The document discusses PERT/CPM (Program Evaluation and Review Technique/Critical Path Method), which are quantitative techniques used to plan, schedule, monitor, and control large projects. PERT uses three time estimates to determine expected activity times probabilistically, while CPM uses fixed times deterministically. Both techniques involve defining activities, determining relationships between activities, drawing a network diagram, and identifying the critical path - the longest sequence of dependent activities that determines the project duration. PERT can also calculate the probability of completing a project by a certain date based on the variance of activities on the critical path.
The document discusses PERT/CPM (Program Evaluation and Review Technique/Critical Path Method), which are quantitative techniques used to plan, schedule, monitor, and control large projects. PERT uses three time estimates to determine expected activity times probabilistically, while CPM uses fixed times deterministically. Both techniques involve defining activities, determining relationships between activities, drawing a network diagram, and identifying the critical path - the longest sequence of dependent activities that determines the project duration. PERT can also calculate the probability of completing a project by a certain date based on the variance of activities on the critical path.
Program Evaluation and Review Technique/Critical Path Method
Introduction Almost every industry worries about how to manage similar large-scale, complicated projects effectively. It is a difficult problem, and the stakes are high. Millions of dollars in cost overruns have been wasted due to poor planning of projects. Unnecessary delays have occurred due to poor scheduling. How can such problems be solved? Introduction The first step in planning and scheduling a project is to develop the work breakdown structure. This involves identifying the activities that must be performed in the project. An activity is a job or task that is a part of a project. The beginning or end of an activity is called an event. There may be varying levels of detail, and each activity may be broken into its most basic components. The time, cost, resource requirements, predecessors, and person(s) responsible are identified for each activity. When this has been done, a schedule for the project can be developed. Introduction The program evaluation and review technique (PERT) and the critical path method (CPM) are two popular quantitative analysis techniques that help managers plan, schedule, monitor, and control large and complex projects. They were developed because there was a critical need for a better way to manage projects. PERT vs CPM For every PERT activity, CPM is a deterministic three time estimates are method since it is assumed combined to determine the that the times are known expected activity with certainty. completion time. Thus, PERT is a probabilistic technique. PERT / CPM While these differences are still noted, the two techniques are so similar that the term PERT/CPM is often used to describe the overall approach. This reference is used in this chapter, and differences are noted where appropriate. How to use PERT / CPM 1. Define the project and all its significant activities or tasks. 2. Develop the relationships among the activities. Decide which activities must precede others. 3. Draw the network connecting all of the activities. 4. Assign time and/or cost estimates to each activity. 5. Compute the longest time path through the network; this is called the critical path. 6. Use the network to help plan, schedule, monitor, and control the project. Critical Path The critical path is important because activities on the critical path can delay the entire project. Finding the critical path is a major part of controlling a project. The activities on the critical path represent tasks that will delay the entire project if they are delayed. Questions answered by PERT. 1. When will the entire project be completed? 2. What are the critical activities or tasks in the project, that is, the ones that will delay the entire project if they are late? 3. Which are the noncritical activities, that is, the ones that can run late without delaying the entire project’s completion? 4. If there are three time estimates, what is the probability that the project will be complete by a specific date? 5. At any date, is the project on schedule, behind schedule, or ahead of schedule? 6. On any given date, is the money spent equal to, less than, or greater than the budgeted amount? 7. Are there enough resources available to finish the project on time? Steps in PERT. 1. The first step is to define the project and all project activities. 2. Immediate predecessors are determined in the second step. 3. Activities and events are drawn and connected in the third step. 4. The fourth step is to assign activity times. 5. The fifth step is to compute the longest path through the network—the critical path. The time estimates in PERT Optimistic time (a) = time an activity will take if everything goes as well as possible Pessimistic time (b) = time an activity would take assuming very unfavorable conditions. There should also be only a small probability that the activity will really take this long. Most likely time (m) = most realistic time estimate to complete the activity. Expected Activity Time (t) in PERT PERT often assumes that time estimates follow the beta probability distribution. This continuous distribution has been found to be appropriate, in many cases, for determining an expected value and variance for activity completion times. How to compute for Expected Activity Time (t) in PERT The Critical Path The critical path is the longest time path route through the network. Ex. A-C-F-H = 16 days, A-C-E-G-H = 22, B-D-G-H = 12; the CP is A-C-E-G-H with 22 days How to find the CP To find the critical path, we need to determine the following quantities for each activity in the network: 1. Earliest start time (ES): the earliest time an activity can begin without violation of immediate predecessor requirements 2. Earliest finish time (EF): the earliest time at which an activity can end 3. Latest start time (LS): the latest time an activity can begin without delaying the entire project 4. Latest finish time (LF): the latest time an activity can end without delaying the entire project Example: Steps 1 and 2 are already done. Now, we proceed to Step 3. Example: Step 4 is partially done, see figure. Now, we just need to find the expected time (t) and the variance (v). Example: Now, we find the critical path. Probability of Project Completion PERT uses the variance of critical path activities to help determine the variance of the overall project. If the activity times are statistically independent, the project variance is computed by summing the variances of the critical activities: Project variance = ∑ variances of activities on the critical path Project standard deviation = σ = √ Project variance Probability of Project Completion Due date - Expected date of completion 𝑍= σ Where Z is the number of standard deviations the due date or target date lies from the mean or expected date.