Gis 42-102
Gis 42-102
GIS 42-102
Applicability Group
Date 3 May 2005
GIS 42-102
DO NOT COPY
BP GROUP
ENGINEERING TECHNICAL PRACTICES
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
Foreword
This is the first issue of Engineering Technical Practice (ETP) BP GIS 42-102. This Guidance on
Industry Standard (GIS) is based on parts of heritage documents from the merged BP companies as
follows:
British Petroleum
GS 118-7 The Fabrication, Assembly, Erection and Inspection of Austenitic and
Duplex Stainless Steel, Cupro-Nickel, Nickel Base Alloy, Titanium and
Zirconium Pipework to ASME B31.3.
Amoco
A PN-PLT-31.3-C Piping—Plant—ASME B31.3—Construction Specification.
A PN-PLT-31.3-CG Piping—Plant—ASME B31.3—Construction and Fabrication Guide.
A PN-PLT-31.3-P Piping—Plant—ASME B31.3—Fabrication Specification.
ARCO
Std 200 Piping Design.
DO NOT COPY
Copyright © 2005, BP Group. All rights reserved. The information contained in this
document is subject to the terms and conditions of the agreement or contract under which
the document was supplied to the recipient’s organisation. None of the information
contained in this document shall be disclosed outside the recipient’s own organisation
without the prior written permission of Director of Engineering, BP Group, unless the
terms of such agreement or contract expressly allow.
Page 2 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
Table of Contents
Page
Foreword............................................................................................................................................2
Introduction ........................................................................................................................................5
Chapter I Scope and definitions........................................................................................................6
300 General statements ..................................................................................................................6
300.1 Scope ............................................................................................................................6
300.4 Status of appendices .....................................................................................................6
Chapter V Fabrication, assembly, and erection ................................................................................7
327 General .....................................................................................................................................7
327.1 Quality assurance and positive material identification ...................................................7
327.2 Material control ..............................................................................................................8
327.3 Pipework marking ..........................................................................................................8
327.4 Fabrication facilities .......................................................................................................8
328 Welding.....................................................................................................................................9
328.2 Welding qualifications....................................................................................................9
328.3 Welding materials ........................................................................................................11
328.4 Preparation for welding................................................................................................12
328.5 Welding requirements..................................................................................................13
330 Preheating ..............................................................................................................................16
330.1 General........................................................................................................................16
331 Heat treatment ........................................................................................................................17
331.1 General........................................................................................................................17
331.2 Specific requirements ..................................................................................................18
332 Bending and forming...............................................................................................................19
332.1 General........................................................................................................................19
332.2 Bending .......................................................................................................................19
335 Assembly and erection ...........................................................................................................20
DO NOT COPY
335.1 General........................................................................................................................20
Chapter VI Inspection, examination, and testing ............................................................................21
341 Examination ............................................................................................................................21
341.3 Examination requirements...........................................................................................21
341.4 Extent of required examination ....................................................................................21
342 Examination personnel ...........................................................................................................21
342.1 Personnel qualification and certification ......................................................................21
343 Examination procedures .........................................................................................................21
344 Types of examination..............................................................................................................22
344.2 Visual examination ......................................................................................................22
Page 3 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
List of Tables
Table 1 – Acceptance criteria for welds (to be read in conjunction with Table 341.3.2 of
ASME B31.3) ..........................................................................................................................24
Table 2 – Acceptable radiographic sensitivity levels (using wire type IQI to ASTM E747 or BS
EN 462-1) ...............................................................................................................................25
List of Figures
DO NOT COPY
Figure 4 – Segmental bends............................................................................................................29
Page 4 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
Introduction
a. Guidance for fabrication, assembly, erection, and inspection of austenitic and duplex
stainless steel, cupro-nickel, nickel base alloy, titanium, and zirconium pipework is based
on American Society of Mechanical Engineers (ASME) B31.3, Process Piping, 2002:
1. Chapter I Scope and definitions.
2. Chapter V Fabrication, assembly, and erection.
3. Chapter VI Inspection, examination, and testing.
b. Guidance statements of this GIS are modifications to ASME B31.3.
c. Modifications to ASME B31.3 are identified as Add, Modify to Read, or Delete.
d. Paragraph numbers in this ETP correspond to ASME B31.3.
e. Paragraphs of ASME B31.3 that are not revised remain applicable.
DO NOT COPY
Page 5 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
300.1 Scope
300.1.3 Exclusions
Add
(e) Sea transport.
(f) Transmission pipelines in land or subsea locations, including risers.
(g) Pipelines of significant length and diameter, e.g., transfer lines between processing units,
storages, and jetties that are specified by BP to be engineered as main pipelines.
(h) Production piping systems, as designated by BP.
Production piping is covered by BS EN 14161 and ASME B31.4.
(i) Underground drainage systems.
(j) Steam piping systems within plot limits of power stations and steam generating stations
outside process areas.
Steam piping is covered by ASME B31.1 and BS EN 13480.
There is no ETP currently available to cover this category. However, guidance on
these systems can be found in ACES A PN-BLR-31.1-E and BP OUS RP 5-5-4.
(k) Heating, ventilating, and domestic water systems within buildings, including offshore
accommodation modules.
(l) Hydraulic systems.
DO NOT COPY
Page 6 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
327 General
Add
DO NOT COPY
should submit positive material identification (PMI) document setting out how they
maintain and verify identification of materials during fabrication. GIS 36-103 sets
out requirements for a PMI system.
Page 7 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
DO NOT COPY
a. Area used for fabrication shall be totally separate from that used for carbon and low alloy
steel.
1. Each alloy type shall be segregated during fabrication.
2. Precautions shall be taken to prevent surface contamination by contact with jigs and
fixtures manufactured in non compatible materials.
3. Separate sets of clearly identified cleaning and grinding equipment shall be provided
for each material.
b. Shop layout, equipment, and production procedures shall be subject to BP approval,
particularly if fabrication of titanium or zirconium is involved.
Page 8 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
328 Welding
DO NOT COPY
Specimen Size (mm) Specimen Size (in) Reduction Factor
10 x 7.5 0.394 x 0.295 0.833
10 x 5 0.394 x 0.197 0.667
10. If welding procedure requiring impact testing is to be used in all positions, separate
2G and 5G qualifications shall be performed.
(e) Modify to Read
Backing rings are not permitted.
(f) Add
P-Numbers (also F-Numbers)
Page 9 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
DO NOT COPY
deposit acceptable root runs in both 2G and 5G positions. With the agreement of BP, this
may be achieved by radiography of welder’s first production welds in 2G and 5G
positions.
(l) Welders and welding operators shall be qualified by visual examination and radiography,
except in case of titanium or zirconium, which also require mechanical testing in
accordance with Appendix O. In the case of 25% Cr duplex stainless steels (Appendix N)
corrosion testing may be required.
Subject to provision of authenticated CV and with agreement of BP, welders and
welding operators may be qualified on their initial production welds for materials
other than 25% Cr duplex stainless steels, titanium and zirconium.
(m) Welder and welding operator qualification tests shall be witnessed by inspector.
Page 10 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
Add
DO NOT COPY
result in a reduction of notch toughness in 300 series austenitic stainless steel weld
metals. If PWHT is specified for pipework in low temperature service or if the piping
design code includes notch toughness requirements, welding procedure tests should
ensure that PWHT does not result in unacceptable embrittlement. This is especially
relevant for filler metals containing niobium or molybdenum.
Higher alloy austenitic stainless steels, such as those containing 20% or greater Ni
and/or 4% or greater Mo often require use of nickel base weld metals to ensure
sound weld metal of adequate corrosion resistance.
Some specific guidance on filler metal selection is provided in the appendices. Final
guidance concerning any special requirements, including selection of filler metal
composition for dissimilar metal joints or fabrication of corrosion resistant alloy
clad components, should be provided by engineering design.
Page 11 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
328.4.1 Cleaning
Add
a. Working practices shall be designed to minimise contamination.
b. Before welding, internal and external surfaces shall be cleaned for distance of at least
50 mm (2 in) from fusion face.
c. Surfaces to be joined by welding shall be stainless steel wire brushed and degreased
immediately prior to welding.
d. On small pipes, for which it is not possible to wire brush internal surface, an approved
chemical cleaning material shall be used.
e. Degreasing agents shall leave no chloride or sulphide containing residues on the surface.
DO NOT COPY
(b) Circumferential welds
(4) Modify to Read
Weld metal buttering shall not be deposited to assist alignment or provide sufficient
material for machining without BP approval.
Add
(6) Prior to fitup, weld bevels shall be visually inspected, supplemented by dye penetrant
or, if appropriate, magnetic particle examination, if considered necessary by
fabricator or BP inspection or welding personnel.
Page 12 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
328.4.3 Alignment
(a) Circumferential welds
Add
(3) Bore misalignment in circumferential butt joints shall not exceed 1.5 mm (1/16 in)
without BP approval.
(c) Branch connection welds
(3) Add
Weld metal shall not be deposited to correct contour, shape, or tolerances without
permission of BP.
Add
(e) Fabrication tolerances
1. Unless approved otherwise, fabrication tolerances shall comply with Figure 2.
2. Category M tolerances shall be used:
a) For service temperatures greater than 460°C (850°F).
b) PN 150 (Class 900) ratings and above.
c) If specified by engineering design.
3. If, when welding austenitic steels, design changes are necessary to comply with
defined tolerances, such changes shall be approved by BP.
Weldments in austenitic steels are prone to distortion due to their high coefficients
of thermal expansion and low thermal conductivity. Fabricators should consider this
before beginning to weld. In some cases, changes to design details will mitigate risk
of distortion.
328.5.1 General
(b) Modify to Read
Welds shall be marked with welder/welding operator identification symbol using marker
pencils or paints that comply with 327.3.
(c) Modify to Read
(1) Preference shall be given to use of lineup clamps or bridge tacks that do not interfere
with deposition of a continuous root run.
DO NOT COPY
(2) Root tack welding, if approved, shall not commence until bore purging has been
established.
(3) Tacks, if they are to be incorporated in final weld, shall be cleaned prior to the root
pass and the ends feathered by grinding.
(4) Interval between tack welding and deposition of root pass shall be minimised to
reduce contamination.
(5) Removal of bridge tacks shall be by mechanical grinding only.
To reduce the risk of contamination of the weld zone clamp, face and bridge tack
materials should be of the same material as or be compatible with that being
welded.
Page 13 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
DO NOT COPY
If erecting pipe spools, particularly in large diameter pipework, forethought should
be given to installation of internal dams to minimise use of purge gas.
If initiating flow of purge gas, a general rule of thumb that may be used is that 'all
air may be removed by admission of a volume of purge gas at least six times the
volume of air being displaced.' However, if welding more reactive materials, such as
titanium and zirconium, dew point measurements are desirable to establish the
quality of the purge. In general, oxygen meters are valuable for monitoring
purposes.
It is often adequate for austenitic steels to ensure a flow of purge gas during the
deposition of the root and the first/second fill passes, provided that the bore is
subsequently sealed to prevent atmospheric ingress. However, in the case of higher
alloy stainless steels, nickel alloys, and the more reactive materials, such as
Page 14 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
titanium and zirconium, a positive purge flow should be maintained throughout the
welding operation.
Guidance on the need for extended purge times is provided in the appendices and
will be supplemented as necessary by the engineering design.
(p) Unless approved otherwise, SAW, FCAW, and GMAW shall not be performed on pipes
smaller than DN 150 (NPS 6).
(q) Root welds should be completed without interruption other than to allow the welder to take
a new length of filler wire or to reposition himself.
(r) Vertical down welding is not permitted.
(s) Temporary attachments
1. Temporary attachments to outside surface of pipe shall be minimised and shall not be
made without BP approval.
2. Attachments that are permitted shall be made in controlled manner to avoid oxidation
of internal surface of pipework.
3. Fabricator shall advise what precautions he proposes to take with regard to fixing and
removing temporary attachments to and from such materials.
(t) If practical, fillet welded joints for pressure containment should have minimum of three
weld passes, two of which should be showing for visual inspection.
The above additions and modifications to welding requirements have been made on
the basis of fabrication experience and allow welding to proceed with improved
level of confidence in workmanship and practice.
DO NOT COPY
If designing angled branch connections, in addition to considering stress concentration effects,
sufficient access shall be provided for welding in acute angle section.
If set on integrally reinforced branch connections are used, it should be noted that
the wall thickness of the connection may well be in excess of that necessary to
provide the required level of reinforcement. Consequently, no reinforcement
contribution is necessary from the weld metal, and the deposition of a branch weld
with an excessive throat thickness may lead to unacceptable distortion of the main
run pipe. The engineering design should provide guidance on the sizing of branch
welds if using this type of fitting and on the need for controlled weld profiles if the
branch is on severe cyclic duty.
If set in integrally reinforced branch connections are used, fit up, jigging, and
developing an overall welding sequence, should minimise the extent of any
"sinking".
Page 15 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
The use of integrally reinforced branch connections on thin wall pipes, sch. 10 and
below, should be avoided.
Add
330 Preheating
330.1 General
In general, materials covered by this GIS do not require preheating for welding
except to drive off moisture or raise component temperature above 0°C (32°F).
DO NOT COPY
330.1.1 Requirements and recommendations
Add
a. Cupro-nickel alloys may be preheated to a maximum temperature of 50°C (120°F).
b. Oxy-fuel gas welding or cutting torches may only be used for preheating if fitted with
proprietary preheating nozzles.
Preheating of cupro-nickel is not normally necessary. However, for high heat sink
welds, i.e., tee butt welds or if one of the members being fabricated is relatively
thick, preheats of up to 50°C (120°F) may be applied to aid fusion.
Page 16 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
Add
331.1 General
DO NOT COPY
(g) Specific applications for which heat treatment is required shall be identified by the
engineering design.
If austenitic stainless steels are exposed to process environments containing
chlorides or polythionic acids, the presence of residual stresses generated by either
welding or mechanical working may lead to stress corrosion cracking. Stress relief
heat treatment may consequently be necessary prior to service.
(h) If stress relief heat treatment of austenitic steels is specified by the engineering design,
welds shall be heated to temperature in range of 900°C - 950°C (1650°F - 1740°F) and
held for 1 hour per 25 mm (1 in) of thickness. Minimum soaking period shall be 1 hour.
(i) Low melting point metals, such as aluminium, lead, tin, copper, zinc, cadmium, and
mercury, and their alloys, shall not be permitted to contact surfaces that will undergo hot
forming, welding, or post weld heat treatment.
Page 17 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
DO NOT COPY
b. In the case of branch attachments, temperature gradient shall be such that length of
material from each crotch heated to temperature equalling half heat treatment temperature
shall be 1.8 Dt (where ‘D’ and ‘t’ are the nominal diameter and thickness of the main
pipe and branch as appropriate) (Figure 3).
c. In a. and b., ‘D’ is expressed as DN (NPS), ‘t’ is expressed in mm (in), and temperature is
expressed in °C.
The above modification is made to clarify the requirements for local post weld heat
treatment.
Page 18 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
332.1 General
Add
a. Bending of stainless steel and nickel alloy pipe should be done cold.
b. If size and schedule of pipe is such that cold bending becomes impractical, hot bending
may be used.
c. Unless specified otherwise, factory manufactured piping fittings shall be solution heat
treated in temperature range specified by alloy manufacturer.
For some highly corrosive applications the use of pulled bends is not permitted. For
such applications, the engineering design will define the appropriate bend
manufacturing processes.
332.2 Bending
DO NOT COPY
If cold bending of alloy pipe produces local strain in excess of 10% consideration
should be given to application of post forming heat treatment and any specific
requirements should be stated in engineering design.
Page 19 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
335.1 General
335.1.1 Alignment
(a) Piping distortions
Add
Piping distortions. Application of heat for correction of minor distortions shall only be
undertaken with BP approval.
Add
DO NOT COPY
Page 20 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
341 Examination
341.3.1 General
(a) Modify to Read
Final examination shall be performed after completion of heat treatment.
DO NOT COPY
d. Personnel qualifications shall be subject to BP approval.
Under most circumstances, ‘equivalent certification’ will only be considered if the
body issuing certification meets the requirements of ISO 9712 or EN 473.
Add
Examination procedures shall comply with 327.1.1.
Page 21 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
344.2.1 Definition
Add
Visual examination shall include examination of internal surface of weld, if possible, using
suitable optical instruments.
344.5.1 Method
Modify to Read
a. X-ray techniques are preferred for shop radiography of pipework up to 25 mm (1 in) wall
thickness.
b. If use of X-rays is impractical, gamma ray isotopes may be used, subject to BP approval.
c. In each case, prior to production radiography the technique shall be qualified using source
side image quality indicator (IQI) of wire type to ASTM E747 or BS EN 462-1, whichever
is applicable.
d. Single wall, single image technique should be used if possible.
e. Lead intensifying screens and fine grain high contrast film shall be used.
f. Film density shall be 2.0-3.0 through thickest portion of weld.
g. IQI specified in accordance with BS EN 462 1 shall have radiographic sensitivity that
complies with Table 2.
h. If complete joint circumference is radiographed in a single exposure, four IQIs placed at
π/2 radian (90 degree) intervals shall be used.
i. Set on branch connections if permitted by engineering design, should be subject to
intermediate radiography.
2. Film shall be on bore side of joint.
3. Radiography shall be performed when weld depth is similar to wall thickness and
before reinforcing fillet is applied.
DO NOT COPY
Modify to Read
Spot radiography shall not be used for girth, mitre, or branch welds.
Page 22 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
complete to depth of approximately 30% of wall thickness. This minimises the need
for through wall repairs.
Following repairs to the root and reexamination, the weld should be completed and
subjected to final examination.
345 Testing
DO NOT COPY
Add
a. Before starting fabrication, the fabricator and BP shall agree which types of welding
defects are to be regarded as notifiable prior to rectification.
b. Fabricator shall subsequently advise BP of need to perform such repair, which shall be
subject to approval prior to commencement of further work on defective welds.
c. Detailed records of repairs shall be retained by fabricator.
d. Repair welding shall comply with approved repair procedures, unless use of original
procedure has been agreed with BP.
Page 23 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
e. As a minimum, repair welds shall be inspected to their full extent using techniques used
for inspection of initial weld.
f. If cracking has occurred in either weld metal or heat affected zone and a repair has been
agreed:
1. The full extent of the original weld shall be re-examined on completion of the repair .
2. BP may require that additional inspection technique to be applied to the joint
following repair.
g. Weld repairs shall, if practical, be performed prior to post weld heat treatment. If a second
heat treatment is necessary, details of procedure qualification requirements shall be agreed
with BP.
Application of a second heat treatment may have adverse effects on the properties of
weld metal and some base materials. Thus, it may be necessary to consider a
qualification test using previously welded and heat treated material for qualification
of repair techniques. In such cases, additional testing of parent material should be
performed.
Table 1 – Acceptance criteria for welds (to be read in conjunction with Table 341.3.2 of ASME B31.3)
DO NOT COPY
Page 24 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
1
Thickness X-Radiography Gamma Radiography
mm in SWSI DWSI DWDI SWSI DWSI DWDI
≤ 4.5 ≤ 0.177 Note 3 Note 3 Note 3 Note 3 Note 3 Note 3
4.5 – 6.0 0.177 – 0.236 2.0% 2.5% 3.2% 2.6% 2.7% 3.5%
6.0 – 9.0 0.236 – 0.354 1.7% 2.0% 3.0% 2.4% 2.5% 3.2%
9.0 – 14.0 0.354 – 0.551 1.5% 1.8% Note 3 2.4% 2.5% Note 3
14.0 – 18.5 0.551 – 0.728 1.4% 1.7% NA 2.0% 2.2% NA
18.5 – 26.0 0.728 – 1.024 1.3% 1.7% NA 1.7% 2.0% NA
26.0 – 40.0 1.024 – 1.574 1.1% 1.7% NA 1.5% 1.8% NA
>40.0 >1.574 Note 3 Note 3 Note 3 Note 3 Note 3 Note 3
1. Thickness for SWSI and DWSI is estimated single weld thickness. Thickness for DWDI is one wall thickness plus one
estimated weld thickness.
2. Sensitivity shall be no worse than the values given in this Table. Sensitivity values are based on IQI placed on film side
for SWSI and DWSI exposures and IQI on source side for DWDI exposures. Sensitivity shall be calculated using the
formula:
Thickness of thinnest wire visible in weld area
Sensitivity = Thickness 1
3. Sensitivity requirement to be agreed with BP following production of test radiographs.
DO NOT COPY
Page 25 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
2mm MAX
FL + 1mm
FL + 2mm
FL + 5mm
DO NOT COPY
NOTCH POSITIONS
Weld metal centre line, FL and FL+2 mm testing is mandatory. The need for other notch locations to be tested shall be identified
by the engineering design.
<25 mm (1 in) wall thickness = charpy specimens to be taken from weld cap.
≥25 mm (1 in) wall thickness = charpy specimens to be taken from the root and cap regions.
Page 26 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
CL
A B
CL
CL D
A
A
A
CL
A
E
DO NOT COPY
Page 27 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
1.8 D1 t 1
1.8 D2t 2
DO NOT COPY
Page 28 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
DO NOT COPY
Page 29 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
ASNT
Add
CP-189 Qualification and Certification of Nondestructive Testing Personnel.
ASTM
Add
E 562 Standard Test Method for Determining Volume Fraction by Systematic
Manual Point Count.
E 747 Standard Practice for Design, Manufacture and Material Grouping
Classification of Wire Image Quality Indicators (IQI) Used for
Radiology.
AWS
Add
QC1 Standard for AWS Certification of Welding Inspectors (1996 or later
edition).
Add
BP
GP 18-02 Guidance on Practice for Storage and Control of Welding Consumables.
BSI Standards
BS EN 462-1 Non-destructive testing - Image quality of radiographs - Part 1: Image
quality indicators (wire type) - Determination of image quality value.
EEMUA standards
EEMUA 153 Process Piping-Supplement to ASME B31.3.
DO NOT COPY
Page 30 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
Add
Appendix N Additional requirements for 22%Cr and 25%Cr duplex stainless steel
materials
N1. Introduction
a. This appendix lists significant differences and additional precautions required for
fabrication of duplex stainless steels.
b. This appendix shall be read in conjunction with main body of this GIS.
N2. Welding
DO NOT COPY
b. Other proprietary compositions specifically manufactured for duplex steels may be
appropriate.
c. Selection shall be made to meet ferrite level of 35% - 65% in all regions of weld metal and
minimum PREn value of 34 for 22%Cr duplex and 40 for 25%Cr duplex.
d. Additional guidance on filler metal selection may be provided by engineering design.
The corrosion resistance of duplex stainless steel weldments is totally dependent on
the two criteria above, ferrite level and PREn, and they must not be relaxed without
specialist consideration.
Page 31 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
DO NOT COPY
N2.7 Preheat and interpass temperature
a. Preheating shall not generally be used except to remove moisture from joint.
b. Maximum interpass temperature for 22%Cr duplex steels shall be 150°C (300°F).
c. Maximum interpass temperature for 25%Cr duplex steels shall be 125°C (257°F).
N3.1 P-Numbers
a. P-Numbers shall not apply to duplex stainless steels.
b. Each alloy designation shall be separately qualified.
Page 32 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
DO NOT COPY
N3.6 Essential variables
The following additional essential variables shall apply to duplex stainless steels:
a. Tolerance of minus 0, plus 2 mm (5/64 in) shall apply to qualified procedure root gap.
b. Each pipe wall thickness less than or equal to 5 mm (3/16 in) shall be separately qualified.
c. For thicknesses greater than 5 mm (3/16 in), the following qualified thickness range shall
apply to each thickness (t) tested:
22%Cr 0.5t (but not less than 5 mm (3/16 in))
–1.5t (subject to a maximum thickness of 25 mm (1 in)).
22%Cr > 25 mm (1 in) and 25%Cr 0.75t (but not less than 5 mm (3/16 in))
–1.0t.
Page 33 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
These thickness limitations reflect the need for control over the thermal cycle
applied to duplex steels during welding in order to maintain the ferrite/austenitic
balance and prevent the formation of intermetallic phases.
d. No change shall be made in type of groove or in basic groove design from that used in
qualified welding procedure specification. If welding in pipe bore is to be applied, an
appropriate welding procedure shall be qualified.
e. Electrode size used in qualified welding procedure may be reduced by no more than one
size. No increase in maximum size of electrode is allowed.
N5.1 General
a. Welding instruction card shall include details of root gap and heat inputs to be used.
b. Bridge tacking shall be used for butt welds.
DO NOT COPY
c. Each temporary attachment shall be subject to BP approval.
Page 34 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
Add
O1. Introduction
a. This appendix lists significant differences and additional precautions required for
fabrication of titanium and zirconium.
b. This appendix shall be read in conjunction with the main body of this GIS.
O3. Welding
DO NOT COPY
a. Filler metals shall:
1. Have same nominal composition as base material.
2. Comply with AWS A5.16/A.16M (titanium) and A5.24 (zirconium).
b. Filler wires shall be thoroughly cleaned and degreased. Degreasing agent shall leave no
chloride and sulphide residues on surface.
c. After cleaning, wires shall be handled with clean gloves specifically issued for either
titanium or zirconium fabrication.
d. Welder shall ensure that end of filler wire is kept within gas shield at all times during
welding by restricting weaving of welding wire to a minimum.
e. Prior to each weld pass, end of filler wire shall be cut to expose clean wire using chromium
plated wire cutters.
Page 35 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
DO NOT COPY
1. Restricted to 100°C (212°F).
2. Measured by contact thermometer.
Page 36 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
O6.1 General
a. Welding instruction card shall emphasise need to strictly adhere to cleaning and gas
shielding/purging procedures.
b. Preference shall be given to use of lineup clamps. Bridge tacks may be used with
agreement of BP.
c. Temporary welded attachments are not allowed.
DO NOT COPY
c. Quality plan and welder instruction card shall clearly define procedure and individual
responsibilities associated with this examination.
Weld Colour Significance Shielding Action
Silver Generally a Good Clean with stainless steel wire brush, proceed to
good weld NDT or next weld pass.
Pale straw Acceptable Fair Discoloration should be removed with stainless steel
weld brush before next pass.
Light Poor weld Poor Remove weld bead and adjacent metal completely;
blue/purple improve shielding before rewelding.
Grey or yellow Very poor weld Extremely Remove weld bead and heat affected zone
powder poor completely. Examine shielding equipment for leaks,
gas supply, etc. Make test welds before re-welding.
Page 37 of 38
3 May 2005 GIS 42-102
Guidance on Industry Standard for Fabrication, Assembly, Erection, and Inspection of Austenitic and Duplex Stainless
Steel, Cupro-Nickel, Nickel Base Alloy, Titanium, and Zirconium Pipework (ASME B31.3)
Bibliography
[2] ASME B31.4 Pipeline Transportation Systems for Liquid Hydrocarbons and other Liquids.
BP
[3] GIS 36-103 Guidance on Industry Standard for Positive Material Identification (PMI).
[6] BS 5383 Material identification of steel, nickel alloy and titanium alloy tubes by continuous
character marking and colour coding of steel tubes.
[8] BS EN 14161 Petroleum and natural gas industries – Pipeline transportation systems.
DO NOT COPY
Page 38 of 38