to-phase overvoltages are calculated us-
ing Equation 4.1 and Equation 4.2
Substation Methodology 25
Chapter 4. Insulation Coordination
: max · * m
* temp-rp-pe = p (4.1)
3
* temp-rp-pp = :d · *m (4.2)
Where:
For voltage systems lower than 36 kV, the maximum phase-to-earth representative overvoltages
are caused by earth faults, often reaching the highest voltages for equipment. Regarding phase-
to-phase overvoltages, discharge faults are considered as the main overvoltage source.
The representative phase-to-earth and the phase-to-phase overvoltages are calculated using Equa-
tion 4.3 and Equation 4.4.
* temp-rp-pe = : · * m (4.3)
* temp-rp-pp = : d · * m (4.4)
Where:
Determination of 2% overvoltages
The value of the phase-to-earth overvoltage that has a 2% of probabilities of being exceeded is
estimated as the average of the values represented in Figure 4.1. The value that has been selected
is D e2 = 2.6 p.u.
The phase-to-phase overvoltage that has 2% of probabilities of being exceeded is given in Fig-
ure 4.2.
Substation Methodology 26
Chapter 4. Insulation Coordination
Figure 4.1: Range of 2% slow-front overvoltages at the receiving end due to line energization and
re-energization [11]
There are two methods to estimate the representative probability distribution from the 2% over-
voltage phase-to-earth value. These are the phase-peak method and the case-peak method. The
phase-peak method has been chosen to calculate the truncation values using Equation 4.5 and
Equation 4.6:
Where:
The parts per one are converted to volts following the Equation 4.7
r
2
*V = · * m · D p.u. (4.7)
3
Substation Methodology 27
Chapter 4. Insulation Coordination
Figure 4.2: Ratio between the 2% values of slow-front overvoltages phase-to-phase and phase-
to-earth. The upper part may be applied to three-phase re-energization, the lower part to ener-
gization. [11]
Where:
• * V is an overvoltage. [V]
• * m is the highest voltage for equipment. [V]
• D p.u is an overvoltage in p.u.
As the lightning arrester has been chosen following the process in section 6.3.1, the switching
impulse protective level equals * ps .
After computing the probability overvoltages, a comparison between the switching impulse pro-
tective level * ps of the lightning arrester and the truncated values of the probability overvoltages
is done in order to obtain the representative overvoltages for slow-front impulses. Equation 4.8
and Equation 4.9 are used.
Where:
Substation Methodology 28
Chapter 4. Insulation Coordination
Where:
Moreover, the coordination factor for slow-front impulses can be determined considering the
relation between the switching impulse protective level * ps and the phase-to-earth and phase-
to-phase 2% distribution overvoltages: * e2 and * p2 . The coordination factor is obtained from
Figure 4.3.
The coordination slow-front overvoltages are obtained from Equation 4.12 and Equation 4.13.
Substation Methodology 29
Chapter 4. Insulation Coordination
Where:
The coordination overvoltages for fast-front impulses proceed as given in Equation 4.14.
· 5s !t
* �-cw = * pl + · (4.14)
# !sp + !f
Substation Methodology 30
Chapter 4. Insulation Coordination
Where:
'a
!f = (4.15)
'km
Where:
According to [14], the values for these parameters can be found in Table 4.3.
Table 4.3: Example for protective zone for air-insulated substations. [14]
Higest voltage [kV] A [kV] 5s N !t [m] !sp [m] 'a [1/year] 'km [1/m.year]
36 2700 0.5 1 3 100 0.25 % 0.006 %
100 2700 0.5 1 15 200 0.25 % 0.001 %
245 4500 0.5 1 30 300 0.25 % 0.001 %
420 7000 0.5 1 30 300 0.25 % 0.001 %
800 11000 0.5 1 40 400 0.2 % 0.00015 %
As the lightning arrester has been presented in section 6.3.1, the lightning impulse protective
level is obtained depending on the nominal discharge current of the lightning arrester.
For nominal currents nom = 10 kA and nom = 20 kA, the corresponding lightning impulse
protective levels are * pl = * pl-10kA and * pl = * pl-20kA respectively.
Substation Methodology 31
Chapter 4. Insulation Coordination
insulation behavior during operation conditions and test conditions, and a correction factor that
considers atmospheric conditions.
The safety correction factors that are applied to each kind of overvoltage: temporary, slow-front
and fast-front, are given in Equation 4.16 and Equation 4.17 respectively.
si = 1.15 (4.16)
se = 1.05 (4.17)
Where:
The atmospheric e�ect is based on the air pressure’s dependence on the altitude. This factor’s
measurement is applied to measure the di�erences in the air dielectric strength as the altitude
increases. Moreover, the atmospheric correction factor can be calculated using Equation 4.18.
✓ ◆
a = exp < · (4.18)
8150
Where:
The results are a set of required withstand voltages for external and internal insulation and for
phase-to-earth and phase-to-phase voltages. They are given by Equation 4.19
* rw = a · s · * cw (4.19)
Where:
Substation Methodology 32
Chapter 4. Insulation Coordination
Figure 4.4: Dependence of exponent m on the coordination switching impulse withstand voltage
[11]
According to class I, the switching impulse withstand voltages are converted to short duration
power frequency withstand voltages and to lightning impulse withstand voltages by applying
the factors given in Table 4.4
Table 4.4: Test conversion factors for range I, to convert required switching impulses withstand
voltages to short-duration power-frequency and lightning impulse withstand voltages [11]
Short duration
Lightning impulse
Insulation type power frequency
Withstand voltage
withstand voltages
External Insulation: Clean and Dry Insulation
0.6 + * rw
1.05 + * rw
phase-to-earth 8500000 6000000
The same principle applies to class II where the short-duration power frequency withstand volt-
ages are converted to switching impulse withstand voltages. In this case, the considered factors
are given in Table 4.5
Substation Methodology 33
Chapter 4. Insulation Coordination
Table 4.5: Test conversion factors for range II, to convert required short-duration power-
frequency withstand voltages to switching impulse withstand voltages [11]
Switching impulse
Insulation type
Withstand voltage
External Insulation Clean: and Dry Insulation 1.4
Internal Insulation: Liquid-immersed Insulation 2.3
The standard withstand voltages for class I substation can be found in Table 4.6. For class II
substations, the reference values are presented in Table 4.7.
The withstand voltages are necessary to obtain the minimum phase-to-earth and phase-to-phase
clearance distances. The clearance distances are required to establish the minimum safety dis-
tances between the elements of the substation.
Substation Methodology 34
Chapter 4. Insulation Coordination
Substation Methodology 35
Chapter 4. Insulation Coordination
Substation Methodology 36
Chapter 4. Insulation Coordination
The tables 4.8, 4.9, and 4.10 present the minimum clearances that ensure the speci�cations of the
insulation coordination.
Table 4.8 associates the standard rated lightning impulse withstand voltages for the substation of
class I with the minimum air clearances for rod-structure and conductor-structure con�gurations.
Moreover, Table 4.9 links the standard rated switching impulse withstand voltages phase-to-earth
with the minimum air clearances for the conductor-structure and the rod-structure con�gura-
tions. Finally, Table 4.10 correlates the air clearances with the standard rated switching impulse
withstand voltages phase-to-phase for the conductor-conductor and rod-conductor con�gura-
tions.
Substation Methodology 37
Chapter 4. Insulation Coordination
Table 4.8: Correlation between standard rated lightning impulse withstand voltages and mini-
mum air clearances for class I [9], [10]
Substation Methodology 38
Chapter 4. Insulation Coordination
Table 4.9: Correlation between standard rated switching impulse withstand voltages and mini-
mum phase-to-earth air clearances [9], [10]
Table 4.10: Correlation between standard rated switching impulse withstand voltages and mini-
mum phase-to-phase air clearances for class II [9], [10]
For class I systems, the phase-to-earth and phase-to-phase air distances are calculated using
Equation 4.20 and Equation 4.21.
Where:
Substation Methodology 39
Chapter 4. Insulation Coordination
3 pp = 3 rod-str (4.21)
Where:
For class II substations, the phase-to-earth and phase-to-phase air distances are calculated using
Equation 4.22 and Equation 4.23.
Where:
Where:
Substation Methodology 40
Chapter 4. Insulation Coordination
The temporary voltages for phase-earth and phase-phase are calculated using Equation 4.24 and
Equation 4.25.
: max · * m
* temp-pe = (4.24)
a
: max · * m
* temp-pp = (4.25)
a
Where:
✓ ◆
X = exp (4.26)
8.9
Where:
* pl
⌫ != (4.27)
:a
Where:
Substation Methodology 41
Chapter 4. Insulation Coordination
As the lightning arrester has been presented in section 6.3.1, the lightning impulse protective
level is obtained depending on the nominal discharge current of the lightning arrester.
For nominal currents nom = 10 kA and nom = 20 kA, the corresponding lightning impulse
protective levels are * pl = * pl-10kA and * pl = * pl-20kA respectively.
The �rst parameter that must be de�ned in the calculation of the BSL is the strength-to-stress
ratio which represents a ratio between the statistical switching overvoltage and the statistical
withstand voltage. The statistical switching overvoltage depicts the minimum insulation strength
required and it is de�ned as ⇢ 2 for the phase-to-earth and the stress ⇢ 2z for the phase-to-phase
insulation. As for the statistical withstand voltage, it is the maximum surge voltage applied to the
equipment and it is de�ned as +3 for the phase-to-earth and +30 for the phase-to-phase insulation.
The determination of the ratio depends on the switching surge �ashover rate (SSFOR) that rep-
resents the number of �ashover per number of applied switching. Therefore, for a giving SSFOR,
a strength-to-stress ratio is determined; in the presented calculation considering a self-restoring
insulation, an SSFOR of 1/100 was chosen.
Based on [12] considering a 1/100 �ashover rate and the use of a surge arrester, the ratio that
has been selected for phase-to-earth insulation is +3 /⇢ 2 = 0.96 p.u and for the phase-to-phase is
+30 /⇢ 2z = 0.94 p.u.
The switching overvoltages are statistically analyzed to obtain a probability of 2% of being ex-
ceeded and this value is the statistical withstand voltage ⇢ 2 for the phase-to-earth and the stress
⇢ 2z for the phase-to-phase insulation.
With the SSFOR of 1/100 chosen and according to [12] the value that has been selected for the
phase-to-earth is ⇢ 2 = 2.59 p.u .
On the other hand, the value of the stress ⇢ 2z is determined from the ratio of the phase-to-phase
statistical switching overvoltages ⇢ 2z /⇢ 2 . In addition, this ratio is determined according to [12];
because the ⇢ 2z values vary between the range of 2 p.u and 3 p.u and the ⇢ 2z /⇢ 2 ratio varies
between 1.3 p.u and 3 p.u; therefore, the value that has been selected for the ratio is ⇢ 2z /⇢ 2 =
1.55?.D. Moreover, the value of ⇢ 2 is kept as 2.59 p.u; hence, ⇢ 2z can then be calculated from the
Equation 4.28
⇢ 2z = ⇢ 2 · 1.55 (4.28)
Where:
Substation Methodology 42
Chapter 4. Insulation Coordination
As all the voltage are per unit, they are converted to volts following the Equation 4.7.
The strength of the insulation is characterized by two main parameters which are the coe�cient
of variation ff /CFO and the critical �ashover voltage CFO. for a switching surge �ashover rate
SSFOR = 1/100, and based on [12] the coe�cient of variation is assumed to be 0.07 for the phase-
to-earth insulation and 0.035 for the phase-to-phase insulation.
As we mentioned above, the strength of the insulation is characterized by two parameters and one
of them is the critical �ashover voltage CFO that corresponds to the 50% probability of �ashover
for a single impulse application. The CFO for the phase-to-earth and phase-to-phase are calcu-
lated using Equation 4.29 and Equation 4.30 respectively.
+3
⇠ $ pe = (4.29)
1 3 · ⇠ff$
Where:
+30
⇠ $ pp = (4.30)
1 3 · ⇠ff$
Where:
After determining all the parameters discussed above, based on [13] the BSL phase-to-earth and
phase-to-phase are calculated using the Equation 4.31 and Equation 4.32 respectively.
Where:
Substation Methodology 43
Chapter 4. Insulation Coordination
Where:
The standard withstand voltages for class I substation can be found in Table 4.11. As for class II
substations, the reference values are presented in Table 4.12.
The withstand voltages are necessary to obtain the minimum phase-to-earth and phase-to-phase
clearance distances. Those distances are signi�cant to establish the minimum safety distances
between the elements of the substation.
Substation Methodology 44
Chapter 4. Insulation Coordination
Highest Voltage Standard rated low frequency, short duration Standard rated lightning
for equipment power frequency withstand voltages impulse withstand voltage BIL
[kV] [kV] [kV]
30
1.2
45
60
5
75
95
15 34
110
26.2 50 150
36.2 70 200
48.3 95 250
95 250
72.5
140 350
140 350
121 185 450
230 550
185 450
145 230 550
275 650
230 550
169 275 650
325 750
275 650
325 750
360 825
242
395 900
480 975
1050
On one hand, for the substation class I, the phase-to-earth clearance distance is calculated based
on the basic impulse lightening voltage following Equation 4.33. Moreover, the standard min-
imum clearances presented in IEEE are based on a CFO value of 605 kV/m, a value which has
been found to represent the typical geometry for an air-insulated substation.
2 ·⌫ !
( pe = (4.33)
⇠ $
Where:
Substation Methodology 45
Chapter 4. Insulation Coordination
Based on [13], the phase-to-phase clearance distance is calculated following Equation 4.34.
( pp = 1.1 · ( pe (4.34)
Where:
On the other hand, for substations of class II, few parameters must be determined for the calcu-
lation of the clearance distances.
The �rst parameter to be de�ned is the gap factor, in [12] typical gap factors for phase-to-earth
and phase-to-phase insulation are presented; hence, the gap factor considered is for the horizon-
tal rod-rod con�guration with a value of g = 1.35 for both insulations.
The other parameter is the re-calculated CFO after the selection of the standard BSL; in this
case, the CFO is calculated following Equation 4.35 and Equation 4.36 for phase-to-earth and
phase-to-phase insulation respectively.
⌫(!upe
⇠ $ re-pe = (4.35)
5pe
Where:
⌫(!upp
⇠ $ re-pp = (4.36)
5pp
Where:
Moreover, the atmospheric correction factor is taken into consideration when the substation is
above sea level. The correction factor is calculated using Equation 4.37.
✓ ◆
m <§
X = exp (4.37)
8.9
Substation Methodology 46
Chapter 4. Insulation Coordination
Where:
Having the re-calculated CFO, the gap factor, and the atmospheric correction factor, the clearance
distances are calculated based on the basic impulse switching voltage following Equation 4.38 and
Equation 4.39 for phase-to-earth and phase-to-phase respectively.
8
( pe = (3400 gX m )
(4.38)
⇠ $ re-pe 1
Where:
8
( pp = (3400 gX m )
(4.39)
⇠ $ re-pp 1
Where:
Substation Methodology 47
Chapter 4. Insulation Coordination
Table 4.13: Correlation between standard rated lightning impulse withstand voltages and mini-
mum air clearances for class I and II [13]
Substation Methodology 48
Chapter 4. Insulation Coordination
Table 4.14: Correlation between standard rated switching impulse withstand voltages and mini-
mum air clearances for class II [13]
Finally, once the standard phase-to-earth and phase-to-phase clearance distances based on the
BSL and BIL voltages are selected, the adopted phase-to-earth and phase-to-phase distances will
be the maximum selected ones; determined following Equation 4.40 and Equation 4.41.
Where:
Where:
Substation Methodology 49
Chapter 5. Safety Distances
Chapter 5
Safety Distances
In this chapter, the safety distances within the substation will be de�ned and derived from the
phase-to-earth and phase-to-phase distances calculated in Chapter 4. These safety distances will
be presented as the minimum distance between the elements located at the substation. A method
according to [15] will be followed for the calculation; however, there may be discrepancies be-
tween the concerned utility and the general model presented due to speci�c or local conditions
or procedures established by the local standards.
5.1 Introduction
There are di�erent methods to determine the safety distances between the elements of a substa-
tion. These safety distances may vary depending on the utility due to the particularity of each
national operating voltages. In this chapter, a generic model to compute the safety clearances is
presented according to [15]. The method of application takes into account not only the voltage
levels but also the operating conditions of the equipment as well as a factor that considers the
movement of the sta� in all three dimensions.
The safety distance is the minimum distance that should be maintained between a live part of the
conductor and the earth or another piece of the equipment. The safety distance is the sum of two
values: a basic value and a factor that considers the movement of the sta� during maintenance,
as shown in Figure 5.1.
• The basic value represents the limit of the danger zone for electrical disturbances and it is
related to the impulse withstand voltage. Depending on the value of this voltage, a safety
coe�cient will be applied to the phase-to-earth clearance that is obtained in Section 4.8.
• The other factor de�nes a safety zone and it is a function of the movements made by the
operators during maintenance. The safety zone determines a zero electrical risk zone for
the authorized personnel.
Substation Methodology 50
Chapter 5. Safety Distances
Figure 5.1: The safety distance is made up of two values: basic value and safety zone for sta�.
Source: Own elaboration from the data provided by [15].
The substation dimensions that came out of this study are the following ones, presented in Fig-
ure 5.2:
• The height of the switchgear. This is the �rst height level of the substation.
• The distance between devices in the bay direction.
• The distance between the conductors.
• The height of the busbar. This is the second height level of the substation.
• The distance between the conductors.
• The busbar span.
Substation Methodology 51
Chapter 5. Safety Distances
Figure 5.2: The safety distance in the substation �eld. Source: Own elaboration.
• The height of the gateway. This is the third height level of the substation.
• The distance between the conductors.
• The gateway span.
• The average height of a worker with his arms raised all the way up and that is equivalent
to r = 2.25 m.
• The average length of a worker with his arms outstretched, that is !o = 1.75 m.
• The average height of a worker with his arms raised to a work of plane, that is rw =1.25
m.
3 bv = 5bv · 3 pe (5.1)
Substation Methodology 52
Chapter 5. Safety Distances
Where:
⌘ device = 3 bv + r (5.2)
Where:
Where:
Where:
An estimation of the safety distance from the extreme position that the live equipment or con-
ductor may occupy to the edge of the following equipment is derived from the same principle
represented in Equation 5.5. However, this safety zone value should never be lower than 3.0 m.
Substation Methodology 53
Chapter 5. Safety Distances
Where:
Where:
Once the distance between conductors has been established, the busbar/gateway span is derived
from Equation 5.7.
Where:
Substation Methodology 54
Chapter 6. Substation Equipment
Chapter 6
Substation Equipment
The power transformer is by far the most important equipment installed in the step up substation.
As the possibilities of selecting a power transformer are immense, a �rst scope is to determine
its basic parameters such as power, short-circuit impedance, and voltage levels based on [16],
[4] and [17] in obedience to the IEC standard and based on [18] and [19] according to the IEEE
standard. A detailed study that would take into account the noise produced by the transformer,
its cooling system, its insulation system or the tap changers is out of the scope. As a summary:
• The rated power of the transformer is equal to the power of the transformer bay.
• The short-circuit impedance is de�ned in Table 6.1 and Table 6.2 according to the IEC and
IEEE standards respectively.
• The high voltage and medium voltage are chosen by the user.
• An oil-�lled power transformer is considered.
• According to [15], the vector group for the step up transformer is Yd11.
• The primary winding will be solidly grounded. The secondary winding will be connected
to earth with an earthing resistance and a reactance.
Substation Methodology 55
Chapter 6. Substation Equipment
Table 6.1: Recognized minimum values of short-circuit impedance for transformers with two
separate windings according to IEC. [4]
Table 6.2: Recognized minimum values of short-circuit impedance for transformers with two
separate windings based on the BIL according to IEEE. [18]
For the impedance calculation of the three-winding power transformer, the total capacity con-
nected to the secondary winding is considered. The impedances of the secondary windings are
calculated based on that of the primary winding. The impedance percentage is the same for all
the parallel transformers.
The capacity is assigned in an equal way between the two secondary windings. Hence, the
number of the MV lines connected to both windings is similar in most cases.
The secondary short circuit current is calculated the same way as in the two-winding transformer,
and it is considered for both secondary and tertiary windings.
Substation Methodology 56
Chapter 6. Substation Equipment
The main objective of an earthing device is to limit the earth fault currents. Furthermore, zig-zag
transformers are one of the most commonly models used to ground a delta secondary winding of
a transformer. Again, the neutral point of the zig-zag transformer can be connected to the ground
by using a resistance. Hence, to calculate the reactance per phase of the zig-zag transformer as
well as its resistance that will later connect its neutral point to the ground, the following steps
have been followed.
According to [20], the parameter for rating the zig-zag transformer must be the thermal current.
This is the current that �ows through the neutral grounding reactor during a worst-case ground-
fault scenario and it has been de�ned as the short-circuit current of the system.
To obtain the rated continuous current that can �ow through the zig-zag transformer, [20] rec-
ommends to multiply the short-circuit current per the values that are presented in Table 6.3.
Table 6.3: Continuous current in percent of thermal current rating [%]. [20]
In addition, there are standard values for continuous currents of grounding devices such as 100,
300, 500, 800, 1000 or 2000 A. Moreover, the duration of the fault considered is 10 seconds; hence,
a 3% is applied to get the continuous current using Equation 6.1. After calculating zig-zag , the
closest major standard value is chosen.
Where:
• zig-zag is the rated continuous current that can �ow through the zig-zag transformer. [A]
• sc is the short-circuit current. [A]
- 0 /- 1 · * mv
-g = p (6.2)
3 · sc
Where:
Substation Methodology 57
Chapter 6. Substation Equipment
* mv
'g = p (6.3)
3 · zig-zag
Where:
The protective level of a surge arrester has to be determined to withstand lightning overvoltages
or high voltages due to switching events. However, during normal operation, they do not have
e�ect on the electrical system. The surge arrester chosen is a metal oxide surge arrester.
The appropriate arrester has to be designed based on a detailed analysis of the protective charac-
teristics required. In order to size the arrester in accordance to the IEC and the IEEE standards,
[14], [22], [23] and [24] have been studied. Some of the most important parameters that must be
calculated are the following ones:
• The rated voltage is the maximum permissible value at which the terminals of a surge
arrester are designed to operate correctly under temporary overvoltages conditions.
• The continuous operation voltage is, usually, the maximum system line-to-ground voltage
for metal oxide surge arresters.
• The capability of the surge arrester to withstand temporary overvoltages. These are power
frequency overvoltages of long duration.
• The nominal discharge current that is the current that �ows through the arrester due to a
surge.
• The lightning and switching impulse protection levels for di�erent nominal discharge cur-
rents.
Substation Methodology 58
Chapter 6. Substation Equipment
5cov · * m
* cov p (6.4)
3
Where:
The next step is to get the temporary overvoltage for the lightning arrester using Equation 6.5.
The temporary overvoltages are produced by earth faults and load rejection. For this purpose, a
TOV factor that takes into account the di�erent overvoltages’ origin will be estimated; and to do
so, the system will be considered as solidly grounded. [22]
Where:
The capability to withstand temporary overvoltages is given based on the equivalent 10 seconds
duration overvoltage, which is calculated using the equation Equation 6.6.
⇣ g ⌘[
* 10s = * tov · (6.6)
10
Where:
The rated voltage of the lightning arrester will be taken as the maximum between the equivalent
10 seconds duration overvoltage and the continuous operating voltage multiplied by a factor of
1.25, as shown in Equation 6.7.
Where:
Substation Methodology 59
Chapter 6. Substation Equipment
The nominal discharge current will be nom = 10 kA for * m 360 kV and nom = 20 kA for
* m > 360 kV, according to [14].
To complete the process of calculating the lightning arrester, a database of commercial lightning
arresters has been added to the software: [22], [25] and [26].
The type of the circuit breaker a�ects the layout and con�guration of the substation. Circuit
breakers are usually classi�ed as dead tank when their terminals are grounded or live tank when
the interrupting mechanisms are mounted on an insulating porcelain column at line potential.
The rated voltage of the circuit breaker is the maximum voltage for which the breaker is designed.
It is given by Equation 6.8.
* cb = * m (6.8)
Where:
The rated normal current is the current that the circuit breaker can carry permanently under
normal conditions of service. It is calculated by Equation 6.9. After obtaining the current, a R10
series standard current will be selected. [31]
5s · %
cb = p (6.9)
*· 3
Where:
The rated short-circuit breaking current is the highest current that the circuit-breaker is able to
break under certain conditions of behaviour prescribed in international standards. It is calculated
by Equation 6.10.
Substation Methodology 60
Chapter 6. Substation Equipment
sc-cb = sc (6.10)
Where:
• sc-cb is the rated short-circuit breaking current of the circuit breaker. [A]
• sc is the design short-circuit current. [A]
The rated frequency of the system that will be considered for calculating the rated short-circuit
making current. The rated short-circuit making current is equal to the rated short-circuit break-
ing current multiplied by a factor, given in Equation 6.11.
Where:
• msc-cb is the rated short-circuit making current of the circuit breaker. [A]
• 5msc is a factor equals to 2.5 if the frequency is 50 Hz and 2.6 if frequency is 60 Hz.
• sc-cb is the rated short-circuit breaking current of the circuit breaker. [A]
6.5 Disconnectors
A disconnector is an o�-load device without the capacity to break the electric circuit. There is a
signi�cant variety of disconnectors for use in outdoor substations. The selection of a disconnec-
tor will depend on the physical layout and on the space restrictions.
Disconnectors can be classi�ed as single or double break with horizontal or vertical isolation.
The most common type of double break disconnectors and the one chosen for pvDesign is the
rotating center post.
To design a disconnector, the main characteristics are de�ned according to [27] and [32] for the
IEC standard and to [30] for the IEEE standard.
The rated voltage is the maximum voltage for which the disconnector is designed. It is given by
Equation 6.12.
*d = *m (6.12)
Where:
The rated normal current is the current that the disconnector can carry permanently under nor-
mal conditions of service. It is calculated by Equation 6.13. After obtaining the current, a R10
series standard current will be selected [31].
Substation Methodology 61
Chapter 6. Substation Equipment
5s · %
d = p (6.13)
*· 3
Where:
The rated short-time withstand current is the current that the disconnector will be required to
carry for one cycle. It is calculated by Equation 6.14.
sc-d = sc (6.14)
Where:
The rated peak withstand current that is equal to the rated short-time withstand current multi-
plied by a factor, given in Equation 6.15.
Where:
The main functions of these devices are to transform the current of high voltage systems to a
value that a relay can measure and to insulate the metering circuit from high voltage systems.
The ideal location of a current transformer within the substation is generally as close as possible
to the equipment to be protected and measured. For dead tank circuit breakers, the secondary
winding of the instrument transformer is mounted over the same structure. For live tank circuit
breakers, the current transformer is usually installed in a separate mounting structure.
The current transformers can be grouped into two categories: metering service and relay ser-
vice. On one hand the current transformers designed for metering services are not prepared for
Substation Methodology 62
Chapter 6. Substation Equipment
protecting services. On the other hand, current transformers used for relay services should not
be used for high-accuracy metering applications.
To design a current transformer, the main characteristics are de�ned according to [33] and [34]
conforming to the IEC standard and according to [35] and [36] for the IEEE standard. In the
latter, the calculations and standard values are applicable only at 60 Hz.
The rated voltage is the maximum voltage for which the current transformer is designed. It is
given by Equation 6.16.
* ct = * m (6.16)
Where:
The rated primary current that the current transformer has to withstand in continuous operation
is calculated by Equation 6.17. After obtaining the current, the closest standard current will
be selected depending on the chosen standard. [34] [35]. In this case, The R10 values are not
followed.
5s · %
ct = p (6.17)
*· 3
Where:
According to the IEC standard, the rated secondary current can be 1 A or 5 A. When instruments
or relays are close to the protected or measured device, the secondary selected current is 5A.
However, 1 A is preferably selected when the distance between the device and the instrument
transformer is above 10 m. As control units are not calculated at the moment, 5 A is chosen. As
for the IEEE standard, the rated secondary current is always 5 A.
The rated continuous thermal current is the current that �ows in the primary winding with
temperature rise exceeding standard requirements. In general it is equal to the primary current.
It is given by Equation 6.18.
t = ct (6.18)
Where:
Substation Methodology 63
Chapter 6. Substation Equipment
The rated short-time thermal current is the maximum current that it can withstand for a period
of one second without breaking the insulator. If it is not speci�ed, it can be equal to the system’s
short-circuit current. It is given by Equation 6.19.
sc-ct = sc (6.19)
Where:
The �rst peak of current during a short-circuit event is the dynamic current. It can reach 2.5
times the rated short-time thermal current in obedience to the international standard and 2.7
times the same rated current according to the IEEE standard . It is given in Equation 6.20.
Where:
On one hand, the IEC standard [34] is used for de�ning the burdens and accuracies. The possible
burdens are 2.5, 5, 10, 15, 30 VA. The metering accuracies are 0.2, 0.2s, 0.5 and 0.5s and the
protection accuracies are 5P and 10P. Burdens for protection services will be higher than those
used for metering services.
On the other hand, the IEEE standard [35] is used for de�ning the burdens, designations, and
accuracies. The possible burdens are 2.5, 5, 12.5, 22.5, 45 VA. The corresponding assignations are
B-0.1, B-0.2, B-0.5, B-0.9, B-1.8. The metering accuracies are 0.15s, 0.15, 0.15N, 0.3s, 0.3, 0.6, and
1.2 and the protection accuracies are C100, C200, C300, C400, C500, C600, C700, C800. Burdens
for protection services will be higher than those used for metering services.
Substation Methodology 64
Chapter 6. Substation Equipment
The primary voltage is the voltage of the system, given in Equation 6.21
*
* vt = p (6.21)
3
Where:
According to the IEC standard [37], the secondary rated current of the equipment can be 100 or
110 V. Di�erently, the IEEE standard states that the secondary rated current can be 115 when
the voltage is above 25 kV and 120 V when it is up to 25 kV [35]. Regarding both high and low p
voltage, the single-phase line to ground voltage will be taken, that is, the voltage divided by 3
in case of a star connection and by 3 for delta windings.
The standards [37] and [38] have been followed to de�ne the burdens and accuracies for the in-
ternational standard and [35] has been followed to de�ne the burdens, assignations, and accuracy
classes according to the IEEE standard.
As reported by the IEC, the burdens are 1, 2.5, 5, 10, 25 50, 100 VA. The accuracy classes are 0.1,
0.2, 0.5, 1, 3 for metering purposes;3P and 6P for protection services; and 0.5-3P for metering/pro-
tection services.
With regard to the IEEE standard, the burdens are 12.5, 25, 35, 75, 200, 400 VA and their corre-
sponding designations are W, WX, WXM, WXMY, WXMYZ, WXMYZZ. In addition, the accuracy
classes are 0.15, 0.3, 0.6, and 1.2 for metering purposes and 1.2 for protection purposes.
For both standards, these cores follow the same principles applied for current transformers: bur-
dens for protection services will be higher than those used for metering services.
6.8 Cables
The cables that connect the primary medium voltage cubicles with the power transformers are
calculated based on the IEC [40] or NEC [41] standards. The cables will be sized following three
criteria:
The most signi�cant criterion that a�ects the high power cables is the maximum current-carrying
capacity. For more details about how to size the cables, it is recommended to read the electri-
Substation Methodology 65
Chapter 6. Substation Equipment
cal methodology which is available in pvDesign. In this document, only the most important
parameters to size the cables are mentioned:
Substation Methodology 66
Chapter 7. Design of the bus in air insulated substations
Chapter 7
This chapter describes the process for designing the busbar of an air-insulated substation based
on main standards such as IEC and IEEE as well as practical guides such as Cigré technical
brochures. Therefore, the objective is to obtain the dimensions of a rigid bus, the forces acting on
the bus structure, and the information related to the busbar’s technical properties: corona e�ect,
thermal short-circuit e�ects, among others. This chapter will provide the necessary information
to calculate the dimensions of a rigid bus.
7.1 Introduction
The following example clari�es the process of designing a rigid busbar for an air-insulated sub-
station using the information presented in [42] and [43]. The parameters required for the bus
design are:
With the parameters listed above, the rigid bus’ dimensions are obtained. In addition, the fol-
lowing design parameters are determined:
• The bus conductor size that withstands both the load current and the short circuit current.
Substation Methodology 67
Chapter 7. Design of the bus in air insulated substations
Table 7.1: Technical characteristics of 6063 T6 aluminium tubes for substations. [44]
2
3 ext 2
3 int
c =c· (7.1)
4
Where:
Substation Methodology 68
Chapter 7. Design of the bus in air insulated substations
4
3 ext 4
3 int
(c = c · (7.2)
32 · 3 ext
Where:
4
3 ext 4
3 int
=c· (7.3)
64
Where:
D bus = F Al · c (7.4)
Where:
5growth · % ac
load = p (7.5)
* hg · 3
Where:
Substation Methodology 69
Chapter 7. Design of the bus in air insulated substations
• load is the load current that the bus will carry. [A]
• 5growth is a factor that equals 1.25.
• %ac is the installed capacity of the photovoltaic plant. [W]
• * hg is the high voltage level. [V]
For an acceptable design, the condition given in Equation 7.6 has to be ful�lled.
Where:
• load is the load current that the bus will carry. [A]
• bus is the ampacity given in Table 7.1. [A]
s ✓ ◆
1 )f 20 + 15150/⌧
bus sc = ⇠ · 1012 · c · log10 (7.7)
C )i 20 + 15150/⌧
Where:
• sc bus is the short-circuit current that the bus is able to withstand. [A]
• ⇠ is a constant that is equal to 2.232 ·106 .
• C is the assigned short-circuit time given in Section 3.4, which is equal to 1. [s]
• c is the conductor area. [m2 ]
• ⌧ is the conductivity for aluminium that is equal to 53%.
• )f is the maximum conductor temperature and it is equal to 250. [ºC]
• )i is the initial conductor temperature and it is equal to 90. [ºC]
For an acceptable operation, the condition given in Equation 7.8 has to be ful�lled.
sc bus sc (7.8)
Where:
Substation Methodology 70
Chapter 7. Design of the bus in air insulated substations
The maximum force acting on the conductor is therefore, the modulus of the sum of the forces
considered at the same time in both the vertical and horizontal direction.
The weight force by unit length on the bus is given by Equation 7.9.
Where:
The ice force by unit length on the bus is calculated based on [45].
Where:
In order to compute the short-circuit force by unit length, the calculation model in [43] has been
followed. First, the peak short-circuit current has been estimated by Section 3.3.
The maximum short circuit force by unit length on the buses is obtained according to Equa-
tion 7.10.
Substation Methodology 71
Chapter 7. Design of the bus in air insulated substations
p
`0 3 1 2
? m3 = peak (7.10)
2c 2 3 bus
Where:
The wind force by unit length on cylindrical surfaces is calculated using Equation 7.11.
✓ ◆2
+wind
? wind = 3 ext · %air · (7.11)
+ref
Where:
7.5.2 Reactions
The loads on the buses are transmitted to the insulators. Therefore, the strength of the insulator
has to be calculated. As the insulator is determined, the wind force on this element should be
considered when combining all the forces.
This section presents a simpli�ed method for analyzing the reactions of di�erent loads from a
static point of view. The forces to consider in the evaluation of the net reaction on an insulator
consist of what it follows.
The force that the insulator withstands will result from the combination of the gravitational,
wind, and short circuit loads on the bus. This force is obtained as a function of the e�ective
conductor’s span length supported by the insulator. In addition, the e�ective conductor’s span
length !E depends on the span length and the bus-support conditions.
Moreover, the bus-support conditions depend on the number of transformer bays. Hence, the
e�ective conductor span length !E is obtained using Equation 7.12. For a single span (that is
single bus bar con�guration with one transformer), the coe�cient is the maximum of the support
conditions’ values.
Substation Methodology 72
Chapter 7. Design of the bus in air insulated substations
Figure 7.1: The forces that a�ect the structure of a busbar. Source: Own elaboration
Where:
Table 7.2: Maximum reaction coe�cients for common bus arrangements. [42], [46]
Support conditions
Bus con�guration Reaction coe�cient
S1 S2 S3 S4 S5
P P 0.5
Single-span P F 0.625
F F 0.5
Two continuous-span P C P 1.25
Three continuous-span P C C P 1.1
Four continuous-span P C C C P 1.145
More than 4 1.145
For insulator P F 0.625
Substation Methodology 73
Chapter 7. Design of the bus in air insulated substations
The reactions on the supports due to the weight, ice, and wind loads by unit length are obtained
using Equation 7.13
= ? · !e (7.13)
Where:
The reactions on the supports caused by the short circuit current forces by unit length are ob-
tained using Equation 7.14
sc = ? r · !e (7.14)
Where:
? r = +r · +F · ? m3 (7.15)
Where:
The reactions on the bus supports caused by wind force on the insulators are obtained using
Equation 7.16.
wind insulator = ? wind insulator · !e insulator = ? wind insulator · ⇠ reaction insulator · !insulator (7.16)
Where:
• wind insulator is the force due to the wind on the insulators. [N]
• ? wind insulator is the force by unit length due to the wind on the insulators. [N/m]
• ⇠ reaction insulator is the reaction coe�cient for insulator obtained from Table 7.2.
• !insulator is the insulator length. [m]
Substation Methodology 74
Chapter 7. Design of the bus in air insulated substations
The total force on the bus supports is the results of the vector sum of all forces as shown in
Equation 7.17
q
2 2
T = weigth + ice +( sc + wind + wind insulator ) (7.17)
fT @ · y (7.18)
Where:
• fT is the total stress on the bus calculated from Equation 7.24. [N/m2 ]
• @ is a factor given by Equation 7.19.
• y is the tensile yield strength for aluminium that is equal to 185 ·106 [N/m2 ]
1 (1 2C/3 ext ) 3
@ = 1.7 (7.19)
1 (1 2C/3 ext ) 4
Where:
The stresses on the bus caused by gravitational and wind forces are obtained using Equation 7.20.
2
? · ⇠ stress · !sp
f= (7.20)
(c
Where:
• f is the mechanical stress caused by gravitational or wind forces by unit length on the bus.
[N/m2 ]
• ? is the gravitational or wind force by unit length. [N/m]
• ⇠ stress is the moment coe�cient given in Table 7.3.
• !sp is the span of the rigid bus. [m]
• ( c is the moment of resistance of the bus. [m3 ]
To obtain the mechanical stress on the bus caused by the short circuit load, the IEC standard [43]
has been followed and Equation 7.21 has been used.
Substation Methodology 75
Chapter 7. Design of the bus in air insulated substations
2
+f · +r · V · ? r · !sp
fsc = (7.21)
8( c
Where:
• fsc is the mechanical stress caused by the short circuit force by unit length on the insulator.
[N/m2 ]
• +f measures the ratio between dynamic and static stresses on the supports.
• +r measures the relation of the di�erent dynamic mechanical loads on the bus due to three-
phase tripping.
• V is a factor.
• ? r is is the equivalent static short-circuit force by unit length. [N/m]
• !sp is the length of the bus. [m]
• ( insulator is the moment of resistance of the bus. [m3 ]
The stress on the bus caused by the wind force on the insulator is obtained using Equation 7.22.
2
? wind · ⇠ stress insulator · !insulator
fwind insulator = (7.22)
( insulator
Where:
• fwind insulator is the mechanical stress caused by the wind force on the insulator. [N/m2 ]
• ? wind is the wind force on the insulator by unit length. [N/m]
• ⇠ stress insulator is the moment coe�cient given in Table 7.3.
• !insulator is the length of the insulator. [m]
• ( insulator is the moment of resistance of the insulator. The moment of resistance of the
insulator is obtained from Equation 7.23. [m3 ]
3 ext insulator
( insulator = c (7.23)
32
Where:
The total force on the bus supports is the result of the vector sum of all the forces as shown in
Equation 7.24
q
2
fT = fweigth + fice + (fsc + fwind + fwind insulator ) 2 (7.24)
Substation Methodology 76
Chapter 7. Design of the bus in air insulated substations
Table 7.3: Maximum stress coe�cients for common bus arrangements. [46]
Support conditions
Bus con�guration Moment coe�cient
S1 S2 S3 S4 S5
P P 1/6
Single-span P F 1/8
F F 1/12
Two continuous-span P C P 0.07
Three continuous-span P C C P 0.08
More than 3 0.08
For insulator P F 1/8
✓ ◆ 13
185 · ⇢ · · 5def
!v = (7.25)
?g
Where:
The de�ection limit is obtained from [44]. If there is no information regarding the de�ection
limit in the data sheet previously commented, a default value of 0.67% will be taken.
s
16 · · 5weld · u
!s = (7.26)
? T · 3 ext
Substation Methodology 77
Chapter 7. Design of the bus in air insulated substations
Where:
The allowable span for the rigid bus of the substation is the resulting minimum value, given in
Equation 7.27.
Where:
For an acceptable operation, the condition given in Equation 7.28 has to be ful�lled.
!sp ! (7.28)
Where:
• !sp is the span of the rigid bus, calculated in Subsection 5.2.5. [m]
• ! is the allowable span. [m]
As the ozone production and light emissions are unacceptable in some communities, and as
corona discharges causes audible noise and can not be eliminated, the right solution is to mitigate
and control these discharges to acceptable levels [42].
✓ ◆
⇠
⇢c = < · ⇢0 · ⇡a 1+ p · 100000 (7.29)
⇡ a · A ext
Substation Methodology 78
Chapter 7. Design of the bus in air insulated substations
Where:
✓ ◆ ✓ ◆
273 + )0
⇡a = · 1 (7.30)
273 + )amb 10000
Where:
⌘e
⇢m = · ⇢a (7.31)
⌘e 3 ext /2
Where:
⌘ busbar · 3 busbar
⌘e = q (7.32)
4⌘ 2busbar + 3 busbar
2
Where:
Substation Methodology 79
Chapter 7. Design of the bus in air insulated substations
1.1 · * hg 1
⇢a = p · ✓ ◆ (7.33)
3 3 ext 4 ⌘e
· ;=
2 3 ext
Where:
For an acceptable operation, the condition given in Equation 7.34 has to be ful�lled.
⇢m ⇢c (7.34)
Where:
( th = th / c (7.35)
Where:
On the other hand and based on [42], the assigned withstand short duration current density is
obtained from Equation 7.36.
s
1 ^ 202d 1 + U 20 (o e 20)
( thr = · · ln (7.36)
)kr U 20 1 + U 20 (o b 20)
Where:
Substation Methodology 80
Chapter 7. Design of the bus in air insulated substations
For a safe design, the condition given in Equation 7.37 has to be ful�lled.
r
)kr
( th ( thr (7.37)
)k
Where:
For a safe design, the condition given in Equation 7.38 has to be ful�lled. In addition, the maxi-
mum withstand voltage and the lightning impulse withstand voltage have to be higher than the
system voltage and the lightning impulse of the system.
T ( Bending (7.38)
Where:
Substation Methodology 81
Chapter 7. Design of the bus in air insulated substations
As an example, a group of post insulators that belong to the same lightning impulse family are
presented in Table 7.4
Substation Methodology 82
Bibliography
Bibliography
[1] Schneider Electric, “Power and distribution transformers,” Schneider Electric Industries
SAS, Catalogue, 2015.
[2] Technical Committee 73, “Short-circuit currents in three-phase a.c. systems - part 0: Cal-
culation of currents,” International Electrotechnical Commision, IEC 60909-0:2016, 2016.
[3] Technical Books Coordinating Committee, “Recommended Practice for Conducting Short-
Circuit Studies and Analysis of Industrial and Commercial Power Systems,” Institute of
Electrical and Electronics Engineers, IEEE 3002.3-2018, 2018.
[4] Technical Committee 14, “Power transformers - part 5: Ability to withstand short circuit,”
International Electrotechnical Commision, IEC 60076-5:2006, 2006.
[5] Viesgo, “Norma instalaciones de enlace en alta tension: lineas de alta tension (>36 kV) y
subestaciones,” Viesgo, Technical Speci�cation NT-IEAT.01, 2017.
[6] Viesgo, “Proyecto tpo de subestacionesc con aparamenta convencional,” Viesgo, Technical
Speci�cation PT-SECO.01, 2017.
[7] J. P. Fernandez and E. Iraburu, “Especi�caciones Particulares. Requisitos Tecnicos de Con-
struccion de Subestaciones conectadas a redes de Alta Tension de Un > 36 kV,” Union
Fenosa Distribucion, Technical Speci�cation IT.07974.ES-DE.NOR, 2017.
[8] Transformers Committee, “IEEE Standard for General Requirements for Liquid-Immersed
Distribution, Power, and Regulating Transformers,” Institute of Electrical and Electronics
Engineers, IEEE C57.12.00-2015, 2015.
[9] Technical Committee 99, “Amendment 1. insulation co-ordination. part 1 de�nitions, prin-
ciples and rules,” International Electrotechnical Commision, International Standard IEC
60071-1:2006, 2006.
[10] Technical Committee 99, “Amendment 1. insulation co-ordination. part 1 de�nitions, prin-
ciples and rules,” International Electrotechnical Commision, International Standard IEC
60071-1:2006/AMD1:2010, 2010.
[11] Technical Committee 99, “Insulation co-ordination. Part 2. Application guidelines,” Inter-
national Electrotechnical Commision, IEC 60071-2:2018, 2018.
[12] Technical Council of the IEEE Power Engineering Society, “IEEE Guide for the Application
of Insulation Coordination,” Institute of Electrical and Electronics Engineers, IEEE 1313.2-
1999, 1999.
Substation Methodology 83
Bibliography
[13] Substations Committee, “IEEE Guide for Recommended Electrical Clearances and Insula-
tion Levels in Air-Insulated Electrical Power Substations,” Institute of Electrical and Elec-
tronics Engineers, IEEE 1427-2006, 2007.
[14] Technical Committee 37, “Surge arresters. part 5 selection and application recommenda-
tions,” International Electrotechnical Commision, International Standard IEC 60099-5:2013,
2018.
[15] T. Krieg, J. Finn, and CIGRE Study Committee B3, Substations. Springer International Pub-
lishing, 2018.
[16] Technical Committee 14, “Power transformers - part 1: General,” International Electrotech-
nical Commision, IEC 60076-1:2011, 2011.
[17] Technical Committee 14, “Power transformers - part 20: Energy e�ciency,” International
Electrotechnical Commision, IEC 60076-20:2017, 2017.
[18] Technical Books Coordinating Committee, “IEEE Standard Requirements for Liquid-Immersed
Power Transformers,” Institute of Electrical and Electronics Engineers, IEEE C57.12.10-
2017, 2017.
[19] Transformers Committee, “IEEE Standard Requirements for Liquid-Immersed Distribution
Substation Transformers,” Institute of Electrical and Electronics Engineers, IEEE C57.12.36
- 2017, 2017.
[20] PE/TR - Transformers, “IEEE Standard for Requirements, Terminology, and Test Proce-
dures for Neutral Grounding Devices,” no. IEEE Std C57.32-2015, 2015.
[21] A. Granero. “Calculo de un transformador zig-zag con resistencia de puesta a tierra para
un sistema de media tension.” (2017), [Online]. Available: http://imseingenieria.blogspot.
com/2017/07/calculo-de-un-transformador-zig-zag-con.html.
[22] ABB, High Voltage Surge Arresters. Buyer s Guide, 2018.
[23] A. Granero. “Eleccion de autovalvulas de oxido de zinc (ZnO) en lineas de alta tension.”
(2015), [Online]. Available: http : / / imseingenieria . blogspot . com / 2015 / 08 / eleccion - de -
autovalvulas-de-oxido-de.html.
[24] Surge Protective Devices Committee, “IEEE Standard for Metal-Oxide Surge Arresters for
AC Power Circuits (>1 kV),” Institute of Electrical and Electronics Engineers, IEEE C62.11,
2012.
[25] Siemens, High-voltage surge arresters. Product guide, 2014.
[26] GE, IEEE/IEC Lightning Arrester. Arresters for AC and DC Applications, 2015.
[27] Technical Committee 17, “High-voltage switchgear and controlgear - part 1: Common
speci�cations,” International Electrotechnical Commision, International Standard IEC 62271-
1:2007, 2007.
[28] Technical Committee 17, “High-voltage switchgear and controlgear - Part 103: Switches
for rated voltages above 1 kV up to and including 52 kV,” International Electrotechnical
Commision, International Standard IEC 62271-103:2011, 2011.
[29] Technical Committee 17, “High-voltage switchgear and controlgear - Part 104: Alternat-
ing current switches for rated voltages higher than 52 kV,” International Electrotechnical
Commision, IEC 62271-104:2015, 2015.
Substation Methodology 84
Bibliography
[30] Switchgear Committee, “IEEE Standard for Ratings and Requirements for AC High-Voltage
Circuit Breakers with Rated Maximum Voltage Above 1000 V,” Institute of Electrical and
Electronics Engineers, IEEE C37.04, 2018.
[31] Technical Committee 8, “IEC standard current ratings,” International Electrotechnical Com-
mision, International Standard IEC 60059:1999, 1999.
[32] Technical Committee 17, “High-voltage switchgear and controlgear - Part 102: Alternating
current disconnectors and earthing switches,” International Electrotechnical Commision,
International Standard IEC 62271-102:2018, 2018.
[33] Technical Committee 38, “Instrument transformers - Part 1: General requirements,” Inter-
national Electrotechnical Commision, International Standard IEC 61869-1:2007, 2007.
[34] Technical Committee 38, “Instrument transformers - Part 2: Additional requirements for
current transformers,” International Electrotechnical Commision, International Standard
IEC 61869-2:2012, 2012.
[35] Transformers Committee, “IEEE Standard Requirements for Instrument Transformers,” In-
stitute of Electrical and Electronics Engineers, IEEE C57.13, 2016.
[36] IEEE Power System Relaying Committee, “IEEE Guide for the Application of Current
Transformers Used for Protective Relaying Purposes,” Institute of Electrical and Electron-
ics Engineers, IEEE C37.110, 1996.
[37] Technical Committee 38, “Instrument transformers - Part 3: Additional requirements for
inductive voltage transformers,” International Electrotechnical Commision, International
Standard IEC 61869-3:2011, 2011.
[38] Technical Committee 38, “Instrument transformers - Part 5: Additional requirements for
capacitor voltage transformers,” International Electrotechnical Commision, IEC 61869-5:2011,
2011.
[39] ABB, “Outdoor Instrument Transformers - Buyer’s guide,” 2008.
[40] Technical Committee 20, “Power cables with extruded insulation and their accessories for
rated voltages from 1 kV (Um = 1,2 kV) up to 30 kV (Um = 36 kV) - Part 2: Cables for rated
voltages from 6 kV (Um = 7,2 kV) up to 30 kV (Um = 36 kV),” International Electrotechnical
Commision, IEC 60502-2:2014, 2014.
[41] National Electrical Code Committee, “NFPA 70 National Electrical Code,” International
Standard, 2017.
[42] IEEE Substation Committee, “IEEE Guide for bus design in air insulated substations,” no. IEEE
Std 605-2008, 2008.
[43] Technical Committee 73, “Short-circuit currents - Calculation of e�ects - Part 1: De�nitions
and calculation methods,” International Electrotechnical Commision, IEC 60865-1:2011,
2011.
[44] Bronmetal, Tubos de aluminio para subestaciones eléctricas, 2019.
[45] Ministerio de Industria, Turismo y Comercio, “Reglamento de lineas electricas aereas de
alta tension,” BOE-A-2008-5269, 2008.
Substation Methodology 85
Bibliography
[46] M. T. Fernández, “Elaboración de fórmulas analíticas y tablas de cálculo para las estruc-
turas metálicas de acero según la normativa eurocódigo 3,” Master Thesis, Escola Tecnica
Superior Enginyeria Industrial de Barcelona, 2015.
[47] The Aluminum Association, Aluminum design manual, 2005.
[48] Porcelanas Industriales, Poinsa, Outdoor and indoor post insulators, 2019.
[49] Technical Committee 32, “Low-voltage fuses - Part 6: Supplementary requirement for fuse-
links for the protection of solar photovoltaic energy systems,” International Electrotech-
nical Commision, IEC 60269-6, 2010.
[50] Technical Committee 8, “IEC standard voltages,” International Electrotechnical Commi-
sion, IEC 60038:2009, 2009.
[51] IEEE Substation Committee, “IEEE Guide for the design and installation of cable systems
in substations,” IEEE Power and Energy Society, IEEE Std 525-2016, 2016.
[52] F. D. B. Metz-Noblat and G. Thomasset, Cuaderno tecnico nº 158. calculo de corrientes de
cortocircuito, 2000.
[53] Transpower New Zeland, “Clearances and conductor spacings – and a safe access for a.c.
switchyards,” Transpower New Zeland, TP.DS 62.01, 2009.
[54] S.M.Cary, “High voltage circuit breaker standards — comparative guide,” Eaton, WP012001EN,
2013.
[55] ABB, Instrument Transformers. Application Guide, 2015.
[56] Iberdrola, “Transformadores de intensidad de medida y proteccion en alta tension hasta
72.5 kV,” Iberdrola, Technical Speci�cation NI 72.50.01, 2003.
[57] Iberdrola, “Transformadores de intensidad de medida y proteccion en alta tension desde
145 hasta 420 kV,” Iberdrola, Technical Speci�cation NI 72.50.02, 2003.
[58] Iberdrola, “Transformadores de tension de medida y proteccion en alta tension hasta 72.5
kV,” Iberdrola, Technical Speci�cation NI 72.54.01, 2003.
[59] Iberdrola, “Transformadores de tension de medida y proteccion en alta tension desde 145
hasta 420 kV,” Iberdrola, Technical Speci�cation NI 72.54.02, 2003.
[60] Iberdrola Distribucion Electrica, “Transformadores trifásicos sumergidos en aceite para
distribución en baja tension,” Iberdrola, Technical Speci�cation NI 72.30.00, 2014.
[61] Endesa, “Especi�caciones tecnicas particulates de subestaciones AT/MT,” Endesa, Techni-
cal Speci�cation SRZ001, 2018.
[62] J. R. Martin, Diseño de subestaciones electricas. McGraw-Hill, 1987.
[63] C. R. Bayliss, C. Bayliss, and B. Hardy, Transmission and distribution electrical engineering.
Elsevier, 2012.
[64] I. Kasikci, Short circuits in power systems. Wiley Online Library, 2003.
[65] T. Thanasaksiri, “Comparison of IEEE and IEC standards for calculations of insulation lev-
els and electrical clearances for 230 kV air insulated substation,” in 2016 13th International
Conference on Electrical Engineering/Electronics, Computer, Telecommunications and Infor-
mation Technology (ECTI-CON), IEEE, 2016, pp. 1–6.
Substation Methodology 86
Bibliography
[66] A. Heyduk and J. Joostberens, “Comparative Analysis of European and American Stan-
dards for Maximum Fault Current Calculations on Medium Voltage Mine Power Net-
works,” Elektronika ir Elektrotechnika, vol. 22, no. 2, pp. 13–20, 2016.
[67] ABB, “Application guide. ABB LIVE Tank Circuit Breakers,” 2009.
[68] ABB, “Horizontal centre break disconnector,” 2019.
[69] ABB, “MV/LV transformer substations: theory and examples of short-circuit calculation,”
ABB, Technical Application Papers, 2008.
[70] Siemens, “Air-insulated substations up to 800 kV,” 2017.
[71] Inael, “SF6 metal enclosed switchgear panels,” 2014.
[72] Ormazabal, “Aparamenta de media tensión tipo GIS, con aislamiento integral en gas SF6,
hasta 40,5 kV según normativa IEC,” 2017.
[73] United States Department of Agriculture, “Design guide for rural substations,” Technical
Speci�cation RUS Bulletin 1724E-300, 2001.
[74] Prysmian Group, “Manual tecnico y practico de cables y accesorios para media tension,”
White paper, 2008.
[75] Nexans, “60-500 kV high voltage underground power cables,” 2004.
Substation Methodology 87
Appendix A. Selecting Circuit Arrangements
Appendix A
The installed capacity of a PV plant is 200 MW. The high voltage level is 132 kV and the medium
voltage level is 30 kV. In addition, there are 10 lines of 20 MW that connect the plant with the
substation.
First, both high and medium voltage short-circuit currents have been selected. As the high volt-
age level is 132 kV, the short-circuit current given by Table 3.1 is 40 kA. For the given medium
voltage level, the short-circuit current is 25 kA.
If all the medium voltage lines that leave the PV plant were grouped in one transformer, the
following results would have been obtained.
• As the power of the bay is 150 MW, per Table 6.1, the short-circuit impedance is 12.5 %.
Then, the admissible current of the bay is given by Equation 2.2.
• However, the total current of the bay is given by the following equation:
( 200 · 106
=p =p ⇡ 3850 (A.2)
3 · * mv 3 · 30000
• In this case, only one of the assumptions given in Chapter 2 has been ful�lled. There is one
transformer with a short-circuit impedance of 12.5 % but the total current is higher than
the admissible current. The reasoning behind this model is the idea that the short-circuit
current at the medium voltage level would be higher than the design short-circuit current.
( 200 · 106
p =p ⇡ 30.7: 25: (A.3)
3 · * mv · I cc 3 · 30000 · 0.125
Substation Methodology 88
Appendix A. Selecting Circuit Arrangements
• As the power of the bays are higher than 63 MW, according to Table 6.1, the short-circuit
impedance of every transformer is 12.5 %.
(1 100 · 106
1 = 2 =p =p ⇡ 1924 < 3150 (A.6)
3 · * mv 3 · 30000
• The short-circuit current is calculated according to the following formula.
( 100 · 106
p =p ⇡ 15.4: 25: (A.7)
3 · * mv · I cc 3 · 30000 · 0.125
• After applying the corresponding correction factors to the cables: 3G (4G630<<2) ; - !%⇢,
the following results were obtained:
Once the number of power transformers has been obtained, the last step is to determine the type
of substation (line to transformer, single busbar or double busbar). For that, the total operating
current of the PV plant is compared with the maximum admissible current.
() 200 · 106
) =p =p ⇡ 3850 3· des = 3 · 3150 = 9450 (A.9)
3 · * mv 3 · 30000
Substation Methodology 89
Appendix B. Calculation of the short-circuit currents
Appendix B
In this annex, the main short-circuit current will be determined following the calculation model
presented in Chapter 3. The previous example will be taken to study the short-circuit currents:
As the high voltage level is 132 kV, the short-circuit current given by Table 3.1 is 40 kA. For the
given medium voltage level, the short-circuit current is 25 kA.
*2 1450002
/ network = = = 2.12 ⌦ (B.1)
( sc 8200 · 106
Substation Methodology 90
Appendix B. Calculation of the short-circuit currents
2 ·* 1.1 · 132000
op-sc = p = p ⇡ 40 : (B.2)
/· 3 2.12 · 3
*2 300002
/ network = = = 0.06 ⌦ (B.3)
( sc 8000 · 106
* 2 I sc 300002
/t = · = · 0.125 = 1.125 (B.4)
( t 100 100 · 106
2 ·* 1.1 · 30000
op-sc = p = p = 16 : (B.5)
/ · 3 (0.06 + 1.125) · 3
3'/- )
^ = 1.02 + 0.984 ( = 1.81 (B.6)
p p
p = op-sc · ^ 2 = 40 · 1.81 2 = 102.36 : (B.7)
p p
p = op-sc · ^ 2 = 16 · 1.81 2 = 41 : (B.8)
1
<= · {4 4·5 ·)k ·;= (^ 1)
1} = 0.048 (B.9)
2 · 5 · )k · ;=(^ 1)
The thermal equivalent short-circuit current can be calculated using Equation 3.7.
Substation Methodology 91
Appendix B. Calculation of the short-circuit currents
p p
th = op-sc < + = = 40 1.048 = 41 : (B.10)
The thermal equivalent short-circuit current can be calculated using Equation 3.7.
p p
th = op-sc < + = = 16 1.048 = 16 : (B.11)
Substation Methodology 92
Appendix C. Insulation Coordination
Appendix C
Insulation Coordination
For the substation that has been proposed in these annexes, the insulation coordination results
are presented in this chapter. The example has the following inputs:
• The rated lightning impulse withstand voltage that is equal to 550 kV.
• The phase-to-earth short-duration power-frequency withstand voltage equals 185 kV.
• The phase-to-phase short-duration power-frequency withstand voltage equals 275 kV.
• The phase-to-earth clearance distance that equals 1.1 m.
• The phase-to-phase clearance distance that equals 1.1 m.
Substation Methodology 93
Appendix C. Insulation Coordination
6. If some required voltages are higher than the maximum standard rated withstand voltage
for a speci�c highest voltage for equipment, a greater value of the standard voltage is
selected even though the highest voltage is superior.
7. Selection of the minimum rod-structure and conductor-structure clearance distances for
the standard rated withstand voltages that have been selected.
8. Identi�cation of the phase-to-earth and phase-to-phase distances.
The phase-peak method has been chosen to calculate the truncation values using Equation 4.5
and Equation 4.6.
The parts per one are converted to volts following the Equation 4.7
r
2
D et = · 145 · 3 = 355 :+ (C.5)
3
r
2
D pt = · 145 · 4.3 = 509 :+ (C.6)
3
As the lightning arrester has been chosen following the process in section 6.3.1, the switching
impulse protective level equals * ps = 272 kV.
Substation Methodology 94
Appendix C. Insulation Coordination
To obtain the representative overvoltages for slow-front impulses, Equation 4.8 and Equation 4.9
are used.
• = 4500 kV.
• 5s = 0.5.
• # = 1.
• !t = 30 m.
Substation Methodology 95
Appendix C. Insulation Coordination
• !sp = 300 m.
• !f = 0.25/0.001 = 250 m. [m]
The lightning impulse protective level of the lightning arrester that was computed in Section E.3
is * pl = 311 kV. The coordination overvoltages for fast-front impulses proceed as given in Equa-
tion 4.14.
· 5s !t 4500 · 0.5 30
* �-cw = * pl + · = 311 + · = 311 + 122 = 433 :+ (C.13)
# !sp + !f 1 300 + 250
si = 1.15 (C.14)
se = 1.05 (C.15)
Moreover, the atmospheric correction factor for temporary and fast-front overvoltages can be
calculated using Equation 4.18.
✓ ◆ ✓ ◆
550
a = exp < · = exp 0.5 · = 1.03 (C.16)
8150 8150
✓ ◆✓ ◆
550
a-pe = exp < · = exp 1 · = 1.07 (C.17)
8150 8150
✓ ◆ ✓ ◆
550
a-pp = exp < · = exp 1 · = 1.07 (C.18)
8150 8150
Substation Methodology 96
Appendix C. Insulation Coordination
The standard withstand voltages for class I (145 kV) substation can be found in Table 4.6.
• As the standard rated lightning impulse withstand voltage is 550 kV, the rod-structure is
1.1 m.
• For 550 kV lightning impulse withstand voltage, a value of 1.1 m of conductor-structure
clearance is taken.
The phase-to-earth and phase-to-phase air distances are calculated using Equation 4.20 and Equa-
tion 4.21.
Substation Methodology 97
Appendix D. Safety Distances
Appendix D
Safety Distances
For the substation that has been proposed in these annexes, the safety distances are presented in
this chapter. The example has the following inputs:
• The rated lightning impulse withstand voltage that is equal to 550 kV.
• The phase-to-earth clearance distance that equals 1.1 m.
• The phase-to-phase clearance distance that equals 1.1 m.
Substation Methodology 98
Appendix D. Safety Distances
For the busbar height, the additional distance 3 bv + rw should be studied. So, 3 bv + rw =
1.21 + 1.25 = 2.46 < 3 <.
For the gateway height, the additional distance 3 bv + rw should be studied. So, 3 bv + rw =
1.21 + 1.25 = 2.46 < 3 <.
; device = <0G (3 bv + !o , 3 pp ) = <0G (1.21 + 1.75 , 1.1) = 2.96 < 3 ) 3 <. (D.5)
3 bus = <0G (3 bv + !o , 3 pp ) = <0G (1.21 + 1.75 , 1.1) = 2.96 < 3 ) 3 <. (D.6)
Once the distance between conductors has been established, the busbar/gateway span is derived
from Equation 5.7.
Substation Methodology 99
Appendix E. Determination of the substation’s equipment
Appendix E
For the substation that has been proposed in these annexes, in this chapter the main charac-
teristics of each equipment of a transformer bay are presented. The example has the following
inputs:
• The high voltage that equals 132 kV and the short-circuit current for this level is 40 kA.
• The medium voltage that equals 30 kV and the short-circuit current for this level is 25 kA.
• The total power of the transformer bay is 100 MW.
• The frequency of the system is equal to 50 Hz.
• The transformer capacity is 100 MVA which equals the power of the bay.
• The voltage ratio is 132/30 kV.
• The vector group is Ynd11.
• The short-circuit impedance is 12.5 % according to Table 6.1.
As 750 A is not contemplated as standard value by the software, the current taken is 800 A.
- 0 /- 1 · * mv 10 · 30000
-g = p =p = 6.93⌦ (E.2)
3 · sc 3 · 25000
* mv 30000
'g = p =p = 21.65⌦ (E.3)
3 · zig-zag 3 · 800
The next step is to get the temporary overvoltage for the lightning arrester using Equation 6.5
The temporary overvoltages based on the equivalent 10 seconds duration overvoltage is calcu-
lated using Equation 6.6.
⇣ g ⌘[ ✓ ◆ 0.02
1
* 10s = * tov · = 128.9 · = 123 :+ (E.6)
10 10
* r = <0G (1.25 · * cov , * 10s ) = <0G (1.25 · 92 , 123) = <0G (115 , 123) = 123 :+ (E.7)
The nominal discharge current is nom = 10 kA due to * m = 145 < 360 kV.
The characteristics already mentioned are not applicable for commercial purposes. For that rea-
son, a database of commercial surge arresters has been added to the software. The selected surge
arrester is presented in Table E.1 and it has the following characteristics:
Table E.1: Technical data for surge arresters - 145 kV. [22], [25] and [26]
* cb = * m = 145 :+ (E.8)
The rated normal current is calculated by Equation 6.9. It is recommended to select 1600 A for
short-circuit currents of 40 kA.
sc-cb = sc = 40 : (E.10)
E.5 Disconnectors
The rated voltage is given by Equation 6.12.
* d = * m = 145 :+ (E.12)
The rated normal current is calculated by Equation 6.13. It is recommended to select 1600 A for
short-circuit currents of 40 kA.
sc-d = sc = 40 : (E.14)
* ct = * m = 145 :+ (E.16)
The rated secondary current is equal to 5 A. The rated primary current is calculated by Equa-
tion 6.17. After obtaining the current, the closest standard current will be selected. [34]. In this
case, The R10 values are not followed.
t = ct = 600 (E.18)
sc-ct = sc = 40 : (E.19)
* 132
* vt = p = p :+ (E.21)
3 3
Appendix F
F.1 Introduction
The following example clari�es the process of designing a rigid busbar for an air-insulated sub-
station using the information presented in [42] and [43]. The parameters required for the bus
design are:
2 2
3 ext 3 int 0.152 0.1342
c =c· =c· = 3562 << 2 (F.1)
4 4
4 4
3 ext 3 int 0.154 0.1344 4
(c = c · =c· = 1.2 · 10 <3 (F.2)
32 · 3 ext 32 · 0.15
4 4
3 ext 3 int 0.154 0.1344 6
=c· =c· = 9.02 · 10 <4 (F.3)
64 64
6
D bus = F Al · c = 2700 · 3562/10 = 9.63 :6/< (F.4)
s ✓ ◆
12 1 )f 20 + 15150/⌧
bus sc = ⇠ · 10 · c · log10 = 319 : (F.7)
C )i 20 + 15150/⌧
The weight force by unit length on the bus is given by Equation 7.9.
? weight = D bus + D damper · 6 = D bus · ⇠ damper · 6 = 9.63 · 1.25 · 9.8 = 118 # /< (F.9)
The ice force by unit length on the bus is calculated based on [45].
p p
? ice = 1.8 3 ext = 1.8 0.15 = 0.69 # /< (F.10)
The maximum short circuit force by unit length on the buses is obtained according to Equa-
tion 7.10.
p p
`0 3 1 2 `0 3 1
? m3 = peak = 1023602 = 608 # /< (F.11)
2c 2 3 pp 2c 2 3
The wind force by unit length on the busbar surfaces is calculated using Equation 7.11.
✓ ◆2 ✓ ◆2
+wind 120
? wind-busbar = 3 ext · % air · = 0.15 · 700 · = 105 # /< (F.12)
+ref 120
The wind force by unit length on the c10-650 post insulator, whose external diameter is 0.4 m, is
calculated using Equation 7.11.
✓ ◆2 ✓ ◆2
+wind 120
? wind-postInsulator = 3 ext · % air · = 0.4 · 700 · = 280 # /< (F.13)
+ref 120
F.5.2 Reactions
The bus-support conditions depend on the number of transformer bays. Hence, the e�ective
conductor span length !E is obtained using Equation 7.12.
The reactions on the supports due to the weight is obtained using Equation 7.13
The reactions on the supports due to the ice is obtained using Equation 7.13
The reactions on the supports due to the wind on the busbars is obtained using Equation 7.13
The reactions on the supports caused by the short-circuit current forces by unit length are ob-
tained using Equation 7.14
The reactions on the bus supports caused by wind force on the insulators, whose length is 1.5 m,
are obtained using Equation 7.16.
wind insulator = ? wind insulator · ⇠ reaction insulator · !insulator = 280 · 0.625 · 1.5 = 262 # /< (F.19)
The total force on the bus supports is the results of the vector sum of all forces as shown in
Equation 7.17
q
2 2
T = ( w + ice ) +( sc + wind-busbar + wind insulator ) = 9974 # (F.20)
2
? weight · ⇠ stress · !sp 118 · 0.07 · 122
fweight = = ⇡ 10 # /<< 2 (F.21)
(c (c
The stresses on the bus caused by ice forces are obtained using Equation 7.20.
2
? ice · ⇠ stress · !sp 0.69 · 0.07 · 122
fice = = ⇡ 0 # /<< 2 (F.22)
(c (c
The stresses on the bus caused by wind forces are obtained using Equation 7.20.
2
? wind-busbar · ⇠ stress · !sp 105 · 0.07 · 122
fwind-busbar = = ⇡ 9 # /<< 2 (F.23)
(c (c
To obtain the mechanical stress on the bus caused by the short circuit load, the IEC standard [43]
has been followed and Equation 7.21 has been used.
2
+f · +r · V · ? r · !sp 0.46 · 1.8 · 0.73 · 531 · 122
fsc = = ⇡ 45 # /<< 2 (F.24)
8( c 8( c
The stress on the bus caused by the wind force on the insulator is obtained using Equation 7.22.
2
? wind · ⇠ stress insulator · !insulator
fwind insulator = ⇡ 0 # /<< 2 (F.25)
( insulator
The total force on the bus supports is the result of the vector sum of all the forces as shown in
Equation 7.24
q
2
fT = fweigth + fice + (fsc + fwind-busbare + fwind insulator ) 2 ⇡ 55 # /<< 2 (F.26)
Where:
1 (1 2C/3 ext ) 3
@ = 1.7 = 1.34 (F.28)
1 (1 2C/3 ext ) 4
✓ ◆ 13 ✓ ◆ 13
185 · ⇢ · · 5def 185 · ⇢ · · 0.0033
!v = = = 14.83 < (F.29)
?g 118
The allowable span based on the �bre stress is obtained using the Equation 7.26.
s r
16 · · 5weld · u 16 · · 0.75 · u
!s = = = 12.6 < (F.30)
? T · 3 ext 1000 · 0.15
The allowable span for the rigid bus of the substation is the resulting minimum value, given in
Equation 7.27.
✓ ◆
⇠
⇢c = < · ⇢0 · ⇡a 1 + p · 100000 = 1600 :+ /< (F.33)
⇡ a · A ext
The maximum voltage gradient at the surface of a three-phase conductor can be estimated using
Equation 7.31.
⌘e 1.46
⇢m = · ⇢a = · 310 ⇡ 310 :+ /< (F.34)
⌘e 3 ext /2 1.46 0.15/2
On the other hand, the assigned withstand short duration current density is obtained from Equa-
tion 7.36.
s
1 ^ 202d 1 + U 20 (o e 20)
( thr = · · ln = 9.3 · 107 /< 2 (F.39)
)kr U 20 1 + U 20 (o b 20)
r
2 )kr
( th = 11.23 /<< ( thr = 93 /<< 2 (F.40)
)k