Labour Boq - D Type Model
Labour Boq - D Type Model
BILL NO. 1
Cost for operation costs including provision of equipment and tools on site
scaffolding, plate compactors, concrete pokers, safety requirements as required,
provision of all necessary secondary equipment i.e dumpy levels to ensure works
are constructed as provided for by the building by laws of Zimbabwe
FOUNDATIONS (PROVISIONAL)
SITE PREPARATION
Site Clearance
A Allow for clearing site including all rubbish, debris and boulders,
cutting down and removing all grass, shrubs and bushes and
trees having a trunk girth e not exceeding 500mm and
grubbing up and removing all roots and filling in with suitable
materials and well consolidating m2 263 0.90 236.70
EXCAVATIONS
C Allow for keeping the excavation free from storm and surface
water by bailing or pumping through out the duration of the contract item R.O 145.00
F Extra over all excavations in pickable material for hard pickable m3 R.O 72.56
material including any extra cost of disposal
H Maintain and support sides of all excavations and make good m2 R.O 62.36
K Approved inert granular filling levelled under solid floors in one layer
average 150mm thick compacted to 98 % H.C.E m3 17 11.50 200.91
Antproofing
L Approved white ant treatment executed by approved specialist
firm on top filling ,the work supplied with a written fifteen
years guarantee against termite infestation m2 117 0.20 23.40
CONCRETING
Concrete (grade 30-20 mm stone) in:
Formwork to:
Sundries
S Strike off and cure level top of ground floor slab m2 117 0.10 11.70
Fabric reinforcement
BRICKWORK (Foundations)
Bricks to foundations shall be load bearing
Foundation depth to be verified by engineer
250 micron black plastic sheeting laid with 150mm wide joints on sand and
sealed at all joints and including all cutting and waste
BILL NO 3 : BRICKWORK
VENTILATION
CONCRETING
Concrete (grade 30-20 mm stone) in:
Formwork to:
reinforcement steel
S eaves beams and lintels kgs 600 0.25 150.00
SUBTOTAL $ 7,952.52
TOTAL $ 7,952.52
MAIN HOUSE LABOUR SUMMARY
SUMMARY
11 GLAZING #REF!
12 PAINTING #REF!
SUBTOTAL #REF!
TOTAL #REF!
Resource Steel and Construction
FOUNDATIONS (PROVISIONAL)
SITE PREPARATION
Site Clearance
A Allow for clearing line including all rubbish, debris and boulders,
cutting down and removing all grass, shrubs and bushes and
trees having a trunk girth e not exceeding 500mm and
grubbing up and removing all roots and filling in with suitable
materials and well consolidating m 273 4.29 1,171.17
EXCAVATIONS
C Allow for keeping the excavation free from storm and surface
water by bailing or pumping through out the duration of the contract item R.O 145.00
3
D Surface trenches not exceeding 1000mm deep m 194 23.49 4,557.06
3
E Extra over all excavations in pickable material for hard pickable m R.O 72.56
material including any extra cost of disposal
3
F Ditto in hard rock ditto (Provisional) m R.O 102.00
2
G Maintain and support sides of all excavations and make good m R.O 62.36
Antproofing
I Approved white ant treatment executed by approved specialist
firm on top filling ,the work supplied with a written fifteen
2
years guarantee against termite infestation m 188 1.20 225.60
CONCRETING
Concrete (grade 25-20 mm stone) in:
3
J Strip footing m 42 464.85 19,523.70
BRICKWORK
Bricks to boundary wall shall be load bearing
2
K One brick wall in Stretcher bond(Wall height 3800mm) m 885 109.04 96,500.40
Sundries
2
P Damp proofing under coping m 92 11.20 1,030.40
FINISHES
2
Q Woodfloat plaster Finish to walls Walls and reveals m 2069 13.78 28,510.82
2
R Paint to Wood float plastered walls m 2069 10.71 22,158.99
METAL WORK
SUBTOTAL 264,781.05
PROPOSED SEPTIC TANK AND SOAK AWAY AT ZVIMBA RDC HEAD OFFICES
SEPTIC TANK
600 x 500mm Heavy duty cast iron manhole cover complete with
M frame placed into position no 2 93.00 186.00
Allow to supply and fix 160mm PVC pipes and accesories as per
N detail item 1 1,200.00 1,200.00
Page 10 of 12
Resource Steel and Construction
Cover stones with metal sheets from used drums or galvanised iron
E sheet covers m2 22 6.23 137.06
Page 11 of 12
Resource Steel and Construction
SUMMARY PAGE
AMOUNT (US$)
10,563.22
1 SEPTIC TANK
SUBTOTAL 1 13,420.07
SUBTOTAL 2 15,620.07
Page 12 of 12