Shoring Procedure

This document provides a shoring procedure for open trenches during pipeline rehabilitation and repair work. It describes installing sheet piles or sheet piles with steel plates to prevent trench collapse. The procedure outlines approval processes, installation methods like driving piles 2/3 into the ground with interlocks, maintaining a 1m distance from pipelines, and only removing shoring with permission when the trench is empty. Records of all shoring work must be maintained.

Uploaded by

chebok man
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
120 views7 pages

Shoring Procedure

This document provides a shoring procedure for open trenches during pipeline rehabilitation and repair work. It describes installing sheet piles or sheet piles with steel plates to prevent trench collapse. The procedure outlines approval processes, installation methods like driving piles 2/3 into the ground with interlocks, maintaining a 1m distance from pipelines, and only removing shoring with permission when the trench is empty. Records of all shoring work must be maintained.

Uploaded by

chebok man
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

ACE ENERGY SDN BHD

No 6-3, Jalan Puncak Setiawangsa 4,


Taman Setiwangsa, 54200 Kuala Lumpur
GST REG : 000777805824

SHORING PROCEDURE

EPCC OF NGDS TO SHAH ALAM FL STAGE 1/22, SHAH


ALAM, SELANGOR DARUL EHSAN (NIPPON ELECTRIC
GLASS (M) SDN BHD)

CONTRACTOR APPROVAL
REV NO. PREPARED DATE CHECKED DATE APPROVED BY DATE
0A
1A
2A

GAS MALAYSIA DISTRIBUTION SDN BHD

REV.NO. REVIEWED DATE APPROVED DATE

0A
1A
2A

Doc.No: P2013-AE (13) 15122020.PIM (01)


DOC NO.
P2203 – AE (03)10052022-PIM (01)
SHORING DATE : 05/05/2023
REVISION : 0
PROCEDURE Page 1 of 52

TABLE OF CONTENTS

1.0 PURPOSE

2.0 SCOPE

3.0 DEFINITIONS

4.0 REFERENCES

5.0 PROCEDURE FOR SHORING

6.0 RECORD
DOC NO.
P2203 – AE (03)10052022-PIM (01)
SHORING DATE : 05/05/2023
REVISION : 0
PROCEDURE Page 2 of 52

1.0 PURPOSE
The purpose of this procedure is to describe and define the methods of installation of shoring for
trench to prevent it from collapsing.
It is the intention of this procedure to act as a guide to personnel engaged in this activity, not to
supersede or override any specifications, codes, standards or statutory regulations.

2.0 SCOPE
The scope of this procedure is for the installation of shoring i.e. sheet pile and sheet pile with
steel plate for the open trench for the rehabilitation and repair work.

3.0 DEFINITIONS
ACE ACE ENERGY SDN BHD
GMDSB GAS MALAYSIA SDN BHD
Subcontractor A company awarded by ACE to perform any work or specific work for
the rehabilitation and repair, after getting approval from GMDSB.
Shoring A method or installation of sheet pile or sheet pile or I-beam combined with steel plate
on the wall of open pipeline trench to prevent it from collapsing.

4.0 REFERENCES
DOC NO.
P2203 – AE (03)10052022-PIM (01)
SHORING DATE : 05/05/2023
REVISION : 0
PROCEDURE Page 3 of 52

5.0 PROCEDURE FOR SHORING


5.1 ACE shall propose types of shoring to GMDSB for approval
5.2 Prior to the activities, ACE shall meet GMDSB for pre-job meeting and secure the necessary
work permit/s.
5.3 Shoring shall only be performed in the presence of GMDSB personnel.
5.4 Shoring shall be performed when the pipeline has been exposed, the open trench is more than 1.5
meter deep and as instructed by GMDSB
5.5 Shoring shall be installed at a minimum distance of 1.0 meter from the pipeline.
5.6 The equipment and machinery used for the installation of shoring must be in good working
condition. All machinery shall be placed away from the buried pipeline. If there is no other area
to place the machinery, steel plate shall be used as a platform for the machinery to be placed
upon. Spark arrestor shall be used for the machinery. The machine operator must be competent
and experience person for the purpose of shoring installation.
5.7 Shoring can be via the following method:-
i. I-beam with steel plate
5.8 When driving the sheet pile into the ground, the sheet pile shall be driven at least 2/3 of its length
buried in the ground. ACE shall ensure that there will be no excessive vibration induced to
GMDSB pipeline that can jeopardize the integrity and safety of the pipeline and personnel
working within the area. Sheet pile shall be installed with interlocking between one another. ACE
shall inspect the sheet pile arrangement and prove to GMDSB that the sheet pile could hold the
ground from collapsing. (If necessary)
5.9 ACE shall ensure that all personnel involved in installing the sheet pile are experienced and
competent. ACE shall ensure that dedicated signal man is available for the activities.
5.10 Should the full sheet pile could not be installed due to whatever reason, ACE will propose to
install sheet pile / I-beam with steel plate. The sheet pile / I-beam will be driven into the ground
as above but within a predetermined spacing and vertical offset between one another and ½’’
steel plate will be placed in between the sheet pile / I-beam all the way until it rest on the ground.
ACE shall inspect the shoring arrangement and prove to GMDSB that it could hold the ground
from collapsing.
5.11 Shoring shall only be removed upon instruction from GMDSB and nobody is working in the
trench.
5.12 ACE shall provide signal man for removal of shoring.
DOC NO.
P2203 – AE (03)10052022-PIM (01)
SHORING DATE : 05/05/2023
REVISION : 0
PROCEDURE Page 4 of 52

5.13 Shoring shall be removed in a very careful and slow manner so as not to damage GMDSB
pipeline.
5.14 Shoring shall be removed in presence of GMDSB personnel.
5.15 The removed sheet pile / I-beam and steel plate shall be placed and stack up in a neat and safe
manner to reduce the risk of toppled down.

6.0 RECORD
6.1 ACE shall maintain all necessary records pertaining to the above activities for GMDSB
verification and endorsement.
SURUHANJAYA TENAGA
NOTES :
INGRESS / EGRESS POINT
SEE DETAIL "A"
METAL LEDDER
WELDING I BEAM 4"X4"
JOINT SOIL
400
0
00
50
3000

SOIL
WELDING

3000

MAX. EXCAVATION DEPTH 7000mm


JOINT I BEAM

MAX. SHEET PILE DEPTH 9000mm


4"X4"

3000
5000 SOIL
TOP VIEW
CLIENT:
GAS MALAYSIA BHD.
NO 5 JALAN SERENDAH
26/17 SEKSYEN 26
PETI SURAT 7901
40732 SHAH ALAM, SELANGOR
TYPE 3A - SHEET PILES CONTRACTOR:
ACE ENERGY SDN BHD
400
CERTIFIED BY COMPETENT PERSON:
NAME:
REG. NO:
CROSS-SECTION VIEW DATE:

150
PROJECT TITLE:
EPCC OF NGDS TO SHAH ALAM FL STAGE 1/22, SHAH
ALAM, SELANGOR DARUL EHSAN (NIPPON ELECTRIC
GLASS (M) SDN BHD)
DRAWING TITLE:


DETAIL 'A' 

DRAWING NO: REV.
P2203-AE(01)10052022-SPSB(01) 00
DRAWN: AKIF OWNER APPROVAL :
DESIGNED: MUIZ
CHECKED: MUIZ
APPROVED:
DATE: MAY 2023
SCALE: N.T.S