BACOSTMX - Module 2
BACOSTMX - Module 2
Required: Determine the amount of the fixed portion of indirect labor expense and the
variable rate for indirect labor expense, using the high and low points method. (Round the
variable rate to three decimal places and the fixed cost to the nearest whole dollar.)
Fixed cost: a = y – bx
Either you use highest or lowest point, you will arrive with the same answer.
1
Part II. Statistical Scatter-graph method
Dale Company management is interested in determining the fixed and variable components
of electricity expense, a semivariable cost, as measured against machine hours. Data for
the first eight months of the current year follow:
X Y
n Month Machine hours Electricity cost
1 January 4,500 650
2 February 4,750 600
3 March 5,000 750
4 April 5,500 700
5 May 7,250 900
6 June 7,500 800
7 July 6,750 825
8 August 5,250 725
Slope (electricity cost per machine hour based on least square method) 0.072062093
Roma 8:28