1. The document contains a 20 question multiple choice exam on statistical process control techniques like X-bar and R charts, I-MR charts, and ANOVA. 2. The questions cover topics such as determining whether a process is stable and ready for improvement, monitoring processes for large sample sizes, and statistical tests to compare means between two related groups. 3. Critical path analysis is also discussed as a project planning method to identify dependent tasks and set realistic deadlines.

Uploaded by

Hussein Mahmoud
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views4 pages

5th Lecture Exam

1. The document contains a 20 question multiple choice exam on statistical process control techniques like X-bar and R charts, I-MR charts, and ANOVA. 2. The questions cover topics such as determining whether a process is stable and ready for improvement, monitoring processes for large sample sizes, and statistical tests to compare means between two related groups. 3. Critical path analysis is also discussed as a project planning method to identify dependent tasks and set realistic deadlines.

Uploaded by

Hussein Mahmoud
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

1

5th lecture Exam


Green Belt

1. To effectively monitor any process, the initial phase the values are used to evaluate …….
A the process Mean and Standard Deviation
B the process Median
C the process Mode
D All of the above
2. During this control phase, we need to
A Monitor any points that moving out of control
B Identify the special cause for variation
C Try to eliminate those causes to make the process in control
D All of the above
3. Which of the following scenarios is best suited to use an X-bar and R chart?
A A smaller sample size is needed
B It is necessary to know when to investigate a process for causes of variation
C The machine capability is wider than the specification
D An acceptable quality level must be established
4. During this control phase generally good to collect data in subgroups, if possible, But sometimes
gathering subgroups of measurements isn't an option because …
A Measurements may be too expensive
B Production volume may be too low
C Products may have a long cycle time
D All of the above
5. The main use of I-MR chart is
A Monitoring the stability of a process
B Determining whether a process is stable and ready to be improved.
C Demonstrating improved process performance.
D All of the above
6. The distribution that follows principles of an exponential distribution is:
A Poisson
B Binomial
C Chi-Square
D Normal
1
2

7. …….. chart can alert you to changes that reveal a problem you should address.
A I-MR
B X-Bar and R-Charts
C X-bar and S chart
D NP Control Chart
8. …chart can confirm (or deny) the stability of your process before you implement a change. 
A I-MR
B X-Bar and R-Charts
C X-bar and S chart
D NP Control Chart
9. Which of the following distributions describes the ratios of two variances drawn from the same
normal population?
A F statistic
B Student's t-test
C Chi-square
D Normal
10. …… charts can provide that proof of process improvement.
A I-MR
B X-Bar and R-Charts
C X-bar and S chart
D NP Control Chart
11. …… used to monitor processes for Large Sample Size
A I-MR
B X-Bar and R-Charts
C X-bar and S chart
D NP Control Chart
12. Which of these are not Multivariate analysis?
A Factor analysis
B MANOVA
C ANOVA
D Cluster analysis

2
3

13. …… used with data collected in subgroups that are the same size
A I-MR
B X-Bar and R-Charts
C X-bar and S chart
D C Control Chart
14. The distribution that follows principles of Coin Flip Distribution is:
A Poisson
B Binomial
C Bernoulli
D Normal
15. Which is true about critical path?
A Zero slack
B Event oriented
C Shortest path
D Time and cost not considered
16. ANOVA analysis is the analysis of variation in ….
A mean
B median
C mode
D All of the above
17. Some activities cannot start until others are finished. Inevitably, that presents the risk of..
A Effectiveness
B bottleneck
C Efficiency
D All of the above
18. Which of the following statistical tests should be used by the Green Belt for testing the means
between two inter-related groups?
A 2 Sample t assuming equal variances
B 2 Sample t assuming unequal variances
C Paired t-test
D z test

3
4

19. …… is a project planning method that focuses on identifying tasks that are depended on other
tasks for their timely completion.
A Improvement Process
B Incremental Improvement.
C Critical Path analysis (CPA)
D All of the above
20. …… used to set a realistic deadline for a project and to track its progress along the way
A Improvement Process
B Incremental Improvement.
C Critical Path analysis (CPA)
D All of the above

‫بالتوفيق‬