The document discusses the process of planning, budgeting, and financing for electric power substations. It covers determining the need for new substations, developing budgets, and obtaining financing. Key steps include evaluating system requirements, determining site needs, creating preliminary designs and cost estimates, and justifying projects during budget cycles.
The document discusses the process of planning, budgeting, and financing for electric power substations. It covers determining the need for new substations, developing budgets, and obtaining financing. Key steps include evaluating system requirements, determining site needs, creating preliminary designs and cost estimates, and justifying projects during budget cycles.
Lecture No. 8 Engr. Raheel Muzzammel Department of Electrical Engineering University of Lahore
Engr. Raheel Muzzammel 1
Electric Power Substation Engineering
Engr. Raheel Muzzammel 2
Electric Power Substation Engineering • Complex Engineering Problem • The construction of new substations and the expansion of existing facilities are commonplace projects in electric utilities. • However, due to its complexity, very few utility employees are familiar with the complete process that allows these projects to be successfully completed.
Engr. Raheel Muzzammel 3
Electric Power Substation Engineering • Major Types of Substations • There are four major types of electric substations. • The first type of substation is the switchyard at a generating station. • These facilities connect the generators to the utility grid and also provide off-site power to the plant. • Generator switchyards tend to be large installations that are typically engineered and constructed by the power plant designers and are subject to planning, finance, and construction efforts different from those of routine substation projects.
Engr. Raheel Muzzammel 4
Electric Power Substation Engineering • The second type of substation, typically known as the customer substation, functions as the main source of electric power supply for one particular business customer. • The technical requirements and the business case for this type of facility depend highly on the customer’s requirements. • The third type of substation involves the transfer of bulk power across the network and is referred to as a system station. • Some of these stations provide only switching facilities (no power transformers) whereas others perform voltage conversion as well. • These large stations typically serve as the end points for transmission lines originating from generating switchyards and provide the electrical power for circuits that feed transformer stations.
Engr. Raheel Muzzammel 5
Electric Power Substation Engineering • They are integral to the long-term reliability and integrity of the electric system and enable large blocks of energy to be moved from the generators to the load centers. • Since these system stations are strategic facilities and usually very expensive to construct and maintain. • The fourth type of substation is the distribution station. These are the most common facilities in power electric systems and provide the distribution circuits that directly supply most electric customers. • They are typically located close to the load centers, meaning that they are usually located in or near the neighborhoods that they supply, and are the stations most likely to be encountered by the customers. Engr. Raheel Muzzammel 6 Electric Power Substation Engineering • Depending on the type of equipment used, the substations could be Outdoor type with air-insulated equipment Indoor type with air-insulated equipment Outdoor type with gas-insulated equipment Indoor type with gas-insulated equipment Mixed technology substations Mobile substations
Engr. Raheel Muzzammel 7
• Need Determination • Budgeting • Financing • Traditional and Innovative Substation Design • Site Selection and Acquisition • Design, Construction, and Commissioning Process
Engr. Raheel Muzzammel 8
Need Determination • An active planning process is necessary to develop the business case for creating a substation or for making major modifications. • Planners, operating and maintenance personnel, asset managers, and design engineers are among the various employees typically involved in considering such issues in substation design as load growth, system stability, system reliability, and system capacity; and their evaluations determine the need for new or improved substation facilities. • Customer requirements, such as new factories, etc., should be considered, as well as customer relations and complaints. • In some instances, political factors also influence this process, as is the case when reliability is a major issue.
Engr. Raheel Muzzammel 9
Need Determination • At this stage, the elements of the surrounding area are defined and assessed and a required in-service date is established. • It is usual for utilities to have long-term plans for the growth of their electric systems in order to meet the anticipated demand. • Ten year forecasts are common and require significant input from the engineering staff. • System planners determine the capacities of energy required and the requirements for shifting load around the system, but engineering personnel must provide cost info on how to achieve the planners’ goals. • Planners conduct studies that produce multiple options and all of these scenarios need to be priced in order to determine the most economical means of serving the customers.
Engr. Raheel Muzzammel 10
Need Determination • A basic outline of what is required in what area can be summarized as follows: • System Requirements including Load growth System stability System reliability System capacity • Customer requirements including Additional load Power quality Reliability Customer relations Customer complaints Neighborhood impact
Engr. Raheel Muzzammel 11
Budgeting • Part of the long-range plan involves what bulk power substations need to be created or expanded in order to move large blocks of energy around the system as necessary and where do they need to be located. • Determinations have to be made as to the suitability of former designs for the area in question. • To achieve this, most utilities rely on standardized designs and modular costs developed over time, but should these former designs be unsuitable for the area involved, that is, unlikely to achieve community acceptance, then alternative designs need to be pursued.
Engr. Raheel Muzzammel 12
Budgeting • Different Cases • In the case of bulk power substations, the equipment and land costs can differ greatly from standard designs. • Distribution stations, however, are the most common on most systems and therefore have the best known installed costs. • Since these are the substations closest to the customers, redesign is less likely to be required than screening or landscaping, so costs do not vary greatly. • Having established the broad requirements for the new station, such as voltages, capacity, number of feeders, etc., the issue of funding should then be addressed.
Engr. Raheel Muzzammel 13
Budgeting • This is typical when real estate investigations of available sites begin, since site size and location can significantly affect the cost of the facility. • Preliminary equipment layouts and engineering evaluations are also undertaken at this stage to develop ballpark costs [an estimate of what something might amount to numerically when a more accurate number is assessed, such as the cost of a product.], which then have to be evaluated in the corporate budgetary justification system. • Preliminary manpower forecasts of all disciplines involved in the engineering and construction of the substation should be undertaken, including identification of the nature and extent of any work that the utility may need to contract out. • This budgeting process will involve evaluation of the project in light of corporate priorities and provide a general overview of cost and other resource requirements. Engr. Raheel Muzzammel 14 Budgeting • Note that this process may be an annual occurrence. • Any projects in which finances have yet to be spent are generally re- evaluated every budget cycle. • Cash Forecasting • Cost estimating also entails cash forecasting; for planning purposes, forecasts per year are sufficient. • This means that every budget cycle, each proposed project must not only be reviewed for cost accuracy, but the cash forecast must also be updated. • It is during these annual reviews that standardized or modularized costs also need to be reviewed and revised if necessary. Engr. Raheel Muzzammel 15 Financing • Once the time has arrived for work to proceed on the project, the process of obtaining funding for the project must be started. • Requirements • Preliminary detailed designs are required to develop firm pricing. • Coordination between business units is necessary to develop accurate costs and to develop a realistic schedule. • This may involve detailed manpower forecasting in many areas. • The resource information has to be compiled in the format necessary to be submitted to the corporate capital estimate system and internal presentations must be conducted to sell the project to all levels of management. • Sometimes it may be necessary to obtain funding to develop the capital estimate.
Engr. Raheel Muzzammel 16
Financing • Why is funding required for capital estimation? • This may be the case when the cost to develop the preliminary designs is beyond normal departmental budgets, or if unfamiliar technology is expected to be implemented. • This can also occur on large, complex projects or when a major portion of the work will be contracted. • It may also be necessary to obtain early partial funding in cases where expensive, long lead-time equipment may need to be purchased such as large power transformers.
Engr. Raheel Muzzammel 17
Traditional and Innovative Substation Design • Substation engineering is a complex multidiscipline engineering function. • It could include the following engineering disciplines: • Environmental • Civil • Mechanical • Structural • Electrical—high voltage • Protection and controls • Communications
Engr. Raheel Muzzammel 18
Traditional and Innovative Substation Design • Traditionally, high-voltage substations are engineered based on pre- established layouts and concepts and usually conservative requirements. • This approach may restrict the degree of freedom of introducing new solutions i.e., only the incorporation of new primary and secondary technology in pre-engineered standards can be achieved. • A more innovative approach is one that takes into account functional requirements such as system and customer requirements and develops alternative design solutions.
Engr. Raheel Muzzammel 19
Traditional and Innovative Substation Design • System requirements include elements of rated voltage, rated frequency, existing system configuration (present and future), connected loads, lines, generation, voltage tolerances (over and under), thermal limits, short-circuit levels, frequency tolerances (over and under), stability limits, critical fault clearing time, system expansion, and interconnection. • Customer requirements include environmental consideration (climatic, noise, aesthetic, spills, and right-of-way), space consideration, power quality, reliability, availability, national and international applicable standards, network security, expandability, and maintainability.
Engr. Raheel Muzzammel 20
Traditional and Innovative Substation Design • Carefully selected design criteria could be developed to reflect the company philosophy. • This would enable, when desired, consideration and incorporation of elements such as life cycle cost, environmental impact, initial capital investment, etc., into the design process. • Design solutions could then be evaluated based on pre-established evaluation criteria that satisfy the company interests and policies.
Engr. Raheel Muzzammel 21
Site Selection and Acquisition • At this stage, a footprint of the station has been developed, including the layout of the major equipment. • A decision on the final location of the facility can now be made and various options can be evaluated. • Final grades, roadways, storm water retention, and environmental issues are addressed at this stage, and required permits are identified and obtained. • Community and political acceptance must be achieved and details of station design are negotiated in order to achieve consensus. • Depending on local zoning ordinances, it may be prudent to make settlement on the property contingent upon successfully obtaining zoning approval since the site is of little value to the utility without such approval. • It is not unusual for engineering, real estate, public affairs, legal, planning, operations, and customer service personnel along with various levels of management to be involved in the decisions during this phase. Engr. Raheel Muzzammel 22 Site Selection and Acquisition • The first round of permit applications can now begin. • Although the zoning application is usually a local government issue, permits for grading, storm water management, roadway access, and other environmental or safety concerns are typically handled at the state or provincial level and may be federal issues in the case of wetlands or other sensitive areas. • Other federal permits may also be necessary, such as those for aircraft warning lights for any tall towers or masts in the station. • Permit applications are subject to unlimited bureaucratic manipulation and typically require multiple submissions and could take many months to reach conclusion. • Depending on the local ordinances, zoning approval may be automatic or may require hearings that could stretch across many months. • Zoning applications with significant opposition could take years to resolve.
Engr. Raheel Muzzammel 23
Site Selection and Acquisition • Site Evaluation Criteria • As a rule of thumb, the following site evaluation criteria could be used: • Economical evaluation • Technical evaluation • Community acceptance • Economical evaluation should address the level of affordability, return on investment, initial capital cost, and life cycle cost. • Technical aspects that can influence the site selection process could include the following: • Land: choose areas that minimize the need for earth movement and soil disposal. • Water: avoid interference with the natural drainage network. • Vegetation: choose low-productivity farming areas or uncultivated land. • Protected areas: avoid any areas or spots listed as protected areas. • Community planning: avoid urban areas, development land, or land held in reserve for future development.
Engr. Raheel Muzzammel 24
Site Selection and Acquisition • Community involvement: engage community in the approval process. • Topography: flat but not prone to flood or water stagnation. • Soil: suitable for construction of roads and foundations; low soil resistivity is desirable. • Access: easy access to and from the site for transportation of large equipment, operators, and maintenance teams. • Line entries: establishment of line corridors (alternatives: multi-circuit pylons, UG lines). • Pollution: risk of equipment failure and maintenance costs increase with pollution level.
Engr. Raheel Muzzammel 25
Site Selection and Acquisition • To address community acceptance issues, it is recommended to • Adopt a low profile layout with rigid buses supported on insulators over solid shape steel structures • Locate substations in visually screened areas (hills, forest), other buildings, and trees • Use gas-insulated switchgear (GIS) • Use colors, lighting • Use underground egresses as opposed to overhead • Other elements that may influence community acceptance are noise and oil leakages or spills. • To mitigate noise that may be emitted by station equipment, attention should be paid at station orientation with respect to the location of noise-sensitive properties and the use of mitigation measures such as noise barriers, sound enclosures, landscaping, and active noise cancellation. • The environmental impact of oil spills and their cleanup is governed by regulatory authorities necessitating increased attention in substations to the need for secondary oil containment and a Spill Prevention Control and Countermeasure (SPCC) plan.
Engr. Raheel Muzzammel 26
Design, Construction, and Commissioning Process • Station Design • The following can be used as a guide for various design elements: 1. Basic layout a. Stage development diagram b. Bus configuration to meet single line requirements c. Location of major equipment and steel structures based on single line diagram d. General concept of station e. Electrical and safety clearances f. Ultimate stage
Engr. Raheel Muzzammel 27
Design, Construction, and Commissioning Process 2. Design a. Site preparation - Drainage and erosion, earth work, roads and access, and fencing b. Foundations - Soils, concrete design, and pile design c. Structures - Materials, finishes, and corrosion control d. Buildings i. Control, metering, relaying, and annunciation buildings—types such as masonry, prefabricated, etc. ii. Metalclad switchgear buildings iii. GIS buildings e. Mechanical systems i. HVAC ii. Sound enclosure ventilation iii. Metalclad switchgear or GIS building ventilation iv. Fire detection and protection v. Oil sensing and spill prevention
Engr. Raheel Muzzammel 28
Design, Construction, and Commissioning Process f. Buswork i. Rigid buses ii. Strain conductors—swing, bundle collapse iii. Ampacity iv. Connections v. Phase spacing vi. Short-circuit forces g. Insulation i. Basic impulse level and switching impulse level h. Station insulators i. Porcelain post type insulators ii. Resistance graded insulators iii. Polymeric post insulators iv. Station insulator hardware v. Selection of station insulator—TR—ANSI and CSA standard vi. Pollution of insulators—pollution levels and selection of leakage distance
Engr. Raheel Muzzammel 29
Design, Construction, and Commissioning Process i. Suspension insulators i. Characteristics ii. Porcelain suspension insulators iii. Polymeric suspension insulators iv. Suspension insulators hardware v. Selection of suspension insulators vi. Pollution of insulators—pollution levels and selection of leakage distance j. Clearances i. Electrical clearances ii. Safety clearances k. Overvoltages i. Atmospheric and switching overvoltages ii. Overvoltage protection—pipe and rod gaps, surge arresters iii. Atmospheric overvoltage protection—lightning protection (skywires, lightning rods)
Engr. Raheel Muzzammel 30
Design, Construction, and Commissioning Process l. Grounding i. Function of grounding system ii. Step, touch, mesh, and transferred voltages iii. Allowable limits of body current iv. Allowable limits of step and touch voltages v. Soil resistivity vi. General design guidelines m. Neutral systems i. Background of power system grounding ii. Three- and four-wire systems iii. HV and LV neutral systems iv. Design of neutral systems n. Station security i. Physical security ii. Electronic security
Engr. Raheel Muzzammel 31
Design, Construction, and Commissioning Process • Station Construction • With permits in hand and drawings published, the construction of the station can begin. • Site logistics and housekeeping can have a significant impact on the acceptance of the facility. • Parking for construction personnel, traffic routing, truck activity, trailers, fencing, and mud and dirt control along with trash and noise can be major irritations for neighbors, so attention to these details is essential for achieving community acceptance. • All the civil, electrical, and electronic systems are installed at this time. • Proper attention should also be paid to site security during the construction phase not only to safeguard the material and equipment but also to protect the public.
Engr. Raheel Muzzammel 32
Design, Construction, and Commissioning Process • Station Commissioning • Once construction is complete, testing of various systems can commence and all punch list items addressed. • To avoid duplication of testing, it is recommended to develop an inspection, testing, and acceptance plan (ITAP). • Elements of ITAP include: • Factory acceptance tests (FATs) • Product verification plan (PVP) • Site delivery acceptance test (SDAT) • Site acceptance tests (SATs) Engr. Raheel Muzzammel 33 Design, Construction, and Commissioning Process • Final tests of the completed substation in a partially energized environment to determine acceptability and conformance to customer requirements under conditions as close as possible to normal operation conditions will finalize the in-service tests and turnover to operations. • Environmental cleanup must be undertaken and final landscaping can be installed. • Note that, depending upon the species of plants involved, it may be prudent to delay final landscaping until a more favorable season in order to ensure optimal survival of the foliage. • Public relations personnel can make the residents and community leaders aware that the project is complete and the station can be made functional and turned over to the operating staff.
Engr. Raheel Muzzammel 34
Generalized Flow Chart of New Substation Establishment