Operational Network Diagram Task

The document outlines a project plan with 7 tasks labeled A through G, including task descriptions and durations in weeks. Critical tasks are highlighted in yellow, and the Coating task of 5 weeks duration has a total float of 3 weeks and free float of 13 weeks. A Gantt chart shows the schedule and dependencies between the tasks over a period of 21 weeks.

Uploaded by

Javed Choudhry
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
17 views

Operational Network Diagram Task

The document outlines a project plan with 7 tasks labeled A through G, including task descriptions and durations in weeks. Critical tasks are highlighted in yellow, and the Coating task of 5 weeks duration has a total float of 3 weeks and free float of 13 weeks. A Gantt chart shows the schedule and dependencies between the tasks over a period of 21 weeks.

Uploaded by

Javed Choudhry
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 13

Task Description of the task Duration (weeks) Predecessors

A General Design 7

B Opearatinal Design 3 A

C Design of building surface solutions 1 A

D Design of lighting 2 B

E Purchase of lighting 6 BD

F Coating 5 C

G Installation of lamps and furnitures 2 EF

Notes: Critical activities are highlighted in yellow.


Total float and free float of Coating Activity are highlighted in green
0
A
7
0
ES TF EF

ID
Activity name
D

LS FF LF

8 0 10
D
Design of lighting
2
8 0 10

7 0 10
B
Operational design
3
7 0 10

0 7
General Design

0 7

7 3 8
C Design of Building
1 Surface Solutions
10 0 11
10 0 16
E
Purchase of lighting
6
10 0 16

16 0 18
G Installation of
2 lamps/furnitures
16 0 18

8 3 13
F
Coating
5
11 3 16
Task Description of the task Duration (weeks) Predecessors

G Installation of lamps/furnitures 2 EF
Dependency type

FS

Gantt chart

1 2 3
A General Design
B Opearatinal Design
C Design of building surface solutions
D Design of lighting
E Purchase of lighting
F Coating
G Installation of lamps and furnitures
4 5 6 7 8 9 10 11 12
13 14 15 16 17 18
week 1 2 3 4 5 6 7 8
A 3 3 3 3 2 2 3 3
B 8 8 8 8
C 4 4 4 4
D 6 5 5
E
F
G
pwd 3 3 3 3 14 20 20 20

week 1 2 3 4 5 6 7 8
A 3 3 3 3 3 3 2 2
B 8 8 8 8
C 4 4 4 4
D 5 6 6
E
F
G
pwd 3 3 3 3 15 20 20 20
PART - a

9 10 11 12 13 14 15 16 17 18 19 20 21

8 8 8 8
4 4 4 4 4 4 4 4 5 5
8 4 4
4 4 3 3 3 3 3 3 4 4 4 4
5 8 8 8 8 7 6 6 6 5
5 5 4
20 20 20 20 15 15 15 15 15 15 15 15 13

PART - b

9 10 11 12 13 14 15 16 17 18 19 20 21

8 8 8 8 2 2
4 4 4 4 4 4 4 4 5 5
8 5 5 6 4 4 6
3 3 3 3 3 3 4 4 4 4 4 4
6 6 6 6 6 8 8 8 6 6
4 4 5
20 20 20 27 19 19 19 14 17 17 16 14 15
22 Workload pwd
22
64
58
32
42
5 72
4 18
9 308

22 Workload pwd
22
68
58
55
6 48
6 72
5 18
17 341