Design Project Part 3
Design Project Part 3
University of Manchester
Abstract
Group MN
May 2023
This report details the final plant design for the sustainable production of urea in Nelson Mandela
Bay, South Africa, using the ACES21 process. The plant is designed to produce 1,000,000 metric
tonnes of urea annually with a purity of 99.8% w/w and targeted fertiliser and agricultural markets. The
process incorporates a green ammonia feedstock, sourced from the surrounding Eastern Cape Town
area. The liquid green ammonia is fed to the bubble column reactor via an HP carbamate ejector,
providing the driving force for circulation in the synthesis loop. A process flow diagram, updated from
Part 1, incorporating designs from Part 2 is presented, with 2D and 3D plant layouts included to pro-
vide a visual aid to the corresponding detailed descriptions. A HAZOP study has thoroughly assessed
and adjusted safety, health and environmental aspects. Furthermore, the three pillars of sustainabil-
ity: social, economic and environmental were comprehensively discussed in relation to the presented
process. A life cycle assessment (LCA) using the software CCalC was performed on a cradle-to-gate
basis, revealing a total carbon footprint of 185kgCO2 eq./fu for the process. Plant-wide control has been
meticulously designed and presented in P&IDs. Operating conditions such as commissioning, start-up,
shutdown maintenance and manning requirements have been outlined per industry standards and are
directly related to the process. Process integration was investigated using SPRINT and yielded an
energy recovery of 6633.2 kW using 11 heat exchangers, an additional steam utility system designed
generating around half of the electricity required for the process through steam turbines. Finally, an
economic evaluation was carried out, giving an ROI over the plant lifetime of 55.14% with a cumulative
cash flow at the end of the project lifetime of almost $9 billion.
Declaration of Participation
No part of the work referred to in this report has been submitted in support of an application for any
Degree or other qualification at this or any other university or institution of learning.
Certification of Acceptance
The work presented in this report in part fulfilment of the Degree of Master of Engineering has been
submitted and examined in accordance to the requirements of the School of Chemical Engineering and
Analytical Science, The University of Manchester.
3.2
Contents
Abstract 3.2
1 Introduction 3.5
1.1 Summary of Units and Changes from Part 1 . . . . . . . . . . . . . . . . . . . . . . . . . 3.6
1.1.1 Synthesis Section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.6
1.1.2 Purification Section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.6
1.1.3 Concentration Section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.6
1.1.4 Recovery Section . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.7
1.2 Wastewater Treatment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.7
1.3 PFD & BFD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.8
1.4 Manning Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.9
2 Detailed Plant Layout 3.10
2.1 Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.10
2.2 Actions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.11
2.2.1 Factors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.11
2.2.2 Ancillaries . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.14
2.2.3 Storage Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.16
2.3 Storage Sizing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.17
2.4 2D & 3D Plant Layout . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.17
3 Safety, Health and Environmental considerations 3.20
3.1 HAZOP study . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.20
3.2 HAZOP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.23
3.3 Process Hazards . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.26
3.4 COSHH Assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.27
3.5 Operability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.31
3.5.1 Control and Instrumentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.31
3.5.2 Fires and Explosions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.31
3.5.3 Permit to Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.31
4 Sustainability Consideration 3.32
4.1 Essential Criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.32
4.1.1 Environmental . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.32
4.1.2 Economic . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.32
4.2 Additional Considerations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.33
4.2.1 Environmental . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.33
4.2.2 Social . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.33
4.3 Life Cycle Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.33
4.3.1 Goal and Scope Definition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.34
4.3.2 Inventory Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.34
4.3.3 Impact Assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.36
4.3.4 Interpretation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.37
5 Control & Instrumentation 3.38
6 Operating Considerations 3.42
6.1 Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.42
6.1.1 Plant Inspection Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.42
6.1.2 Flushing and Cleaning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.43
6.1.3 Chemical Trials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.43
6.1.4 Handover Phase . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3.43
3.3
Contents 3.4
3.5
1.1. Summary of Units and Changes from Part 1 3.6
HP Stripper
The stripping column in the synthesis section, S-101, was designed as a heat exchanger in Part 2.
For this reason, the conversion of ammonium carbamate to carbon dioxide and split of ammonia and
carbon dioxide in the liquid and gas were specified. The conversion remained the same as for Part 1
at 70%, however the amount of ammonia and carbon dioxide in the liquid phase was determined by
comparing the design to patents of similar inventions to find an accurate approximation.
VSCC
The vertically submerged carbamate condenser (VSCC) was considered to have a packed bed section
at the top that would allow for the collection of ammonia and carbon dioxide so it could be separated
from the rest of the products. However, in the design it is assumed that this will be in a gaseous state
and behave like ideal gases and therefore a packed bed is not required, meaning that the gases would
collect naturally in the outlet pipe to be carried over the next section of the plant.
Operators
The following equation can be used to find the number of operators required according to the units
on-site3 .
Where NOL is the number of operating workers at a time, P is the number of process steps involving
handling solids, and Nnp is the number of process steps not involving solids handling. Extracting the
relevant information from the process, we can establish that P equals 2 and Nnp equals 16. Plugging
these into Eq.1.1 results in a value of 11.7, rounding up to 12 operators required at any one time. In
order to find out how many operators are required in total, this value must be multiplied by the fraction
of total shifts taken per year over the number of shifts per operator as is shown in the equation below3 :
The number of total shifts a year can be found by assuming there are 3 8-hour shifts each day3 , and
the number of days of operation can be found by dividing the number of annual operating hours, 8000,
by 24 giving 334 of operation. Multiplying this by 3 gives exactly 1000 shifts per year. Next, the number
of shifts per operator must be determined. It is assumed that each operator can work 5 shifts per week
for 49 weeks a year (accounting for holidays and sick leave) giving a value of 245 shifts per operator
per year3 . Plugging all values into Eq.1.2 gives a total number of operators of 49.
Other
The daily requirement of workers for the various ancillaries on-site must also be determined. Estima-
tions must be made for these as the actual number required won’t be known until the plant is under
operation and the workload can be gauged, with redundancies made for surplus staff4 . These will be
displayed in the following table:
Overall
The total number of workers at the plant at any one time will be made up of the operators and the
other workers. This sums up to a value of 32. In terms of the total number, for use in the economic
breakdown, this number is 127 per day. With this information, we can now size the various ancillaries
described in the next section.
2
Detailed Plant Layout
Plant layout is a crucial factor to consider when trying to increase the efficiency of a plant whilst also
ensuring safe operation. Operating units, as well as ancillary buildings, must be arranged in such a
way that their location is logical and the space available is effectively used. These ancillary buildings
include offices, control rooms, storage vessels and utilities to name a few5 . When arranging the plant,
several considerations must be made to ensure the previously mentioned criteria are achieved using
heuristics and logic where appropriate.
2.1. Considerations
Cost
Cost can be reduced through efficient pipe networks. Having short runs of pipes will mean less material
use in addition to the decrease in inventory stored in pipes at any time6 . This may not be optimal for
other factors such as safety, maintenance or future expansion, however. With the many recycle loops
present in the process, careful consideration of the units’ proximity to one other must be taken into
account to reduce the pipe requirements as well as providing more convenience to operators. Speed
of construction, maintenance and operation are important factors for ensuring a plant minimises the
overall cost7 therefore keeping the plant as compact and accessible as possible is a key goal.
The choice of utility, and integration of heat from them, will also affect the cost. The operating conditions
chosen for each unit, and the plant as a whole, have been chosen in such a way as to maximise the
integration of heat from each unit8 . In the synthesis section, high temperature and pressure are seen,
generally decreasing from unit to unit. The differential in process heat can be used to generate varying
pressure steam for use in other units, therefore units should be arranged based on utility requirements
in order to minimise pipe requirement and maximise heat integration possible.
Operation
Operation of a site involves many considerations, the main aim of which being to optimise the plant
layout to make this as easy and time-efficient as possible for the operator. Convenience to workers is
important for maintaining and encouraging efficiency. During operation, any units which require regular
attention should be located in close proximity to the control room6 . Accessibility is also important for
allowing workers to reach certain sections easily or replace parts when necessary.
There are several tall vessels present on site where access to the top sections may be difficult.
Ensuring as much of the operating equipment as possible is located accessibly near the bottom of
each vessel will improve the working environment for operators. Of course, for maintenance of the top
of vessels, this can’t really be avoided. Lifts could be implemented to help access the top as some
vessels exceed 80 m in height. This would also help the less mobile workers to inspect these areas.
3.10
2.2. Actions 3.11
Maintenance
Maintenance is required at regular intervals for each piece of equipment on site. Maintenance includes
replacements of parts, cleaning of vessels to avoid contaminant and corrosion build-up, and general
check-ups on the equipment’s state and operability. To minimise the downtime during maintenance,
these should be scheduled to overlap as much as possible. Of course, certain units will require more
frequent check-ups than others. In order to minimise the disruption caused during periods of mainte-
nance, accessibility to the equipment must be optimised. For the stripper, decomposers and other heat
exchangers, tube bundles must be accessible for check-ups and replacement as the least permanent
component of these vessels. Therefore, a large clearing should be ensured to allow for their removal
and replacement. The choice of material being DP28W for these tubes has meant that replacement
should be less frequent due to the reduced rate and severity of corrosion build-up.
Safety
As the feed ammonia is to be sourced from a nearby green ammonia plant, pipe lines between the two
plants can be established to avoid the use of large pressurised vessels filled with ammonia. This is also
a feasibility constraint as the required hourly supply of ammonia is around 70,000 tons per hours, as
per the Part 1 design. Storing this quantity, without a steady stream entering the site, would be nigh on
impossible which explains why most, if not all, urea plants are integrated with ammonia plants on-site9 .
On a smaller scale, the general health of workers must be considered also. Operators must not be put
under unnecessary physical or mental strain during normal operation of the plant7 . Preventing workers
from being exposed to chemical fumes is critical in ensuring their health and well-being. Arranging the
plant in open air will help to keep fumes from accumulating to dangerous concentrations if there were
to be loss of containment.
Future Expansion
The plant must be laid out in a way that allows for expansion in the future. This may entail the addition
of extra units to increase output, replacement of existing equipment for more sophisticated equipment
available with future developments, or a new section of the plant for making the feedstocks if that
were to be desirable in the future. Currently, the target output of urea is around 100,000 kilograms per
hour or 800 million kilograms per year, assuming 8000 operating hours annually. For this reason, up-
scaling isn’t a priority in the near future. However, the current feedstock for ammonia is from a nearby
green ammonia plant. It may be that in the future development of an on-site green ammonia facility be
economically and environmentally advantageous, therefore it may be worth attributing space for that
future development in the layout of the plant.
2.2. Actions
2.2.1. Factors
Location
The determining factor for the plant location is its proximity to the upcoming green ammonia plant. It
has been stated that this is to be built in the Coega Special Economic Development Zone10 as is shown
in Figure 2.1 below. As you can see, the plot chosen for the urea plant is within this development zone
meaning piping of ammonia for the feedstock will be minimal in both length and disruption. Intermediate
storage will still be necessary to hold inventory on-site in case supply fluctuates or stops completely.
The area covered by this land is approximately 250,000 m2 or 25 hectares giving ample space to fit
the process equipment as well as all ancillaries, all adequately spaced from each other to mitigate
propagation of incidents on-site. An added benefit of the plant’s proximity to the green ammonia plant
is that surplus water generated during the production process can be fed back to the green ammonia
plant as a feedstock, thus improving the environmental sustainability of both processes and potentially
offsetting some of the costs from purchasing the green ammonia in the first place.
Wind
The prevailing wind is from the west meaning the plant will be downwind from the nearest urban area11 .
This is beneficial for minimising the impact of any vapours emitted from the plant. The plant will be
2.2. Actions 3.12
Figure 2.1: Image of Coeaga Special Economic Development Zone and the specific plot of land for plant
laid out in such a way that all the buildings and facilities used by workers are upwind, so west, of the
process units. This will ensure that if there were loss of containment, the workers won’t be subjected to
additional danger from vapours being blown towards them. Additionally, the flammability of ammonia
in certain concentrations would pose a risk to the urban area which is likely to contain many ignition
sources9 . The wind was also considered for the mechanical design of each vessel, accounting for
the maximum bending stressed due to wind. Therefore, they are all suitably designed for outdoor
installation which is desirable for the large vessels with potentially hazardous material contained as
previously mentioned.
Spacing
All units must be spaced out an appropriate amount from one another based on how hazardous they
are. The ancillary equipment, such as pumps or heat exchangers, must also be appropriately spaced
according to their contents. Heuristics exist for this and are shown in Figures 2.2 and 2.3 below.
2.2. Actions 3.13
The main constraints for spacing are between the units in synthesis section as well as the pressurised
storage of ammonia and carbon dioxide. According to Figure 2.2, adjacent ’High Hazard’ process units
must be a minimum of 200 ft (60 m) from each other whilst these high hazard process units must also be
350 ft (110 m) from pressurised storage. The only pressurised storage on-site will be the intermediate
ammonia and carbon dioxide tanks which feed the reactor. It is stated that spherical pressurised vessels
2.2. Actions 3.14
2.2.2. Ancillaries
Building/Facility Details
Control Room The control room will be located remotely, away from the process units. This
is to ensure the safety of operators and operation of the controllers in the case
of an incident. As per Figure 2.2, they must be located at least 350 ft (110 m)
from pressurised storage and 300 ft (90 m) from high hazard processes. Sizing
requirements state that an area of 10 m2 be allocated per worker. With 12
operators, only a quarter of them will be required in the control room, therefore
3 operators require 30 m2
Roads There already exists one access road to this plot of land on the eastern edge.
This will be the entrance closest to the process units and therefore will likely be
used for deliveries of materials and equipment. Another access point must be
added for the workers and as a separate exit in case of emergency whereby
access to the original exit is obstructed14 .
There also must be roads between units to allow access from vehicles. The
standard width for roads in a chemical plant is 8.5 m to allow for large vehicles
and emergency services to navigate the plant with relative ease14 . Secondary
access roads can be smaller, around 3.5 m2 , for access from employees and
visitors, for example15 . Additionally, these must be elevated in order to avoid
flooding14 .
Security At each of the 2 entry points, security must present 24/7 to ensure nobody
trespasses and tampers with equipment. Therefore, security outposts must be
constructed at each entrance with adequate surveillance of the plant meaning
CCTV may need to be installed. Tall, rigid fencing must be erected around the
perimeter of the site to prevent unlawful access to the plant. Ideally, barbed
wire will also be added as a further deterrent. 3 security staff are required at
any one time, 1 for each entrance and another in reserve in case of issues.
Utilities Utilities required for the process include: process steam, electricity and steam
cooling. Process steam is required at varying pressures and temperatures for
different units on-site. To step down the pressure, and thus the temperature,
a steam turbine system will be used to generate electricity from this change
in pressure. This electricity can then be used to help power certain electrical
equipment on-site.
2.2. Actions 3.15
Building/Facility Details
Car Park/Load- Car parking will be required for both employees and visitors, the latter requiring
ing Areas significantly less space. To account for the number of employees when first
opening the plant as well as any increase in the future, a surplus of car parking
spaces will be provided. The average car parking space is around 12 m2 per
car16 meaning that with 20 employees at any one time and a 10% surplus of
parking space, an area of 264 m2 must be available for cars to park.
Loading of trucks with the urea product will be done adjacent to the urea stor-
age. The capacity of trucks for carrying cargo is around 45,000 lbs (20410 kg)17
meaning that, in order to deal with the hourly production of urea of 100,000 kg
per hour, at least 5 trucks loading spaces will be required at any one time as-
suming an hour round trip on average to load and unload the product as well
as the travel time in between. In terms of sizing, the loading dock must be able
to fit a container truck which has dimensions of 70 ft by 96” or, 21.3 m by 2.4
m18 . The width of each bay should be 12 ft, or 3.6 m18 , in actuality to allow
ample clearance for each truck. Therefore, the overall area required for each
dock will be 77 m2 meaning that, with 5 loading docks, the area allocated to
loading will be 384 m2 .
Offices Offices will be required to house employees whilst not directly operating on-site.
These will be located on the south-side of the site, away from hazards. As this
is where most time will be spent by employees, it would make sense to position
it locally to the most frequently accessed facilities such as the canteen, car
park, toilets etc. Recommended sizing for offices states that 10 m2 be allocate
per administrative employee15 , therefore with 5 employees, the offices should
occupy 50 m2 .
Canteen Providing food for the workers is a necessity for worker satisfaction and effi-
ciency. This will be located on the opposite end of the plant to the process
equipment as to avoid any contamination of food and drink with hazardous
chemicals. It must be suitably sized to deal with workers entering at similar
times such as during their lunch breaks. It is advised to allocate 1 m2 space
per dining space and 3.5 m2 per canteen for kitchens and storage15 . Assuming
there are 20 employees and one canteen, this will require an area of 23.5 m2 .
Laboratory The laboratory is essential for analysing samples taken from the process. This
will be done to ensure all units are operating properly and that the urea product
is of the purity required for sale. It is recommended that there be 20 m2 space
allocated per lab employee15 , therefore with 2 lab employees, 40 m2 will be
required.
Fire Station A fire station is required to provide emergency response to any fires on-site.
Fire propagation must be prevented as soon as possible to avoid large scale
disaster. It is recommended to allow 500 m2 for the fire station including the
vehicle space as well as emergency supplies15 . This must be positioned 350
ft (110 m) from all storage facilities14 but ideally near an access road.
Medical Centre In the case of an accident on-site, there must be a medical facility in order
to provide emergency care to employees. Recommended sizing states that
a medical centre should allow 0.1 m2 per employee with a minimum size of
10 m215 . This minimum value will therefore be chosen. Accessibility to this
building for emergency vehicles is important, thus, it should be positioned near
an access road. However, as a service building, it must be 400 ft (110 m) from
high hazard process units, such as the reactor14 .
Workshop A workshop will be placed near to the processing section of the plant. The
purpose of this building is to allow for on-site repairs for processing equipment,
pumps or any other faulty equipment. This will help to decrease the downtime
of the plant if something were to fail as it can repaired on site.
2.2. Actions 3.16
Building/Facility Details
Shop A shop will be available on-site to sell some urea fertiliser in smaller quantities,
for personal use. This will be located near the urea storage and by the visitor
car park to encourage visitors to stop by and purchase the product or any
refreshments.
Ammonia
Ammonia is the most hazardous chemical requiring storage on-site. Loss of containment of this could
cause severe health complications for those working in the plant or even in surrounding land. For that
reason, the means of storing it must be robust. With a density of 596 kg/m3 under the storage conditions
of 100 bar and 35 ºC19 , 70,000 kg/hr equates to 117.5 m3 /hr. For safety reasons, it will be designed with
a 10% overfill margin. This provides some flexibility to the tank in the case that the level control fails
and the tank overfills. The 10% increase equates to a new hourly volume requirement of 130 m3 . For
pressurised ammonia storage, Horton sphere tanks are often used20 . The benefits of using this style
of tank range from the decrease in weld joints required for construction, thus decreasing the chance
for manufacture errors, savings in raw material use as pressure is distributed more evenly across a
spherical body, and the reduction in man-hours required for construction of the vessel21 .
Using the following equation, the diameter of the tank needed to provide the volume required can be
determined.
4 3
V = πr (Eq.2.1)
3
The diameter comes out to be 6.3 m and, assuming the tank is ground level with supports on the sides,
the height is also 6.3 m. It is common practise to have a bund surrounding the vessel to contain any
spilled liquid from the tank9 . This prevents flooding of nearby vessels and ancillaries if a spillage were
to occur. Similarly-designed Horton spheres used for ammonia storage have been constructed out of
HT60 steel22 to provide high strength to cope with the high pressure conditions.
Carbon Dioxide
Carbon dioxide needs to be stored in a similar way to ammonia to minimise the space occupied and
to safely and securely keep inventory in case supply fluctuates. For the same reason as for ammonia,
a blast wall will be built around this vessel. The hourly requirement for carbon dioxide, for use as a
feedstock and stripping agent, is 90 T/hr. With a density of 210 kg/m3 under the storage conditions of
155 bar and 185 ºC, the hourly volumetric requirement of carbon dioxide on-site is 430 m3 /hr23 . Again,
building in a 10% safety margin gives a volume requirement of 470 m3 . Similarly to before, it will be
designed as a Horton sphere meaning the diameter can be found using Eq.2.1. This gives a diameter
of 9.6 m. It is stated in literature that CO2 pressure vessels are constructed from stainless steel24 , thus
the industry standard SAE 304 stainless steel will be used.
Water
In this process, water is generated in large quantities is treated in the water treatment section. From
here it must be stored before being used as make-up for the steam system or being sent to the nearby
green ammonia plant as a feedstock. Any overflow may also be sent to the on-site reservoir to prevent
flooding of the process site. The material required for this must be corrosion resistant due to waters
high tendency to oxidise, therefore stainless steel will be used, 304 SS to be exact. The sizing was
done in the introductory section as part of the wastewater treatment section sizing, however for clarity
it will be added to the Table 1.2 below.
2.3. Storage Sizing 3.17
Urea
Urea being produced in the form of solid prills means that they cannot simply be piped into a storage
tank in the same way as with the liquid and gas feeds. Instead, it must be conveyored from the prilling
tower to a storage warehouse where it will be boxed up in air-tight boxes as was stated before. Another
consideration when handling fine prills, and conveying solids in general, is the formation of dust. These
pose a respiratory risk to workers and a fire risk if aerated25 . Therefore, several measure must be taken
to reduce formation, accumulation and aeration of these particles. These methods include reducing
any drop height for solid particles and controlling the air flow around the material25 . Moisture addition
is the most common and least expensive method of dust control25 however, due to the requirement
that the urea product be left dry, away from even atmospheric moisture, means that this method is
infeasible. The hourly production rate of urea is around 125 T/hr meaning, with a density of 1323
kg/m326 , the minimum volume required for an hours production would be 95 m3 . In order to account for
accumulation of urea product, from either low sales or slow exporting rate, the warehouse size will be
scaled up to provide 5 times more storage than required meaning the volume of the warehouse must
be 500 m3 . This will help to deal with sudden changes in the market and consumer demand.
To size the warehouse, the height must be set first. This can be done by finding the height reachable by
a forklift in order to load and unload the urea crates. It can be seen than warehouse forklifts can reach
anywhere from 6 m to 16 m27 , a reasonable value must be chosen from this range. In order to avoid
the requirement for specialist equipment, the lower bound of this will be taken at 6 m. This means that
the floor area needed for the warehouse will be around 83 m2 . Of course, this doesn’t allow for the
maneuvering of a forklift around the warehouse or accessibility to each shelf, thus an additional 25%
will be allowed for the floor space meaning the new area occupied by the warehouse will be 100 m2 .
Fluid Storage
Solid Storage
The study recommends ways to mitigate the consequences of deviations and return to normal and safe
operations. The term ’deviations’ refers to the systems physical properties like flow, pressure, temper-
ature etc.These deviations are paired with guide words that indicate the direction of change, such as
more, less, no or reverse.
Before starting the study, a matrix was created to define the meaningful combinations of deviations and
guide words for the HAZOP analysis, and is presented in Table 3.1.
3.20
3.1. HAZOP study 3.21
Parameter Guideword
More Less No Reverse Other
Flow x x x x
Temperature x
Pressure x x
Level x x
Maintenance x
Composition x
Corrosion x
To evaluate the identified hazards, a risk matrix is utilised and illustrated in Table 3.2, which involved risk
ranking by combining severity and likelihood. This step is often referred to as the ”As Low as Reason-
ably Practicable” (ALARP) process since it involves identifying reasonable and effective ways of further
reducing risks until the cost of investment outweighs the benefit of risk reduction gain.
By using a risk matrix, the severity and likelihood of each hazard is evaluated and the most significant
risks are prioritised, allowing for efficient allocation of resources to reduce risks to an acceptable level.
The risk matrix provides a valuable tool for ensuring that the ALARP principle is applied, and risks are
reduced to a level that is both reasonable and practical.
The P&ID section relevant to this HAZOP study is shown in Figure 3.1 below for reference throughout
the HAZOP. The finalised HAZOP is presented in Tables 2.3-X. Following the completion of the study,
the P&ID was updated as per Figure 3.1, any changes identified are marked in red.
1 Slight injury Slight damage Slight effect (local Slight impact (short Low Low Low Low Low
or health scale, short term term local concern)
effect (re- damage -weeks)
stricted work
case or LTI)
2 Major injury Moderate dam- Moderate effect (lo- Moderate impact Low Low Medium Medium High
or health ef- age cal scale, medium (medium-term na-
fect (partial terms damage- tional concern)
disability) years)
3 < 3 fatalities, Major damage Major effect (lo- Major impact (re- Low Medium Medium High High
or perma- cal scale, long gional or persistent
nent total term damage – national concern)
disabilities decades)
4 > 3 fatalities Massive dam- Massive effect (re- Massive impact Medium Medium High High High
age/ total loss gional scale, per- (global concern
manent damage) and media cover-
age)
3.2. HAZOP
Inventory of Liquids
The inventory of fluids, namely water, on-site poses a potential risk were it to be released from contain-
ment. Flooding of the plant and subsequent damage to mechanical and electrical equipment could lead
to severe consequences such as electrical fires, loss of controller function, and corrosion to equipment
which would decrease its effective lifespan. With electrical failures, if the proper safeguards aren’t put
in place in the event of loss of power, many unforeseen complications may arise with few immediate
means of mitigating these.
3.4. COSHH Assessment 3.27
Symbol Meaning
Corrosive
Hazardous to environment
Wear respirator
3.5. Operability
4.1.1. Environmental
Reduction of Utilities
Reducing utility use is a major factor in reducing the environmental burden of a process. Due to the high
temperatures and pressures found in the synthesis section, for example, a lot of utility must be used in
order to achieve these conditions. Reduction of utility can be achieved through heat integration across
the plant.
4.1.2. Economic
Reduction of Operating and Capital Costs
Ensuring money is not spent excessively is important in retaining financial incentive to stakeholders.
Saving in one area can allow for otherwise wasted funds to either be saved, contributing to paying off
loan payments, or spent elsewhere on improving conditions for workers or the local community. Capital
cost can be reduced primarily by making equipment smaller or less intricate. In most cases, this won’t be
feasible due to the production requirements and Part 2 designs which would require complete revision.
This is an inefficient use of time and as such this must be minimised by other means. Cheaper materials
or simpler construction methods can be introduced to reduce the capital cost. Operating costs include
the feedstock, fuel, electricity, wages and waste disposal costs. The most significant of these will likely be
the fuel costs for heating steam. Therefore, reducing heating utility will be important in reducing operating
costs. This, again, can be done via heat integration. By using a steam turbine system for supplying high,
3.32
4.2. Additional Considerations 3.33
medium and low pressure steam to the processes, extra energy can be generated when letting down the
pressure. This can help with providing electricity on site for computers, sensors or pumps.
Reduce Waste
Waste can be seen as lost profits or wasted feedstock, therefore reducing waste produced throughout
the process is an important consideration. This could also be considered an environmental consideration
as waste often is disposed of in non-environmentally friendly ways. Waste production is controlled by the
purge stream. This stream consists of ammonia, carbon dioxide and air. If it were deemed appropriate,
these could be separated and recycled to the reactor feed to further improve the overall conversion of the
process. If the means of separation is not too expensive and the quantity of waste present is sufficient
to be worth recovering, this would be a suitable method of reducing process waste.
Maximising Lifespan
Maximising the lifespan of instrumentation and equipment used on site is an important consideration
when considering the environmental impact of a chemical plant. Expensive, resource-heavy equipment
should be built to last many thousands of hours worth of operation to avoid replacement, which would
slow down the productivity of the plant and require disposal if not built in a reusable, recyclable way.
Proper maintenance of machinery will help to keep equipment running effectively and efficiently whilst
also reducing the build-up of contaminants within the system. In addition, corrosion can be monitored
such that any hotspots can be treated before irreversible mechanical failure occurs. This will lengthen
the lifespan of equipment further.
4.2.2. Social
Reduce Noise Pollution
Noise pollution is a common result of large chemical plants. If not considered, it could reduce locals’
property value if residential, or in extreme cases, cause hearing damage for workers and locals. This
outcome must be avoided, therefore plant location and configuration must be assessed. The plant should
be placed in an industrial area, downwind from the nearest residential area. This will also help reduce
pollution of the area and, were there to be any loss of containment of chemicals, would prevent toxic
chemicals from poisoning local residents.
in modern-day industries which applies life cycle thinking in order to assess the environmental conse-
quences as a result of human activities. It reviews the quantification of environmental burdens of prod-
ucts, processes or activities and then using these burdens to reveal what potential impacts they could
have. Finally, identification of opportunities for improvements along the whole life cycle can be carried
out. LCA is conducted in four main steps; the goal and scope definition, which defines the purpose of the
study, system boundary and functional unit; inventory analysis, which involves defining the system, data
collection and environmental burdens; impact assessment, which determines the impact categories and
environmental impacts; and the interpretation, which involves hotspot analysis, evalueation of results,
sensitivity and uncertainty analysis, and reporting of findings.
For the purpose of this particular LCA, the functional unit to be selected is “Production of 1000kg of pure
urea”.
A carbon footprint sensitivity analysis was carried out by varying the ratio of urea distributed locally
vs urea distributed overseas to depict the change in total carbon footprint emitted per functional unit.
According to a urea market analysis for the continent of Africa, South Africa is the majority importer
of urea in Africa with 42% of total urea imports in 2021 with the next largest importer of urea in Africa is
Djibouti with 9.1% of total urea imports in Africa41 .
Since South Africa is the biggest importer of urea in Africa by such a big margin, it was decided that all
urea not distributed overseas should be distributed to South Africa. Within South Africa it was found that
KwaZulu-Natal and Limpopo have the most fertile land in the country42 . The distances of KwaZulu-Natal
and Limpopo from our urea plant are 1245km and 1430km respectively. Under the assumption that half
of the locally distributed urea prills go to each of the two destinations an average of the two distances
can be calculated to estimate the distance locally distributed urea has to travel. This mean distance is
1338km and is inputted into CCalc2 to estimate the carbon footprint of the locally distributed urea. The
mode of transport to distribute urea prills locally is to be 22t trucks.
According to a global urea import study carried out in 2019, the largest importers of urea by volume
in the world are India and Brazil with 9679 metric tons and 5897 metric tons per year respectively43 .
The shortest distance from South Africa to India by cargo ship is 10,054 kilometres and to Brazil is
7780km. Similarly, under the same assumption used for local distribution, a mean distance between the
two distances was calculated to estimate the total carbon footprint when emitted overseas and this is
8917km. Urea to be distributed overseas travels 7km from the plant to the port via a 22t truck and then is
shipped by a cargo ship to its destination. The carbon footprint per functional units of the different cases
was calculated on the software CCalC2 using the distances and transport modes that were mentioned
and the results are presented in Table 4.2.
Using green ammonia instead of ammonia completely eradicates any carbon footprint associated with
ammonia, therefore significantly reducing the carbon footprint from raw material since most of the raw
material emissions is due to ammonia. The carbon footprint emitted by raw materials decreases by
87.4% when using green ammonia compared to the ammonia, decreasing from 1565kgCO2eq./fu to
196kgCO2eq./fu. So when green ammonia is used instead of ammonia the total carbon footprint would
decrease to 185kgCO2eq./F.U in the case of 50/50 split of local and oversees distribution
The packaging used for urea prills were chosen to be in the form of large HDPE bags and it was assumed
that 0.333kg worth of bags were used per functional unit. However this only accounts for a very small
percentage of the total carbon footprint so this would not be a point for improvement in the process.
4.3. Life Cycle Analysis 3.36
a) b)
c) d)
e)
Figure 4.3: Carbon footprint overview of varying local to overseas shipping ratios: a)75:25 b) 25:75 c)100:0 d)0:100 e)50:50
4.3. Life Cycle Analysis 3.37
4.3.4. Interpretation
The final step of the LCA aims to transfer the environmental burdens from the impact assessment into the
potential impact they could have on the environment. The focus of this LCA was on global warming which
is defined by means of kg.CO2eq. basis. One of the main concerns currently in terms of environmental
sustainability is the issue of global warming due to the links it has to climate change which poses a serious
threat to life on Earth in the forms of widespread flooding and extreme weather as well as worsening the
quality of air and water we consume.
As can be seen from Figure 4.3 and in Table 4.2, the total carbon emission show a slight decrease when
more urea is distributed overseas than distributed locally. This is surprising as one may think the longer
distance travelled must mean more carbon emissions are given off, however the carbon emissions given
off per km is considerably larger for trucks than for cargo ships.
It may be easy to say that all the urea produced by the plant should be exported since India and Brazil
are the largest urea importers in the world and has a lower carbon footprint, but the social considerations
must be taken into account: How may the local community take the fact that none of the urea produced
is actually being used in the country in which it was produced? In addition, since South Africa is the
biggest importers of urea in Africa as mentioned previously, distributing urea locally to South Africa will
help reduce the carbon footprint indirectly of other exporters looking to export their urea to South Africa
since there is less demand for urea if our urea plant is supplying enough.
5
Control & Instrumentation
The design of a control system for the entire process is critical to ensure a consistent quality of urea
output is achieved in the most efficient, safe and sustainable method. The individual designs from Part
2 were used as a base control system for the whole process. The plant is split into six different sections,
with each sheet of the P&ID representing two sections in order to provide clear, detailed and legible
P&IDs. Figure 5.1 shows the P&ID of Sections 1 (Synthesis section) and 2 (Purification section) of the
process, Figure 5.2 shows the P&ID of Sections 3 (Concentration section) and 4 (Prilling section) of the
process, and Figure 5.3 shows the P&ID of Sections 5 (Wastewater Treatment section) and 6 (Recovery
section) of the process.
In Figure 5.1, changes made to the system as a result of the HAZOP performed in chapter 3 of this
report are highlighted in red. When collating the individual control systems onto an overall P&ID, it was
important to acknowledge conflicting nodes on connecting streams. This would cause the system to be
over-controlled or over-specified which is a violation to degrees of freedom. This problem is easily solved
by simply removing one of the duplicated control systems on a given stream ensuring that the system’s
control was not hindered.
The legend used for the P&IDs are presented in Table 5.1 below:
3.38
Figure 5.1: Section 1&2 P&ID. Equipment in red illustrate new safety features added as a result of the HAZOP
3.39
Figure 5.2: Section 3&4 P&ID
3.40
Figure 5.3: Section 5&6P&ID
3.41
6
Operating Considerations
6.1. Commissioning
All systems and components must comply with operating specifications before being put into commission.
It demands for procedures including testing, site verification, and equipment inspection. This essential
procedure guarantees a seamless transition from plant construction to operation while reducing costs
and delays. It is important to confirm that the equipment complies with design requirements and P&IDs.
Successful commissioning lowers financial risks and facilitates dependable and safe plant operation.
Unit inspections and testing identify risks, safeguard personnel, and reduce any negative effects on the
environment44 .
3.42
6.1. Commissioning 3.43
Table 6.1: Inspection checklist for various sections of the plant prior to commissioning
It is imperative to rectify any errors or problems found during the preliminary plant inspection before
the commissioning phase gets underway. The procurement team establishes the structure for commis-
sioning after making the required modifications. This team is made up of members from the design,
construction, and operations teams as well as, if necessary, specialised consultants. The procurement
team prepares a work schedule, develops a thorough execution plan, and decides on the commissioning
phase’s objectives and scope together. They guarantee the availability of resources, such as personnel,
equipment, and materials52 .
6.2. Start-up
To ensure that a chemical plant can transition from a non-operational condition to an operating state
in a safe and dependable way, a set of carefully designed stages must be followed. This procedure is
required following plant commissioning, maintenance, or regular/emergency shutdowns. It is essential
to consider any hazards that could develop as a result of the unsteady state conditions that are involved
during the start-up. Every main operation in the plant should have a clear procedure for starting up in
order to restore normal operating conditions following every shutdown. Start-up procedures must be
executed in a manner that has the least negative financial impact and has the most operating capacity
possible55 .
6.2.2. Reactor
In order to search for any damage or corrosion that might have happened during maintenance or com-
missioning, the reactor and its related systems must first undergo a thorough inspection. An inert gas,
such as nitrogen, is used to fill the reactor when the examination is over. This displaces any air and
prevents explosive mixtures from forming. The reactor is then gradually filled with ammonia until the
desired pressure is achieved. To reach the desired temperature, hot oil or steam is used to preheat the
reactor57 .
At this point, the system is gradually infused with carbon dioxide, which causes it to react with the
ammonia in the reactor and the products follow the process as expected. Any abnormalities are quickly
corrected to stop equipment damage and the production of undesirable byproducts. To guarantee a
seamless and secure start-up, qualified personnel are required to be present57 .
6.2.3. Ancillary
One of the first pieces of equipment to be turned on during start-up is the pumps. It is important to evaluate
the condition of the pumps and the correct installation of all required valves and pipelines before turning
on the pumps. The flow rates and pressures are carefully monitored after the pumps are turned on to
guard against any process or equipment damage58 .
The heat exchangers are examined to make sure there isn’t any damage or corrosion that could affect
how well they work before they are put into service. They are progressively heated and inflated to their
operating pressure after being deemed to be in good condition59 .
The control systems are also important supporting components in the process since they are utilised
to track and regulate the many process variables, such as temperature, pressure, flow rates, and com-
positions. The calibration and functionality of all required sensors and equipment are verified before the
control systems are started, as well as their accuracy. In order to make sure they are running within the
proper range after they have been started, they are constantly checked.
6.3. Shutdown 3.45
6.3. Shutdown
The objective of a chemical plant’s shutdown procedure is to maintain a safe and stable state while
reducing the danger of equipment damage and personnel harm. To isolate equipment, depressurise
systems, drain vessels, and perform appropriate repair procedures, it entails a sequence of controlled
actions. The plant can ensure worker safety, safeguard the environment, and enable a smooth restart
with little to no downtime and the avoidance of expensive repairs by strictly adhering to the shutdown
protocol60 .
ESVs can be made to be fail-safe, which means that if there is a power outage or a loss of control signal,
they will shut down automatically.
The emergency response team is informed after the emergency shutdown valves have been activated,
and the evacuation procedure is then initiated. As soon as the emergency has been contained, the team
will evaluate the situation, take the appropriate action, and attempt to safely halt the procedure and limit
any additional harm. The emergency response team will also start other emergency procedures, such
as firefighting, first aid, and environmental protection measures62 .
6.5. Maintenance
Equipment maintenance provides for optimal performance and longevity. Inadequate maintenance in-
creases the likelihood of accidents, downtime, and poor production, all of which are extraneous expenses
for businesses63 .
Chemical plants may occasionally have duplicates of significant process equipment, such as cold
standby pumps, to ensure uninterrupted operation in the event of equipment breakdown. This improves
the reliability of the plant as a whole since the duplicate equipment may be immediately turned on to fill
in for the failed equipment’s function. This helps to decrease downtime and production losses64 .
Normally, maintenance work is documented, including information on what was done, why, when,
and by whom. When doing retrospective hazard reviews to detect prospective safety dangers that may
develop due to equipment failure, this historical data might be helpful. A typical failure rate can be
established by including equipment dependability into a LOPA (layer of protection analysis), which can
assist in identifying and reducing potential risks65 .
6.5.1. Corrective
Equipment that has broken down or malfunctioned must be repaired or replaced. Corrective maintenance
aims to get the machinery back to its optimal operational condition, minimising downtime and increasing
production. Wear and tear, improper use, or external factors like power interruptions or environmental
conditions are potential causes of breakdown and malfunction. This form of maintenance can prevent
extended downtime, lower repair costs, and extend the life of the equipment by responding quickly and
effectively to equipment faults66 . The workshop on-site will be where most of these repairs occur, unless
the repair must be performed in-situ.
6.5.2. Preventative
In order to avoid failures altogether, equipment or machinery undergoes routine checking, cleaning, and
maintaining to make sure it stays in prime condition. Preventative maintenance aims to locate issues
and address them before they worsen and result in prolonged equipment downtime or damage. This
is usually accomplished by adhering to a schedule of regular maintenance procedures, such as lubrica-
tion, cleaning, calibration, and the replacement. Preventative maintenance is typically less costly and
time-consuming than corrective maintenance, making it a cost-effective strategy for equipment manage-
ment67 .
6.6. Specific Maintenance 3.47
6.5.3. Predictive
Predictive maintenance uses data analysis and machine learning to anticipate equipment breakdowns,
enhancing lifespan and reducing repair costs by planning suitable maintenance tasks. It enhances safety
by identifying potential issues in advance. Methods like statistical analysis, machine learning, and AI ana-
lyze sensor data like vibration, temperature, and pressure to detect potential problems. These algorithms
learn from past data to recognize anomalies indicating issues.68 .
6.6.1. Reactor
The reactor operates at a high temperature of 185°C and a pressure of 155 bar. The materials involved
in this process include ammonia and carbon dioxide, the former being flammable under certain concen-
trations9 . A thorough maintenance schedule should be put in place due to the potential risks associated
with this operation. The internal reaction is exothermic, which means it generates heat. Since the high
temperature and pressure can lead to corrosion, erosive wear, and fatigue, this places additional strain
on the equipment. High-strength alloys and coatings that resist corrosion and wear are employed as a
means of addressing this issue. The reactor is also built with cooling devices to control temperature and
avoid overheating69 .
6.6.4. Ancillaries
Preventative maintenance is frequently employed for pumps, which entails routine inspections, cleaning,
and replacing worn-out parts like seals and bearings. Predictive maintenance techniques like vibration
analysis and oil analysis can also be used in order to diagnose issues in the equipment. Corrective main-
tenance, which may involve repairing or replacing the pump, may be necessary if a pump malfunctions72 .
Preventative maintenance involves checking and repairing worn parts and cleaning heat exchanger sur-
faces to prevent fouling. If malfunctions occur, corrective maintenance, including heat exchanger repair
or replacement, may be necessary. Regular inspection and replacement of gaskets and seals are es-
sential to prevent fluid leaks, which pose operational and safety risks. Deterioration due to corrosive
substances, extreme heat, and pressure might require a complete heat exchanger replacement to mini-
mize production disturbance.73 .
E
Cp = A + Bt + Ct2 + Dt3 + (Eq.7.1)
t2
Furthermore, in Part 1, it was assumed that process to process heat transfer already occurs in both the
cooling of wastewater and in the recycle loop between the hydrolyser and process condenser stripper
as per the ACES21 brochure8 . For the purpose of designing an optimal heat exchanger network, and
to ensure that the energy balance is satisfied with the newly calculated enthalpies from ASPEN, this
integration was omitted, and the streams were treated individually.
3.48
7.1. Process Streams 3.49
The streams above were entered into SPRINT software with a minimum approach temperature of 10°C
to yield the grand composite curves in figure 1 below. It was found that the minimum total hot utility
requirement was 5003.46kW and the minimum cold utility requirement was 622.884kW.
In order to design the heat exchanger network, the utilities that will be used must firstly be chosen, which
is further discussed in the following section.
LP decomposer requires 3.5 bar steam. Finally, it was decided to use the large duty in the reactor to
generate another level of steam at 8 bar, to be used for process heating and electricity generation. 8 bar
steam was chosen here as it was the highest level of steam that did not violate a ∆T min of 10°C given
an assumed water feed temperature of 125° to the jacket of the reactor.
As the duty for the vacuum evaporator is so low it was decided to operate this unit adiabatically, leading
to a final outlet temperature of 136°C
It was decided that the VSCC would be focused on first as this is the unit that operates at the highest
temperature with one of the largest duties. Thus, the utility used to cool the VSCC as the exothermic
reaction occurs could be used to generate steam to heat units such as the decomposers and to be used
in heat exchangers. In the units designed in Part 2, the highest-pressure steam requirement is the 17
bar steam used in the MP decomposer, therefore ideally, the steam generated in the VSCC should be of
this pressure or higher. The saturation temperature of 17 bar steam is 204.3°C from steam tables77 and
assuming that the feed to the VSCC cooling jacket is at 125°C, the log mean temperature difference of
the jacket can be calculated using Eq.7.3 below, modelling the jacket as counter current flow.
Substituting in Thi = 213 ºC, Tho =183 ºC, Tci =125 ºC and Tco = 204.3 ºC gives a log mean temperature
difference (LMTD) of 26 ºC, much larger than the minimu temperature difference. Next, the enthalpy of
cold water at 125 ºC and 17 bar was found from cold water tables (ref) and the enthalpy of the steam
generated at 17 bar was found again from steam tables to be hf = 526.1 kJ/kg and hg =2794.53 kJ/kg.
These values were substituted into Eq.7.4 below along with the duty of the VSCC to give the mass
flowrate of steam generated for the unit to be 9.83 kg/s.
7.1. Process Streams 3.51
Q
mgen = (Eq.7.4)
(hg − hf )
This process was repeated for the reactor, generating 8 bar steam, the MP absorber, generating 3.5 bar
steam, and the LP absorber, vacuum concentrator, and process condensate stripper all used to heat
cooling water from 20°C to 125°C. These results are shown in the table below. Note that hg for all units
preheating feedwater to 125°C is the enthalpy of liquid water at this temperature and a pressure of 3.5
bar, shown by the * in the hg column. A pressure of 3.5 bar was chosen as to minimize the thickness
requirements of the vessel wall whilst keeping the water in the liquid phase as these units are operating
below 3.5 bar pressure.
Table 7.3: Table of unit stream unit stream enthalpies and generated steam mass flowrates
The steam generated from D-101, C-101 and AB-602 can now be used to heat process units and as a
utility to heat process streams. Firstly, the process units will be considered and the steam requirements
of the units must be calculated. This is completed by using Eq.7.5 and the results can be seen in the
table below.
Q
mreq = (Eq.7.5)
(hg − hf )
Table 7.4: Table of unit stream enthalpies and required steam mass flowrates
This shows that the 17 bar steam generated in C-101 can be consumed by the heating requirement of
E-201, and the leftover steam is let-down through a condensing steam turbine to 15 bar. The flowrate of
steam let-down to generate 15 bar steam is 9.83-5.43 = 4.4 kg/s, and is insufficient to satisfy the heating
requirement of E-101, thus more 15 bar steam must be generated. This was done by using a natural
gas boiler to generate 40 bar steam, which was let-down through a condensing steam turbine to give 15
bar steam. The supply of 3.5 bar steam generated in AB-602 is sufficient to meet requirements in E-202
with 9.566kg remaining to be used in process heating or further let down to generate electricity.
7.1. Process Streams 3.52
dHb
PHP S = PF + + PBF W (Eq.7.6)
ηB
Where PHP S is the prices of the high pressure steam in R/ton, PF is the prices of the fuel, in this case
natural gas with the price taken to be 53.91 R/GJ from the South African Department of Energy’s web-
site78 , dHB is the heating rate in GJ/ton of steam, ηB is the boiler efficiency assumed to be 0.85, and
PB F W is the price of boiler feedwater which is assumed to be negligible due to the contribution from
condensate recycle. Assuming a boiler feedwater temperature of 125°C and pressure of 40 bar, hg and
hBF W can be calculated from compressed water and steam tables. These were found to be 2801 kJ/kg
and 527.7 kJ/kg respectively. These can be substituted into Eq.7.7 to find the heating rate.
Giving a final heating rate of 2.31 GJ/ton of steam. This is substituted back into Eq.7.6 to give a final
price of 56.6 R/ton of steam for 40 bar steam.
The price of the 17 and 15 bar steam used for process heating was calculated by finding the power
generation from letting the 40 bar steam down to 17 and 15 bar and the return from selling the electricity
generated back to the South African grid. Example calculations for the 15 bar steam are shown below.
Firstly, an isentropic efficiency for the turbine used to expand the steam was assumed to be 0.8, and
the inlet conditions of the high-pressure steam are the saturated conditions at 40 bar. The isentropic
efficiency is defined by Eq.7.8.
hin − hout
ηIS = (Eq.7.8)
hin − hIS
Where hin =2801 kJ/kg from saturated steam tables at 40 bar. To find hIS , the entropy of the outlet steam
at the new saturation pressure was found and compared with the inlet entropy of Sin =6.067 kJ/kG.K. If
the new value of Sout at isentropic conditions, Sout =Sin =6.067 kJ/kg.K, was lower than the Sout at the
saturation pressure, it was determined there would be wet steam at the outlet, thus a wetness check
under isentropic conditions as per Eq.7.9 was carried out. As the entropy of 15 bar steam is 6.444
kJ/kg.K, Eq.7.9 was used to find the isentropic dryness fraction, with values of Sf =2.315 kJ/kg.K and
Sf g =4.129 kJ/kg.K.
Where Swet =Sin , XIS is the isentropic dryness fraction, and Sf and Sf g are the entropies of the liquid
and the difference between the entropies of the liquid and gas respectively at the new lower saturation
pressure of 15 bar from saturated steam tables. This equation was rearranged to find the dryness fraction
under isentropic conditions, XIS =0.9092. The wet enthalpy of the stream was then calculated from
Eq.7.10.
7.1. Process Streams 3.53
Using the previously calculated value for XIS , and finding hf =844.7 kJ/kg and hf g =1947 kJ/kg from
saturated steam tables at the new saturation pressure, hwet was calculated to be 2615 kJ/kg. As XI S
was determined under isentropic conditions, hwet =hIS , and can be substituted into Eq.7.8 to find hout .
Now that the outlet enthalpy has been found, a final wetness test, shown in Eq.7.11, is carried out on the
outlet steam to ensure the dryness fraction, X, at real conditions, is not below 0.88 as cited in literature79 .
This is because excessive wetness in the turbine can cause corrosion and damage to the equipment.
Where hwet =hout . The dryness fraction at the real conditions was found to be 0.928. Assuming a flowrate
of 1 ton/hour of steam for comparison with the calculated price of high pressure steam being 56.6 R/ton,
the turbine shaft work, W , can be calculated from Eq.7.12.
This gives a work W =41.3 kWh. The price of the sale of electricity back to the grid was taken from the
National Energy Regulator of South Africa, NERSA, at 0.7898 R/kWh80 . The price of the lower pressure
steam can now be calculated for 1 ton using Eq.7.13.
This gave a price of 15 bar steam of 24.0 R/ton. The above calculations were repeated for 17 bar steam,
using saturated steam tables for the physical properties of the steam to give a price of 28.0 R/ton. These
prices per ton can be converted into R/kWh by using dimensional analysis to give Eq.7.14.
3600P15bar
P ∗15bar = (Eq.7.14)
1000(hg − hf )
This gives P ∗15bar =0.0443 R/kWh, P ∗17bar =0.0523 R/kWh and P ∗HP S =0.119 R/kWh. These were then
converted into dollars using an exchange rate of 1 Rand=$0.053 (as per 2nd May), to find P ∗15bar =
$0.00235 /kWh, P ∗17bar = $0.0028 /kWh and P ∗HP S = $0.0063 /kWh.
The maximum loads of the ‘free’ 8 bar and 3.5 bar steam generated to be used for process heating can
be calculated by subtracting the steam used for process unit heating from the total amount of steam on
each level generated. This was found to be 11.8 kg/s for 8 bar steam and 9.566 kg/s for 3.5 bar steam.
Using Eq.7.15 the maximum heating load of these streams can be calculated.
This was found to be 24200 kW for the 8 bar steam and 20500 kW for the 3.5 bar steam.
7.2. Heat Exchanger Network 3.54
The objective of the NLP optimization was to find the minimum total cost by changing the duty and branch
flowrate of all of the streams. The was completed with the constraint of a minimum exchanger duty of
300 kW and a minimum approach temperature of 10°C. The final HEN is shown in Figure 7.2 on the
following page yielding a total heat recovery of 6633.62kW. The final hot utility requirement was 5190 kW
and the cold utility requirement 622.915 kW. This shows that the objective of the cold utility requirement
was met however the minimum hot utility requirement was not. Upon further simulation and investigation
it was apparent that this was due to the large amount of heat exchangers required to meet the hot utility
requirement and the optimal design for the minimization of the total costs slightly exceeds the minimum
hot utility due to cross pinch heat transfer in exchangers 1, 3 and 7.
It was also discovered that the SPRINT software used no 15 or 3.5 bar steam to heat the process streams.
The use of this excess steam in addition to excess 8 bar and 17 bar steam will be further discussed in
the following section with a steam balance over the whole system.
It was decided that a final level of steam at 2.32 bar would be used in order to generate additional
electricity from the excess 8 bar and 3.5 bar steam. Furthermore, as the 2.32 bar steam has a saturation
temperature of 125°C, it could be used as boiler feed water upon condensation. The electricity produced
from the turbines was calculated using Eq.7.8 Eq.7.12 for each level of steam and the process heating
duty was calculated by finding the sum of the duties of the exchangers in the HEN which the steam
level was involved in. The overall required heating and cooling utility requirement to be supplied to the
process is now only 13.2 kg/s of 40 bar steam in addition to the 29.8 kg/s of cooling water. As the costs
of all of the utilities were added to the SPRINT software, an economic summary can be made available.
The final hot utility cost was calculated to be $57,400 per year and the cold utility cost to be $203 per
year, giving a cumulative cost of $57,600 per year. The capital cost of the heat exchanger network will
be calculated in further detail in the economics section.
8
Economics
To ensure that the plant is economically sustainable, a full economic analysis must be carried out and key
economic performance indicators analysed to ensure profitability and to attract investors. The economic
indicators that will be used are the cash flow, cumulative cash flow, net present value and payback
time. To perform a full economic analysis for the urea plant design it became clear that the urea plant
could not be considered as a standalone plant due to the high-cost price of ammonia, R12 204/ton of
ammonia, compared to the price of urea R12 890/ton of urea82 . The price of carbon dioxide supplied by
a nearby Kenako concrete was taken to be negligible as the second phase of the South African carbon
tax introduces the removal of any carbon allowances83 in addition to a progressive increase in the cost
of emissions of carbon dioxide to $20/ton by 202584 . This gave a gross margin with the production rate
of 3000 MT/D of urea consuming 2200 MT/D of ammonia calculated from Eq.8.1.
This gave a gross margin of 11,821,200 R/day which can be converted to $/day by multiplying by the
exchange rate of 0.053 $/R (2nd May) to find a GM=627,000 $/day. Despite this being a large positive
value, it was decided that a partnership would be proposed between our plant and the HIVE Energy
green ammonia plant from which we source our ammonia. This partnership would assume that our
plant is pitched to HIVE Energy as an extension of their plant thus assuming our feedstock price for the
ammonia could be calculated from the levelized cost of production. The equation for this is shown below
in Eq.8.285 .
In the International Energy Agency’s 2019 report on The Future of Hydrogen86 , a graphical method for
estimating this levelized cost is given for three routes of ammonia synthesis: using hydrogen from natural
gas; using hydrogen from natural gas with carbon capture; and using hydrogen from electrolysis of water,
as done in the new HIVE Energy plant. Figure 8.1 below was taken directly from Figure 42 in the report86
in lieu of using the data upon which it was based due to lack of access to the data.
This graph shows that if the cost of renewable electricity is less than around 50 $/MWH the cost of green
ammonia from electrolysis is less than that of both unabated grey ammonia and blue ammonia using
carbon capture87 . As the electricity price can be found from the energy.gov.za website, the LCOA of
green ammonia can now be calculated.
3.57
8.1. Capital Cost 3.58
8.1.1. ISBL
The ISBL was calculated using the detailed factorial method from Sinnott and Towler’s Chemical En-
gineering Design (6th Edition)88 . This was completed using equation (3) and the coefficients in Table
8.1.
∑
i=M
C= Ce,i,CS [(1 + fp )fm + (fer + fel + fi + fc + fs + fl )] (Eq.8.3)
i
Where C is the ISBL cost M is the total number of pieces of equipment, Ce,i,CS is the price of purchased
equipment in carbon steel and the installation factors are defined in Table 8.1. Any value with an *
denotes that it is used for fluid-solid process types and is used in the costing of the prilling tower.
The purchased equipment cost, Ce,i,CS , was calculated using the estimation method from Sinnott and
Towler’s Chemical Engineering Design (6th Edition)88 . As the values for these cost approximations were
taken from 2007, they must be updated to modern prices. This was done using the CEPCI with an initial
value of 509.7 and a final value of 813.0 for the year 202290 and Eq.8.4 below.
813
Cost in 2022 = Cost in 2007 × (Eq.8.4)
509.7
Finally, as the estimations are based on the cost of production of the U.S Gulf Coast basis, this was
converted using a location factor of 0.965 for South Africa91 .
This gives a final value for the IBSL of $191,000,000, which can be used to estimate the OSBL, engi-
neering costs and contingency charges.
This gives the final fixed capital investment to be $361,000,000. This can now be converted to an annu-
alised cost using an estimated plant lifetime of 40 years92 and an interest rate from the Bank of South
8.2. Operating Costs 3.60
i(1 + i)n
ACCR = (Eq.8.5)
(1 + i)n − 1
Where i=0.0775 and n=40, giving an ACCR of 0.0816, multiplied by the fixed capital investment to give
an annualised capital investment of $29,400,000 per year.
8.2.1. FCOP
The average salary for a plant operator in South Africa was found to be R213,600 per year94 , converted
to $11,320 per year with an interest rate of 0.053$/R. This was applied to all 86 workers as discussed in
the manning requirements section to find the operating labour cost. The other costs associated with the
FCOP were estimated based on this value in addition to the ISBL and OSBL calculated previously and
are shown in Table 8.4.
8.3. Taxes & Depreciation 3.61
8.2.2. VCOP
In order to calculate VCOP, an energy price must be used to find an approximate LCOA for the ammonia
feedstock. This was found to be 90.03 Rc/kWh from the most recent South African Energy Price Report
in 2021,78 converting this to 0.047 $/kWh or 47$/mWh. This electricity price can also be used to calculate
the cost of the electricity requirements for the pumps, subtracting the electricity generated by the steam
turbines, to give a final electricity price of $1,480,000 per year. Determining the LCOA graphically by tak-
ing an average from the high and low bounds for the LCOA of ammonia in Figure 1 at this electricity price
gives an estimated value of $520 per ton of ammonia. The variable cost of the utility system was costed
in the process integration section and found to have an annual cost of $57,600 per year. Consumable
costs were neglected due to there being no catalysts, acids, bases or solvents used in the process and
waste disposal costs were neglected as waste from the wastewater treatment section is recycled and the
waste from the purge on the MP Absorber was considered to be negligible. Calculating the raw material
cost with a 2200 ton/day requirement operating for 333.3 days per year gave the annualised raw material
cost of $381,000,000 per year. As the utility cost is so small in comparison, the contribution is negligible
when rounded to 3 significant figures giving a final VCOP of $383,000,000 per year.
the third year as production scaled up based on heuristics88 until finally full production was reached in
the 5th year.
To calculate the cash flow first the gross profit must be calculated. This was done using Eq.8.6 below:
The gross profit under normal operation at full capacity was found to be GP=$274,000,000 per year From
the gross profit the cash flow can be calculated using Eq.8.7.
Where CF is the cash flow, D is the depreciation allowance, found to be 10% of the ISBL and OSBL
for the first 10 years and tr is the tax rate, a flat rate of 15%. The cash flow changed annually with an
average of $233,000,000 per year and a graph of the cumulative cash flow against plant life can be seen
in Figure 8.2 below.
From the cash flow the return on investment can be calculated using Eq.8.8.
cumulative cashflow
ROI = × 100 (Eq.8.8)
plant life × initial investment
The return on investment after 10 years was found to be 48.8% and at the end of the plant life to be
55.45%. The net present value can also be calculated from the cash flow using Eq.8.9.
∑
N =t
CFn
NPV = (Eq.8.9)
(1 + i)n
N =1
The simple payback time was calculated using Eq.8.10 and was found to be 1.75 years.
8.5. Economic Sensitivity 3.63
Total Investment
Simple Payback Time = (Eq.8.10)
Average Annual Cashflow
The actual payback time can be determined from Figure 8.2 as the point on the x axis at which the
cumulative cash flow crosses $0 in the positive direction. This was found to be 4.54 years.
Figure 8.3: Electricity cost compared with cumulative NPV (left) and ROI (right)
Figure 8.4: Taxation rate compared with ROI (top) and payback time (bottom)
3.66
References
1 16
Concrete: the most destructive material on earth What are the dimensions of a parking space?,
| cities | the guardian, https : / / www . https://www.interparking- france.com/
theguardian . com / cities / 2019 / feb / en / what - are - the - dimensions - of - a -
25 / concrete - the - most - destructive - parking-space/.
material-on-earth. 17
How much weight can a truck carry - logity dis-
2
Dti, idc fund kenako concrete, https : / / www . patch, https://logitydispatch.com/how-
bizcommunity . com / Article / 196 / 493 / much-weight-can-a-truck-carry/.
170585.html. 18
Design the loading dock | nova technology
3
jverrett, R. Qiao, and R. A. Barghout, Cost of op- loading dock equipment, https : / / www .
erating labour, Aug. 2020. novalocks . com / design - the - loading -
4
dock/.
Staffing levels & workload – human factors 101,
https : / / humanfactors101 . com / topics /
19
Online calculation of ammonia, https : / / www .
staffing-levels-workload/. peacesoftware . de / einigewerte / calc _
nh3.php7.
5
R. K. Sinnott and G. Towler, 14.3 site layout (El- 20
sevier, 2009). S. Nand, M. Goswami, and A. Jain, “Operation,
inspection and maintenance of ammonia storage
6
R. K. Sinnott and G. Towler, 14.4 plant layout (El- tanks in fertilizer industry”, Indian Journal of Fer-
sevier, 2009). tilisers 17, 432–438 (2021).
7 21
S. Moran, Applied guide to process and plant de- Spherical storage tank design - chemical engi-
sign (2nd edition) (Elsevier, 2019). neering world, https : / / chemicalengineer
8
“Aces21 urea process by toyo - advanced pro- ingworld.com/spherical- storage- tank-
cess for cost and energy saving”, design/.
22
9 “Horton sphere ammonia storage tanks at sfc
E. M. H. M. E. M. M. Z. E. A. Q. G. Fadl and
kota”,
E. M. M. Z. E. A. Q. G. Fadl, “Alexfert experience
in commissioning and operation of ammonia stor- 23
Online calculation of carbon dioxide, https://
age tank. prepared by: presented by”, www . peacesoftware . de / einigewerte /
10 calc_co2.php7.
Hive hydrogen to launch south africa’s first-ever
green ammonia plant, https://energycapit Co2 storage tanks | igc engineering, https :
24
3.67
3.68
32
“Section 3. composition/information on ingredi- 49
Piping inspection, https://www.inspection-
ents section 4. first aid measures”, for - industry . com / piping - inspection .
33 html.
“Material safety data sheets”, 41–143 (2004).
34
“Safety data sheet ghs product identifier”,
50
Electrical inspection and testing | croner-i, ht
35 tps : / / app . croneri . co . uk / topics /
“Section 3. composition/information on ingredi-
electrical - inspection - and - testing /
ents section 4. first aid measures”,
summary?product=133.
36
Auto-ignition temperature test | sigma-hse, htt 51
ps : / / www . sigma - hse . co . in / process - “Machinery, plant and equipment (labour admin-
safety - testing / auto - ignition - istration and inspection)”,
temperature.html. 52
The commissioning process: a step-by-step
Dsear regulations - fire and explosion, https :
37 guide - commissioning academy, https : / /
/ / www . hse . gov . uk / fireandexplosion / commissioningandstartup . com / the -
dsear-regulations.htm. commissioning - process - a - step - by -
38 step-guide/.
K. Sano, Y. Koshiba, and H. Ohtani, “Emer-
gency shutdown of fluidized bed reaction sys- 53
Guide to flushing and pre-commission cleaning
tems”, Journal of Loss Prevention in the Process of pipework | wts, https://watertreatment
Industries 68, 104277 (2020). services . co . uk / guide - flushing - pre -
39
The purpose of a permit to work system - has- commission-cleaning/.
pod, https : / / www . haspod . com / blog / 54
Inspection technique for plants and vessels | rls
paperwork / purpose - permit - to - work - human care, https : / / rlsdhamal . com /
system. inspection - techniques - for - plants -
40
Port elizabeth climate: weather by month, tem- vessels-and-procedures/.
perature, precipitation, when to go, https : / / 55
S. Mukherjee, “Preparations for initial startup of
www . climatestotravel . com / climate /
a process unit; here is what to do just after a
south-africa/port-elizabeth.
new plant is built, to make sure it will have a
41
Africa’s urea market report 2023 - prices, size, smooth startup”, Chemical Engineering 112, 36–
forecast, and companies, https : / / www . 43 (2005).
indexbox . io / store / africa - urea -
market - analysis - forecast - size -
56
Utility systems - processdesign, https : / /
trends-and-insights/. processdesign.mccormick.northwestern.
edu/index.php/Utility_systems.
42
Who owns sa’s land? | news24, https://www.
57
news24.com/news24/who-owns-sas-land- Reactor startup - an overview | sciencedirect top-
20171028. ics, https : / / www . sciencedirect . com /
43 topics/engineering/reactor-startup.
Urea imports worldwide by country | statista,
https://www.statista.com/statistics/ 58
The basics of pump startup | pumps & systems,
1281701 / global - urea - import - volume - https : / / www . pumpsandsystems . com /
by-country/. basics-pump-startup.
44
Commissioning • addison, https://addisong 59
R. Smith, M. Pan, and I. Bulatov, “Heat trans-
roup.uk/commissioning/. fer enhancement in heat exchanger networks”,
45 Handbook of Process Integration (PI): Minimisa-
What is commissioning - complete commission-
ing, inc. https : / / completecx . com / what - tion of Energy and Water Use, Waste and Emis-
is-commissioning/. sions, 966–1039 (2013).
46
Inspection of work equipment - equipment and 60
Effective plant maintenance shutdown from cole-
machinery, https://www.hse.gov.uk/work- parmer, https : / / www . coleparmer .
equipment-machinery/inspection.htm. com / tech - article / plant - shutdown -
47
Design codes - plant, https://www.hse.gov. maintenance.
uk/comah/sragtech/techmeasplant.htm. 61
Seven steps for a successful shutdown | plant en-
48
Heat exchanger inspection, https : / / www . gineering, https://www.plantengineering.
inspection - for - industry . com / heat - com / articles / seven - steps - for - a -
exchanger-inspection.html. successful-shutdown/.
3.69
62 75
Difference between process shutdown and emer- Y. Chen, Y. Lyu, X. Yang, X. Zhang, H. Pan, J.
gency shutdown, https : / / instrumentati Wu, Y. Lei, Y. Zhang, G. Wang, M. Xu, and H.
ontools . com / process - shutdown - and - Luo, “Performance comparison of urea produc-
emergency- shutdown/?utm_content=cmp- tion using one set of integrated indicators consid-
true. ering energy use, economic cost and emissions’
63
What is plant maintenance? | rasmussen me- impacts: a case from china”, Energy 254, 124489
chanical, https://www.rasmech.com/blog/ (2022).
what-is-plant-maintenance/. 76
J. C. M.W., “Nist-janaf themochemical tables,
64
Maintenance and repair safety of plant equip- fourth edition”, J. Phys. Chem. Ref. Data, Mono-
ment using hasps locks » locksafe, https : / / graph 9, 1–1951 (1998).
locksafe . com . au / blog / maintenance - 77
Online calculation of properties of water and
and - repair - safety - of - plant - steam, https : / / www . peacesoftware . de /
equipment-using-hasps-locks/. einigewerte/wasser_dampf_e.html.
65
R. J. Willey, “Layer of protection analysis”, Proce- 78
K. Ratshomo and R. Nembahe, “Energy price re-
dia Engineering 84, 12–22 (2014). port 2021”, ¥ South African Energy Price Report
66
What is corrective maintenance? (definition, pros, ¥ (2021).
cons and examples) - twi, https://www.twi- 79
Steam and gas turbines and power plant engi-
global.com/technical- knowledge/faqs/ neering by r. yadav | goodreads, https://www.
what-is-corrective-maintenance. goodreads.com/en/book/show/28257926.
67
What are the benefits of preventative mainte- 80
Cape town to pay cash for electricity – with aim to
nance? | plant engineering, https : / / www . cut load shedding by 4 stages | business, https:
plantengineering . com / articles / what - //www.news24.com/fin24/economy/cape-
are - the - benefits - of - preventative - town-to-pay-cash-for-electricity-to-
maintenance/. businesses-households-20230124.
68
Predictive maintenance explained, https : / / 81
R. Sinnott and G. Towler, “Costing and project
www . reliableplant . com / Read / 12495 / evaluation”, Chemical Engineering Design, 275–
preventive-predictive-maintenance. 369 (2020).
69
Operation and maintenance of nuclear power 82
“Executive summary � international and domes-
plants | iaea, https : / / www . iaea . org / tic price trends for selected fertilisers”, (2021).
topics/operation-and-maintenance.
83
70
South africa: carbon tax - impact on carbon-
News and views from the tracerco marketing intensive businesses and the way forward,
team | distillation column maintenance, https : https : / / www . globalcompliancenews .
//blog.tracerco.com/marketing/topic/
com/2022/09/16/south- africa- carbon-
distillation-column-maintenance.
tax - impact - on - carbon - intensive -
71
Storage tank preventative maintenance / manag- businesses-and-the-way-forward/.
ing ageing plant | assentech limited, http : / / 84
Carbon tax: will allowances, after 2022, be re-
breather - valves . co . uk / preventative -
duced or removed?, https://www2.deloitte.
maintenance - site - agent - service -
com/za/en/pages/tax/articles/carbon-
safety/.
tax-will-allowances-after-2022.html.
72
Pump maintenance – why when and how! | cas- 85
A. Bose, N. Lazouski, M. L. Gala, K. Manthiram,
tle pumps, https://www.castlepumps.com/
and D. S. Mallapragada, “Spatial variation in cost
info - hub / pump - maintenance - why - when -
of electricity-driven continuous ammonia produc-
and-how1/.
tion in the united states”, ACS Sustainable Chem-
73
Heat exchanger maintenance guide | sterling tt, istry and Engineering 10, 7862–7872 (2022).
https : / / www . sterlingtt . com / 2021 / 86
pidjoe, “The future of hydrogen”,
08 / 07 / heat - exchanger - maintenance -
87
guide/. The cost of co2-free ammonia – ammonia energy
74
Valve and instrumentation calibration and main- association, https : / / www . ammoniaenergy .
org / articles / the - cost - of - co2 - free -
tenance | sgs ecuador, https : / / www .
ammonia/.
sgs . com / en - ec / services / valve -
and- instrumentation- calibration- and- 88
R. K. Sinnott and G. Towler, 6. costing and project
maintenance. evaluation (Elsevier, 2009).
3.70
89
Uns s32808 stainless steel :: makeitfrom.com,
https://www.makeitfrom.com/material-
properties / UNS - S32808 - Stainless -
Steel.
90
Fluid mechanics, https : / / personalpages .
manchester . ac . uk / staff / tom . rodgers /
Interactive _ graphs / CEPCI . html ?
reactors/CEPCI/index.html.
91
How to determine the location factor? - chemi-
cal engineering blogger, http : / / nikraftar .
com / how - to - determine - the - location -
factor/.
92
The state-of-the-art urea reactor - ureaknowhow,
https : / / ureaknowhow . com / the - state -
of-the-art-urea-reactor/.
93
Bank of south africa interest rate 2023 | take-
profit.org, https : / / take - profit . org /
en / statistics / interest - rate / south -
africa/.
94
Plant operator salary in south africa - average
salary, https : / / za . talent . com / salary ?
job=plant+operator.
95
“Simplified overview of special economic zones
tax and customs incentives”,
96
12i tax allowance incentive – the department of
trade industry and competition, http : / / www .
thedtic . gov . za / financial - and - non -
financial - support / incentives / 12i -
tax-allowance-incentive/.
97
T. Matsuo and T. S. Schmidt, “Managing trade-
offs in green industrial policies: the role of renew-
able energy policy design”, World Development
122, 11–26 (2019).