US Industrial Construction Cost Guide 2023
US Industrial Construction Cost Guide 2023
INDUSTRIAL
CONSTRUCTION
COST
GUIDE
2023
INTRODUCTION
Construction activity in the
industrial sector has raced to
keep up with robust demand
of the last two years in North
American markets. While industrial
construction pipelines continue
at historically high levels, the
sector is facing several headwinds.
Pandemic-related supply chain
constraints, which helped drive
commodities costs up, continue to
have a lingering impact on overall
costs and material lead times.
A significantly higher interest
rate environment in the United
States provides additional upward
pressure to costs. The fed rate
is currently 4.25%-4.5% up from
nearly zero in March 2022. As the
sector faces a potential cooling
down in 2023, we are closely
monitoring the costs and material
lead times which could allow
projects more flexibility in their
delivery timelines.
43
MARKETS IN
NORTH AMERICA
KEY
TAKEAWAY
• Steel prices remain elevated
at a 20% increase year-over-
year (YoY). Prices are ECONOMIC OVERVIEW
forecast to drop slightly
and level out over the next Strong demand for industrial properties, fueled in great part by the rise
couple of years. in e-commerce, has led to historic levels of construction in the sector.
Competition for materials in a commodity constrained market, coupled
• After reaching peak levels with inflationary pressures, has driven construction costs higher across
in 2021 Q2, lumber pricing all real estate sectors.
has moderated, registering
Commodities Pricing Update: Pandemic related supply chain
a 6% increase YoY. Pricing
constraints, which led to elevated commodities pricing, have begun
is forecast to level out but
to ease. Bottlenecks of container ships at ports are no longer the
remain above pre-pandemic norm. According to FreightWaves, North American container ship
levels for the next few years. traffic on November 23rd was down 60% from recent highs. Only 59
container ships were waiting for a berth. However, this was still above
• Copper prices have faced pre-pandemic levels, which were typically in single digits. The easing of
significant volatility, but traffic at ports may signal forthcoming easing of materials availability.
after hitting a peak at the That said, due to continued pent up demand, costs have not fallen to
beginning of this year, 2022 pre-pandemic levels.
Q1, they have fallen 16% on a
YoY basis. A modest drop in Concrete pricing has increased 14% from Q3 2021 and is currently at its
prices is forecast for 2023. peak pricing and YoY growth. Though pricing is unlikely to fall, the rate
of growth will slow to more moderate levels in the next couple years.
700
400
300
6%
200 increase
YOY
100
80% 44%
63%
60%
63%
63%
40%
41%
20% 25%
16% 19%
13%
6% 6%
0%
General GC's Subs & General GC's Subs &
Contractors Suppliers Contractors Suppliers
$400,000
$375,000
$350,000
Non-residential
building starts
$325,000
declined 19.9% from
February 2020 to
Millions USD, SAAR
$300,000
KEY
TAKEAWAY
• Labor constraints will
continue to impact
construction employment in
Employment and Construction: Non-residential new
the near-term. An increase
construction starts accelerated in 2022. After slowing from
in retirements due to an
February to April 2021, starts accelerated and peaked in
aging workforce, coupled
September 2022 at a 32.7% increase on a YoY basis. While
with a lack of young workers
increased materials costs did not slow starts in 2022, the
from the overall talent pool addition of accelerated interest rate increases on financing
is impacting wages and could slow the growth as costs are compounded.
costs as well as project
timelines. The introduction • U.S. construction employment grew 3.8% YoY basis in
of skills-based programs for 2022 Q3. Wages in the construction sector have risen at a
young workers in addition faster pace in order to attract talent in a labor constrained
to competitive wages may market. On a YoY basis, wages grew 11.4% in 2022 Q3.
help fill the talent gap in
the coming years. A recent • Canadian construction employment grew nearly 6.0%
survey by The Associated YoY as of 2022 Q2, while wages grew 3.5% YoY. Wage
General Contractors of growth have been more moderated in Canada. However,
America (AGC) found that inflationary pressures may impact near-term wage
70% of respondent firms growth.
plan to increase headcount
in 2023, however, over 80%
are having difficulty filling
open positions. Additionally,
the AGC survey indicates
that companies will increase
pay (72% of respondent
firms), provide incentives
and bonuses and increase
their corresponding payment
of benefit packages to retain
and attract talent.
KEY
contractors responding, 44% believe that lead times
had remained constant (38%) or decreased slightly
(6%); the remaining 56% of respondents believe lead
times increased slightly (38%) or significantly (19%)
over the previous six months. Project execution delays
have been more challenged. Only 9% didn’t experience
TAKEAWAY
increases while 86% saw slight (69%) to significant (19)
increases. A recent report from Associated Builders
Construction contractors
and Contractors points to project backlog increases expect increased challenges
in commercial construction 2 . As of November 2022, in project execution timelines
the backlog increased to 9.1 months, the highest level and material lead times. The
since 2019 Q2, indicating that timelines will remain vast majority (85%) expect
constrained. Large commercial projects have been a slight (66%) to significant
major contributor to backlog increases. (19%) increases in material
lead times. This is marginally
more optimistic than
2 Commercial, Institutional and Health Care Construction Drive ABC’s Backlog Indicator sentiment from a year ago
to Highest Level Since Q2 2019”; Associated Builders and Contractors; https://www.abc. when 88% of GCs expected
org/News-Media/News-Releases/entryid/19722/commercial-institutional-and-health-
care-construction-drive-abcs-backlog-indicator-to-highest-level-since-q2-2019; accessed
material lead times to increase
December 16, 2022. slightly (36%) to significantly
(52%). While the industry may
see material lead times easing,
significant issues remain with
electrical gear and regionally
with core materials, such as
cement and sand.
38%
60%
69% 66%
40% 72%
38%
20%
9%
9%
6% 6% 3%
0% 3%
Material Project Material Project
Lead Times Execution Lead Times Execution
Time Time
KEY
the winners in the wake of the pandemic. Skyrocketing e-commerce
demand—along with focus on improved supply chains and increased
TAKEAWAY
interest in manufacturing onshore—has driven North American industrial
demand over the past three years. In the U.S. alone, over 1.3 billion
square feet (bsf) was absorbed between 2020 and the end of 2022.
That is 56% higher than the next best three-year period (2017-2019)
and is 100 msf larger than all of the industrial space in the Americas’ Record demand has driven
largest market, Chicago. Looking forward, e-commerce demand may sub-4% vacancy rates across
be easing but retail, manufacturing, battery manufacturing and storage, the region. As of Q4 2022, the
semiconductor manufacturing and specialty use demand is replacing it. national Canadian vacancy
rate was 1.4%, the U.S. 3.3%,
and both Mexico City and
Monterrey, Mexico were below
STRONGEST 3-YEAR PERIODS OF NET ABSORPTION (MSF) 3%. As vacancy has grown
600 #1 tighter industrial asking
1,336 MSF rents have increased. In Q4
2022, U.S. asking rents were
500 up 18.6% YoY and up 38%
since the beginning of the
pandemic. Canadian asking
400 rents have increased even
#2
#4 #5 #3 854 MSF more substantially: up 45%
300
721 MSF 684 MSF 838 MSF YoY and 81% since Q4 2019.
Latin American rents are down
from pre-pandemic highs but
200 have increased by 12% YoY.
100
TAKEAWAY APAC
250
LATAM Greater China Canada EMEA United States
0
Q1 2020
Q4 2020
Q1 2021
Q1 2022
Q3 2020
Q4 2021
Q4 2022
Q3 2021
Q3 2022
Q2 2020
Q2 2021
Q2 2022
*Q4 2022 data not available for other regions at time of publication.
Source: Cushman & Wakefield Research
KEY
TAKEAWAY
The pipeline remains
strong, with over 230 msf
ABSOLUTE BASIS: COMPLETIONS SINCE BEGINNING OF of industrial space currently
PANDEMIC (Q1 2020-Q4 2022) under construction in the
five markets with the largest
Central Valley CA pipeline. Five U.S. Sunbelt
Charlotte markets have construction
Louisville West pipelines above 10% of current
Las Vegas South inventory: Phoenix, Savannah,
Nashville Northeast
Las Vegas, Charleston, Austin
Salt Lake City
and Fredericksburg. Outside
Midwest
of the U.S., Toronto has the
Denver Latin America most construction activity
Philadelphia Canada (21 msf) while Mexico City,
Mexico City Vancouver and Calgary each
New Jersey - Central have between 8 and 9 msf
Kansas City under construction. The two
Sao Paulo Mexico markets Cushman &
Savannah Wakefield tracks—Mexico City
Columbus and Monterrey—and three
Memphis
Canadian markets— Calgary,
Vancouver and London—have
Toronto
construction pipelines that
Indianapolis
amount to over 3.0% of
Inland Empire current inventory.
Phoenix
PA I-81/I-78 Corridor
Chicago
Atlanta
Construction Activity in Key Markets:
Houston
Construction activity has been broad-
Dallas/Ft. Worth
based as demand for additional space
0 20 40 60 80 has been strong across the region.
MSF Since the beginning of 2020, eight
*Latin America as of Q3 2022 different markets have seen more than
Source: Cushman & Wakefield Research
50 msf of new construction delivered
SHARE OF INVENTORY: COMPLETIONS SINCE BEGINNING OF and 19 markets have seen more
PANDEMIC (Q1 2020-Q4 2022) than 20 msf. This is led by large U.S.
Sunbelt markets—Dallas/Ft. Worth,
Total Completions Since 2020 Share of Inventory (rhs) Atlanta and Houston—and major
90 40% Midwest industrial hubs—Chicago and
Indianapolis. Outside the U.S., recent
Share of Current Inventory
80 35%
70 30%
deliveries have been largest in Sao
60 Paulo (27 msf) and Toronto (34 msf).
25%
50
On a percentage basis, smaller
MSF
20%
40 Sunbelt markets have led the way.
15%
30 More than a fifth of current inventory
20 10% has been delivered in the past three
10 5% years in Birmingham, Savannah and
0 0%
Austin. Already large industrial hub
markets have added approximately
Boise
Houston
Phoenix
Charleston
Memphis
Atlanta
Austin
Palm Beach County
Colorado Springs
Philadelphia
Louisville
Birmingham
Indianapolis
Savannah
Fredericksburg
Salt Lake City
Las Vegas
Columbus
Central Valley CA
Tampa
KEY
TAKEAWAY
National and Market Vacancy Rates: The majority of North
American industrial markets currently have vacancy rates
below 5.0%, including 73 U.S. markets, 11 Canadian markets
and both markets in Mexico. In most cases, vacancies are
considerably tighter than was experienced during the Even with all of the
2000s expansion. In fact, even if all of the space currently aforementioned construction
under construction (731 msf) across the Americas were to likely outpacing tenant
deliver without any of it being leased, region-wide vacancy demand over the next
would remain below 7.0%, and North American vacancy few years, vacancy rates
(U.S. & Canada) would still be 7.2%. are expected to stay near
historical lows. National U.S.
• The ongoing tight market conditions and competition for vacancy is forecast to increase
space saw another quarter of rent growth in Q4 2022, by 100-130 basis points in
increasing 18.6% YoY. At $8.81 per square foot (psf), 2023, still a healthy level for
Q4 2022 is the third quarter to eclipse $8.00 psf in U.S.
the U.S. market.
industrial history. Asking rental rate growth will persist
going forward. However, growth rates are projected to
moderate compared to the double-digit growth rates
observed in recent quarters as the pipeline brings more
space to the market. There will be a flight to the quality
space that comes online.
70 21%
60 18%
50 15%
MSF
40 12%
30 9%
20 6%
10 3%
0 0%
*Mexico as of Q3 2022
Source: Cushman & Wakefield Research
10%
8%
6%
4%
2%
0%
> The priciest markets are located in Western U.S. and Canada. Of the top six most
expensive markets, four are located on the West Coast and two are located in
Canada. The most expensive market is Portland, where costs for medium size
projects average $105 psf and large size projects average $98 psf.
Portland San Diego Oakland
Medium - $105 psf Medium - $101 psf Medium - $100 psf
Large - $98 psf Large - $92 psf Large - $93 psf
Calgary Seattle Montreal
Medium - $101 psf Medium - $100 psf Medium - $97 psf
Large - $98 psf Large - $92 psf Large - $93 psf
• Houston
> The most cost-effective • Memphis
markets include a mix of • Mexico City
markets in Mexico and the • Guadalajara
midwestern and southern U.S. • Nashville
• Louisville
Across all markets and project The second highest cost Site work accounts for 17% of
sizes, the structural (slab on category is building total costs across all markets
grade and structural framing enclosure (exterior wall, and project size.
system) is the largest category exterior panels, windows,
of fit-out costs, accounting for roofing, exteriors doors,
25% of the total. etc.) at 24% of total for both
medium and large projects.
7% 6% 5%
• The industrial build-to-suit project data is based on • Allowances for site concrete, paving, landscaping,
modern-day distribution centers for two different storm retention and site utilities are included. The
sizes (476,400 RSF and 901,000 RSF). Office and pricing does not include soft costs or purchase of land.
other ancillary spaces customary in a distribution
facility are included. The intended construction of • Given the fluidity of the construction market, a ten
the building is either precast insulated panels or percent (10%) contingency allowance has been
tilt-up concrete panels with steel frame. The roof is included in the cost.
a Thermoplastic Polyolefin (TPO) roof pitched to
overflow scuppers for drainage. Floors are 8” thick • Costs in this guide were compiled from responses
slab with reinforced 4,000 psi concrete. Each building to a survey of general contractors (GCs) focused on
size has appropriate quantities of dock doors, levelers industrial properties. 50 GCs representing 43 North
and drive-in ramps and overhead door. The office American markets responded to the survey.
area is constructed with basic finishes excluding
Furniture, Fixtures or Equipment (FF&E) and low
voltage cabling, security or audio/visual equipment
and systems. The office area is fully conditioned
space with the warehouse unconditioned. Warehouse
includes LED high-bay lighting.
Greenville
Miami
Minneapolis
Guadalajara
Memphis
Houston
Philadelphia
Monterrey
Portland
Oakland
Phoenix
Salt Lake
Greensboro
Dallas
Inland Empire
Calgary
Central Valley, CA
Vancouver
Denver
Toronto
Kansas City
Los Angeles
Charlotte
Orange Co.
Cleveland
New Jersey
Indianapolis
Detroit
Baltimore
Louisville
Mexico City
Nashville
Seattle
Montreal
Chicago
Pittsburgh
Columbus
Milwaukee
Penn Corridor
St. Louis
Cincinnati
$0 $50 $100
Portland
San Diego
Seattle
Oakland
Central Valley, CA
Denver
Phoenix
Salt Lake
Los Angeles
Greensboro
Greenville
Miami
Charlotte
Orange Co.
Dallas
Inland Empire
Chicago
Cleveland
Pittsburgh
Minneapolis
Atlanta
New Jersey
Philadelphia
Indianapolis
Columbus
Milwaukee
Penn Corridor
St. Louis
Cincinnati
Site Work
Detroit
Base Bldg Structural &
Kansas City Enclosure
Baltimore Base Building Architectural
Louisville Base Bldg MEP
Nashville
GC’s and GR’s & Fee
Memphis
Contingency
Houston
Source: Cushman & Wakefield Project & Development Services
Portland
San Diego
Seattle
Oakland
Central Valley, CA
Denver
Phoenix
Salt Lake
Los Angeles
Greensboro
Greenville
Miami
Charlotte
Orange Co.
Dallas
Inland Empire
Chicago
Cleveland
Pittsburgh
Minneapolis
Atlanta
New Jersey
Philadephia
Indianapolis
Columbus
Milwaukee
Penn Corridor
St. Louis
Cincinnati
Site Work
Detroit
Base Bldg Structural &
Kansas City Enclosure
Baltimore Base Building Architectural
Louisville Base Bldg MEP
Nashville
GC’s and GR’s & Fee
Memphis
Houston Contingency
Calgary
Montreal
Vancouver
Toronto
Calgary
Montreal
Contingency
Source: Cushman & Wakefield Project & Development Services
Calgary
Montreal
Vancouver
Toronto
Calgary
Montreal
Contingency
Source: Cushman & Wakefield Project & Development Services
Monterrey
Guadalajara
Mexico City
Monterrey
Guadalajara
Site Work
Base Bldg Structural &
Enclosure
Base Building Architectural
Mexico City
Base Bldg MEP
Contingency
Source: Cushman & Wakefield Project & Development Services
Monterrey
Guadalajara
Mexico City
Monterrey
Guadalajara
Site Work
Base Bldg Structural &
Enclosure
Base Building Architectural
Mexico City
Base Bldg MEP
Contingency
Source: Cushman & Wakefield Project & Development Services
$225
$200
$175
$150
$125
$100
$75
$50
$25
$0
$225
$200
$175
$150
$125
$100
$75
$50
$25
$0
Base Bldg Structural & Enclosure $42.30 $38.57 Base Bldg Structural & Enclosure $36.14 $33.64
Base Bldg Architectural $5.12 $6.76 Base Bldg Architectural $5.83 $6.07
Base Bldg MEP $5.71 $5.27 Base Bldg MEP $7.48 $7.17
GC's and GR's & Fee $6.90 $5.71 GC's and GR's & Fee $2.88 $1.88
Base Bldg Structural & Enclosure $53.34 $50.49 Base Bldg Structural & Enclosure $42.47 $37.88
Base Bldg Architectural $5.01 $6.27 Base Bldg Architectural $5.35 $6.98
Base Bldg MEP $6.45 $5.20 Base Bldg MEP $7.07 $6.76
GC's and GR's & Fee $8.53 $7.07 GC's and GR's & Fee $7.59 $6.79
CHICAGO CINCINNATI
Medium Large Medium Large
Base Bldg Structural & Enclosure $44.77 $40.59 Base Bldg Structural & Enclosure $35.27 $34.48
Base Bldg Architectural $5.13 $6.11 Base Bldg Architectural $4.87 $6.27
Base Bldg MEP $7.10 $6.10 Base Bldg MEP $9.10 $8.78
GC's and GR's & Fee $5.53 $4.48 GC's and GR's & Fee $4.88 $3.61
NOTES:
1. Medium (476,400 RSF)
2. Large (901,000 RSF)
3. All costs in USD; conversions made using 2022 rates
CLEVELAND COLUMBUS
Medium Large Medium Large
Base Bldg Structural & Enclosure $37.38 $36.55 Base Bldg Structural & Enclosure $35.97 $35.17
Base Bldg Architectural $5.16 $6.65 Base Bldg Architectural $4.97 $6.40
Base Bldg MEP $9.65 $9.30 Base Bldg MEP $9.28 $8.95
GC's and GR's & Fee $5.17 $3.83 GC's and GR's & Fee $4.97 $3.68
DALLAS DENVER
Medium Large Medium Large
Base Bldg Structural & Enclosure $49.80 $46.61 Base Bldg Structural & Enclosure $40.47 $32.31
Base Bldg Architectural $3.55 $5.91 Base Bldg Architectural $18.29 $22.19
Base Bldg MEP $6.33 $5.76 Base Bldg MEP $4.75 $4.46
GC's and GR's & Fee $4.12 $3.54 GC's and GR's & Fee $2.81 $2.62
DETROIT GREENSBORO
Medium Large Medium Large
Base Bldg Structural & Enclosure $41.19 $37.34 Base Bldg Structural & Enclosure $43.15 $38.06
Base Bldg Architectural $4.72 $5.62 Base Bldg Architectural $5.35 $6.98
Base Bldg MEP $6.54 $5.61 Base Bldg MEP $7.07 $6.76
GC's and GR's & Fee $5.09 $4.12 GC's and GR's & Fee $7.64 $6.73
NOTES:
1. Medium (476,400 RSF)
2. Large (901,000 RSF)
3. All costs in USD; conversions made using 2022 rates
Base Bldg Structural & Enclosure $43.27 $38.31 Base Bldg Structural & Enclosure $14.56 $11.94
Base Bldg Architectural $5.35 $6.98 Base Bldg Architectural $3.56 $4.96
Base Bldg MEP $7.07 $6.81 Base Bldg MEP $17.74 $15.57
GC's and GR's & Fee $7.67 $6.77 GC's and GR's & Fee $3.68 $2.35
Base Bldg Structural & Enclosure $37.35 $37.61 Base Bldg Structural & Enclosure $42.98 $40.57
Base Bldg Architectural $6.02 $6.78 Base Bldg Architectural $9.45 $10.91
Base Bldg MEP $7.73 $8.01 Base Bldg MEP $7.30 $6.10
GC's and GR's & Fee $2.97 $2.11 GC's and GR's & Fee $7.20 $5.99
Base Bldg Structural & Enclosure $41.19 $37.34 Base Bldg Structural & Enclosure $44.41 $41.70
Base Bldg Architectural $4.72 $5.62 Base Bldg Architectural $10.25 $11.69
Base Bldg MEP $6.54 $5.61 Base Bldg MEP $7.81 $6.50
GC's and GR's & Fee $5.09 $4.12 GC's and GR's & Fee $7.42 $6.20
NOTES:
1. Medium (476,400 RSF)
2. Large (901,000 RSF)
3. All costs in USD; conversions made using 2022 rates
LOUISVILLE MEMPHIS
Medium Large Medium Large
Base Bldg Structural & Enclosure $34.56 $33.79 Base Bldg Structural & Enclosure $38.61 $35.21
Base Bldg Architectural $4.77 $6.15 Base Bldg Architectural $4.68 $6.17
Base Bldg MEP $8.92 $8.60 Base Bldg MEP $5.22 $4.81
GC's and GR's & Fee $4.78 $3.54 GC's and GR's & Fee $6.30 $5.21
MIAMI MILWAUKEE
Medium Large Medium Large
Base Bldg Structural & Enclosure $47.01 $42.62 Base Bldg Structural & Enclosure $42.31 $38.36
Base Bldg Architectural $5.38 $6.42 Base Bldg Architectural $4.84 $5.78
Base Bldg MEP $7.46 $6.40 Base Bldg MEP $6.71 $5.76
GC's and GR's & Fee $5.81 $4.70 GC's and GR's & Fee $5.23 $4.23
MINNEAPOLIS NASHVILLE
Medium Large Medium Large
Base Bldg Structural & Enclosure $42.75 $38.76 Base Bldg Structural & Enclosure $39.81 $36.30
Base Bldg Architectural $4.90 $5.84 Base Bldg Architectural $4.82 $6.36
Base Bldg MEP $6.78 $5.82 Base Bldg MEP $5.38 $4.96
GC's and GR's & Fee $5.28 $4.28 GC's and GR's & Fee $6.49 $5.37
NOTES:
1. Medium (476,400 RSF)
2. Large (901,000 RSF)
3. All costs in USD; conversions made using 2022 rates
Base Bldg Structural & Enclosure $37.37 $34.02 Base Bldg Structural & Enclosure $57.21 $54.12
Base Bldg Architectural $6.02 $6.14 Base Bldg Architectural $5.09 $6.33
Base Bldg MEP $7.73 $7.25 Base Bldg MEP $6.90 $5.49
GC's and GR's & Fee $2.97 $1.90 GC's and GR's & Fee $8.95 $7.42
Base Bldg Structural & Enclosure $43.46 $40.81 Base Bldg Structural & Enclosure $36.79 $33.28
Base Bldg Architectural $9.65 $11.10 Base Bldg Architectural $5.93 $6.00
Base Bldg MEP $7.39 $6.18 Base Bldg MEP $7.61 $7.09
GC's and GR's & Fee $7.27 $6.06 GC's and GR's & Fee $2.93 $1.86
PHILADELPHIA PHOENIX
Medium Large Medium Large
Base Bldg Structural & Enclosure $37.37 $34.02 Base Bldg Structural & Enclosure $40.47 $32.31
Base Bldg Architectural $6.02 $6.14 Base Bldg Architectural $18.29 $22.19
Base Bldg MEP $7.73 $7.25 Base Bldg MEP $4.75 $4.46
GC's and GR's & Fee $2.97 $1.90 GC's and GR's & Fee $2.81 $2.62
NOTES:
1. Medium (476,400 RSF)
2. Large (901,000 RSF)
3. All costs in USD; conversions made using 2022 rates
PITTSBURGH PORTLAND
Medium Large Medium Large
Base Bldg Structural & Enclosure $37.95 $35.32 Base Bldg Structural & Enclosure $56.05 $52.58
Base Bldg Architectural $6.12 $6.37 Base Bldg Architectural $6.14 $8.12
Base Bldg MEP $7.85 $7.53 Base Bldg MEP $6.89 $6.23
GC's and GR's & Fee $3.02 $1.98 GC's and GR's & Fee $9.01 $7.57
Base Bldg Structural & Enclosure $40.47 $32.31 Base Bldg Structural & Enclosure $58.66 $54.48
Base Bldg Architectural $18.29 $22.19 Base Bldg Architectural $5.02 $6.28
Base Bldg MEP $4.75 $4.46 Base Bldg MEP $6.50 $5.23
GC's and GR's & Fee $2.81 $2.62 GC's and GR's & Fee $8.99 $7.42
Base Bldg Structural & Enclosure $57.93 $54.30 Base Bldg Structural & Enclosure $41.63 $37.75
Base Bldg Architectural $5.05 $6.30 Base Bldg Architectural $4.77 $5.68
Base Bldg MEP $6.70 $5.36 Base Bldg MEP $6.61 $5.67
GC's and GR's & Fee $8.97 $7.42 GC's and GR's & Fee $5.15 $4.17
NOTES:
1. Medium (476,400 RSF)
2. Large (901,000 RSF)
3. All costs in USD; conversions made using 2022 rates
Base Bldg Structural & Enclosure $47.80 $43.13 Base Bldg Structural & Enclosure $41.95 $39.09
Base Bldg Architectural $6.08 $6.66 Base Bldg Architectural $8.24 $9.28
Base Bldg MEP $15.19 $15.19 Base Bldg MEP $7.97 $8.34
GC's and GR's & Fee $6.18 $5.39 GC's and GR's & Fee $16.45 $15.10
TORONTO VANCOUVER
Medium Large Medium Large
Base Bldg Structural & Enclosure $42.20 $37.20 Base Bldg Structural & Enclosure $41.18 $40.01
Base Bldg Architectural $5.31 $6.02 Base Bldg Architectural $8.20 $9.24
Base Bldg MEP $6.31 $5.54 Base Bldg MEP $7.97 $8.34
GC's and GR's & Fee $3.72 $2.94 GC's and GR's & Fee $13.54 $13.13
NOTES:
1. Medium (476,400 RSF)
2. Large (901,000 RSF)
3. All costs in USD; conversions made using 2022 rates
Base Bldg Structural & Enclosure $27.85 $27.85 Base Bldg Structural & Enclosure $27.85 $27.85
Base Bldg Architectural $7.30 $6.97 Base Bldg Architectural $7.30 $6.97
Base Bldg MEP $11.76 $11.76 Base Bldg MEP $11.76 $11.76
GC's and GR's & Fee $14.15 $14.15 GC's and GR's & Fee $14.15 $14.15
MONTERREY
Medium Large
NOTES:
1. Medium (476,400 RSF)
2. Large (901,000 RSF)
3. All costs in USD; conversions made using 2022 rates
AUTHORS
BRIAN UNGLES
Project & Development Services
Americas Leader
[email protected]
Cushman & Wakefield (NYSE: CWK) is a leading global real estate services firm that delivers
exceptional value for real estate occupiers and owners. Cushman & Wakefield is among the largest
real estate services firms with approximately 50,000 employees in over 400 offices and 60 countries.
In 2021, the firm had revenue of $9.4 billion across core services of property, facilities and project
management, leasing, capital markets, valuation and other services.