Ss 11
Ss 11
1.1 The Gujarat Energy Transmission Corporation Ltd., Baroda hereinafter called
‘GETCO’/ ‘OWNER’ intends to receive bids for Design, Engineering, manufacturing,
Supply, erection, testing and commissioning of 400KV and 220KV GIS Equipment &
material on Turnkey basis including all civil works at 400KV Dholera GIS S/S as per
detailed in the accompanying specifications in accordance with Terms and Conditions
herein. The bids shall be prepared and furnished as per these Instructions.
Defination of terms :
Note: ‘Owner’ shall mean the Gujarat Energy Transmission Corporation Ltd
Vadodara or any of its group companies i.e. GUVNL, GSECL, MGVCL, DGVCL,
PGVCL, UGVCL and shall include its legal representatives, successors and
assigns.
1.2 Any Bidder from a country which shares a land border with India will be eligible to bid
only if the Bidder is registered with the Competent Authority as per order no.
F.No.6/18/2019-PPD (Order Public Procurement no.1) dated 23/07/2020 and
F.No.6/18/2019-PPD (Order Public Procurement no.2) dated 23/07/2020, issued by
Public Procurement Division, Department of Expenditure, Ministry of Finance,
Government of India (DoE Order).
However, the aforesaid condition for registration of Bidders from countries (even if
sharing land border with India) shall not be applicable to Bidders from such countries to
which Government of India has extended lines of credit or in which Government of India
is engaged in development projects.
(ii) “Bidder from a country which shares a land border with India” for this purpose means:
a. An entity incorporated, established or registered in such a country; or
b. A subsidiary of an entity incorporated, established or registered in such a country; or
c. An entity substantially controlled through entities incorporated, established or
registered in such a country; or
d. An entity whose beneficial owner is situated in such a country; or
e. An Indian ( or other) agent of such an entity; or
f. A natural person who is a citizen of such a country; or
g. A consortium or joint venture where any member of the consortium or joint venture
falls under any of the above
1. In case of a company or Limited Liability Partnership, the beneficial owner is the natural
person(s), who, whether acting alone or together , or through one or more juridical person,
has controlling ownership interests or who exercises control through other means
Explanation-
a. “Controlling ownership interest” means ownership of or entitlement to more than twenty-
five percent of shares or capital or profits of the company
b. “Control” shall include the right to appoint majority of the directors or to control the
management or policy decisions including by virtue of their shareholding or management
rights or shareholders agreement or voting rights;
2. In case of a partnership firm, the beneficial owner is the natural person(s) who, whether
acting alone or together, or through one or more juridical person, has ownership of
entitlement to more than fifteen percent of capital or profits of the partnership;
4. Where no natural person is identified under (1) or (2) or (3) above, the beneficial owner is the
relevant natural person who holds the position of senior managing official
5. In case of a trust, the identification of beneficial owner(s) shall include identification of the
author of the trust, the trustee, the beneficiaries with fifteen percent or more interest in the
trust and any other natural person exercising ultimate effective control over the trust through
a chain of control or ownership.
An Agent is a person employed to do any act for another, or to represent another in dealings
with third person.
Further, the successful Bidder shall not allowed to subcontract works to any contractor from a
country which shares a land border with India unless such contractor is registered with the
Competent Authority.
The Bidder shall in its bid submit a certificate in compliance to DoE order as per the given format.
Further, the firm has to be a ‘Class-I local supplier’ as defined under Public Procurement
(Preference to Make in India) Order, 2017 issued by Department for promotion of Industry
and Internal Trade (DPIIT), Ministry of Commerce and Industry, Government of India vide order
dated 15/06/2017, its revision dated 04/06/2020 (PPP-MII Order) read in conjunction with
‘Public Procurement (Preference to Make in India) to provide for Purchase Preference
(linked with local content) in respect of Power Sector’ order dated 28/07/2020 issued by
Ministry of Power (MoP Order) and subsequent modifications/amendments if any
Firms who are not ‘Class-I local supplier ‘ shall not be eligible to bid.
Registration desirable by DPIIT is must be valid till the expiry of validity of offer. Mere
application for registration will not be consider and bid is liable to rejected.
Eligible Bidder should submit the aforesaid registration documents and if not applicable, the
undertaking is to be submitted along with bid, stating that bidder are not falling under requirement
of registration as per DPIIT Guideline and will follow applicable DPIIT Guideline and appropriate
guideline regarding import of material as per DPIIT in toto.
2.1 The Scope of the proposal shall be on the basis of a single Bidder’s responsibility,
completely covering all the equipments and installation services specified under the
accompanying Technical Specifications. It will include among others as specified therein
the following:-
2.2 No deviation whatsoever to certain conditions of the bidding documents permitted by the
Owner and therefore, the Bidders are advised that while making Bid Proposals and
quoting prices these conditions may appropriately be taken into consideration. Bidders
are required to furnish a certificate in this regard as per the format provided in Special
Conditions of Contract in a separate sealed envelope containing Bid security, which shall
accompany the Technical Bid. Any Bid not accompanied by such certificate shall be
rejected by the Owner and shall not be opened.
2.3 Bids not covering the above cited entire scope of works may be treated as incomplete
and hence rejected.
2.4 The Bidder shall complete all the schedules & annexure in the Bid Proposal Sheets,
Technical Data Sheets and specified elsewhere. The Qualifying Data should be filled in
the required schedule of Bid Proposal Sheets.
2.5 This specification covers the detailing, designing, engineering, manufacturing, testing at
works, packing, supply, storage, insurance and handling at site, Design, Engineering,
manufacturing, Supply, erection, testing and commissioning of 400KV and 220KV GIS
Equipment & material on Turnkey basis including all civil works at 400KV Dholera GIS S/S.
The work includes Design, Engineering, manufacturing, Supply, erection, testing and
commissioning of 400KV and 220KV GIS Equipment & material on Turnkey basis including
all civil works at 400KV Dholera GIS S/S.
2.6 basis including all civil work including Cabling, Wiring, Earthing , yard lighting etc.
as stated hereunder & detailed in the Schedules so as to complete the project as
per approved bill of quantities and layout drawings.
(A) SCADA
(A) Complete Sub-Station automation including hardware & software for local control
station along with associated equipments as defined in tech specifications.
(B) Other activities for GIS Sub-Station.
(i) Complete relay & protection system including design, engineering,
calculations etc.
(ii) Air conditioning system – For control room (split A/C )
(iii) LT Switchgear (A/C & D/C Distribution board)
(iv) Batteries & battery chargers for
a) As per BOQ
b) Control Cables
(v) Fire detection & Alarm system for Building
Mandatory Spares
– As specified in BOQ & tech specification part –II.
(vi) Other associated equipments, accessories etc, as per layout.
(vii) Structures:
Design & engineering of gantry structures are in the scope of
bidder
(vii) Earthing:
a. Complete Earthing system including Earth mat. and protection against direct stroke
of lightning.
b. Execution of earthing work includes supply of all earthing materials.
(viii) Lighting.
(i) Yard Lighting of the switchyard.
(ii) Illumination design to be done as per CBIP manual.
(iii) Illumination of GIS housing & CR building.
Seal & Signature of Bidder 14
(iv) Scope is as per BOQ & Specifications as per Part –II & III.
(ix) This is being a turnkey project therefore any item , accessories, work etc
required for completion and successful operation of entire project shall be
considered in the scope.
1. Contractor has to provide all engineering drawings , data calculations etc for owners
approval as specified in part –I, GCC, general Information.(Tech) – Clause No. 1.2
The scope of work under this contract shall include construction of all the items mentioned
hereunder, but not limited to, which are required for satisfactory & successful completion and
commissioning of 400KV GIS Sub-station at Dholera in the state of Gujarat except exclusion
specifically mentioned elsewhere in this document.
1.0 GENERAL
The contractor shall provide all labor, tools, plants & equipments, material, temporary works,
construction plants & machinery, fuel supply, transportation, insurance and all other incidental
items not specified but as they may be required for complete performance of the works in
accordance with approved drawings, specifications, applicable IS codes & direction of the
GETCO.
The work shall be carried out according to design & drawings approved by GETCO. The
successful bidders shall be fully responsible for the fulfilling functional requirement such as
operational & maintenance requirements etc. of the project & work shall be carried out as per
the applicable IS codes & International standards. In case of ambiguity between codes,
specifications and drawings, the most stringent of them shall govern. Certain general
requirements are indicated hereunder;
2.0 The scope of work under this contract shall include following in general.
1. Control Room Building & GIS housing with EOT crane arrangement
and cable celler.
2. Security Cabin.
3. Foundations for Switch Yard Structures & Equipments.
5. Transformer Foundations with marshalling work & its track up-to road
8. Bore well.
9. Water Supply System internal & external with(U/G + O/H tanks) tanks.
16. Furniture, RO Plant for potable water, Water Coolers , split A.C etc,
17. Any other civil work which are required for successful completion &
commissioning of 220kv GIS.
In the tender separate schedules for Civil works at 400KV GIS Dholera are enclosed.
Contractor shall have to quote the rates in figure & in words for each item of work, separately.
In case of any ambiguity the rates quoted in words shall govern.
6.2 Any verbal/telephonic clarifications and information given by the Owner or his employee
(s) or his representative(s) will not in anyway be binding on the Owner.
At any time prior to the deadline for submission of Bids the Owner may, for any reason,
whether at his own initiative or in response to a clarification requested by the intending
Bidder, modify the Bidding Document with amendment(s).
7.2 The amendment will be notified in writing or Fax /web site to all intending Bidders who
have received the Bidding Document at the address contained in the letter of request for
issue of Bidding document from the Bidders. Owner will bear no responsibility or liability
arising out of non-receipt of the same in time or otherwise.
7.3 In order to afford prospective bidders reasonable time in which to take the amendment
into account in preparing their bids, the Owner may, at his discretion, extend the deadline
for the submission of bids.
7.4 Such amendments, clarifications etc. shall be binding on bidders and will be given due
consideration by the Bidders while they submit their bids and shall invariably enclose
such documents as a part of the bid.
Language Of Bid:
8.1 The Bid prepared by the Bidder and all correspondence and documents relating to the
Bid, exchanged by the Bidder and the Owner, shall be written in the English language,
provided that any printed literature furnished by the Bidder may be written in another
language so long as accompanied by an English translation of its pertinent passages.
Failure to comply with this may disqualify a bid. For purposes of interpretation of the bid,
the English translation shall govern.
Bidders have to make the Bid in the formats furnished with this Document. verbatim
without adding any printed/typewritten text of their own.
9.1 It will be imperative on each Bidder to fully inform himself of all local conditions and
factors which may have any effect on the execution of the Contract covered under these
documents and specifications. The Owner shall not entertain any request for
clarifications from the bidders, regarding such local conditions.
9.2 It must be understood and agreed that such factors have properly been investigated and
considered while submitting the proposals. No claim for financial adjustment to the
Contract awarded under these specifications and documents will be entertained by the
owner. Neither any change in the time schedule of the Contract nor any financial
adjustments arising thereof shall be permitted by the Owner, which are based on the
lack of such clear information or its effect on the cost of the works to the Bidder.
10.0 Documents comprising the Bid:
10.1 The Bidder shall complete the Bid form inclusive of Price Schedules, Technical Data
Requirements etc. furnished in the Bidding Documents, indicating, for the goods to be
supplied and services to be rendered, a brief description of goods and services, quantity
and price.
10.2 The Bidder shall also submit documentary evidence to establish that the Bidder meets
the Qualification Requirements as detailed in Special Conditions of Contract and GCC.
10.3 All Tender Documents/ formats are to be returned completed in all respects and
signed by the Company Authorized Signatory wherever specified.
All Bid documents duly signed & sealed shall be submitted with technical bid.
10.4 The Bid Guarantee shall be furnished in a separate cover in accordance with clause at
GCC.
11.1 The Bidder shall indicate, in the price schedules, enclosed in bid proposal sheet the
F.O.R. Destination prices for Goods, the price for erection, testing and commissioning,
price for associated civil, structural works and other services it proposes to furnish under
the contract, EXCLUDING GST and Cess along with the total bid price.
GST shall be applicable at the rate of 9% CGST plus 9% SGST or 18% IGST,
or as applicable to composite supplies in the nature of Works Contract
applicable from time to time will be paid within the original contractual
delivery period. However, the Classification Codes (i.e. HSN or SAC) for
each item of different segments or portions of the Works Contract, shall be
specified separately, for information and technical identification purpose
only.
11.2 Detailed break up, covering all the price components of unit prices as well as total bid
price, as stipulated in the appropriate price schedules of bid proposal sheet shall be
i. PRICES:
Prices quoted should be FIRM and on F.O.R. Destination basis (i.e. any of the stores of
COMPANY in Gujarat). However, the Tenderer should indicate in Price Bid, the break-
up of Total Unit F.O.R. Destination Price stating the Unit Ex-works price, freight, packing
& forwarding charges, Insurance Charges, separately in price bid, which is a must. The
rate of GST shall be 9% CGST plus 9% SGST or 18% IGST or as applicable to
composite supply in the nature of Works Contract, applicable from time to time.
ii. This tender is to be treated as a contract for composite supply under the category of
Works Contract, which is, as per the provisions of Section 2(30), read with, Section
2(119), further read with, Paragraph 6(a) of the Schedule II, to the CGST Act, 2017 and
similar provisions, applicable under UTGST Act, 2017 and the IGST Act, 2017. However,
the classification Codes (HSN/SAC) for each item under different segments or portions
of the Works Contract, shall be specified separately for the knowledge and transparency
purpose which shall have no bearing on price or taxation payment.
iii. The offered prices to be indicated in online mode of tender in the format given (i.e.
Schedule-______). The price bid submitted in physical mode shall not be considered.
iv. The Tenderer should invariably indicate the total unit end cost price considering all
their costs / calculations in the Price bid itself for each item and all sub-items if any. This
is a must. Cost components hidden / furnished elsewhere will not be considered and will
be ignored out rightly.
v. Every bidder shall inform their GSTIN No. of the registered place(s) wherefrom the
bidder intends to supply the goods / services, meaning thereby the bidder has to supply
the goods / services from the relevant declared / registered place of supply only.
11.3 The bidder’s separation of price components in accordance with above clause No: 11.2
will be solely for the purpose of the facilitating the comparison of Bids by the owner, for
contract price amendment due to quantity variation and for on account payments (in
case of award) and shall not in any way limit the Owner’s rights.
11.4 The Price quoted by the bidder shall remain firm during the contract period
and shall not be subject to variation on any account or for change in
quantity.
11.5 The Bidder shall specifically note that the Tenders are invited on item rate base.
12.1 The bidder shall furnish, as a part of its bid EMD, bid security for an amount of 15.0 Lacs
to be paid as under:
a) 50% OR 100% In the form of crossed DD drawn in favor of Gujarat Energy Transmission
Corporation Limited payable at Vadodara.
b) Remaining 50% amount in form of BG from approved banks of GETCO having validity
of Six months from the date of bid opening of Technical Bid.
12.2 The bid security is required to protect the owner against the risk of Bidder’s conduct,
which would warrant the guarantee forfeiture, pursuant to relevant paras elsewhere The
bid guarantee shall be made payable to the Owner without any condition whatsoever.
12.3 Any bid not secured in accordance with above will be rejected by the Owner as non-
responsive. No exemptions are made in the furnishing of the security.
12.5 The successful bidders, Bid Security will be discharged upon, furnishing the contract
performance guarantee
a) If a Bidder withdraws its bid during the period of bid validity specified by the
bidder on the bid Form:
b) If a bidder refuses to accept the contract or fails to commence the works (
including supplies within thirty days of letter of award of contract )
13.2 The original and all copies of the bid shall be typed or written in indelible ink and shall
be signed by the Bidder or a person or persons duly authorized by the Bidder to sign the
Contract. The letter of authorization shall be indicated by written power-of-attorney
accompanying the bid. All pages of the bid, except for un-amended printed literature,
shall be initiated by the person or persons signing the bid.
13.3 The Bidders must submit the qualifying data in one original and one duplicate copy as
required in this Instructions to Bidders in separate envelopes sealed and enclosed in the
envelope submitting proposals, super scribed as under :
Note: The Prices are to be filled online only. Price Bids are not to be
submitted with physical documents.
All Bid documents duly signed & sealed shall be submitted with technical bid.
Must contain conditions and schedules of Part- III without prices and Technical Data
Requirement Sheets (Cover I, II, III will be collectively called Technical Bid).
All Bid documents duly signed & sealed shall be submitted with technical bid.
14.1 The bid must contain the name, residence and place of business of the person or
persons making the bid and must be signed and sealed by the Bidder with his usual
signature. The names of all persons signing should also be typed or printed below the
signature.
14.2 Bid by a partnership must be furnished with full names of all partners and be signed with
the partnership name, followed by the signature(s) and designation(s) or the authorized
partner(s) or other authorized representative(s).
14.3 Bids by Corporation/Company must be signed with the legal name of the
Corporation/Company by the President/Managing Director or by the Secretary or other
person or persons authorized to bid on behalf of such Corporation/Company in the
matter.
14.4 A bid by a person who affixes to his signature the word ‘President’, ‘Managing Director’,
‘Secretary’, ‘Agent’ or other designation without disclosing his Principal will be rejected.
14.5 If it is found that two or more persons who are connected with one another either
financially or as a principal and agent have bid under different names without disclosing
their connection then such bids will be liable for rejection. Satisfactory evidence of
authority of the person signing on behalf of the Bidder shall be furnished with the bid.
14.6 The Bidder’s name stated on the proposal shall be the exact legal name of the firm.
14.7 Bids not conforming to the above requirements of signing may be disqualified and EMD
forfeited.
15.0 Sealing and marking of bids:
Cover-I, Cover-II ,Cover-III shall be individually sealed and super scribed as indicated
above and should be enclosed in the main cover duly sealed and super scribed as
Tender for …………………………………… against Bid No…………… due
on…………… containing Cover-I, Cover-II, Cover-III of this tender.
The original Bid and accompanying documents clearly marked “Original” plus one copy
for Cover I, II, III shall be submitted by the Bidder at the date, time and place specified.
In the event of any discrepancy between the original and the copies, the original shall
govern.
The Bid shall be submitted by RPAD or through speed post services at the Office
of the CE (P & C) GETCO, Bids submitted should be posted with due allowance for any
postal delay. The Bids received after the Due Date and Time of opening are liable to be
rejected. Telegraphic/Telex/Fax/e-mail Bids shall not be entertained.
15.2 The Bidders shall seal the original and each copy of the bid in an inner and an outer
envelope, duly marking the envelopes as “original” and “copy”.
b. Bear the name of package bid enquiry number, name of the work and the words. “DO
NOT OPEN BEFORE……………………
15.4 The inner envelope shall indicate the name and address of the Bidder to enable the
bid to be returned unopened in case it is declared “late” or “rejected”.
15.5 If the outer envelope is not sealed and marked as required by Clause No: 15.1 the Owner
will assume no responsibility for the bid’s misplacement or premature opening.
15.6 The Bid Security conditions must be submitted in a separate sealed envelope.
16.1 Bids submitted by telex/telegram will not be accepted. No request from any Bidder to the
Owner to collect the proposals from airlines, cargo agent etc. shall be entertained by the
Owner.
16.2 Bids must be received by the Owner at the address specified under Clause No: 15.3,
not later than the time & date mentioned in the Invitation to Bid.
17.1 Any bid received by the Owner after the time and date fixed or extended for submission
of bids prescribed by the Owner, will be rejected and not considered for evaluation.
18.1 The Bidder may modify or withdraw its bid after the bid’s submission provided that written
notice of the modification or withdrawal is received by the Owner prior to the deadline
prescribed for submission of bids.
18.2 The Bidder’s modification or withdrawal notice shall be prepared, sealed, marked and
dispatched in accordance with the provisions of clause No: 15.0. The envelope should
clearly indicate whether the modification is for the Technical bid or the Price bid. No bid
modifications notice by Telex/Grams/Fax shall be entertained by the Owner.
18.3 No bid shall be modified in any manner, whatsoever subsequent to the deadline for
submission of bids.
18.4 No bid may be withdrawn in the interval between the deadline for submission of bids and
the expiration of the period of bid validity specified by the Bidder on the Bid Form.
Withdrawal/modification of a bid during this interval may result in the Bidder’s forfeiture
of its bid security.
19.1 The bids must clearly indicate the name of the manufacturer, the type and/or model of
each principal item of equipment proposed to be furnished and erected. The bid should
also contain drawings and descriptive materials indicating general dimensions, materials
from which the parts are manufactured, principles of operation, the extent of pre-
assembly involved, major construction equipment proposed to be deployed, method of
erection and the proposed erection organizational structure.
19.2 The above information shall be provided by the Bidder in the form of separate sheets,
drawings, enclosed etc. in two copies along with soft copy.
19.3 Any bid not containing sufficient descriptive material to describe accurately the
equipment proposed may be treated as incomplete and hence rejected. Such descriptive
materials and drawings submitted by the Bidder will be retained by the Owner. Any major
departure from these drawings and descriptive material submitted will not be permitted
during the execution of the Contract without specific written permission of the Owner.
19.4 Oral statements made by the Bidder at any time regarding quality, quantity or
arrangement of the equipment or any other matter will not be considered.
19.5 Standard catalogue pages and other documents of the Bidder may be used in the bid to
provide additional information and data as deemed necessary by the Bidder.
20.1 The Owner will open the bids in the presence of Bidder’s representatives who
choose to attend on the date and time mentioned for opening of bids in the Invitation
to Bid or in case any extension has been given thereto, on the extended bid opening
date and time notified to all the Bidders who have purchased the bidding document. The
Bidder’s representatives who are present shall sign a register evidencing their
attendance.
20.2 The Bidder’s names, Technical modifications, Bid withdrawal and such other details as
the Owner, at his discretion may consider appropriate, will be announced in the
Technical Bid Opening.
20.3 The price bids of all the “Techno-Commercial” Responsive Bidders shall be opened in
the presence of representatives (up to two per firm) of such bidders who choose to be
present. The date & time of opening the Price Bid shall be intimated to all such qualified
bidders by Fax/Telex, at least one week in advance besides inviting final price bid if
found appropriate after evaluation of Technical bids.
20.4 The Bidder’s name, Bid Price, all discounts if any, modifications in the Price Bid and any
such other details as the Owner, at his discretion, may consider appropriate, will be
announced/ furnished in the Price Bid Opening.
21.1 The Bids received/accepted/opened will be evaluated by the Owner to ascertain the
technical responsiveness of the bid for the complete scope of the proposal, as covered
under these specifications and documents. All technically responsive bids shall then be
examined to determine the lowest evaluated commercially and technically responsive
bids.
22.1 Bids shall be deemed to be under consideration immediately after opening of Technical
Bid and until such time official intimation of award/rejection is made by the Owner to the
Bidders. While the Bids are under consideration, Bidders and/or their representatives
and other interested parties are advised to refrain from contacting by any means, the
owner and/or his employee’s representatives on the matters related to Bids under
consideration.
To assist in the examination evaluation and comparison of Bids the owner may on his
own ask the Bidder for a clarification of its bid. The request for clarification and the
response shall be in writing and no change in the price or substance of the bid shall be
sought, offered or permitted.
23.1 The Owner will examine the bids to determine whether they are complete, whether any
computational errors have been made, whether required sureties have been furnished,
whether the documents have been properly signed, and whether the bids are generally
in order.
If there is a discrepancy between the unit price and the total price that is obtained by
multiplying the unit price and quantity, the unit price shall prevail and the total price shall
be corrected. If there is a discrepancy between the total bid amount and the sum of total
costs, the latter shall prevail and the total bid amount will be corrected accordingly. If
there is a discrepancy between words and figures, the amount advantageous to the
Owner will prevail. If the Bidder does not accept the correction of the errors as above,
his Bid will be rejected and the amount of Bid Security will be forfeited. The Bidder should
ensure that the prices furnished in various price schedules are consistent with each
other. In the case of any inconsistency in the prices furnished in the specified prices
schedules to be identified in Bid Form for this purpose, the Owner shall be entitled to
consider the highest price for the purpose of evaluation and for the purpose of award of
Contract use the lowest of the prices in these schedules.
23.3 Prior to the detailed evaluation, the Owner will determine the substantial responsiveness
of each bid to the Bidding Document. For purpose of these Clauses, a substantially
responsive bid is one which conforms to all the terms and conditions of the Bidding
Document without material deviations. A material deviation is one which affects in any
way the prices, quality, quantity or delivery period of the equipment, completion of works
or which limits in any way the responsibilities or liabilities of the Bidder of any right of the
Owner as required in these specifications and documents. The Owner’s determination
of a bid’s responsiveness shall be based on the contents of the bid itself without recourse
to extrinsic evidence.
23.4 A bid determined as not substantially responsive will be rejected by the Owner and may
not subsequently be made responsive by the Bidder by correction of non-conformity.
23.5 The Owner may waive any minor informality or non-conformity or irregularity in a bid
which does not constitute a material deviation, provided such waiver does not prejudice
or affect the relative ranking of any Bidder.
24.1 The owner will award the contract to the successful Bidder, whose bid has been
determined to be substantially responsive and has been determined as the lowest
evaluated bid, providing further that the Bidder is determined to be qualified to perform
the contract satisfactorily. The Owner shall be the sole judge in this regard.
24.3 Further, the Owner reserves the right to award separate contracts to two or more parties
in line with the terms and conditions specified in the accompanying Technical
Specifications.
25.0 Owner’s right to accept any bid and to reject any or all bids:
25.1 The Owner reserves the right to accept or reject any bid, and to annual the bidding
process and reject all bids at time prior to award of contract, any without thereby incurring
any liability to the affected Bidder or Bidders or any obligation to inform the affected
Bidder or Bidders of the grounds for the Owner’s action.
26.1 Prior to the expiration of the period of bid validity and extended validity period, if any, the
Owner will notify the successful Bidder in writing by registered letter or cable or telex or
FAX, to be confirmed in writing by registered letter, that its bid has been accepted.
26.2 The notification of award will constitute the formation of the Contract.
26.3 Upon the successful Bidder’s furnishing of performance guarantee pursuant to relevant
clause No: 36 & 38, the Owner will promptly notify each unsuccessful Bidder and will
discharge its bid security, pursuant to Clause No: 12.00.
27.1 At the same time as the Owner notifies the successful Bidder that his bid has been
accepted, the Owner will send the Bidder the detailed of Award, incorporating all
agreements between the parties.
27.2 Within 15 days of receipt of the detailed of Award, the successful bidder shall sign the
same with date and return it to the Owner.
27.3 The Bidder will prepare the Contract Agreement as per the proforma prescribed and the
same will be signed within 30 (Thirty) days of notification of Award.
28.1 The ‘Contract’ means the agreement entered into between the Owner and the Contractor
as per the Contract Agreement signed by the parties, including all attachments and
appendices thereto and all documents incorporated by reference therein.
28.2 ‘Owner’ shall mean the Gujarat Energy Transmission Corporation Ltd Vadodara or any
of its group companies i.e. GUVNL, GSECL, MGVCL, DGVCL, PGVCL, UGVCL and
shall include its legal representatives, successors and assigns.
28.3 ‘Contractor’ or ‘Manufacturer’ shall mean the Bidder whose bid is accepted by the Owner
for the award of the Works and shall include such successful Bidder’s legal
representatives, successors and permitted assigns.
28.6 The terms ‘Equipment’, ‘Stores’ and ‘Materials’ shall mean and include equipment,
stores and materials to be provided by the Contractor under the Contract.
28.7 ‘Works’ shall mean and include the furnishing of equipment, labour and services, as per
the Specifications and complete erection, testing and putting into satisfactory operation
including all transportation, handling, unloading and storage at the Site as defined in the
Contract.
28.8 ‘Specifications’ shall mean the Specifications and Bidding Document forming a part of
the Contract and such other schedules and drawings as may be mutually agreed upon.
28.9 Site’ shall mean and include the land and other places on, into or through which the
works and the related facilities are to be erected or installed and any adjacent land,
paths, street or reservoir which may be allocated or used by the Owner or Contractor in
the performance of the Contract.
28.10 The term ‘Contract Price’ shall mean the Firm price quoted by the Contractor in his bid
with additions and/or deletions as may be agreed and incorporated in the Letter of Award
and the contract agreement for the entire scope of the works.
28.11 The term ‘Equipment Portion’ of the Contract price shall mean the ex-works value of the
equipment/Materials supplied include structures, town materials insulators, conducting
etc.
28.12 The term ‘Erection Portion’ of the Contract price shall mean the value of field activities of
the works including erection, testing and putting into satisfactory operation including
successful completion of performance and guarantee tests to be performed at Site by
the Contractor including cost of insurances.
28.13 ‘Manufacturer’s Works’ or ‘Contractor’s Works’, shall mean the place of work used by
the manufacturer, the Contractor, their collaborators/associates or Sub-Contractors for
the performance of the Contract.
28.16 Site Engineer ‘Inspector’ shall mean the Owner owner’s Engineers or any person
nominated by the time to inspect the equipment; stores or Works under the Contract
and/or the duly authorized representative of the Owner.
28.17 ‘Notice of Award of Contract’/’Letter of Award’/’Telex of Award’ shall mean the official
notice issued by the Owner notifying the Contractor that his bid has been accepted.
28.18 ‘Order’ shall mean the official letter issued by the Owner informing the acceptance of the
bid.
28.19 ‘Date of Contract’ shall mean the date on which Notice of Award of Contract/Letter of
Award has been issued.
28.20 ‘Month’ shall mean the calendar month. ‘Day’ or ‘Days’ unless herein otherwise expressly
defined shall mean calendar day or days of 24 hours each.
28.22 Writing’ shall include any manuscript, type written or printed statement, under or over
signature and/or seal as the case may be.
28.23 When the words ‘Approved’, ‘Subject to Approval’, ‘Satisfactory’, ‘Equal to’, ‘Proper’,
‘Requested’, ‘As Directed’, ‘Where Directed’, ‘When Directed’, ‘Determined by’,
28.24 Test on completion shall mean such tests as prescribed in the Contract to be performed
by the Contractor before the work is taken over by the Owner.
28.25 ‘Performance and Guarantee Tests’, shall mean all operational checks and tests required
to determine and demonstrate capacity, efficiency, and operating characteristics as
specified in the Contract Documents.
28.26 The term ‘Final Acceptance’/‘Taking Over’ shall mean the Owner’s written acceptance
of the Works performed under the Contract, after successful commissioning/completion
of Performance and Guarantee Tests, as specified in the accompanying Technical
Specifications or otherwise agreed in the Contract.
28.27 ‘Guarantee Period’/’Maintenance Period’ shall mean the period during which the
Contractor shall remain liable for repair or replacement of any defective part of the works
performed under the Contract.
28.28 ‘Latent Defects’ shall mean such defects caused by faulty designs, material or work-man-
ship which cannot be detected during inspection, testing etc, based on the technology
available for carrying out such tests.
c) Drawings submitted by the Contractor with his bid provided such drawings are
acceptable to the Owner/Consultant.
e) Engineering data and drawings submitted by the Contractor during the progress of
the work provided such drawings are acceptable to the Engineer/Owner.
28.30 ‘Codes’ shall mean the following including the latest amendments and/or replacements,
if any :
a) Indian Electricity Act, 1905 and Rules and Regulations made there under.
b) Electricity Act 2003 and Rules & Regulations made there under.
c) Indian Factory Act, 1948 and Rules and Regulations made there under.
d) Indian Explosives Act, 1884 and Rules and Regulations made there under.
e) Indian Petroleum Act, 1934 and Rules and Regulations made there under.
j) Other Internationally approved standards and/or rules and regulations touching the
subject matter of the Contract.
28.31 Words imparting the singular only shall also include the plural and vice –versa where the
context so requires.
28.32 Words imparting ‘Person’ shall include firms, companies, corporations and associations
or bodies of individuals, whether incorporated or not.
28.33 Terms and expressions not herein defined shall have the same meaning as are assigned
to them in the Indian Sale of Goods Act (1930), failing that in the Indian Contract Act
(1872) and failing that in the General Clauses Act (1897) including amendments thereof,
if any.
Or
In addition to the above the following definitions shall also apply.
28.35 Works contract means a Contract for composite supply and covered under the
definition of Works Contract as defined under Section 2(119) of the CGST Act,
2017 or SGST Act, 2017 and similar provisions, applicable under the UTGST Act,
2017and the IGST Act, 2017.
29.0 APPLICATION
These General Conditions shall apply to the extent that they are not superceded by
provisions in other parts of the Contract.
30.0 STANDARDS
The goods supplied under this Contract shall conform to the standards mentioned in the
Technical Specifications, and, when no applicable standard is mentioned, to the
authoritative standard appropriate to the goods and such standards shall be the latest
issued by the concerned institution.
31.0 LANGUAGE AND MEASURES
All documents pertaining to the Contract including specifications, schedules, notices,
correspondences, operating and maintenance instructions, drawings or any other writing
shall be written in English language. The Metric System of measurement shall be used
exclusively in the Contract.
32.1 The Price shall be quoted on firm basis except for supply of substation structure
materials (including nut-bolts) for which Price variation will be applicable.
32.2 The Price quoted by the bidder shall remain fixed for all the items except substation
structure materials (including nut bolts); during the bidder's performance of the contract
and shall not be subject to variation on any account save for change in quantity. A bid
submitted with an adjustable price quotation shall be treated as non-responsive and
rejected.
P0 SBLR SBIR Zn W
P= ( 9+ 35 + 27 + 13 + 16 )
100 SBLRo SBIRo Zno W0
Wherein,
P = Price payable as adjusted in accordance with the above
formula.
P0 = Price quoted/confirmed.
SBLR0 = Price of Steel Blooms- Retail (refer notes)
This price is as applicable for the month, ONE month prior to the
date of tendering.
SBIR0 = Price of Steel Billets- Retail (refer notes)
This price is as applicable for the month, ONE month prior to the
date of tendering.
Zn0 = Price of Electrolytic high grade zinc (refer notes)
This price is as applicable for the month, ONE month prior to the
date of tendering.
Wo = All India average consumer price index number for industrial
workers, as published by the Labour Bureau, Ministry of Labour,
Govt. of India (Base: 2016 = 100) (Refer notes)
This index number is as applicable for the month, THREE months
prior to the date of tendering.
For example, if date of tendering falls in November 2023, the applicable prices of
Steel
Bloom-Retail (SBLR0), Steel Billets-Retail (SBIR0) and Zinc (Zn0) should be for the
month
The above prices and indices are as published by IEEMA vide circular reference
number
IEEMA (PVC)/TLT- 2022/_/_ ONE month prior to the date of tendering
21.1 The price variation amount in the ex-works price of fabricated structure members
(including bolts & nuts) calculated by the above formula shall not be subject to any ceiling,
whatsoever.
21.2 The price variation formula will be applicable from the date of inspection / waival of
inspection for the material offered.
21.3 The price variation will be applicable during contractual delivery period only. However,
any decrease in the price variation during delayed period shall be applicable.
21.4 Price variation shall not be allowed beyond the original delivery date unless specifically
stated in the time extension letter. As a rule, no price adjustment shall be allowed for the
period of delay for which the supplier is responsible; however purchaser will be entitled
for any decrease in the prices during this delayed period.
21.5 In case of non-publication of applicable indices on a particular month, which happens to
be the applicable month for price variation purpose, the published indices prevailing
immediately prior to the particular month shall be applicable.
21.6 If the price adjustment amount works out to be positive, the same is payable to the
contractor by the owner and if it works out to be negative, the same is to be recovered
by the owner from the contractor.
21.7 No price variation will be allowed on the freight and insurance component of FOR
destination prices.
33. 1 33.1 The F.O.R. Destination prices are excluding GST and Cess as applicable
which will be paid extra on a given taxable goods and/or services within the
original contractual delivery period. The amount and % of GST and Cess as
applicable should clearly be indicated separately. (GST/Cess means all
applicable Tax/Cess under GST Laws. GST Laws means IGST Act,
GST(Compensation to the State for Loss of Revenue) Act, CGST Act, UTGST
Act and SGSCT Act, 2017 and all related ancilliary legislations).
33. 2 You shall have to submit a C.A Certificate & duly authorized Signatory of
successful bidder, certifying that you have not claimed Refund of any applicable
GST and Cess, charged to COMPANY or shall not claim any such Refund, on a
future date, from the concerned Authorities and if, any Refund, in respect of such
GST and Cess, is claimed by you, it will be immediately passed on to the
COMPANY, without COMPANY making any specific Claim, for the same, either
from the Department or from you.
33. 3 The offers having price INCLUSIVE OF GST and Cess is likely to be rejected if
the rate of GST and Cess is not mentioned clearly unless the bidder has opted
for Compostion Scheme under GST Act, which should be clearly indicated in the
price bid. COMPANY may at its discretion consider such offer with presumption
of highest applicable rate of GST and Cess prevailing when the price quoted is
inclusive of GST and Cess.
33. 4 If the Supplier/Contractor has opted for the Composition scheme of GST, the
same must be clearly specified with valid Declaration & Certificate from
Department. In the event of withdrawal/cessation of the Supplier from
Composition scheme during the tenure of the contract, the rate mentioned in the
price bid shall be final and any additional GST will have to be borne by the
tenderer. In no case additional amount towards tax or otherwise will be paid /
reimbursed to supplier/contractor. Further Statutory Variation clause will not be
applicable in case of Supplier / Contractor has opted for Composition Scheme
under GST.
33. 6 Further, the Company has a right to recover the amount of GST along with penal
interest at the rate of 15% per annum if GST charged is not paid / short paid to
the government or fail to upload the details or uploads inaccurate particulars on
GSTIN portal by the Supplier / Contractor within the stipulated time limit.
33. 7 In case, Govt. revises the rate of GST rate / Code during the tenure of the
contract, the provision of GETCO’s statutory variation clause shall apply.
33. 9 GST, other taxes and other levies and duties including custom duty solely in
respect of the transaction between the owner and the contractor under this
contract, if any, shall be included in the bid price. These shall also be indicated
separately wherever applicable as mentioned in the Tender .
33. 10 As regards the income Tax, surcharge on income tax and any other corporate
tax, including GST if any the owner shall not bear any tax liability whatsoever.
The bidder shall be liable and responsible for payment of such taxes as attracted
under the provisions of the law.
33. 11 Notwithstanding the tax liabilities as per the sub-clause 35.10 above the owner
shall have the right to make deduction at source from the amounts payable to the
contractor in respect of Income Tax (on the cost of items of supply included in
the works contract) as may be mandatory in terms of the law. The owner shall
not bear any liability in this regard but shall issue necessary certificate in respect
of such deduction made.
33. 14 The owner’s liability for all taxes and duties including GST under the contract
shall be limited to those indicated by the Bidder in the Bid Proposal Sheets,
subject to the statutory variations and variations as per Clause No. 35.4.
33. 15 If the cost to the Contractor during the performance of the ‘Contract’ shall be
increased or reduced by reasons of the making, passing or promulgation of any
law after the date of submission of bid or by any order, regulation or bye-law
having the force of law the amount of such increase or reduction shall be added
to or deducted from the “Contract Price” as the case may be for direct
transactions between contactor & owner. It is the Bidders responsibility to furnish
details of taxes, duties, levies etc. applicable as on the date of submission of the
bid.
33. 16 No claim for any increase towards the statutory variation regarding enhancement
of existing tax or duty or introduction of a new tax or duty applicable shall be
entertained by the Owner during the extended period of contract, if any, provided
the extension of the contract is required by causes attributable to the contractor.
However, the decrease in any taxes/duties shall be passed on to GETCO.
33. 17 The provision of statutory variation regarding enhancement of existing tax or duty
or introduction of a new tax or duty will be applicable only to the direct transaction
between the contractor and the owner.
33. 18 Before quoting, the bidder may ascertain from the concerned tax authorities of
Government for the applicability of Entry Tax, GST etc. in respect of this work
and include the same in the quoted price. No separate claim in this regard will be
entertained by the Owner, as it is the responsibility of the Bidder to pay all these
taxes.
35.1 GOODS AND SERVICE TAX (GST): GST and Cess as applicable shall be
payable/ receivable as mentioned in clause no.33 of GCC supra
35.2 The prices quoted shall be all inclusive of freight, transportation, loading, –
unloading & stacking at site of materials supplied by Contractor as well as owner
supplied item if any
35.3 No extra payment toward any type of templates and erection tools /materials
will be made.
35.4 Statutory Variations:
Any statutory increase or decrease in the taxes and duties including GST
and Cess as applicable or in the event of introduction of new
tax/cess or cessation of existing tax/cess subsequent to suppliers offer
if it takes place within the original contractual delivery date will be to
COMPANY’s account subject to the claim being supported by documentary
evidence. However, if any decrease takes place after the contractual delivery
date, the advantage will have to be passed on to COMPANY.
35.5 Income Tax
Income-tax at source at the prevailing rate will be deducted from bills in
accordance with the provision of Income-Tax Laws and to that effect a certificate
will be issued to the contractor.
36.1 As a contract performance security, the successful bidder, to whom the work is awarded,
shall be required to furnish a performance guarantee as per clause No. 38 in form of
Bank guarantee from a Public Sector Indian bank/Scheduled, Commercial Bank in the
form to be furnished and it shall guarantee the faithful performance of the Contract in
accordance with the terms and conditions specified in these documents and
specifications.
36.2 The Performance Guarantee shall cover additionally the following guarantees to the
Owner:
a) The successful Bidder guarantees the successful and satisfactory operation of the
equipment furnished and erected under the Contract, as per the specifications and
documents.
b) The successful Bidder further guarantees that the equipment provided by him/his sub-
vendors and installed by him shall be free from all defects in design, material and
workmanship and shall upon written notice from the Owner fully remedy free of
expenses to the Owner such defects as developed under the normal use of the said
equipment within the period of guarantee specified in the relevant clause of the
General Terms and Conditions in the Part-I.
36.3 The Contract Performance Guarantee is intended to secure the performance of the entire
contract. However, it is not to be construed as limiting the damages under clause entitled
“Equipment Performance Guarantee” in Technical Specifications, Part-II and damages
stipulated in other clauses in the Bid documents.
36.4 The Contract performance guarantee will be discharged without any interest on
successful completion of order and only after the performance guarantee condition is
Seal & Signature of Bidder 35
fulfilled. The Contractor shall furnish Contract Performance Guarantee(s) for the proper
fulfillment of the Contract in the prescribed form within fifteen(15) days of “Notice of
Award of Contract”. The performance guarantee(s) shall be as per terms prescribed.
37.10 The Guarantee period for individual equipment / item indicated in the tender
specification remains unchanged and shall have to be adhering to as indicated
below.
400 KV CT & PT–You have to give assurance for trouble free and maintenance free
performance for a period of 60 Months from the date of receipt of stores. During this
period, the CTs /PTs shall be repaired/reconditioned/replaced free of cost immediately in
case of any trouble.
40.1 The time and the date of completion of the Contract as stipulated in the Contract by the
Owner without or with modifications, if any, and so incorporated in the Letter of Award,
40.2 The Contractor shall submit a detailed PERT network/bar chart within the time frame
agreed consisting of adequate number of activities covering various key phases of the
work such as design, procurement, manufacturing, shipment and field erection activities
within fifteen (15) days of the date of Notification of Award. This network shall also
indicate the interface facilities to be provided by the Owner and the dates by which such
facilities are needed. The Contractor shall discuss the network so submitted with the
Owner and the agreed network shall form part of the Contract documents. During the
performance of the Contract, if in the opinion of the Engineer, proper progress is not
maintained, suitable changes shall be made in the Contractor’s operations to ensure
proper progress without any cost implication to the Owner. The interface facilities to be
provided by the Owner in accordance with the agreed network shall also be reviewed
while reviewing the progress of the Contractor.
40.3 Based on the above agreed network/bar chart fortnightly reports shall be submitted by
the Contractor as directed by the Engineer.
40.4 Subsequent to the finalization of the network, the Contractor shall make available to the
Engineer a detailed manufacturing programme in line with the agreed Contract network.
Such manufacturing programme shall be reviewed, updated and submitted to the
Engineer every month thereafter.
40.5 The above bar charts/manufacturing programme shall be compatible with the Owner’s
computer environment and furnished to the Owner on such media as may be desired by
the Owner.
40.6 If the progress is found low, GETCO reserves the right to get the work executed through
any other agency at the risk & cost of contractor without assigning any reason(s) and/or
notice.
41.2 The penalty plus GST as applicable will be deducted from bills payable either
against this contract or from any Bank Guarantee or any other amount payable
under any other contract with the GETCO.
41.3 In event of failure of the contractor to pay the amount of penalty as demanded, the owner
shall be entitled to deduct the amount of penalty for delay from the amounts
payable to the contractors under any bills raised under this contract or any other
amount payable under any other contract with the GUVNL and its Subsidiary
companies i.e. GETCO, GUVNL, GSECL, MGVCL, DGVCL, PGVCL, UGVCL. It is
permissible for the owner to adjust the amount of penalty of delay against any Bank
Guarantee furnished by the contractor under this contract or any other contract with
GUVNL and/or its subsidiary companies.
Whenever any claim or claims for payment of a sum of money arises out of or under the
contract against the contractor, the owner shall be entitled to withhold and also have a
lien to retain such sum or sums in whole or in part from the security, if any, deposited by
the contractor and for the purpose aforesaid, the Owner shall be entitled to encash and
withhold the amount of performance Bank Guarantee or other security, if any, furnished
as the case may be. The Owner shall also have a lien over the same pending finalization
or adjudication of any such claim. In the event of the security is insufficient to cover the
claimed amount or amounts, the Owner shall be entitled to withhold and have lien to
retain to the extent of the such claimed amount or amounts referred to above, from any
sum or sums found payable or which at any time-thereafter may become payable to the
contractor under the same contract or any other contract with the owner or GUVNL or
its Subsidiary companies pending finalization or adjudication of any such claim.
a) Any sum of money due and payable, to the contractor (including the security deposit)
under the contract may be withheld or retained by way of lien by the Owner against any
of its claim in respect of payment of a sum of money arising out of or under any other
contract made by the Contractor with the Owner or GUVNL or any of its subsidiary
companies.
b) It is an agreed that the sum of money so withheld or retained under this clause by the
Owner will be kept withheld or retained as such by the Owner till its claim arising out of
the same contract or any other contract is either mutually settled or determined by the
arbitrator or competent court, as the case may be, and the Contractor shall have no claim
for interest or damages whatsoever on this account or on any other ground in respect of
any sum of money withheld or retained under this clause and as may be duly notified to
the contractor.”
41.4 Tenderer shall have to supply all materials to match with the erection activities.
41.5 If the Contractor fails to successfully complete the commissioning within the time
fixed under the Contract, the Contractor shall pay to the Owner as penalty plus
GST as applicable a sum specified for each specified period of delay.
41.6 Equipment and materials will be deemed to have been delivered only when all its
components, parts are also delivered. If certain components are not delivered in time
the equipment and materials will be considered as delayed until such time the missing
parts are also delivered.
41.7 For the purpose of penalty, contractual obligation shall be completion of all the Civil,
supply and erection contracts as per time schedule & value of these contracts shall be
“total contract value” (Sum of three individual contract value) for the working of penalty
in line with above relevant cl. No.41.1
42.1 In case the Contractor’s performance is delayed due to any act of omission on the part
of the Owner or his authorized agents, then the Contractor shall be given due extension
of time for the completion of the Works, to the extent such omission on the part of the
Owner has caused delay in the Contractor’s performance of the Contract.
42.2 In addition, the Contractor shall not be entitled to any claim whether demonstrable or
reasonable compensation if such delays have resulted in any increase in cost
44.0 PAYMENT
44.1 The payment to the Contractor for the performance of the works under the Contract will
be made by the Owner as per the guidelines and conditions specified herein. All
payments made during the Contract shall be on account payments only. The final
payment will be made on completion of all Works and on fulfillment by the Contractor of
all his liabilities under the Contract.
Welfare Cess
The modality of payment/ reimbursement of welfare cess will be as under.
On receipt of A/T, the contractor / bidder will get them registered under Welfare Cess
Act and submit the documentary evidence to the concern office.
Before release of payment of first R.A.Bill, the contractor has to submit the documentary
evidence of registration. Only thereafter, the bill will be processed for payment.
Before release of payment of subsequent R.A.Bills, the contractor has to submit the
documentary evidence of payment of welfare cess of previous R.A.Bill.
Before release of payment of Final Bill, the contractor has to submit the documentary
evidence of payment of welfare cess of previous R.A.Bill as well as the final bill.
If the R.A.Bill happens to be first and final bill, then before release of payment, contractor
has to submit documentary evidence of registration under Welfare Cess Act and
evidence of payment of welfare cess.
The welfare cess shall be reimbursed to the contractor on submission of copy of
documentary evidence of payment by observing due formalities.
Payment shall be as per contract price schedule agreed based on unit rate. The final
price schedule shall be based on approved drawings & BOQ.
The tender BOQ is indicative. Supply & Erection of quantities shall be as per approved
Drgs. & BOQ and excess shall not be accepted.
45.2 Each such application shall state the amount claimed and shall set forth in detail, in the
order of the Payment Schedule, particulars of the Works including the Works executed
at Site and of the equipment shipped/brought on to the site pursuant to the Contract up
to the date mentioned in the application and for the period covered since the last
preceding certificate, if any.
45.3 Every interim payment certificate shall certify the Contract value of the Works executed
up to the date mentioned in the application for the payment certificate, provided that no
sum shall be included in any interim payment certificate in respect of the works that,
according to the decision of the Engineer, does not comply with the Contract.
45.5 Payment due on dispatch of equipment shall be made by the Owner through Owner’s
Bank or directly to the Contractor as per the payment schedule.
45.6 The payment of test charges, if any, payment, taxes and duties (whenever admissible)
inland transportation (including port handling), insurance and the erection portion of the
Works shall be made direct to the Contractor by the Owner.
45.7 All payments under the Contract shall be made as stipulated in the Contract after signing
the Contract Agreement. The payments linked with the dispatch of materials shall only
be made after production of all dispatch documents as specified in the relevant Contract
conditions which will interalia include the Material Inspection Clearance Certificate
issued by the Owner.
Progressive payments linked with erection shall only be made after the issue of
certificates by the Engineer, one for the quantum of work completed and the other for
the successful completion of quality check points involved in the quantum of work billed.
45.8 Billing and breakup: Price breakup for supply items will be considered only for billing
purpose & not for actual payment. Payment for equipments supplied shall be released
as per price schedule given in the tender specifications.
All costs, damages or expenses which the Owner may have paid, for which under the
Contract the Contractor is liable, or any other retention award will be claimed by the
Owner. All such claims shall be billed by the Owner to the Contractor regularly as and
when they fall due. Such bills shall be supported by appropriate and certified vouchers
or explanations, to enable the Contractor to properly identify such claims. Such claims
shall be paid by the Contractor within thirty (30) days of the receipt of the corresponding
bills and if not paid by the Contractor within the said period, the Owner may then deduct
the amount, from any monies due or becoming due by him to the Contractor under the
Contract or may be recovered by sections of Law or otherwise.
47.0 Terms of Payment
The payment for materials to be supplied and erected shall be made as under only after
execution of the contract documents/furnishing of Security Deposit and on execution of
substation work.
(i) 80% of supply value for each consignment of Sub-Station material including
accessories on submission of invoice along with 100% GST, duties, F & I shall
be paid from corporate office within 30 days from actual material receipt date
mentioned in SR Note after verifying the following documents.
A. Tax invoice.
B. Delivery challan.
C. Endorsed RR / LR copy.
D. Dispatch clearance certificate / letter wherever applicable.
E. E Way Bill, if applicable
(ii) 10% payment out of balance 20% shall be released from corporate office within
30 days on completion of Sub –Station work, handing over and preliminary
acceptance certificate issued by the Site Engineers in charge after rectification
work if any and settlement of material account according to actual quantity
utilized for completion of S/S. Supply to be made as per approved drawing/ BOQ
.
(iii) Balance10% of supply value shall be paid from corporate office on successful
commissioning of Sub-Station against completion certificate and only after
settlement of material account statement of items supplied, used, erected and
successful commissioning is settled for complete job and will be released within
30 days only after passing of final bill.
(i) 90% payment of amount claimed covering various activities such as excavation,
foundation, erection, earthing, stringing of bus bar and earthwire including insulator
hoisting works against R.A. bills duly certified by EIC within 30 days from the date of
R.A. bill.
(ii) Balance 10% of erection value shall be paid within 30 days against commissioning
of Sub-Station only after settlement of material account statement of items supplied,
used, erected and successful commissioning of Sub-Station line the same amount will
be release in final bill only and payment will be made only after passing of final bill.
(iii)If net payable amount is more than Rs 5.0 Lacs, payment will be released from circle
office/corporate office.
On receipt of A/T, the contractor / bidder will get them registered under Welfare Cess
Act and submit the documentary evidence to the concern office.
Before release of payment of first R.A.Bill, the contractor has to submit the documentary
evidence of registration. Only thereafter, the bill will be processed for payment.
Before release of payment of subsequent R.A.Bills, the contractor has to submit the
documentary evidence of payment of welfare cess of previous R.A.Bill.
Before release of payment of Final Bill, the contractor has to submit the documentary
evidence of payment of welfare cess of previous R.A.Bill as well as the final bill.
If the R.A.Bill happens to be first and final bill, then before release of payment, contractor
has to submit documentary evidence of registration under Welfare Cess Act and
evidence of payment of welfare cess.
The welfare cess shall be reimbursed to the contractor on submission of copy of
documentary evidence of payment by observing due formalities.
Seal & Signature of Bidder 43
The welfare cess shall be reimbursed to the contractor on submission of copy of documentary
evidence of payment by observing due formalities
The Bidder’s insurance liabilities pertaining to the scope of Works are detailed out in
Clauses titled Insurance Bidder’s attention is specifically invited to these clauses. Bid
price shall include all the costs in fulfilling all the insurance liabilities under the Contract.
49.1 The Contractor at his cost shall arrange, secure and maintain all insurance as may be
pertinent to the Works and obligatory in terms of law to protect his interest and interests
of the Owner against all perils detailed herein. The form and the limit of such insurance
as defined herein together with the under-writer in each case shall be acceptable to the
Owner. However, irrespective of such acceptance, the responsibility to maintain
adequate insurance coverage at all time during the period of Contract shall be of
Contractor alone. The Contractor’s failure in this regard shall not relieve him of any of
his contractual responsibilities and obligations. The insurance covers to be taken by the
Contractor shall be in the joint name of the Owner and the Contractor. The Contractor
shall, however, be authorized to deal directly with Insurance Company or Companies
and shall be responsible in regard to maintenance of all insurance covers. Further the
insurance should be in freely convertible currency.
49.3 The perils required to be covered under the insurance shall include, but not be limited to
fire and allied risks, miscellaneous accidents (erection risks) workman compensation
risks, loss or damage in transit, theft, pilferage, earth quake, riot and strikes and
malicious damages, civil commotion, weather conditions, accidents of all kinds, etc. The
scope of such insurance shall be adequate to cover the replacement/reinstatement cost
of the equipment for all risks up to and including delivery of goods and other costs till the
equipment is delivered at Site. The insurance policies to be taken should be on
replacement value basis and/or incorporating escalation clause. Notwithstanding the
extent of insurance cover and the amount of claim available from the underwriters, the
Contractor shall be liable to make good the full replacement/rectification value of all
equipment/materials and to ensure their availability as per Project requirements.
49.4 All costs on account of insurance liabilities covered under the Contract will be on
Contractor’s account and will be included in Contract Price, However, the Owner may
from time to time, during the pendency of the Contract, ask the Contractor in writing to
limit the insurance coverage, risks and in such a case, the parties to the Contract will
agree for a mutual settlement, for reduction in Contract price to the extent of reduced
premia amount. The Contractor, while arranging the insurance shall ensure to obtain all
discounts on premia which may be available for higher volume or for reason of financing
arrangement of the PROJECT.
49.5 The clause entitled ‘Insurance’, covers the additional insurance requirements for the
portion of the works to be performed at the Site.
50.1 The Bidder shall include in his proposal the Quality Assurance Programme containing
the overall quality management and procedures which he proposes to follow in the
performance of the Works during various phases as detailed in relevant clause of the
General Technical Conditions.
50.2 At the time of Award of Contract, the detailed Quality Assurance Programme to be
followed for the execution of the Contract will be mutually discussed and agreed and
such agreed Programme shall form a part of the Contract.
50.3 The Bidder shall clearly specify the list of sub-vendors from whom the bought out items
are being supplied. Such details shall be accompanied by their list of previous supplies
made performance reports etc. However, in case of orders are placed, specific approval
shall be obtained from the owner for the vendor supplied materials. The quality
assurance program shall be furnished for each material separately for approval.
The Bidder under a separate schedule, in his proposal shall include a list of all-special
equipment tools & tackles etc. which he proposes to bring to site for the purpose of
erection, handling, testing and commissioning including performance and guarantee
tests of the equipment. However such tools tackles brought to the site for purpose of
erection, handing testing & commissioning shall remain property of the contractor and
can be taken back after completion of the work.
52.1 The specific reference in these specifications and documents to any material/equipment
by brand name make or catalogue number shall be construed as establishing standards
of quality and performance and not as limiting competition. However, Bidders may offer
other similar material/equipment provided they meet the specified standard, design and
performance requirements. The Bidder shall furnish adequate technical information
about such alternative material equipment to enable the Owner to determine its
acceptability. The Owner shall be the sole judge on the acceptability or otherwise of such
alternatively material/equipment.
52.2 The bidder shall noet that standards for workmanship material and equipment, and
reference to brand name of catalogue numbers designed by the Owner in its Technical
Specifications are intended to be descriptive only and not restrictive. The Bidder may
substitute alternative standards, brand name and/or catalogue numbers in its bid,
provided that it demonstrates to the Owner’s satisfaction that the substitutions are
substantially equivalent or superior to those designed in the Technical Specification.
53.1 The term Contract Documents shall mean and include the following which shall be
deemed to form an integral part of the Contract:
a) Invitation to Bid including letter forwarding the Bidding Documents, General Terms
and Conditions of Contract and all other documents included under Part I and the
Special Conditions of Contract.
c) Contractor’s Bid Proposal and the documents attached there to including the letters
of clarifications thereto between the Contractor and the Owner prior to the Award
of Contract except to the extent of repugnancy.
d) All the materials, literature, data and information of any sort given by the Contractor
along with his bid, subject to the approval of the Owner /Consultant.
e) Letter of Award and any agreed variations of the conditions of the documents and
special terms and conditions of Contract, if any.
53.2 In the event of any conflict between the above mentioned documents the matter shall be
referred to the Engineer whose decision shall be considered as final and binding upon
the parties.
54.1 The Contractor shall not, without the Owner’s prior written consent, disclose the
Contract, or any provision thereof, or any specification, plan, drawing, pattern, sample
or information furnished by or on behalf of the Owner in connection therewith, to any
person other than a person employed by the Contractor in the performance of the
Contract. Disclosure to any such employed person shall be made in confidence and shall
extend only so far as may be necessary for the purpose of such performance.
54.2 The Contractor shall not, without the Owner’s prior written consent, make use of any
document or information enumerated in various Contract documents except for the
purpose of performing the Contract.
54.3 The Contractor shall not communicate or us in advertising, publicity, sales releases or
in any other medium, photographs or other reproduction of the Works under this
Contract, or descriptions of the site, dimensions, quantity, quality or other information,
concerning the works unless prior written permission has been obtained from the Owner.
54.4 Any document, other than the Contract itself, enumerated in various Contract documents
shall remain the property of the Owner and shall be returned (in all copies) to the Owner
on completion of the Contractor’s performance under the Contract if so required by the
Owner.
55.1 Notwithstanding anything stated elsewhere in the bid documents, the Contract to
be entered into will be treated as a works contract for Civil, Supply and Erection
work. However, Separation of the Contract into Supply of Goods, Services and
Civil Work, is only for convenience and better economical management and for
the ease of Accountancy but the entire Contract, is to be assessed under GST
Law, as a contract for composite supply under the category of Works Contract,
which is, as per the provisions of Section 2(30), read with, Section 2(119), further
read with, Paragraph 6(a) of the Schedule II to the CGST Act, 2017 or SGST Act,
2017 and similar provisions, applicable under the UTGST Act, 2017and the IGST
Act, 2017 and the entire activity, would be subjected to levy of Tax, at the rate of
9% CGST + 9% SGST or 18% IGST, under the GST Law. However, Classification
Codes for different segments or portions of the Works Contract, may be specified
separately, in the Supplies, with a final common Classification Code of Works
Contract Service.
55.2 In case of divisible supply and erection Contract, or where the Owner hands over his
equipment to the Contractor for executing, then the Contractor shall at the time of taking
delivery of the equipment/dispatch documents be required to execute an Indemnity Bond
in favour of the Owner in the form acceptable to the GETCO for keeping the equipment
in safe custody and to utilize the same exclusively for the purpose of the said Contract.
Samples of proforma for the Indemnity Bond will be furnished during award of Contract.
55.3 The Contract shall in all respects be construed and governed according to Indian Laws.
55.4 It is clearly understood that the total consideration for the Contract(s) has been broken
up into various components only for the convenience of payment under the Contract(s)
and for the measurement of deviations or modifications under the Contract(s).
56.1 The laws applicable to the Contract shall be the laws in force in India. The Courts of
Vadodara shall have exclusive jurisdiction in all matters arising under this Contract.
57.1 The Owner, after the issue of the Letter of Award to the Contractor, will send one copy
of the final agreement to the Contractor for his scrutiny and approval.
57.2 The Agreement, unless otherwise agreed to, shall be signed within 30 days of the
acceptance of the Letter of Award, at the office the Owner at Vadodara on a date and
time to be mutually agreed. The Contractor shall provide for signing of the Contract,
Performance Guarantee, appropriate power of attorney and other requisite materials. In
case the Contract is to be signed beyond the stipulated time, the Bid Guarantee
submitted with the Proposal will have to be extended accordingly.
57.3 The Agreement will be signed in copies to be specified and the Contractor shall be
provided with one signed original and the rest will be retained by the Owner.
57.4 The Contractor shall provide free of cost to the Owner all the Engineering data, drawings,
and descriptive materials submitted with the bid including soft copy, to form a part of the
Contract immediately after issue of Letter of Award .
57.5 Subsequent to signing of the Contract, the Contractor at his own cost shall provide the
Owner with copies of agreement within fifteen (15) days after the signing of the
Contractor.
58.0 ENFORCEMENT OF TERMS
58.1 The failure of either party to enforce at any time any of the provisions of this Contract or
any rights in respect thereto or to exercise any option therein provided, shall in no way be
construed to be a waiver of such provisions, rights or options or in anyway to affect the
validity of the Contract. The exercise by either party of any of its rights herein shall not
preclude or prejudice either party from exercising the same or any other right it may have
under the Contract.
59.1 Unless otherwise terminated under the provisions of any other relevant clause, this
Contract shall be deemed to have been completed on the expiry of the guarantee period
as provided for under the clause entitled ‘Guarantee’
Royalties and fees for patents covering materials, articles, apparatus, devices,
equipment or processes used in the works shall be deemed to have been included in
the Contract Price. The Contractor shall satisfy all demands that may be made at any
time for such royalties or ts and he alone shall be liable for any damages or claims for
patent infringements and shall keep the Owner indemnified in that regard. The
Contractor shall, at his own cost and expense, defend all suits or proceedings that may
be instituted for alleged infringement of any patents involved in the Works, and, in case
of an award of damages, the Contractor shall pay for such award. In the event of any
suit or other proceedings instituted against the Owner, the same shall be defended at
the cost and expense of the Contractor who shall also satisfy/comply with any decree,
order or award made against the Owner. But it shall be understood that no such
machine, plant, work, material or thing has been used by the Owner for any purpose or
any manner other than that for which they have been furnished and installed by the
Contractor and specified under these specifications. Final payment to the Contractor by
the Owner will not be made while any such suit or claim remains unsettled. In the event
any apparatus or equipment, or any part thereof furnished by the Contractor, is in such
suit or proceedings held to constitute infringement, and its use is enjoined, the Contractor
shall at his option and at his own expense, either procure for the Owner, the right to
continue the use of said apparatus, equipment or part thereof, replace it with non-
infringing apparatus or equipment or modify it, so it becomes non-infringing.
The final payment by the Owner in pursuance of the Contract shall mean the release of
the Contractor from all his liabilities under the Contract. Such final payment shall be
made only at the end of the Guarantee/Warranty period, and till such time as the
Contractual liabilities and responsibilities of the Contractor, shall prevail. All other
payments made under the Contract shall be treated as on-account payments. The
aggregate liabilities are limited up to the total contract value.
64.1 In respect of all matters which are left to the decision of the Engineer including the
granting or with-holding of the certificates, the Engineer shall, if required to do so by the
Contractor, give in writing a decision thereon.
64.2 If, in the opinion of the Contractor, a decision made by the Engineer is not in accordance
with the meaning and intent of the Contract, the Contractor may file with the Engineer,
within fifteen (15) days after receipt of the decision, a written objection to the decision.
Failure to file an objection within the allotted time will be considered as an acceptance
of the Engineer’s decision and the decision shall become final and binding.
64.3 The Engineer’s decision and the filing of the written objection thereto shall be a condition
precedent to the right to request arbitration. It is the intent of the Agreement that there
shall be no delay in the execution of the works and the decision of the Engineer as
rendered shall be promptly observed.
65.2 In the event of Engineer requiring any variation, a reasonable and proper notice shall be
given to the Contractor to enable him to work his arrangement accordingly, and in cases
where goods or materials are already prepared or any design, drawings or pattern made
or work done as per the contract requires to be altered, a reasonable and agreed sum
in respect thereof shall be paid to the Contractor.
65.3 In any case in which the Contractor has received instructions from the Engineer as to
the requirement of carrying out the alterations or additional or substituted work which
either then or later on, will in the opinion of the Contractor, involve a claim for additional
payment, the Contractor shall immediately and in no case later than thirty (30) days,
after receipt of the instructions aforesaid and before carrying out the instructions, advise
the Engineer to that effect. But the Engineer shall not become liable for payment of any
charges in respect of any such variations, unless the instructions for the performance of
the same shall be confirmed in writing by the Engineer.
65.4 If any variation in the Works results in reduction of Contract Price, the parties shall agree,
in writing, so to the extent of any change in the price, before the Contractor proceeds
with the change.
65.6 Notwithstanding anything stated above in this clause, the Engineer shall have the full
power to instruct the Contractor, in writing, during the execution of the Contract to vary
the quantities of the items or groups of items in accordance with the provisions of clause
entitled ‘Change of Quantity’ in section GCC. The Contractor shall carry out such
variations and be bound by the same conditions as though the said variations occurred
in the Contract Documents. However, the Contract Price shall be adjusted at the rates
and the prices provided for the original quantities in the Contract.
66.1 The Contractor may, after informing the Chief Engineer (P) & getting written approval,
assign or sub-let the Contract or any part thereof other than for raw material, for minor
items or for any part of the plant for which makes are identified in the Contract. Suppliers
of the equipment not identified in the Contract or any change in the identified suppliers
shall be subject to approval by the Chief Engineer. The experience of equipment
vendors under consideration by the Contractor for this Contract shall be furnished to the
Chief Engineer for approval prior to procurement of all such items/equipment. Such
assignment/sub-letting shall not relieve the Contractor from any obligation, duty or
responsibility under the Contract. Any assignment as above, without prior written
approval of Chief Engineer, shall be void.
In case of Erection/Civil activity, the contractor may after getting written approval
from CE(Project ), assign or sublet any part of erection or as a whole. To do so contractor
have to apply for such subletting with a clear proposal stating details & experience of the
subletting agency, along with the tender or within 30 days from the date of LOI & decision
thereof will be conveyed within 30 days thereafter by GETCO. The proposed
erection/civil agency shall have experience of executing similar job of voltage class of
220Kv & above during last five years. (Experience shall be as per Annexure – A) The
decision of competent authority in this regard shall remain final and binding to the agency
– The approval will be given based on assessments (Quality, timely execution of work,
safety required machinery, of subletting contractor, his past performacne, financial,
ongoing contracts on hand and fulfilling other legal requirements. Subletting will not be
allowed to the bidders having more than 3 PROJECTs on hand (having value more than
50% of this contract for civil and electrical part individually) and having total contracts on
hand, having total value equivalent to 150% of erection cost for electrical and civil cost
for civil work. If subletting contractor is working in civil as well as electrical he will be
evaluated as above considering 100% cost as total of civil and electrical cost.
8 I.T. PAN CARD: The bidder should submit I.T. PAN CARD: The bidder should
the attested zerox copy of PAN Card of submit the attested zerox copy of PAN
their firm. Card of their firm.
Note: If subletting contractor is working in civil as well as electrical work, agency will be
evaluated as above considering 100% cost as total of civil and electrical cost and documents
as mentioned above.
66.2 For components/equipment procured by the Contractor for the purposes of the Contract,
after obtaining the written approval of the Owner, the Contractor’s purchase
specifications and enquiries shall call for quality plan to be submitted by the suppliers
along with their Proposals. The quality plans called for from the Vendors shall set out,
during the various stages of manufacture and installation, the quality practices and
procedures followed by the Vendors’ quality control organization, the relevant reference
document/standard used, acceptance level, inspection documentation raised, etc. Such
quality plans of the successful vendors shall be discussed and finalized in consultation
with the Engineer and shall form a part of the Purchase Order/Contract between the
Contractor and the Vendor. Within three weeks of the release of the Purchase
Orders/Contracts for such bought out items/components a copy of the same without price
details but together with detailed purchase specifications, quality plans and delivery
conditions shall be furnished to the Engineer by the Contractor.
67.1 During the execution of the Contract, the Owner reserves the right to increase or
decrease the quantities of items under the Contract but without any change in unit price
or other terms & conditions. Such variations unless otherwise specified in the
accompanying GCC and/or Technical Specifications, shall not be subjected to any
limitation for the individual items but the total variations in all such items under the
Contract shall be limited to the extent of 30%(Thirty Percent ) of the contract price by
way of suitable amendment to the contract.
67.2 The Contract price shall accordingly be adjusted based on the unit rates available in the
Contract for the change in quantities as above. The base unit rates, as identified in the
Contract shall however remain constant during the currency of the Contract, In case the
unit rates are not available for the change in quantity, the same shall be subjected to
mutual agreement.
67.3 As this is an EPC contract, Design will be done by the Contractor. Responsibility of
material will be that of the contractor.
68.1 The Contractor, wherever applicable, shall after proper painting, pack and crate all
equipment in such a manner as to protect them from deterioration and damage during
rail and road transportation to the Site and storage at the Site till the time of erection.
The Contractor shall be held responsible for all damages due to improper packing.
68.2 The Contractor shall notify the Owner of the date of each shipment from his works, and
the expected date of arrival at the Site for the information of the Owner.
68.3 The Contractor shall also give all shipping information concerning the weight, size and
content of each packing including any other information the Owner may require.
68.4 The following documents shall be sent by registered post to the Owner within three days
from the date of shipment, to enable the Owner to make progressive payments to the
Contractor:-
Application for payment in the standard format of the Owner
Invoice
Packing list
Pre-despatch clearance certificate, if any
Test Certificate, wherever applicable
Insurance Certificate
68.5 The Contractor shall prepare detailed packing list of all packages and containers,
bundles and loose materials forming each and every consignment despatched to Site.
The Contractor shall further be responsible for making all necessary arrangements for
loading, unloading and other handling right from his works up to the Site and also till the
equipment is erected, tested and commissioned. He shall be solely responsible for
proper storage and safe custody of all equipment.
69.0 COOPERATION WITH OTHER CONTRACTORS AND CONSULTING ENGINEERS
The Contractor shall agree to cooperate with the Owner’s other Contractors and
Consulting Engineers and freely exchange with them such technical information as is
necessary to obtain the most efficient and economical design and to avoid unnecessary
duplication of efforts. The Engineer shall be provided with three copies of all
correspondence addressed by the Contractor to other Contractors and Consulting
Engineers of the Owner in respect of such exchange of technical information, wherever
needed.
Neither the inspection by the Owner or the Engineer or any of their officials, employees,
or agents nor any order by the Owner or the Engineer for payment of money or any
payment for or acceptance of, the whole or any part of the Works by the Owner or the
Engineer, nor any extension of time, nor any possession taken by the Engineer shall
operate as a waiver of any provision of the Contract, or of any power herein reserved to
the Owner or any right to damages herein provided nor shall any waiver of any breach
in the Contract be held to be a waiver of any other or subsequent breach.
No interim payment certificate of the Engineer, nor any sum paid on account by the
Owner, nor any extension of time for execution of the Works granted by the Engineer
During the various stages of the work in pursuance of the Contract, the Contractor shall
at his own cost submit periodic progress reports as may be reasonably required by the
Engineer with such materials as, in approved MS PROJECT ,charts, net-works,
photographs, test certificates, etc. Such progress reports shall be on monthly base for
supply items & fortnightly for erection activities in the form and size as may be required
by the Engineer.
Upon successful completion of all the tests and commissioning by the Contractor, the
Engineer shall issue to the Contractor a Taking Over Certificate (TOC) as a proof of the
final acceptance of the equipment. Such certificate shall not unreasonably be withheld
nor will the Engineer delay the issuance thereof on account of minor omissions or defects
which do not affect the commercial operation and/or cause any serious risk to the
equipment. Such certificate shall not relieve the Contractor of any of his obligations
which otherwise survive, by the terms and conditions of the Contract after issue of such
certificate.
In the event of completion of pre commissioning tests carried out jointly, if energization
of the substation is prevented for reasons not attributable to the successful bidder, the
Preliminary Acceptance Certificate shall be given within 30 days of pre commissioning
tests prior to Taking Over Certificate (TOC).
74.1 Transfer of title in respect of equipment and materials supplied by the Contractor to
GETCO pursuant to the terms of the Contract shall pass on to GETCO with negotiation
of dispatch documents.
74.2 This Transfer of Title shall not be construed to mean the acceptance and the consequent
“Taking Over” of equipment and materials. The Contractor shall continue to be
responsible for the quality and performance of such equipment and materials and for
their compliance with the specifications until “Taking Over” and the fulfillment of
guarantee provisions of this Contract.
74.3 This Transfer of Title shall not relieve the Contractor from the responsibility for all risks
of loss or damage to the equipment and materials as specified under the clause entitled
“Insurance” of this Section.
Under the Contract, the Contractor shall be responsible for loss or damage to the plant
until the successful completion of commissioning as defined else where in the Bid
document.
77.1 Force majeure is herein defined as any cause which is beyond the control of the
Contractor or the Owner as the case may be, which they could not foresee or with a
reasonable amount of diligence could not have foreseen and which substantially affects
the performance of the Contract, such as:
a. Natural phenomena, including but not limited to floods, droughts, earthquakes and
epidemics;
b. Acts of any Government, domestic or foreign, including but not limited to war,
declared or undeclared, priorities, guarantees, embargoes.
Provided either party shall within fifteen (15) days from the occurrence of such a cause
notify the other in writing of such causes.
77.2 The Contractor or the Owner shall not be liable for delays in performing his obligations
resulting from any force majeure cause as referred to and/or defined above
78.1 The Owner reserves the right to suspend and reinstate execution of the whole or any
part of the Works without invalidating the provisions of the Contract. Orders for
suspension or reinstatement of the Works will be issued by the Engineer to the
Contractor in writing. The time for completion of the works will be extended for a period
equal to duration of the suspension.
78.2 Any necessary and demonstrable cost incurred by the Contractor as a result of such
suspension of the works will be paid by the Owner, provided such costs are
substantiated to the satisfaction of the Engineer. The Owner shall not be responsible
for any liabilities if suspension or delay is due to some default on the part of the
Contractor or his Sub-Contractor.
79.1 If the Contractor shall neglect to execute the works with due diligence and expedition or
shall refuse or neglect to comply with any reasonable order given to him, in writing by
the engineer in connection with the works or shall contravene the provisions of the
contract, the Owner may give notice in writing to the Contractor to make good the failure,
neglect or contravention complained of. Should the contractor fail to comply with the
If such excess is greater than the sums due to the contractor, the contractor shall
pay the balance to the Owner and if such excess is less than the sums due to the
Contractor, Owner shall pay the balance to the Contractor. For facilitating such
payment, Owner shall encash the Bank Guarantees of Contractor available with
Owner/s and retain such other payments due to the contractor under the Contract
in question or any other Contract that the Owner/s may have with the Contractor.
Such payment of excess amount shall be independent of the liquidated damages for
delay which the Contractor shall have to pay if the completion of works is delayed.
79.2 In addition, such action by the Owner as aforesaid shall not relieve the Contractor of his
liability to pay liquidated damages for delay in completion of Works .
79.3 Such action by the Owner as aforesaid the termination of the Contract under this clause
shall not entitle the Contractor to reduce the value of the Contract Performance
Guarantee nor the time thereof. The Contract Performance Guarantee shall be valid for
the full value and for the full period of the Contract including guarantee period.
80.1 The Owner reserves the right to terminate the Contract either in part or in full due to
reasons other than those mentioned under clause entitled ‘Contractor’s Default’. The
Owner shall in such an event give fifteen (15) days notice in writing to the Contractor of
his decision to do so.
80.2 The Contractor upon receipt of such notice shall discontinue the work on the date and
to the extent specified in the notice, make all reasonable efforts to obtain cancellation of
all orders and Contracts to the extent they are related to the work terminated and terms
satisfactory to the Owner, stop all further sub-contracting or purchasing activity related
to the work terminated, and assist Owner in maintenance, protection, and disposition of
the works acquired under the Contract by the Owner.
In the event of such a termination the Contractor shall be paid compensation, equitable
and reasonable, dictated by the circumstances prevalent at the time of termination.
80.3 If the Contractor is an individual or a proprietary concern and the individual or the
proprietor dies and if the Contractor is a partnership concern and one of the partners
dies then unless the Owner is satisfied that the legal representatives of the individual
Contractor or of the proprietor of the propriety concern and in the case of partnership,
the surviving partners, are capable of carrying out and completing the Contract the
Owner shall be entitled to cancel the Contract as to its in completed part without being
81.2 In the event of non-availability or suspension of funds for any reasons, whatsoever
(except for reason of willful or flagrant breach by the Owner) and/or Contractor then the
works under the Contract shall be suspended.
81.3 In the event referred to in sub-clauses 81.1& 81.2 above the parties shall mutually
discuss to arrive at reasonable settlement on all issues including amounts due to either
party for the work already done on quantum merit_ basis which shall be determined by
mutual agreement between the parties.
83.2 If any dispute or difference of any kind, whatsoever, shall arise between the Owner and
the Contractor, arising out of the Contract for the performance of the Works whether
during the progress of the Works or after its completion or whether before or after the
termination, abandonment or breach of the Contract, it shall, in the first place, be referred
to and settled by the Engineer, who, within a period of thirty (30) days after being
requested by either party to do so, shall give written notice of his decision to the Owner
and the Contractor.
83.4 If after the Engineer has given written notice of his decision to the parties, no claim to
arbitration has been communicated to him by either party within thirty (30) days from the
receipt of such notice, the said decision shall become final and binding on the parties.
83.5 In the event of the Engineer failing to notify his decision as aforesaid within thirty (30)
days after being requested as aforesaid, or in the event of either the Owner or the
Contractor being dissatisfied with any such decision, or within thirty (30) days after the
expiry of the first mentioned period of thirty days, as the case may be, either party may
require that the matters in dispute be referred to arbitration as hereinafter provided.
84.0 ARBITRATION
84.1 All disputes or differences in respect of which the decision, if any, of the Engineer has
not become final or binding as aforesaid shall be settled by arbitration in the manner
hereinafter provided.
84.1.1 The arbitration shall be conducted by three arbitrators, one each to be nominated by the
Contractor and the Owner and the third to be appointed as an umpire by both the
arbitrators in accordance with the Indian Arbitration Act. If either of the parties fails to
appoint its arbitrator within sixty (60) days after receipt of a notice from the other party
invoking the Arbitration clause, the arbitrator appointed by the party invoking the
arbitration clause shall become the sole arbitrator to conduct the arbitration.
84.1.2 The arbitration shall be conducted in accordance with provisions of Indian Arbitration Act
1996 or latest amendment thereof.
84.2 The decision of the majority of the arbitrators shall be final and binding upon the parties.
The arbitrators may, from time to time with the consent of all the parties enlarge the time
for making the award. In the event of any of the aforesaid arbitrators dying, neglecting,
resigning or being unable to act for any reason, it will be lawful for the party concerned
to nominate another arbitrator in place of the outgoing arbitrator.
84.3 The arbitrator shall have full powers to review and/or revise any decision, opinion,
direction, certification or valuation of the Engineer in accordance with the Contract, and
neither party shall be limited in the proceedings before such arbitrators to the evidence
or arguments put before the Engineer for the purpose of obtaining the said decision.
84.4 No decision given by the Engineer in accordance with the foregoing provisions shall
disqualify him as being called as a witness or giving evidence before the arbitrators on
any matter whatsoever relevant to the dispute or difference referred to the arbitrators as
aforesaid.
84.5 During settlement of disputes and arbitration proceedings, both parties shall be obliged
to carry out their respective obligations under the Contract.
84.6 All questioins, disputes or differences, whatsoever which may at any time arise between
the parties to this contract in connection with the contract or any matter arising out of or
in relation there to shall be referred to the “Gujarat public works contracts disputes
arbitration tribunal” as per the provisions of the Gujarat public works contracts disputes
arbitration tribunalact,1992.
The Contractor shall prepare and submit every two months, a statement covering
payments claimed and the payments received vis-à-vis the works executed, for
reconciliation of accounts with the Owner. The Contractor shall also prepare and submit
a detailed account of Owner Issue materials received and utilized by him for
reconciliation purpose in a format to be discussed & finalized with the Owner before the
award of Contract.
All new bidders / Vendors have to register themselves with the GETCO by paying
Rs.10,000/- (Non-refundable) plus GST as applicable. Regular suppliers are
registered automatically looking to their performance. They shall have to fill up a
prescribed form attached herewith within two months giving basic details of their set
up, turn over, ISO certification, etc. However, they shall have to re-register by paying
Rs.10,000/-(Non-Refundable) plus GST as applicable after 05 years from
01/03/2001. Factory inspection for new entrants is a must. Factory inspection shall
be conducted for the period of every 2 years from where the supplier is supposed
to supply the materials. This new rule shall come in to force after 06 months from
01/03/2001 so that party gets enough time for registration. However in the meantime
all the New Vendors shall have to pay Rs.10,000/-(Non-refundable) plus GST as
applicable towards registration fees as explained above, before submission of bids
and the proof of the same may be given with the technical bid otherwise tender will
be ignored out rightly.
Vendor registration upto tender value of Rs.1 Lac (One Lac) for the new entrant is
not required. However, Rs.1000/- plus GST as applicable towards Vendor
registration shall be payable for the tender value between Rs.1 Lac and including
upto Rs.5 Lacs. Vendor registration beyond Rs.5 lacs will be applicable and shall
have to pay Rs.10,000/- plus GST as applicable for new entrant as specified above.
If the tendered is new & not registered with the GETCO, then they should Pay
Rs.10,000/- plus GST as applicable before opening of the tender itself and the copy
of Money Receipt should be submitted in the EMD Cover, otherwise their tender will
be ignored without any further communication in the matter.
As per the Section 206AB of Income Tax Act, TDS under Income Tax will be
deducted at higher rates of the following rates: (non-fillers of ITRs for the past
two
fiscal years will be subjected to higher TDS).
(a) At twice the rate specified in the relevant provision of the Act
(b) At twice the rates in force
(c) At the rate of 5%
94.0 Bidder should follow the GOI guideline of Restrictions under rule 144 (xi) of
the General Financial Rules (GFRs), 2017 vide office memorandum
no. F.No.6/18/2019-PPD Dt: 23.07.2020. The copy of subject
memorandum is attached in technical specification of Tender.
95.0 All the financial documents/work done complication certificate/ ongoing contract
on hand to be submitted certified by CA and satisfactory completion certificate
from respective department should be submitted in notarized.
96.0 Responsibility for correctness of the information submitted in the bid lies with
bidder. If any information furnished in the bid is proved to be false at a later
date, GETCO reserveright to reject the bid and the bid will not only be rejected
but the bidder will be BLACKLISTED as per GUVNL Policy.