To Be1
To Be1
Stock Transfer
STO Purchase requisition is created.
PR is released as per release strategy predefined.
Stock Transport Order is created with reference to purchase requisition.
Planned freight cost is entered in STO.
PO is released as per release strategy predefined.
Quantity to be moved from supplying plant against delivery.
GR is done at receiving plant against STO
Invoice verification is done for transporters payment.
Stock Material procurement via Purchase Order (Domestic)
Purchase requisition is created
PR is released as per release strategy predefined.
Request for quotations are created for purchase requisition, Vendor is entered while creating RFQ. RFQ is printed and sent to vendor. Quotations are received from
vendor and are entered in SAP for price comparison.
Purchase order is created with reference to approved RFQ. Pricing conditions, Payment terms, delivery terms and tax code are entered in PO.
PO is released as per release strategy predefined.
GR is done against purchase Order.
Invoice verification for vendor and transporters is done.