Bid Breakdown PDF
Bid Breakdown PDF
SUBJECT : GENERAL CONSTRUCTION WORKS INCLUSIVE OF SITE DEVELOPMENT WORKS AND SPECIALTY TRADE WORKS
PROPOSAL
DATE : MAY 4, 2023
I Building Works
A. General Requirements
1.0 Preliminaries
1.1 Temporary Facilities 1.00 lot L.S. p 100,000.00
1.2 Temporary Power & Lighting 1.00 lot L.S. 50,000.00
1.3 Temporary Water 1.00 lot L.S. 20,000.00
1.4 Telephone / Communication 1.00 lot L.S. 20,000.00
1.5 Security Services 1.00 lot L.S. 200,000.00
1.6 General Clearing, Sanitation, Safety and Disposal of Waste and Dewatering 1.00 lot L.S. 100,000.00
1.7 Mobilization 1.00 lot L.S. 100,000.00
1.8 Site Management and Equipment 1.00 lot L.S. 150,000.00
1.9 Miscellaneous
2.0 As-Built Plan 1.00 lot L.S. 50,000.00
2.1 Surveying 1.00 lot L.S. 50,000.00
2.0 Security Bond 85,767.85
2.1 Demobilization 1.00 ls 100,000.00
Sub-total 1: 1,025,767.85
2.0 Bonds and Insurance (Provisional Sum)
2.1 Performance Bond 1.00 lot L.S. p
% of bond coverage: 20%
Cost Premium
2.2 Guarantee Bond 1.00 lot L.S.
% of bond coverage: 10%
Cost Premium
2.3 Contractor's All Risk Insurance 1.00 lot L.S.
% of bond coverage: 100%
Insurance Cost of Premium
2.4 Performance Bond (FBDC) 1.00 lot L.S.
2.5 Construction Deposit Guarantee 1.00 lot L.S.
2.6 7% General Contractor's Mark-Up 1.00 lot L.S.
Note: Above cost are procivional only. Final cost shal be based on actual premium
at secured from BDO Insurance plus seven (7%) (for Owner's approval)
General Contractor's Markups
Sub-total 2 : -
3.0 Permits (Provisional Sum)
3.1 Building Permit
a. Receipted Amount 1.00 lot L.S. p 50,000.00
Subtotal 3.1 : 50,000.00
3.2 Occupancy Permit
a. Receipted Amount 1.00 lot L.S. 50,000.00
Subtotal 3.2 : 50,000.00
3.3 Miscellaneous Permits
a. Fire Safety Inspection Certificate 1.00 lot L.S. 30,000.00
b. Fire Safety Evaluation Certificate 1.00 lot L.S. 30,000.00
Subtotal 3.3 : 60,000.00
3.4 Environmental Compliance Certificate
a. Receipted Amount 1.00 lot L.S. 100,000.00
Subtotal 3.3 : 100,000.00
3.5 7% General Contractor's Mark-Up on Reciepted Amount 18,200.00
Sub-total 3 : 278,200.00
TOTAL AMOUNT I-A (General Requirement) : 1,303,967.85
B. REMEASURABLE ITEMS
1.0 Testing of Construction Materials (Provisional Sum) 1.00 lot L.S. p 50,000.00
Sub-total 1: 50,000.00
2.0 Earthworks
2.1 Machine Excavation - cu.m - p -
2.2 Manual Excavation 110.00 cu.m 250.00 27,500.00
2.3 Backfilling & Compaction (From Site Materials) 88.00 cu.m 200.00 17,600.00
2.4 Gravel Fill 18.65 cu.m 1,800.00 33,570.00
2.5 Manual Trimming 375.00 sq.m. 200.00 75,000.00
2.6 Clearing and Grubbing 375.00 sq.m. 100.00 37,500.00
Sub-total 2 : 191,170.00
3.0 Concrete and Steelworks
3.1 Foundation Structures (Column Footings, Tie Beams, Wall Beams. Grade Beams)
a. Concrete 13.50 cu.m 5,000.00 p 67,500.00
b. Rebars 1,194.48 kg 50.00 59,724.00
c. Formworks 43.20 sq.m 450.00 19,440.00
Sub-total 3 : 1,441,360.43
4.0 Masonry Works
4.1 CHB Wall ( Load Bearing, 750psi)
a. 6" CHB Wall 254.00 sq.m. 675.00 p 171,450.00
b. 4" CHB Wall 437.00 sq.m. 575.00 251,275.00
4.2 Horizontal & Vertical Stiffeners 100.00 l.m 350.00 35,000.00
4.3 Lintel Beams 15.00 l.m 435.00 6,525.00
Sub-total 4 : 464,250.00
5.0 Floor Finishes
5.1 Plain Cement Straight to Finish (Basement Parking) 30.00 sq.m. 180.00 p 5,400.00
5.2 Plain Cement Finish (Ready to Receive Homogenous Tiles) 352.00 sq.m. 180.00 63,360.00
5.3 Plain Cement Finish Floor Topping 352.00 sq.m. 220.00 77,440.00
5.4 Homogeneous Tiles Installation (600mm x 600mm) 352.00 sq.m. 700.00 246,400.00
5.5 Homogenous Tiles Installation (300mm x 300mm) 29.00 sq.m. 700.00 20,300.00
5.6 Ramp Linear Curb 50.00 l.m. 85.76 4,288.00
5.7 Wheel Stop 5.00 sets 650.00 3,250.00
Sub-total 5 : 420,438.00
6.0 Wall Finishes
6.1 Interior Wall Finishes
a. Plain Cement Plaster Finish on CHB Wall 870.00 sq.m. 225.00 p 195,750.00
b. Plain Cement Plaster Finish on R.C Wall/Columns 20.00 sq.m. 250.00 5,000.00
c. Homogenous Tiles Installation (600 x 600mm) 91.00 sq.m. 800.00 72,800.00
d. Countertop (width: 0.60m) Granite Finish 9.00 l.m. 10,000.00 90,000.00
Subtotal 6.1 : 363,550.00
6.2 Exterior Wall Finishes
a. Plain Cement Plaster Finish on CHB Wall 254.00 sq.m. 200.00 50,800.00
b. Plain Cement Plaster Finish on R.C Wall/Columns 5.00 sq.m. 250.00 1,250.00
Subtotal 6.2 : 52,050.00
Sub-total 6 : 415,600.00
7.0 Ceiling Finishes
7.1 Spandrel 70.00 sq.m. 1,000.00 p 70,000.00
7.2 Acoustic Board 152.00 sq.m. 820.00 124,640.00
7.3 Gypsum Board 12mm thk. 137.00 sq.m. 820.00 112,340.00
7.4 Moisture Resistant Gypsum Board 12mm thk. (Toilets) 56.00 sq.m. 820.00 45,920.00
Sub-total 7 : 352,900.00
8.0 Waterproofing Works
8.1 Toilet Waterproofing 30.00 sq.m. 500.00 p 15,000.00
8.2 Elastomeric Waterproofing Paint 254.00 sq.m. 460.00 116,840.00
Sub-total 8 : 131,840.00
9.0 Wooden and Metal Doors
9.1 Doors
D1 Powder Coated Aluminum Frame 2.75 x 2.45 2.00 sets 20,212.50 p 40,425.00
D2 Single Leaf Flush Door (S) 1.20 x 2.40 5.00 sets 13,000.00 65,000.00
D3 Single Leaf Flush Door (S) 0.90 x 2.10 12.00 sets 10,000.00 120,000.00
D4 Single Leaf Flush Door (S) 0.70 x 2.10 2.00 sets 9,800.00 19,600.00
D5 Single Leaf Flush Door (S) 0.70 x 2.10 2.00 sets 9,800.00 19,600.00
D6 Single Leaf Flush Door W/ Louver (S) 0.90 x 2.10 3.00 sets 10,000.00 30,000.00
D7 Single Leaf Flush Door W/ Louver (S) 0.80 x 2.10 2.00 sets 9,800.00 19,600.00
D8 Single Leaf Flush Door (W) 0.70 x 2.10 3.00 sets 9,800.00 29,400.00
D9 Single Leaf Flush Door (AL) 1.80 x 2.10 1.00 sets 13,230.00 13,230.00
D10 Single Leaf Flush Door (AL) 0.90 x 2.10 2.00 sets 8,500.00 17,000.00
D11 Single Leaf Flush Door (S) 1.50 x 2.10 2.00 sets 19,000.00 38,000.00
D12 Single Leaf Flush Door (S) 0.90 x 2.10 1.00 sets 10,000.00 10,000.00
D13 Single Leaf Flush Door (S) 1.28 x 2.10 1.00 sets 13,000.00 13,000.00
D14 Single Leaf Flush Door (AL) 0.55 x 2.10 2.00 sets 4,042.50 8,085.00
9.2 Windows
Prepared by:
DAMARA CONSTRUCTION
General Contractor