11.15 Tech 1
11.15 Tech 1
T
he Dauphin Island Water & Sewer Author- prepared. The evaluation narrowed the prospective
ity (Authority), in Dauphin Island, Ala., treatment alternatives to two possible secondary Vaile Feemster is general manager with
owns and operates a reverse osmosis (RO) options of the primary CO2 /lime (slurry) dosing Dauphin Island Water & Sewer Authority in
drinking water treatment facility that first came on- option. The Authority pilot-tested the two selected Dauphin Island, Ala., and Jim Smith, P.E., is
line in May 2010. The facility serves Dauphine Is- methods and then selected the most advantageous
project manager with Constantine
land’s 1,200 permanent residents, and a seasonal option for poststabilization at its water treatment
Engineering in Fort, Payne, Ala.
tourist population of more than 20,000. The barrier facility.
island is located off the coast of the state, approxi- The Authority commissioned a new RO treat-
mately 30 mi south of Mobile. The facility treats ment facility in May 2011. From start-up, the facil-
water from a sand aquifer that is about 700 ft below ity has experienced problems with corrosive water feed water, including calcium and bicarbonate/car-
the ground’s surface. The water is relatively good and meeting the Alabama Department of Envi- bonate ions. The resulting RO permeate will typi-
quality and only requires treatment for chlorides in ronmental Management (ADEM) requirements cally have low levels of calcium hardness and
the 1,700-parts-per-mil (ppm) range. The facility for lead levels. The Authority initially implemented alkalinity and is “stabilized” to protect distribution
currently operates at a recovery rate of 75 to 80 per- a corrosion control program, held over from a pre- pipelines, pump stations, and storage tanks. The
cent (depending on the season) and can supply a vious iron removal plant, by treating the plant ef- Authority has attempted to provide stabilization
production of up to 1.2 mil gal per day (mgd). fluent with a proprietary blended with proprietary blended phosphates and pH ad-
The RO treatment of brackish water purifies zinc-orthophosphate. In August 2011, the Author- justments using sodium hydroxide. This approach
and significantly changes the mineral composition ity failed the ADEM lead sample limits; in January has provided adequate poststabilized water; how-
of the water. Pure water is considered a reactive 2012, it implemented a new corrosion control plan ever, the lead corrosion continues to bump the ex-
chemical, and water containing little to no hard- that included changing the corrosion inhibitor to ceedance level and a new approach should be
ness is often found to be aggressive towards distri- a blended orthopolyphosphate and increasing the implemented.
bution system components. Consequently, corrosion inhibitor dosage. The new plan also in- The chemical stability of potable water is typ-
poststabilization of RO-treated water is required cluded extensive testing at the water plant and in ically determined by three parameters:
prior to storage and distribution. the system. The sampling plan and performance pH buffering capacity or alkalinity
The Authority re-evaluated its post-treatment monitoring program included corrosion test Tendency of the water to precipitate calcium car-
and stabilization treatment after failing a lead cor- coupons located at various locations in the Au- bonate or scaling potential
rosion sample soon after the plant was commis- thority’s service area, frequent water sampling, and Concentration of soluble calcium ions in the
sioned. It looked at four primary options for trending of historical data. water
improving its poststabilization treatment: In September 2013, the Authority again failed
Chemical addition: minerals other than lime or the ADEM lead exceedance level. Since that time, The pH is relevant in the finished water, but it
calcite Constantine Engineering has worked with the Au- is dependent on the values of the three parameters
Blending with a water containing high mineral thority’s operators to develop, evaluate, and imple- listed. Several calculated indices are used in the
content ment alternative water treatment processes that water industry for water stability control to deter-
Carbon dioxide (CO2) addition, followed by cal- provide stable finish water chemistry and eliminate mine the scaling tendency of calcium carbonate.
cite or dolomite dissolution the permit violations. The most commonly accepted indices are calcium
CO2 addition, followed by lime (slurry) dosing carbonate scaling potential (CCSP), Ryznar Stabil-
Study Objectives ity Index (RSI), and Langelier Saturation Index
Each of these four methods was reviewed and (LSI).
a cost evaluation for implementing each option was The RO process removes dissolved solids from The targeted post-treatment water quality ob-
jectives are as follows:
40<alkalinity<80 mg/L as calcium carbonate
Table 1. Common Chemicals that Add Carbonate or Shift Carbonate Species (mg/L as CaCO3)
LSI>0
50<calcium (Ca)<120mg/L as CaCO3
8.0<pH<8.5
Pilot Testing
Bulk-Delivered Liquid Lime
Cal-Flo bulk-delivered liquid lime supplied
by Burnett Lime Company Inc., which was
pilot-tested in October 2013. Burnett Lime sup-
plied a complete liquid lime feed system that in-
cluded a bulk storage tank, feed pumps, mixers,
and a programmable logic control (PLC) con- $330,000, and the yearly operating cost is esti- Pros Cons
trol system. The Cal-Flo system consists of the mated to be $12,000. Precise application Higher operation
following major items: Cal-Flo presented an option to purchase a cost
16,000-gal lime slurry tank used system that was approximately $100,000 Low maintenance Requires large
Feed pump building less than the cost of a new system, stating that it bulk tank
Feed pumps would provide a warranty and support the used No dust Single supplier
Control panel and instrumentation system as if it were sold as new. Nonhazardous
Tank mixer There could be some potential cost savings Predictable results
by designing and implementing a system other Dissolves on contact
The Cal-Flo system capital cost for equip- than that presented in the Cal-Flo proposal. The
ment and installation is estimated to be Continued on page 8
Authority can purchase an exterior tank and
mixer and utilize a transfer pump-to-pump liq-
uid lime to the existing chemical feed room; a
new day tank and mixer would be required,
along with an additional chemical feed pump.
It’s estimated that the cost for this used liquid
bulk lime alternate system would be $115,000,
which would be a savings of $100,000 over a
new system. A major disadvantage is that the
Cal-Flo feed system is patented, and dosing its
product with alternate equipment would elimi-
nate the operation guarantee from Burnett Lime
for the performance of the system.
The Cal-Flo system pilot-tested very well
and the operators found it to be easy to operate
and maintain. When the system was running,
the water quality was easy to maintain, pH was
stable, and alkalinity was easily adjusted by
changing the lime dosing rate (Tables 2 and 3).
The following shows the pros and cons of the
system, both subjective and quantitative: Hydrated Lime Bag Delivery