9575 TDGGuidelinesBusTerminals CITY REV
9575 TDGGuidelinesBusTerminals CITY REV
Bus Terminals
1.0 Introduction
2.0 Existing Guidance
3.0 Objectives
4.0 Design Guidance
City of Toronto
Transit Design Guide
Acknowledgements:
Access Planning
Figure 1: High-quality bus terminal design at Pioneer Village station,
Perkins&Will Toronto (Photo Credit: Wade Zimmerman, Azure Magazine)
1.0 INTRODUCTION
Toronto Examples.
1.1 Definition Victoria Park: Single direction bus loop allowing Housing
Bus Terminals | TRANSIT DESIGN GUIDE
Now development
2
stations on the future Line 5. These are found primarily at • Vertical Circulation: Stairs, escalators and elevators
The guidance in this document is specific to bus terminals and The supportive components of bus terminal function relevant to
are distinct from on-street stops which constitute a separate this guide include:
transit element with a unique set of design requirements1. • Transit Priority Measures: Infrastructure and Intelligent
Transportation Systems (ITS) measures to improve the
The core components of bus terminal function relevant to this reliability of travel time for buses in the immediate vicinity of
guide include: the terminal such as slip lanes or transit signal priority.
• Bus Bays and Platforms: Designated stopping locations • Future-Ready Utilities: Provisions for future systems such
for buses to accommodate pick-up and drop-off functions, as dynamic signage and electrification infrastructure for
typically signed for specific routes through static or variable buses and other modes.
signage. May be arranged in a saw-tooth, linear or drive-
through configuration to allow efficient ingress and egress • Active Transportation Integration: Interface between bus
of vehicles. terminal and active modes such as walking and cycling and
their associated infrastructure.
• Ingress & Egress Points: Access points for buses between
the bus terminal and the public right of way, typically • Climate Resilience Measures: Measures to mitigate the
crossing the sidewalk and curb bike lane (where existing). impacts of extreme weather events such as stormwater
management and heat resistance.
• Building Envelope: Terminal station buildings including
footprint on the site plan and massing. The TOD components of bus terminal function relevant to this
• Pedestrian Crossings: Designated places for interaction with guide include:
pedestrians and buses. • Overbuild Protections: Structural accommodations
• Layover Space: Spaces for buses to take scheduled necessary for future overbuild including support columns.
recovery time or to park while out of revenue service, may • Adjacent Development Parcels: Areas of land protected in
be separate from or combined with the pick-up/drop-off bay. bus terminal planning for future development opportunities
• Operator Facilities: Washrooms and break space for bus with necessary frontages and access opportunities to make
operators during layovers. development viable.
3
1.2 Areas of Influence
Bus Terminals | TRANSIT DESIGN GUIDE
The Zones of influence allow for the bus terminal guidance The size and footprint of the terminal itself inside Zone 3, as
to be applied in a way that respects agency jurisdiction while well as its access points, have profound implications for other
recognizing the need to coordinate overlapping objectives and areas outside of the bus operator’s jurisdiction. Furthermore,
manage/mitigate impacts. The internal design and operation the surrounding urban context has important implications for
of the bus terminal itself, particularly in off-street situations, is transit operations. The immediate surrounding transportation
recognized as being with the jurisdiction of the TTC (or other network accommodates bus access to the terminal, while
relevant transit operator). Considerations such as network plazas or other public realm provide pedestrian and cyclist
design, layover function, scheduling and stop assignment access to the transit station. Integrated and surrounding
are core areas of transit authority jurisdiction. Design development also helps to increase transit mode share and may
considerations in this guidance pertaining to this Zone 3 are provide important amenities to transit users that enhance the
therefore limited to how it interacts with and influences the customer experience and attractiveness of transit.
other zones.
4
In the context of Bus Terminals, the Zones of influence can be Zone 3 Core Transit Facilities: Includes the core area of the
5
1.3 Applications of Bus Terminals
Bus Terminals | TRANSIT DESIGN GUIDE
The application of bus terminal design is derived both from its role in the transit network and its immediate urban context. As such,
two groupings of applications have been developed to help understand bus terminals and provide more nuanced guidance to their
context. The applications may not be mutually exclusive.
Figure 9: Bus Network configured to provide heavy service to the current subway Figure 10: Local transit hub, Rosedale Station, Toronto (Photo Credit: TTC, Wiki Commons)
terminus at Finch Station, Toronto (Photo Credit: TTC, Wiki Commons)
6
Service and Form Applications (cont.)
Figure 13: Integrated facility, UBC Exchange (Photo Credit: Marcus Bowman)
Integrated Facility
This application refers to bus terminals that are fully integrated
into a larger facility that includes uses other than transit. This
may include either large mixed-use developments or public
facilities. Public facilities may include civic or educational uses
such as libraries, educational buildings or municipal offices.
Bus facilities may be fully or partially integrated within the
1 On-street transfers are distinct from Bus terminals, application of
facility, typically at- or below-grade. this guidance to these facilities should be read in conjunction with forthcoming
guidance for on-street stops.
7
Situational Applications
Applications of situation describe important context of the immediate surrounding area that impact the design of the facility. Bus
terminals have a fundamental connection to their surrounding urban environment which must be included throughout the design
Bus Terminals | TRANSIT DESIGN GUIDE
process, the applications described below represent some key drivers of design influence and are not exclusive of all considerations.
Figure 14: TOD Program at Exhibition Station, Toronto (Photo Credit: Infrastructure Ontario) Figure 15: Bus terminal siting for future redevelopment in the Mount Dennis Mobility Hub
Study (Photo Credit: Metrolinx)
Figure 16: Hydro Corridor condition at Kipling Station (Photo Credit: Wiki Commons)
8
1.4 Typical Project Delivery
1 2 3 4 5 6 7
At the Strategic Planning and Business Case Stage, work In the Design Development / Pre-Procurement, City Capital
should be undertaken to begin identifying typologies and the Works Coordination Stage, work should focus on translating
role of the bus network in supporting a rapid transit project. the master planning and site work into specific reference
This may include understanding the importance of connecting concept designs and requirements. Drawing on previous
bus transfers to driving ridership and other benefits as well as work identifying requirements of shared interest is important
identifying the key area(s) of interaction between the project under tight timelines during a procurement process. Design
and the overall bus network. needs from all collaborators can be adapted to the site-specific
context and balanced with shared objectives through a design
At the Master Planning and Preliminary Design Stage, work process that accommodates urban integration, site circulation
should focus on refining and confirming the typological and and optimal transit operations.
network role of Bus Terminal sites and incorporating these
with other city-building objectives. This includes understanding Collaborative Design Process
which sites will be the focus of integrated development Inter-agency planning processes are constructive and lead to
opportunities as well as the type of development anticipated. outcomes acceptable to participants when they are structured
Identifying the shared objectives of sites early enough in the and managed to identify and involve stakeholders from an
process will allow for integration with master planning and for early stage, when stakeholders understand basic elements
transit operators to properly understand potential implications of the process such as timelines, constraints and limitations,
for network design. This stage should also identify the major requirements, and anticipated outcomes. Bringing together the
goals of adjacent site circulation, including connections to objectives of all project partners and realizing the principles of
area master-planning work, potential transportation network the Guide and other existing guidance requires a collaborative
modifications and servicing requirements. At this stage, process that begins early with a common understanding of
operational needs from transit operators including TTC should shared objectives and outcomes for the site. These shared
be identified along with where specific design interventions objectives can then be translated into specific operational and
may be required. Undertaking substantial work in this area early design needs to meet overall objectives.
in the process will allow for well-informed inputs to reference
concept and detailed designs.
9
Unconstrained cumulative requirements can result in negative impacts to the urban environment and make other objectives such
as TOD, unviable. Recognizing this, trade-offs in program and design must be identified to meet the most important operational
requirements of specific interest and objectives, supported by analysis to demonstrate the site function. Through the design
Bus Terminals | TRANSIT DESIGN GUIDE
process, site requirements and needs can be adapted to the specific context of a site in question with regard for constraints
including the overall project budgets and value of land.
A design process that is collaborative and iterative can incorporate and balance objectives. Specific testing and proof of concept
development can be used to assure all parties that requirements are being satisfied. Outputs of the design process provide the
specifications necessary for project delivery and to support design review meetings with delivery proponents. An indicative design
process is mapped below.
Phase 1. Defining the Problem Phase 2. Iteration & Trade-Offs Phase 3. Detail & Delivery
Identification of Realization of
Trade-Offs and Prioritization
Key Objectives and Identified Objectives
Benefits & Benefits
Protec s
ting Key O l Need
pera tional & Functiona
• Service Modelling
• Micro-simulation
• Specifications
• Operator consultation
Design Process Delivery Process • Design review
• Master plan integration
CITY OF TORONTO
• Planning sequencing
• Proof of concept
• Iteration
2022
10
2.0 EXISTING GUIDANCE
11
3.0 OBJECTIVES
User Experience
They should maintain, enhance and/or establish new
opportunities for safe, accessible and direct access for all
modes of active transport to the surrounding public realm
rather than create barriers within a community. They should
also provide efficient and convenient connections to other
transit services.
12
4.0 DESIGN GUIDANCE
Urban Integration
3. Identify opportunities to wrap operational structures such 6. Assess the number and location of bus driveways along the
as operator break rooms with active frontages. Such street to balance pedestrian and bus movement objectives,
operational structures may also be located away from including redundancy.
exterior walls and as close to bus bays and layover spaces
7. Enable flexibility to use on-street pick-up/drop-off and
as possible.
layover as part of the bus terminal operation where feasible
4. Recognize the intrinsic connection of the local street grid for operations.
to the operation of the bus terminal by designing the street
8. Consider bus circulation routing as part of road network
grid surrounding the bus terminal to:
designs through area plans and studies.
a. Provide options for direct access routes to the bus
9. Recognize the need to accommodate scheduled layover and
terminal that provide efficient bus travel times and
recovery times at terminals sites and incorporate planning
network redundancies.
for layover spaces into overall site design.
b. Design access roads and impacted road right-of-way
10. Where on-street layover is considered, plan for specific
elements to support future multi-modal mobility and
locations and include design features that mitigate
community intensification under a Complete Streets
the impacts layover and address operational concerns
lens
including:
c. Support complimentary development and TOD
a. Plantings, screening and setbacks that minimize
opportunities
impacts on adjacent properties and the pedestrian
d. Provide multiple access routes to the bus terminal realm
entrance using the urban street grid to allow for
b. Maintain sightlines and visibility for pedestrians.
spreading bus volumes to different streets, reducing
bottlenecks and pedestrian conflict points where c. Pavement treatments that mitigate the visual impact of
possible. oil staining.
e. Assess the need to accommodate 180 degree turning d. Minimize circulation routes to the pick-up/drop-off area.
movements and associated large curb radii within the
bus terminal and minimise where feasible by providing e. Reasonable walking distances for vehicles operators to
efficient on-street options for turning movements, station facilities.
phased with the realization of a necessarily supportive
street grid.
13
Urban Integration
Bus Terminals | TRANSIT DESIGN GUIDE
Best Practices
Urban Integration at Bus Terminals
Figure 20: Prioritizing active urban frontages, Christchurch (Photo Credit: Michal
Klajban)
Figure 24: In the middle of Downtown Toronto, the newly opened Union Station Bus
Terminal is integrated directly inside the large station building. This location and
design help with preserving the urban landscape of the neighbourhood characterized
by high-class towers.
CITY OF TORONTO
Figure 21: Site permeability and visual cues, London Stratford, UK (Photo Credit:
2022
Marcus Bowman)
14
Urban Integration
11. Optimize the design of the bus terminal as well as the street 13. Design terminals with rectangular or regularly shaped
Best Practice
Supportive Urban Street Grid Surrey Centre, BC
Figure 26: Bus terminal setbacks to preserve a development parcel on the street Figure 27: Bus terminal configuration around perimeter of site allowing for future
frontage, Science Centre Station (Photo Credit: Metrolinx) redevelopment of commuter parking at 777 Victoria Park Ave. The yellow boundary
denotes entire property, not specific to development site (Photo Credit: CreateTO)
15
Urban Integration
14. Position adjacent development parcels to optimize active 15. Minimize driveways, blank walls and operational areas
Bus Terminals | TRANSIT DESIGN GUIDE
frontages, such as retail space, fronting onto principal along street frontages.
streets.
16. Provide a clear visual presence for the station pedestrian
Encourage Operational
functions setback
entrance.
from street frontage 17. Where TOD includes overbuild of the Bus terminal:
Building
a. Clearly identify objectives of built form characteristics.
Bus Platform b. Include necessary structural protections during initial
design and construction for potential overbuild to
reduce disruption once the terminal is operational.
Developable
Parcel c. Avoid structural elements that impede visibility for
safety, wayfinding, pedestrian and bus circulation and
avoid significant column placement on platforms and
Building passenger waiting areas.
Figure 28: Desirable bus terminal integration that allows for developable parcels on the e. Locate overbuild and integrated development above
street
layover functions to maximize daylighting of passenger
Irregular parcel 20. Prioritize at-grade retail frontages where bus terminals are
prevents development situated within a continuous at-grade retail context.
16
Urban Integration
Case Study With strong visual linkages to both the main street and
Urban Integration Focus Christchurch Bus buses on the interior of the site, the hall provides a point of
Interchange, New Zealand arrival and departure that looks to celebrate public space
and make use of the public transport system an enjoyable
In 2011 a powerful earthquake caused significant damage experience for all.
to the City of Christchurch, New Zealand. A new central bus
interchange was used as a catalyst for development and *The case study of Christchurch is used here to demonstrate some
potential approaches to active street frontages. It is not intended to
signal of the government’s commitment to the downtown
provided a direct example of how to design a bus terminal in Toronto as it
area. Urban Integration, including active frontages and is not consistent with TTC operating practices.
development potential were heavily prioritized in the
design. This unique development context offers several
innovative approaches for a how a bus terminal may
.
optimize its urban integration.
How Urban Frontages Were Achieved:
Active frontages were achieved on two of the four sides
(west and north) with the east and south sides enable
future integrated development or the expansion of the
facility. The L-Shaped concourse provides a “strong Figure 31: Christchurch frontage (Photo Credit: Christchurch Council)
urban edge” on the north and west streets, which are the
prominent sun-lit aspects for a building in the southern
hemisphere. A strong contextual link is created by the
materiality and façade articulation along a main arterial,
which references the adjacent historic buildings that
survived the earthquakes. On Christchurch’s main street, a
large folding roof shape provides scale and articulation to
signal the building’s civic function.
Figure 32: Christchurch frontage and synergy with bus terminal (Photo Credit:
Christchurch Council)
17
Urban Integration
-
facilities to consolidate facility footprints.
Bus Platform
Bus Terminal
25. Consider desire lines for pedestrian movements within and
around the bus terminal site and accommodate the most
direct paths in the configuration of the bus terminal.
Bus Terminal
Building Building
CITY OF TORONTO
Figure 34: Undesirable bus terminal integration with multiple site barriers preventing easy
access to the terminal
2022
18
Urban Integration
Figure 37: High-quality design in civic placemaking, Chatham Waterfront, UK (Photo Figure 38: Retail frontages as a design priority at Christchurch Bus Interchange,
Credit: Wiki Commons) Christchurch, New Zealand (Photo Credit: Google Maps)
19
User Experience
Figure 39: Lightwell integrated into bus terminal overbuild at Lonsdale Quay Exchange,
2022
20
User Experience
"B" signal
indicates buses
Two cycle signals can proceed
which are triggered
when a bus approaches
Pedestrian "do-not-
cross" synchronized
with cycle signal
21
Sustainability &
Resilience
4.3 Resiliency and Sustainability
Bus Terminals | TRANSIT DESIGN GUIDE
Best Practice
1. Provide green roof or solar energy generation where
Bioswales at Bus Terminals, Springfield, OR
overbuild is not planned or feasible (e.g. hydro corridor).
2. Locate pedestrian and waiting areas away from bus idling With large areas of paved surface, bus terminals
areas. can present an opportunity to mitigate stormwater
runoff. Landscaping elements can be combined to
3. Minimize the circulation distances required by buses, direct pedestrian paths and prevent conflicts with bus
within and around terminals, to reach pick-up and drop-off circulation. Bioswale functions may make use of remnant
bays, to reduce vehicle kilometers travelled and associated parcels.
emissions.
Opened in 2006 the Springfield Bus Terminal prioritized
4. Avoid large areas of impermeable surface and consider
stormwater management with extensive landscaping in
incorporating the use of bioswales and natural planting
the design. A central landscaped area within the island
areas; these features may also be used to help discourage
platform connects to an adjacent bioswale for treating
unsafe pedestrian crossings.
stormwater quantity and quality.
5. Include durable plantings in traffic islands and boulevards.
Figure 43: Landscaping around Springfield Bus Terminal (Photo Credits: Federal
CITY OF TORONTO
Transit Administration)
2022
22
Intermodal
Operations
4.4 Intermodal Operations
3. Provide sufficient frontage for site access and consolidate b. Repurposing general purpose or median turn lanes for
access points at signalized intersections for adjacent reserved bus lane to avoid widening roadways.
development parcels and integrated development sites.
Bus Loop
as necessary to manage potential delays to buses that
would impact the operator’s ability to maintain schedule
adherence.
Figure 44: Desirable bus terminal integration with consolidated access points
b. Ensure that such consolidated access points provide and visible crossing allowing for safe movement of users
23
Intermodal
Operations
Bus Terminals | TRANSIT DESIGN GUIDE
Figure 48: Transit station plaza area, Fairbank Station (Photo Credit: Metrolinx)
24
Accountability
4.5 Accountability
2. Consider design implications of potential near-future 5. Seek opportunities to accommodate growth through
changes in policy and technology such as: increased efficiency rather than additional space allocation.
a. Different fare payment models that may reduce the 6. Consider dynamic passenger messaging systems or
need for fare-paid areas; dynamic bus bay assignment where appropriate that may
help to marginally increase bus terminal capacity in case of
b. New technologies such as autonomous vehicles; and
future demand growth.
c. New service delivery models such as micro-transit.
Best Practice
*Not all terminus stations will see reduced volumes if a line is extended,
Temporary Terminus Point, Mount Dennis
careful coordination with service planning is required to understand
Mobility Hub Study, Toronto network assumptions.
Figure 50: Mount Dennis Mobility Hub Study - Long term (Photo Credit: Metrolinx)
25
Accountability
Bus Terminals | TRANSIT DESIGN GUIDE
Best Practice
Dynamic Bus Bay Assignment
26
Bus Terminals | TRANSIT DESIGN GUIDE
This page is intentionally left blank.
27
Figure 53: York University Station, Toronto (Photo Credits: Shai Gil) @CityplanTO toronto.ca/planning