4 WBS
4 WBS
Steps
Defining the project scope
◦ Project objectives
◦ Deliverables
◦ Milestones
◦ Technical requirement
◦ Limits & exclusion
◦ Reviews with customer
Establishing project priorities
Creating WBS
Integrating WBS with OBS
Coding the WBS for the IS
MATERI
1. Penentuan tujuan proyek
2. Penentuan spesifikasi proyek
3. Penentuan hal-hal yang harus
dikerjakan (task)
4. Pembagian tanggung jawab secara
umum
1. PENENTUAN TUJUAN PROYEK
Tujuan proyek akan tergantung pada jenis proyek itu sendiri
Jenis proyek yang dimaksud adalah:
◦ Proyek engineering-konstruksi: pembuatan gedung bertingkat,
jembatan, dsb (pengkajian kelayakan, design engineering,
pengadaan & konstruksi)
◦ Proyek engineering-manufaktur: menghasilkan produk baru (desain
engineering, pengembangan produk, pengadaan, manufaktur,
perakitan, uji coba fungsi dan operasi produk)
◦ Proyek penelitian & pengembangan: output dan tahapannya
bervariasi
◦ Proyek pelayanan manajemen: merancang sistem informasi, dsb
(perencanaan, implementasi, evaluasi, laporan akhir)
◦ Proyek kapital: pembebasan tanah, penyiapan lahan, pembelian
material dan peralatan (kebutuhan, perencanaan, eksekusi,
evaluasi)
2. PENENTUAN RUANG LINGKUP
(SPESIFIKASI) PROYEK
1. Project objectives
2. Deliverables
3. Milestones
4. Technical requirement
5. Limits & exclusion
6. Reviews with customer
Project Scope
PROJECT OBJECTIVES
◦ To construct a high quality, custom home within five months
at cost not to exceed $150,000.
DELIVERABLES
◦ A 2,200-square foot, 2 1/2 bath, 3 bedroom, finished home.
◦ A finished garage, insulated and sheetrocked.
◦ Kitchen appliances to include range, oven, microwave, and
dishwasher.
◦ High-efficiency gas furnace with programmable thermostat.
MILESTONE
◦ Permits approved – March 5.
◦ Foundation poured – March 14.
◦ Final inspection – June 7
PROJECT MANAGEMENT TRADE-OFFS
Performance
Quality
Cost Time
CONSTRAIN IN PROJECT
SCOPE
BUDGET SCHEDULE
Quality
Project life cycle
Level
of
effort
Constrain
Enhance
Accept
3. PENENTUAN TASK -
WORK BREAKDOWN STRUCTURE
Level Hierarchical breakdown Description
1 Complete project
Project
4 Lowest management
Lowest subdeliverable responsibility level
Grouping of work packages
5
Cost account* for monitoring progress and
responsibility
Lowest manageable
5 subdeliverables Motor Circuit Chassis Read/write
board frame head
WBS OBS
Work Package 1
Work Package 2
Work Package 3
CODING THE WBS
1.0 Computer Project
1.1 Disk storage unit
1.1.1 Floppy
1.1.2 Optical
1.1.3 Hard
1.1.3.1 Motor
1.1.3.1.1 Sourcing work package
.
.
.
1.1.3.2 Read/write head
1.1.3.2.1 Cost account
LATIHAN
Tentukan proyek berserta output yang
diharapkan
Tentukan ruang lingkupnya
Buat work package untuk salah satu
task
Buat WBS