General Specifications
General Specifications
General Specifications
UPDATING
The BE Department or the document owner will issue updates to all registered holders of each “hard copy” of this document. The registered
holder will be responsible for updating the document by replacing pages or sections as instructed. Printed copies will automatically assume as
“unmaintained” status.
Copyright Notice ©Copyright 2021
All rights reserved. This is the property of National Water Company “NWC” The contents of this document, either in full or in part, are not allowed
to be copied in any form or used by anyone outside NWC unless specifically authorized in writing by the document owner of other authorized
representative of NWC.
History Page
Prepared
Issue Issue Reviewed By Owned By Endorsed Approved By
By
No. Date (Name) (Name) By (Name) (Name)
(Name)
Bander Alshammari
Khalid Alhusain
Table of Contents
Issue Page ........................................................................................................................... 2
History Page ........................................................................................................................ 3
1 INTRODUCTION....................................................................................................... 5
1.1 Purpose ..................................................................................................................... 5
1.2 Glossary (Definitions) ................................................................................................ 5
1.3 Ownership ................................................................................................................. 5
1.4 Applicability ............................................................................................................... 6
1.5 Maintenance of This Document ................................................................................ 6
1.6 Document Roles and Responsibilities / Authority Matrix ........................................... 6
2 General Specifications Index .................................................................................... 7
1. General Specifications
2. Typical Drawings
4. Design Manual
5. Technical Specifications
6. Design Guidelines
7. Design Models
This document describes the (General Specifications) part of the project . The general specifications
divisions and sections are prepared according to CSI (Construction Specifications Institute) standards .
This document covers the general specification part for water treatment, tanks and pumping station works.
The general specification covers the general requirements including but not limited to: basic specifications to
cover general requirements, project scope of works, administrative requirements, projects’ documentation,
quality control, security, quality control, temporary facilities, regulatory requirements, execution and closeout
requirements, O&M data, general commissioning, among other general requirements.
1.3 Ownership
This document is owned by BE department, all inquiries and matters relating to this document shall
be addressed to the said department.
All.
Prepare/
Maintain
Update/ Review Endorse Approve Publish
Register
Amend
Owner YES
Stakeholder YES
Business Excellence YES YES YES
XXXXXXX YES
PART 1 - GENERAL
1.1 SUMMARY
A. Contract Works
The Contract works comprises the Works [for [insert name of plant]
Water Treatment Plant, at [insert region name], in the Kingdom of
Saudi Arabia]
[The capacity of the water treatment plant is […] m³/d as treated product
water. The overall plant design is based on [insert technology type
conventional/desalination/…] treating raw water from [insert source of raw
water dam/well/etc…].
The proposed water treatment plant in [insert region name] shall comprise:
• Raw water storage tank;
• Disinfection;
• Influent metering and rapid mix;
• Coagulation [using alum and polymer (coagulant aid)/other/etc./…];
• Flocculation;
• Sedimentation [circular sedimentation tank/lamella/etc…];
• Filtration [pressure filtration/rapid dual media (sand/anthracite)/etc…];
• Cooling towers;
• Reverse Osmosis;
• Treated water storage tank;
• Treated water pumping station;
• […].
Other facilities included in the design of the plant are:
• Administrative and operation building;
• Laboratory;
• Guard room;
• Workshop and storage building;
• Chemical storage, preparation and dosing systems and buildings;
• Sludge Treatment system;
• Service water, sludge, drain, and irrigation networks;
• Fence and access gates;
• Electrical power distribution system;
• […].
[The Treated Water Maximum Permissible Values shall abide to the latest
applicable GCC STANDARDIZATION ORGANIZATION (GSO) Unbottled
drinking water. For parameters not mentioned under GSO Unbottled
drinking water, the Treated Water Maximum Permissible Values shall abide
to the latest applicable MEWA standards]
The Contractor shall as part of his duties undertake but without any
limitations, the following:
Submit all required hard and soft copies of the data sheets, technical
leaflets, calculation notes, detailed design/shop drawings,
manufacturers’ recommendations and other documents as required and
approved by the Engineer.
The location of the Works Site is [insert region name] and as shown on
Drawings.
1. 2 CONTRACT
B. The Specifications given in one section shall apply to other sections unless
otherwise stated.
E. The work to be performed under this Contract includes, but is not necessarily
limited to, the furnishing of all supervision, labor, materials, plant, supplies,
construction equipment and facilities, and all services and items necessary
for the execution and completion of the Works in a professional and
workmanlike manner and in accordance with the Contract Documents.
I. The Owner and the Engineer and any person authorized by them shall at all
times have access to the Works and to the Site and to all workshops, stores
and places associated with the Works.
A. During the construction of the Works the Contractor shall ensure that his
activities shall not interfere or cause any undue hindrance to works of other
Subcontractors assigned and approved by the Owner in performance of
their duties. The Contractor is required to coordinate his works and
cooperate with all other works carried out by others on or adjacent to the
site.
A. The Contractor shall maintain access to the Site at all times and he shall take
all necessary steps to ensure the safety of persons on the Site.
1. Following such approvals, all such areas shall also be designated and
treated as included within the definition of the word "Site".
C. Contractor shall be responsible for safeguarding all other work sites in the
vicinity of the Site.
1. Shall ascertain from the public utility authority positions of all existing
underground services.
3. Shall provide all necessary security elements and resources to protect the
Site and all persons required to be present at the Site.
4. Shall indemnify the Owner’s side against any risk or damage that may be
caused to persons or to works or to third party in relation to the Works of
this Contract, and shall provide all necessary insurance policies and
coverage to keep the side of the Owner free of any claim.
1. The Owner reserves the right to place and install any items of equipment,
etc., in completed or partially completed areas of the Works upon the
understanding that the exercising of such right will not substantially
interfere with the regular progress and completion of the Works.
1. The Owner reserves the right to occupy partially or totally any spaces or
areas of the completed Works prior to the substantial completion of the
whole of the Works, provided that such occupancy does not interfere or
hinder the completion of the remaining areas of the Works.
A. The Contractor shall coordinate with all local authorities and obtain all
necessary approvals from such authorities for the proper and safe execution
of the Works and shall coordinate with Owner’s Engineer in case any
assistance is needed (legal papers or introduction letters) from the Owner
for this purpose.
Health and Keep uniforms and PPE clean and in good condition and
Environment replace them semi-annually;
Provision of personal ID cards for all employees;
Provision of adequate loading and off-loading areas;
Development of emergency response plans for the site
particularly in case of fire or explosion;
Provision of on-site medical facility/first aid;
Provision of appropriate lighting during night-time works;
Implementation of speed limits for trucks entering and
exiting the site;
Implementation of nationally and internationally adopted
safety guidelines
The summary in Table 1 is a basic general requirement for EIA. The Contractor shall
follow all necessary [MEWA – GAMEP] requirements for EIA.
The summary in Table 2 is a basic general requirement for EIA. The Contractor shall
follow all necessary [MEWA – GAMEP] requirements for EIA.
C. Noise, Vibration, and Odors: Coordinate operations that may result in high
levels of noise and vibration, odors, or other disruption to Owner occupancy
with Owner.
1. 9 CLIMATIC CONDITIONS
A. Provide equipment, materials, tools, safety items, test equipment that will
be suitable for the climatic conditions experienced in […] region, Saudi
Arabia.
Design equipment to operate satisfactorily to its full capacity in the following
conditions:
1. Maximum ambient temperature […] oC and minimum […]oC.
2. Metal surfaces in direct sunlight can reach […] oC.
3. Maximum relative humidity is […] %.
4. Mean annual rainfall is about […] mm.
5. [Dust and sand storms occur frequently]. Wind velocity of […] km/hr.
shall be considered for all above ground structures.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. All work shall be performed under the observation of and in the presence of
the Owner assigned Engineer’s representative or his authorized delegates.
1. Approval of the Contractor’s supervisory staff does not waive the right of
the Engineer to withdraw that approval at any time thereafter as provided
for by the Conditions of Contract.
C. It is pointed out that the provision of the Contractor’s supervisory and office
staff submitted by the Contractor as detailed in his Tender, does not relieve
him in any way of his liability under the Contract to provide all the staff
necessary for the satisfactory completion, commissioning and maintenance
of the Works and within the dates stated in the Contract.
D. The Contractor shall provide to the Engineer for approval the names and
details of the experience, qualifications and previous appointments for the
Contractor’s supervisory staff including those of the Subcontractors who will
be allocated to the Project.
A. Contractor shall not use the Site for any purpose other than carrying out the
Works.
1. 4 ADVERTISING
A. The normal working hours of the Engineer’s Supervisory Staff shall be [8]
hours per day excluding Fridays and local public holidays. The Contractor
shall immediately advise the Engineer when Overtime work is unavoidable
or absolutely necessary in which case a written permission from the
Engineer will be given.
1. The Engineer will give the Contractor due notice of his intention to carry
out any inspections during the defects liability period.
2. The Contractor shall arrange for a responsible representative to be
present at the times and dates named by the Engineer.
3. The Contractor’s Representative shall render all necessary assistance
and take note of all matters and issues to which the Engineer directs his
attention.
The Contractor shall, as part of his duties and responsibilities, according to the
terms and requirements of the Contract undertake the following:
A. Provide and maintain during the execution of the Works all shoring, strutting,
needling and other supports as may be necessary to preserve the stability of
all roads utilities, plant and property that may be endangered or affected by
the Works.
A. Ensure that no damage beyond fair wear and tear is caused by site traffic to
existing roads and footpaths outside the site boundaries and adequately
maintain approaches to the Site.
B. Contractor shall immediately repair damages which are directly attributable
to his works on site work.
A. No overtime work shall be carried out except with prior approval of the
Engineer.
A. The Contractor shall file with the Engineer, the names, addresses, and
telephone numbers of representatives who can be contacted at any time, in
case of emergency.
A. The Contractor shall carry out the Works in such manner that existing
facilities, pipelines, etc. are kept operational, and where inevitable such
existing facilities are interfered with to the minimum extent.
B. In no case shall the Contractor interfere with the operation of existing facilities,
pipelines, cables etc., without first obtaining the permission of the Engineer
and the relevant Authority to which such facility pertains.
C. The Contractor shall request officially from the Owner all drawings for the
existing properties for his reference.
A. The Contractor will encounter existing services and activities during the
course of the construction of the Works. The Contractor shall refer to the
Specifications and coordinate with the Engineer and local authorities.
B. The Contractor must obtain his own information regarding the position of all
pipelines, electricity lines and other services affected by the Works.
1. The Engineer does not guarantee either the accuracy of the information
or the location of such services as shown on the Drawings.
2. No warranty must be implied as to the position, depth, size or gradient
thereof.
3. Obtain information from the relevant Authority for the existing and planned
services.
D. Before opening up the ground on or adjacent to the site for any purpose, the
Contractor must obtain information regarding the location of all surface and
underground services.
E. All locating work shall be carried out in advance of excavation work. The
Contractor shall be responsible for:
All costs for executing any geotechnical boreholes or trial holes or excavation
pits shall be deemed to be included in the Contractor’s rates for the relevant
item or items in the Bills of Quantities. The Contractor shall carry out locating
work in accordance with any special requirements of the service authority
concerned and in conformity with their rules and regulations.
The Contractor shall not be permitted to work in areas until all services in the
area concerned have been located, clearly demarcated and proper signage
used for identification of existing services. The Engineer shall have the right
to stop the work in any part of the Works where the Contractor fails to take
the necessary measures to uncover such services
I. Contractor shall, at all times during the progress of the works, afford facilities
to all Services Authorities for access to all or to any of their apparatus situated
in or adjacent to the Site, as may be necessary.
K. Payment for complying with the above is deemed to be included in the rates
in the Bill of Quantities.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
1.2 COORDINATION
A. General:
The Contractor shall be required, but without any limitation, to undertake
following activities, among others:
B. Administrative Procedures
a. Such administrative activities include, but are not limited to, the
following:
Preparation of schedules
Installation and removal of temporary facilities
Delivery and processing of submittals.
Progress meetings
Project Closeout activities.
C. Drawings
1.Contractor shall be responsible for and shall pay the extra cost, if any,
occasioned by any discrepancies, errors, or omissions in the Drawings
and other submittals furnished by him, whether they have been approved
by the Engineer or not.
D. Specifications
B. If the Engineer shall direct the Contractor to coordinate the Works with the
work of another contractor or contractors in a certain manner and if the
Engineer shall determine that the Contractor is failing so to coordinate the
Works with the work of another contractor or contractors :
1. The Owner shall have the right to withhold any payments due under the
Contract until the Engineer’s directions are complied with by the
Contractor; and
2. The Contractor shall indemnify the Owner for any and all claims or
damages and from any costs or damages to which the Owner may be
subjected or which the Owner may suffer or incur by reason of the
Contractor’s failure to comply promptly with the Engineer’s directions.
D. Should the Contractor sustain any damage through any act or omission of
any other contractor having a contract with the Owner or through any act or
omission of any sub-contractor of said other contractor, the Contractor shall
have no claim against the Owner for said damage.
E. Should any other contractor having or which shall have a contract with the
Owner sustain damage through any act or omission of the Contractor or
through any act or omission of a Sub-contractor, the Contractor shall
reimburse said other contractor for all said damages and shall indemnify and
hold the Owner harmless from all said claims.
PART 1 – GENERAL
1.1 SUMMARY
1. Pre-Construction Conference
2. Progress Meetings
3. Subcontractor’s Site Meetings
4. Pre-Installation Conference
5. Pre-Startup Conference
6. Post-Construction Conference
7. Minutes of Meetings
A. Held at the project site within 7 days after the Commencement Date.
a. Actual start and finish dates for activities completed during the
update period.
b. Remaining durations and percentage of completion for all activities
not completed.
c. Logic, activity duration and cost data for Variation Order work that
will be incorporated into the construction schedule.
d. Contractor’s proposed measures to recover lost time and place the
project back on schedule by increasing manpower, materials and
equipment resources and working extended hours, additional shifts,
etc.
C. The time and location of the progress meetings shall be as directed by the
Engineer. The Engineer or his designee shall chair the meetings.
E. The Contractor shall provide a corrective action plan for the agreed actions
in meetings.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
1. Construction Schedule
2. Updates and Revisions
3. Payment Applications
4. Requested Time Adjustment Schedule
5. Schedule of Off-Site Activities
6. Daily program
A. The required time to complete the Works is indicated in the Appendix to Bid
included in the Contract Documents.
B. Contractor shall schedule all project activities using critical path scheduling
techniques and update the schedule as specified. Unless otherwise
approved the schedule and all reports shall be based on Primavera Project
Planner, latest version.
1. Adjustments shall account for events which include but are not limited to
the following:
a. Schedule slippages.
b. Delays.
c. Sequence changes necessitated by project conditions.
d. Labor inefficiency.
A. Submit Construction Schedule to the Engineer for approval within the period
stated under the Conditions of Contract.
1. The Engineer will review the schedule but will not be responsible for
whether the schedule will result in timely project completion.
G. The Construction Schedule shall be such that work included under this
Contract does not affect or unduly interfere with work being undertaken by
the Owner or another contractor.
1. Labor resources.
2. Equipment resources.
3. Quantities placed.
4. Work shifts (e.g. single, double, or triple shifts)
5. Work weeks (5, 6, or 7 day work week)
6. Production rates.
B. Progress Reports
6. Updates and revisions to required schedules and reports shall not modify
or limit in any way, the Contractor’s obligations to meet the Time for
Completion.
A. Contractor shall submit to the Engineer at the end of each calendar month
or as otherwise agreed, an approximate valuation of the total work done with
items set out in full, in accordance with the Conditions of Contract and as
specified in the BOQ.
B. Include schedule forecasts that predict the actual project completion date
and which forecast milestone achievement dates with the request for time
adjustment.
D. The Engineer shall not be obligated to consider any time extension request
unless all specified contract requirements are met.
E. “Float” or “slack time” is defined as the amount of time between the early
start date and the late start date or between the early finish date and the
late finish date of any activity in the Construction Schedule.
F. Variation Orders
1. If a milestone or completion date is modified by a variation order issued
by the Engineer, the Contractor shall modify his Construction Schedule
accordingly.
2. All activities impacted by the variation order shall be adjusted to reflect
the revised requirements.
H. Contractor shall make the following available to the Engineer within seven
(7) calendar days of receiving a written request.
1. All documents, data, etc. which support or provide the basis for
schedules, reports, and project forecasts.
2. Subcontractor documents and data.
B. The “Off Site Activities Schedule” shall include but not necessarily be limited
to:
D. Notify the Engineer in writing whenever it is anticipated that the delivery date
of any material or equipment will be later than shown on the latest approved
Construction Schedule. Include Contractor’s measures that will be taken to
avoid delay.
B. The format of the daily program shall be agreed with the Engineer.
END OF SECTION
PART 1 – GENERAL
1.1 SUMMARY
1.3 DEFINITIONS
A. Shop Drawings
1. Shop drawings include drawings, diagrams, illustrations, brochures,
schedules, bills of materials, and other data prepared specifically for
the Work.
2. Shop drawings may be prepared by the Contractor, Subcontractors,
suppliers or distributors, product manufacturer, or fabricators.
B. Product Data
1. Product data is general information which illustrates or describes
manufacture, fabrication, testing, and installation of the Work or a
portion thereof.
2. Product data may only be prepared by the manufacturer of the
products.
D. Working Drawings
1. Contractor prepared plans for temporary structures and facilities.
2. Elements of work which may affect the safety of persons or property
shall be certified by a qualified Engineer.
3. Calculations demonstrating adequacy of Contractor’s design shall be
submitted with the working drawings.
4. Follow submittal requirements for shop drawings.
E. Samples
1. Physical examples illustrating materials, plant/equipment, or
workmanship for permanent Works.
2. Establish standards by which the Work will be judged.
2.3 SAMPLES
A. Samples shall be furnished as required by the individual specification
sections for approval by the Engineer.
B. If not included with a product submittal, samples shall be accompanied
by a transmittal form, unless otherwise accepted by the Engineer.
C. Unless otherwise specified, samples shall be labeled as follows:
1. Corresponding Submittal No.
2. Date Submitted
3. Contract or Project Identification Number
4. Contractor Subcontractors
5. Product Description
6. Product Identification (Trade Name if applicable)
7. Supplier / Manufacturer
8. Specification section and applicable paragraph numbers
9. Intended Application
D. Three sets of samples shall be submitted, unless otherwise specified or
approved by the Engineer.
1. One set of approved samples and all disapproved samples will be
returned to the Contractor.
2. If requested in writing by the Contractor, samples of value will be
returned to the Contractor after completion of the Work.
3. Approved samples returned to the Contractor may only be
incorporated into the work upon written approval of the Engineer.
A. The Contractor shall supply as a part of the Contract all spares identified
in the Specifications.
B. The Contractor shall supply spare parts required for […] years of
operation after turnover, in accordance with the manufacturer’s
recommendations. The spare parts required for […] of operation after
turnover shall be inclusive of the spare parts that are specifically
identified in the Specifications.
C. The spares shall be boxed or packaged separately for long term storage.
The spares shall be plainly marked for reordering.
E. The Contractor shall provide special tools, special tool lists, equipment,
and accessories required to install or maintain the equipment.
A. Only the Contractor shall make submittals to the Engineer and all
submittals, including the work of Subcontractors and Suppliers, shall be
through the Engineer.
1. All submittals shall be in English.
2. The Contractor shall review all submittals before delivery to the
Engineer to ensure compliance with Contract requirements. The
Contractor shall stamp each submittal as evidence of its approval of
the submittal. Submittal of materials to the Engineer will indicate that
the Contractor has verified all materials, field measurements, field
construction criteria, and similar items and that the Contractor has
coordinated information contained in submittal with requirements of
other trades.
3. The following submittals shall be delivered to the Engineer in digital
format on compact disks (CDs), as appropriate, along with three hard
copies:
a. Final design drawings.
b. Product data.
c. Shop drawings.
d. Operations and maintenance manuals.
e. Products list and submittal schedule.
f. Work plans.
g. Health, safety and environmental plan.
h. Accident report.
i. Progress report.
j. Procurement status report.
k. Inspection and test reports.
l. Survey data.
m. Close-out submittals.
n. Record drawings.
o. Schedule of Values.
p. Letter of Authority.
q. Organization Chart.
r. Site layout for Contractor’s facilities.
s. Correspondence
t. Risk management and analysis report
4. The Engineer may request additional hard copies of any submittal by
notifying the Contractor in writing. Such additional copies shall be
provided by the Contractor at no additional cost to the Owner.
5. All digital media submitted to the Engineer shall be in Adobe Acrobat
(.pdf) format excluding the Final Design Drawings and Record
Drawing, which shall be submitted in AutoCAD (.dwg) format.
6. Drawing submittals shall be no larger than 600 mm high by 840 mm
wide.
7. Samples shall be submitted as described in the Contract Documents.
END OF SECTION
PART 1 – GENERAL
1.1 SUMMARY
A. This Section specifies the minimum safety and security measures to be
taken by the Contractor during all phases of the Contract.
1.3 REFERENCES
A. Safety requirements shall comply with the Contractor’s Health, Safety
and Environmental (HSE) Manual.
B. Safety requirements shall comply with the directives of Safety and fire
protection directives for industrial facilities – Kingdom of Saudi Arabia,
Ministry of Interior – High Commission for Industrial Security –
Secretariat General – latest edition (SAF).
C. Security requirements shall comply with the directives of Security
directives for industrial facilities – Kingdom of Saudi Arabia, Ministry of
Interior – High Commission for Industrial Security – Secretariat General
– latest edition (SEC).
1.5 SUBMITTALS
A. The Contractor shall not begin work at the site until the HSEP has been
approved by the Engineer. The HSEP shall describe all of the
Contractor’s safety personnel, precautions and other safety documents
that will be used throughout the project.
PART 2 – PRODUCTS
PART 3 – EXECUTION
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. The Contractor shall comply with all specified codes and standards, and
requirements of regulatory agencies having jurisdiction over this project
including, but not limited to, those specified herein.
B. There may be items for which there are no relative codes, specifications or
standards.
C. Pipe Color Coding should be applied for project different pipes, where
applicable based on piping material. And necessary pipe works tagging shall
be applied to all pipe works.
A. The Contractor shall carry out the works in accordance with current
regulations, local and administrative orders, and requirements of the local and
service authorities.
B. The Contractor shall carry out the works in accordance with the directives of
Safety and fire protection directives for industrial facilities – Kingdom of Saudi
Arabia, Ministry of Interior – High Commission for Industrial Security –
Secretariat General – latest edition (SAF).
C. The Contractor shall carry out the works in accordance with the directives of
Security directives for industrial facilities – Kingdom of Saudi Arabia, Ministry
of Interior – High Commission for Industrial Security – Secretariat General –
latest edition (SEC).
1. Adjacent property.
2. Improvements.
3. Facilities.
1. Buildings
2. Roads
3. Culverts
4. Signs
5. Structures
6. Electric installations
7. Pipelines
8. Other improvements within or adjacent to the Contractor’s operations.
C. The Contractor shall provide and install suitable safeguards to protect all
objects under the above paragraph from injury or damage.
D. The Contractor shall not disturb any property corners or survey markers
without permission from the Engineer.
E. The Contractor shall be responsible for all damage to streets, utilities, roads,
highways, ditches, embankments, bridges, culverts or other public or private
property, which may be caused by transporting plant, equipment, materials,
or men to or from the Site of Works.
A. General
1.6 HOUSEKEEPING
A. Throughout the progress of his work, the Contractor shall keep the Site and
all working areas:
1. Be removed from the Site, but otherwise shall be dispersed about the
Site in an orderly fashion.
2. Shall be properly and securely stored thereon.
A. Before application is made for the Engineer to accept the work, all items of
work shall be complete, ready to operate and in a clean condition.
B. All trash, debris, unused building material and temporary structures shall
have been removed from the site of the work.
C. Tools and construction machinery not needed for repair and adjustment
consequent to operational tests shall not be on the Site.
D. Walkways, parking areas and roadways, streets and lanes pertaining to the
Works shall be completely cleaned.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. The Contractor shall comply with all codes, regulations, specifications and
standards referred to in the Contract Documents.
1.2 DEFINITIONS
A. Where "as shown", "as indicated", "as detailed", or words of similar import are
used, it shall be understood that reference to the Drawings accompanying the
Specifications is made unless otherwise stated.
B. Where "as approved", "as reviewed", "as accepted", or words of similar import
are used, it shall be understood that the approval, direction, requirement,
permission, authorization, review, or acceptance of the Engineer is intended,
unless otherwise stated.
END OF SECTION
PART 1 GENERAL
E. Where both a standard and a brand name are specified for a product
in Contract Documents, proprietary product named shall meet or exceed
requirements of specified reference standard.
Abbreviation Definition
AA Aluminum Association
AABC Associated Air Balance Council
AAMA Architectural Aluminum Manufacturers Association
AAN American Association of Nurserymen
AASHTO American Association of State Highways and Transportation Officials
ACI American Concrete Institute
ADC Air Diffuser Council
AFI Air Filter Institute
AFMA Anti-Friction Bearing Manufacturers Association
AGMA American Gear Manufacturers Association
AIMA Acoustical & Insulation Materials Association
ANSI American National Standards Institute
AMCA Air Moving & Control Association
AISI American Iron & Steel Institute
API American Petroleum Institute
ASCE American Society of Civil Engineers
ASHRAE American Society of Heating, Refrigeration and Air Conditioning
Engineers
ASME American Society of Mechanical Engineers
ASTM American Society for Testing and Materials
AWS American Welding Society
AWWA American Water Works Association
BS British Standards
BS CP British Standards Codes of Practice
BS EN British European Standards Specifications
BSI British Standards Institution
CCITT International Telephone and Telegraph Consultative Committee
1.3 UNITS
A. All units of weight and measurement shall utilize the Metric system of
Weights and Measurements based on the International System of Units
(SI System); except standard products which may be expressed in
nominal units of the Imperial System.
Main units which may be made reference to in the Contract Documents,
with their corresponding abbreviations used are listed in the next three
tables.
Prefix factors
Multiplication Factors Prefix Symbol
1 000 000 000 000 = 10^12 tera T
1 000 000 000 = 10^9 giga G
1 000 000 =10^6 mega M
1 000 =10^3 kilo k
100 = 10^2 hecto h
10 = 10^1 deka da
0.1 = 10^-1 deci d
0.01 = 10^-2 centi c
0.001 = 10^-3 milli m
0.000 001 = 10^-6 micro µ
0.000 000 001 = 10^-9 nano n
0.000 000 000 001 = 10^-12 pico p
0.000 000 000 000 001 = 10^-15 femto f
0.000 000 000 000 000 001 = 10^-18 atto a
Abbreviation Definition
A Aluminum
AA Activated Alumina
AC Activated Carbon
As Arsenic
Ca Calcium
CaCO3 Calcium Carbonate
Cl Chlorine
CO2 Carbon Dioxide
CO3 Carbonate - Carbon Trioxide
Cu Copper
DO Dissolved Oxygen
DOC Dissolved Organic Carbon
F Fluoride
GAC Granular Activated Carbon
H2 Hydrogen
H2S Hydrogen Sulfide
H2SO4 Sulfuric Acid
HCl Hydrochloric Acid
HCO3 Bicarbonate
K Potassium
Mg Magnesium
Mn Manganese
Na Sodium
NH3 Ammonia
NH4 Ammonium
NO2 Nitrite
NO3 Nitrate
PAC Powdered Activated Carbon
Abbreviation Definition
CS Carbon Steel
Cu Copper
DI Ductile Iron
FRP Fiber Reinforced Plastic
GLS Glass Lined Steel
GRP Glass Fiber Reinforced Plastic
HDPE High-Density Polyethylene
PP Polypropylene
PVC Polyvinyl Chloride
SS Stainless Steel
XLPE Cross linked Polyethylene
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section specifies the Quality Assurance/Quality Control (QA/QC)
activities that the Contractor shall perform during all phases of the
Contract, including:
1. General Quality Requirements.
2. Independent Inspection Services.
3. Independent Laboratory Services.
4. Contractor’s Quality Personnel.
5. Contractor’s Quality Plan.
6. Contractor’s Quality Control Procedures.
7. Contractor’s Method Statements.
8. Contractor’s Inspection and Test Plans.
9. Contractor’s Inspection and Test Records.
10. Contractor’s Inspection Request to Engineer.
11. Contractor’s Site Laboratory and Test Procedures.
12. Document and Submittal Control.
13. Material / Equipment Receipt and Storage.
14. Execution of Inspections and Tests.
15. Non-Conformance Monitoring.
16. Contractor’s Quality Assurance Audits.
17. Contractor’s Quality Records.
18. Workmanship.
B. The contractor should be ISO certified (for: quality, safety,
environmental, etc…). The Contractor may assign an independent third
party to control the (QA/QC) activities at the Contractor’s expenses.
1.3 REFERENCES
A. Inspection and testing shall comply with the following references, unless
stated otherwise in the Specification or unless otherwise approved by
the Contractor.
1. ASTM C1077 Practice for Laboratories Testing Concrete and
Concrete Aggregates for Use in Construction and
Criteria for Laboratory Evaluation.
2. ASTM D3740 Practice for Evaluation of Agencies Engaged in Testing
and/or Inspection of Soil and Rock as Used in
Engineering Design and Construction.
1.5 SUBMITTALS
A. The Contractor shall submit a Quality Organization Plan to the Engineer
no more than 15 days after the start of the Contract. The Quality
Organization Plan shall provide the name, qualifications, and experience
of the Organization of Contractor’s quality team and shall include the
following:
1. An organization chart identifying QA/QC personnel, showing that the
positions are independent of the job execution staff and that a clear
line of authority exists to the Contractor’s senior management.
2. A description of responsibilities and authority of each individual on
the QA/QC team.
B. The Contractor shall submit a Quality Assurance Plan no more than 30
calendar days after the start of the Contract. The Quality Plan shall
describe all of the Contractor’s quality control procedures, method
statements, inspection and test plans, and other quality documents that
will be used throughout the project. No work shall begin until the Quality
Plan has been approved.
C. The Quality Assurance Plan shall include a schedule of anticipated
submission dates for Quality Control Procedures, Laboratory
Procedures, Work Instructions, Method Statements, Inspection and Test
Plans, and Records.
The Quality Control Procedures, Laboratory Procedures, Work
Instructions, Method Statements, Inspection and Test Plans, and
Records shall be submitted no more than 30 calendar days before using
such documents. The Contractor shall not begin work governed by the
PART 3 - EXECUTION
3.1 GENERAL
A. The Contractor shall maintain sufficient QA/QC staff on site to implement
all aspects of the approved Quality Plan.
B. The Contractor shall provide all equipment, instruments, qualified
personnel and facilities necessary to inspect the Work and perform all
the tests required by the Contract Documents or provide independent
inspection agencies or laboratories to do the same.
C. The Contractor shall repeat tests and inspections after correcting non-
conforming work until all work complies with the requirements. All re-
testing and re-inspections shall be performed at no additional cost to the
Owner.
D. The Engineer may perform additional inspections and test at the place
of the manufacture or the shipping point to verify compliance with
applicable Specification requirements. Inspections and tests performed
by the Engineer shall not be considered a guarantee that materials
delivered at a later time will be acceptable. All costs associated with
unacceptable materials being delivered to the Site shall be borne by the
Contractor.
E. Inspections and tests conducted by persons or agencies other than the
Contractor shall no way relieve the Contractor of its responsibility and
obligation to meet all Specifications and referenced standards.
3.8 WORKMANSHIP
A. The Contractor shall comply with industry standards except when
Contract Documents indicate more rigid standards or more precise
workmanship is required.
B. All personnel shall be suitably qualified, trained and equipped to produce
workmanship of the required quality.
C. The Contractor shall comply with manufacturer’s published installation
instructions in full detail, including each step in sequence. Should
instructions conflict with Contract Documents, the Contractor shall
request clarification from the Engineer before proceeding.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
1.3 SUBMITTALS
A. Provide and maintain temporary and interim utility services necessary for
performance of the Work.
B. Install and maintain utilities to comply with applicable codes, safety and
services authorities’ requirements.
C. Connect to the service authority utility only on approval of the Engineer and
the concerned authority.
1.6 VENTILATION
1. Cure materials
2. Disperse humidity
3. Prevent accumulations of dust, fumes, vapors, or gases.
4. Maintain required conditions as necessary.
B. Provide and maintain bottled water, including dispensers for cooling the
delivered water, for Engineer’s site offices.
1.9 BARRIERS
B. Provide barriers around trees, plants and other areas designated by the
Engineer.
1.10 ENCLOSURES
C. Protect finished floors and stairs from traffic, movement of heavy objects,
and storage damage.
B. Contractor’s access for works within the area protected by security fence
shall be subject to the gate pass control and work permit procedures
required by the Engineer.
D. Allow for protection from rain storm and floods by taking appropriate control
measures.
A. Within 14 days of the date of the Letter of Acceptance, the Contractor shall
submit plans showing his proposed location and layout for:
B. Setup and layout shall be made with the general approval of the Engineer.
C. Site office shall be completed with all the equipment and furnishings by end
of the Mobilization Period but no later than 28 days after the
Commencement Date.
D The Engineer’s temporary site offices shall present a neat business like
appearance and shall be of substantial construction as approved by the
Engineer.
E Contractor shall provide one dedicated telephone line with the required
extensions and one dedicated line for facsimile facilities.
1. All telephone and facsimile charges within the country shall be paid by
the Contractor.
2. International call charges incurred by the Engineer shall be reimbursed
to the Contractor for the Owner.
F. Maintenance of the facilities shall also include the maintenance and routine
servicing of all electrical and electronic appliances.
G. All Engineer’s Site offices facilities, furnishings, equipment and related items
supplied by the Contractor shall be:
1. New;
2. Of approved quality and type.
3. Upon satisfactory Contract Completion, the facilities including furniture
and equipment shall be removed by the Contractor.
1. All car ports shall be properly and fully shaded and shall be for the
exclusive use of Engineer’s staff and visitors. Placards shall be provided
to identify each car port.
[At least […] office rooms (4m x 4m), […] toilets, […], Kitchen, […] car shades.
Resident Engineer: […] room
Offices for Engineers: […] rooms
Offices for Inspectors: […] rooms
Offices for QS: […] rooms
Offices for surveyors: […] rooms
Office for secretary & Doc. Controller: […] rooms
Store: […] rooms
Meeting Room: […] rooms
[…]
The fittings required for the rooms within the Engineer’s Site offices indicated in the
Schedule of Offices, shall be to the Engineer’s approval and are as follows:
Item Description:
7 Reference table
for drawings nr […]
20 Maximum-minimum
thermometer nr […]
22 Computer, as specified
hereinafter nr […]
24 Color Printer
with all
accessories nr […]
25 Scanjet with
PC interface and
accessories kit nr […]
26 Plotter nr […]
29 Digital Camera
(auto focus with
required range lens
and panoramic view
and date imprint facility) nr […]
30 Binding Machine
[…]
The Contractor shall provide and maintain in good condition at all times, the following
new survey equipment and materials during the continuance of the Contract for the
exclusive use of the Engineer and his staff:
O. Computer:
The Computer, Word Processor and Printer shall be supplied with approved
licensed software including network cabling, connectors and other miscellaneous
items required to put the system in operation, including dust covers, user’s manual
etc.
R. Plotter:
Plotter fit for purpose and approved by the Engineer
B. Submit drawings showing the proposed location and size of all shops,
storage areas, security fencing, stationary equipment, and similar facilities.
B. The Engineer shall notify the Contractor of any noncompliance and the
corrective action required.
1.23 HOARDING
A. Throughout the progress of his work, the Contractor shall keep the Site and
all working areas:
1. In tidy and workman-like condition,
2. Free from rubbish and waste materials.
B. All trash, debris, unused building material and temporary structures shall
have been removed from the site of the work to an approved tip.
C. Tools and construction machinery not needed for repair and adjustment
consequent to operational tests shall with the consent of the Engineer, be
removed from the Site.
B. Contractor shall not draw any water from a fresh water source or fire hydrant
for use on the work, without first obtaining permission from the relevant
Authority. The water source for site use shall be supplied by the Contractor
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
1.3 SUBMITTALS
B. Shop Drawings
1. Shop drawings for all areas requiring traffic regulation, even if such areas
are not shown on the contract drawings to include but not be limited to:
D. Temporary roads and access to the site shall include but not necessarily be
limited to:
1. Field surveys,
2. Construction and maintenance of paved and unpaved roads including
earthwork,
3. Providing and installing barriers, drainage, lighting, traffic signals, signs,
barricades, and other traffic control devices.
4. Drawings showing details of the proposed roads shall be submitted to
the Engineer for approval.
5. Temporary protection of existing utility services as required by the
Engineer.
6. Removal of roads and restoration of surfaces to their original condition
(or such other condition as directed or approved by the Engineer) when
the roads are no longer required.
B. Dust control shall be by watering using tanker trucks with spray attachments
or by other approved methods at no additional cost to the Owner.
PART 2 - PRODUCTS
A. All traffic control devices shall be approved by the Engineer before being
used on the Site.
1. After the initial use is complete, the Contractor may reuse any approved
items as the need arises.
B. All sign panels, barricades, drums, vertical panels and flagmen's paddles
shall be reflectorized.
C. Barricades shall be made of metal or plastic and shall collapse when tipped
over.
1. All cones shall be red and shall have a white reflectorized band.
2. Cones shall be capable of remaining upright during normal traffic flow
and wind conditions in the area where they are used.
A. Provide and maintain traffic control devices, both inside and outside the
Contract Limits, as needed to direct traffic and ensure vehicular and
pedestrian safety.
1. Remove or cover all warning signs except those required for public
safety during non-working hours or when construction in that area is
completed.
2. Cover signs with either metal or plywood sheets so that the entire sign
cannot be seen by on-coming traffic.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section covers the fabrication and installation of project
identification signs.
1.4 SUBMITTALS
A. Shop drawings showing at least the following details shall be submitted
in accordance with Section 01 33 00:
1. Content and layout details.
2. Structural and foundation details.
B. Samples of the proposed sign painter’s work shall be submitted for
approval in accordance with Section 01 33 00. Inferior quality work
shall be cause for rejection of the proposed sign painter
PART 3 - EXECUTION
3.1 ERECTION
A. The Contractor shall erect the project identification sign not later than
30 days after receiving notice to commence.
B. Signs shall be erected where shown on the Contract Drawings or as
approved by the Engineer.
END OF SECTION
PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
1.2 DEFINITIONS
B. Product Data: Collect information into a single submittal for each element
of construction and type of product or equipment.
1. Certificate of origin.
A. Deliver, store, and handle products using means and methods that will
prevent damage, deterioration, and loss, including theft. Comply with
manufacturer's written instructions.
C. Storage:
B. Warranty Requirements:
END OF SECTION 01 60 00
PART 1 - GENERAL
1.1 SUMMARY
1.3 DEFINITIONS
B. Time of Close-out
8. Dismantle and remove temporary facilities and services from the project
site.
a. This includes utilities, construction tools, buildings and facilities,
mockups, and similar elements.
9. Complete final cleaning.
10. Repair and restore exposed finishes which have been marred or
otherwise damaged.
11. Submit all spare parts, tools and maintenance equipment.
12. Submit an itemized list of all deviations and non-conformances to the
contract requirements.
a. Include a detailed plan to correct each deviation and non-
conformance.
B. Notify the Engineer that the facility or Works is ready for the substantial
completion inspection.
1. Include the itemized list of deviations and non-conformances in the
notification letter.
B. Notify the Engineer that the facility or Works is ready for the final inspection.
1. Include the itemized list of deviations and non-conformances in the
notification letter.
B. When Contractor considers work has reached final completion, submit the
following:
1. Certificate that:
a. Contract Documents have been reviewed.
b. Work has been inspected.
c. Work is complete and meets the requirements of the Contract
Documents.
2. Provide all submittals required by the Contract Documents.
3. Submit a final statement of accounting giving total adjusted contract
sum, previous payments, and the sum remaining due.
5. Note related variation order numbers as applicable, next to the mark up.
6. Submit documents with transmittal letter containing date, project title,
Contractor’s name and address, itemized list of documents, and the
Contractor’s signature.
A. Provide operating and maintenance data and instructions for all plant,
equipment and systems.
2. Index and present data in a three-ring side binder with durable plastic
cover.
3. Present data on A4 size paper.
4. Separate data by system and type.
1. Date when equipment is placed into full time operation for the Owner’s
benefit and with the Owner’s approval, or
1. Include itemized list of all items furnished, describing each item and
citing the appropriate specification section and paragraph.
2. Package each item for long term storage.
3. Mark or tag each item for easy identification.
4. Submit certificate confirming compliance with specified requirements.
1. Inventory items with the Engineer and store where directed by the
Engineer.
END OF SECTION
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes requirements and procedures for submission of
Operation and Maintenance Manuals (OMMs). Contractor shall provide
OMMs related to vendor-supplied items and shall cover all works equipment
and products including the following:
1. [Pumps]
2. [Motors]
3. [Anchor Crane]
4. [HVAC Equipment]
5. [Bar Screen Equipment]
6. [Flash mixing Equipment]
7. [Flocculator/Clarifier]
8. [Chemical Feed Equipment]
9. [Chlorinators]
10. [Filtration Equipment]
11. [Cooling Tower Equipment]
12. [Ultrafiltration Equipment]
13. [Reverse Osmosis Equipment]
14. [Disinfection Equipment]
15. [Compressors]
16. [Motor Control Centers]
17. [Instrumentation]
18. [Laboratory Equipment]
19. [Workshop Equipment]
20. […]
Additional items […] will be added to cover all the equipment of the
treatment units need for each Project to cover site specific conditions
and specific project requirements.
1.4 FORMAT
A. The Table of Contents shall provide the title of the Project; names,
addresses, and telephone numbers of the Engineer and Contractor,
including the names of responsible parties; schedule of products and
systems, indexed to content of the volume.
B. For each product or system, the Contractor shall list names, addresses
and telephone numbers of Subcontractor and suppliers, including local
source of supplies and replacement parts.
C. Product data shall be included, with each sheet marked to clearly identify
specific products and component parts, and data applicable to
installation. Inapplicable information shall be deleted.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Within this Section, the term Warranty and litigation in case of conflict, shall be
used to mean warranties of various types, equipment performance certifications,
and similar performance guarantees.
B. Within this Section, the term Product shall be used to mean equipment, systems,
products, components, and other similar aspects of the Work that have a
manufacturer’s or installer’s warranty.
END OF SECTION
PART 1 – GENERAL
1.1 SUMMARY
1.4 SUBMITTALS
A. All submittals shall be as specified in Section 01 33 00.
B. The Contractor shall submit the following:
1. Task and Skills Analysis: Identify the following:
a. Tasks requiring training.
PART 2 - PRODUCTS
2.1 MATERIALS
A. The Contractor shall provide all materials and supplies (including
consumables) necessary for training and demonstrations, special tools
required for training and demonstrations, and safety equipment required
by instructors.
3.1 TRAINING
A. The Contractor shall verify that the Engineer has accepted or approved
the required submittals.
B. The Contractor shall assemble instruction materials and set up
demonstration materials before the start of training.
C. The Contractor shall provide training including:
1. One day of classroom training for each system and part of the Work
before Taking-Over on each of the following: system operation,
system maintenance, and electrical and instrumentation.
2. One day of hands-on demonstration and operator training at the
installed equipment, after the manufacturer validates equipment
operation.
D. The Contractor shall prepare a training evaluation for each attending
trainee.
E. The Contractor shall evaluate trainees understanding of course material,
conduct a written test at the end of each training segment, grade the
tests, and evaluate fulfillment of course objectives.
F. The Engineer will evaluate the Contractor’s training methods, teaching
techniques, and trainer qualifications. Unacceptable training shall be
repeated at the Subcontractor’s cost.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Commissioning work shall ensure that all equipment and systems have been
completely and properly installed, tested, function together correctly to meet the
design intent, and to document system performance parameters for fine-tuning
of control sequences and operating procedures. The commissioning process
shall provide system documentation, equipment start-up, system calibration,
testing, training, verification and performance testing.
B. The Contractor shall coordinate and direct each step of the commissioning
process. The commissioning team shall be made up of representatives from the
Contractor, sub-Contractors, professionals, major equipment suppliers, and
construction trades.
C. System installation, start-up, testing, balancing, preparation of operation and
maintenance manuals, and operator training are the responsibility of each Sub-
Contractor, with coordination, observation, verification and commissioning the
responsibility of the Contractor. The commissioning process does not relieve the
Sub-Contractors or the Contractor from the obligations to complete all portion of
work in a satisfactory and fully operational manner.
PART - 2 PRODUCTS
PART - 3 EXECUTION
3.1 GENERAL
A. A pre-construction meeting of all commissioning team members shall be held at
a time and place designated by the Engineer. The purpose shall be to familiarize
all parties with the commissioning process, and to ensure that the responsibilities
of each party are clearly understood.
B. The Contractor shall complete all phases of work so the systems can be started,
tested, balanced and acceptance procedures undertaken. This includes the
complete installation of all equipment, materials, software, controls, etc. per the
contract documents and related directives, clarifications, and change orders.
If the deadline(s) pass without resolution of the problem, The Owner reserves the
right to obtain supplementary services and/or equipment to resolve the problem.
Costs incurred to solve the problems in an expeditious manner shall be the
Contractor’s responsibility.
END OF SECTION
PART 1 GENERAL
1.1 SUMMARY
A. The works covered under this contract include the supply, installation,
testing, adjusting and putting into operation systems, components of
systems, and individual items of equipment, and work related thereto, in
accordance with the project Tender Documents. Products not mentioned
but obviously necessary for the completion of those Works shall be
provided.
E. Fire standpipe shall not be used in any way to provide water for other
purposes.
H. All local alarms shall be linked with the electrical fire control panel as
shown on drawings and or specified in such a way that whenever any local
alarm is initiated, a corresponding pilot and alarm shall be actuated on the
main fire control panel to indicate occurrence of fire in the particular zone.
1.4 APPLICATION
A. The manufacturers of all materials and equipment must have at least ten
years of experience in the design and manufacture of their products.
1.6 APPROVALS
A. The Drawings are based on design and include general layouts and typical
details of various systems to be installed. The Contractor shall make the
installations in a workmanlike manner to conform to the structure, to avoid
obstructions, to preserve head room, and to keep openings and passage
ways clear without additional instruction and without additional cost to the
owner.
A. The Contractor shall submit Shop Drawings showing the exact routing and
locations of all the piping, ducting, equipment, etc., all in their respective
locations and according to the dimensions of the approved manufacturer.
Shop Drawings scale shall be 1/10, 1/20, 1/50 and 1/100 as applicable and
as approved by the Engineer.
E. All materials shall be supplied from the main factories in the country of
origin of the manufacturer. Any deviation from this, like supplying
equipment assembled in another different country under a license or
another name is not accepted unless approved by the Engineer.
1.10 ABBREVIATIONS
PART 2 - PRODUCTS
NOT USED
PART 3 EXECUTION
3.2 TESTS
D. All defective work shall be promptly repaired or replaced and the tests shall
be repeated until the particular system and component parts thereof receive
the approval of the Engineer and authorities having jurisdiction, and at no
additional cost to the Owner.
3.4 PERMITS
A. The Contractor shall obtain and pay for all necessary permits, inspections
and tests, for the proper installation of his work, as may be required by the
various administrative authorities having jurisdiction.
C. After the pipe lines have been tested and approved, backfill shall be
compacted thoroughly by hand tampers below center lines of pipes and to
at least 300mm above it. No backfill shall be placed in such a manner as
to cause damage or misalignment to the pipes or protective coating if used.
Backfill material under such conditions shall be earth or gravel above the
top of piping and hubs.
END OF SECTION
PART 1 GENERAL
1.1 SUMMARY
A. The works covered under this contract include the supply, installation,
testing, adjusting and putting into operation systems, components of
systems, and individual items of equipment, and work related thereto, in
accordance with the project Tender Documents. Products not mentioned
but obviously necessary for the completion of those Works shall be
provided.
C. The following electrical works and materials for the mechanical equipment
shall be supplied and installed under the electrical part of this contract.
4. Empty conduits with pull wires for all cables and wires classified under
the mechanical scope of works.
5. Control outlet boxes for all control equipment classified under the
mechanical scope of works.
1.3 APPLICATION
B. The manufacturers of all materials and equipment must have at least ten
years of experience in the design and manufacture of their products.
A. The plumbing works including all related systems shall comply with the
latest applicable codes and standards of the following:
A. The Drawings are based on design and include general layouts and typical
details of various systems to be installed. The Contractor shall make the
installations in a workmanlike manner to conform to the structure, to avoid
obstructions, to preserve head room, and to keep openings and passage
ways clear without additional instruction and without additional cost to the
owner.
B. The Contractor shall submit catalog cuts and brochures of products with
reference to proper paragraph in specifications. All submittals shall be
bound in one Booklet.
C. All materials shall be supplied from the main factories in the country of
origin of the manufacturer. Any deviation from this, like supplying
equipment assembled in another different country under a license or
another name is not accepted unless approved by the Engineer.
A. The Contractor shall furnish and submit to the Engineer in electronic and
hard copy triplicate bound, A4 size, Instruction Manuals containing the
following material;
B. Brief description of each system and its service and basic operation
features.
K. All items shall be available at least four weeks prior to the substantial
completion date.
1.12 Workmanship
PART 2 PRODUCTS
(NOT USED)
PART 3 EXECUTION
3.2 TESTS
G. Tests to be performed shall include but will not be limited to the following:
1. Noise and vibration isolation test
2. Insulation test
3. Sanitary drainage test
4. Pump tests
5. Noise and vibration measurement
6. Water heaters
7. Area storm drainage
8. Domestic water supply test
3.5 PERMITS
A. The Contractor shall obtain and pay for all necessary permits, inspections
and tests, for the proper installation of his work, as may be required by the
various administrative authorities having jurisdiction.
A. All trench bottom grading required for plumbing work shall be done under
the requirements of this section of the Specifications. The bottom of all
trenches shall be trimmed by hand method to receive pipes at their
respective finish levels. Trenches shall not be excavated below grade by
machine.
B. After the pipe lines have been tested and approved, backfill shall be
compacted thoroughly by hand tampers below center lines of pipes and to
at least 300mm above it. No backfill shall be placed in such a manner as
to cause damage or misalignment to the pipes or protective coating if used.
Backfill material under such conditions shall be earth or gravel above the
top of piping and hubs.
END OF SECTION
PART 1 GENERAL
1.1 SUMMARY
A. The works covered under this contract include supply, installation, testing,
adjusting and putting into operation systems, components of systems, and
individual items of equipment, and work related thereto, in accordance with
the project Tender Documents. Products not mentioned but obviously
necessary for the completion of those works shall be provided such as, but
are not limited to the following:
1. Requirements of fire dampers wherever duct crossing firewall.
2. System air balancing and associated requirements to do the balancing
3. Insulation of valves and valve boxes.
4. Maintaining the noise levels as specified
5. Steel platforms (fly over) above services in plant rooms and roof.
6. Chemical dosing and flushing of heating water system to the
satisfaction of the Engineer.
9. Power supply to disconnect switches when the switches are built-in the
equipment.
10. Empty conduits with pull wires for all cables and wires classified under
the mechanical scope of works.
11. Control outlet boxes for all control equipment classified under the
mechanical scope of works.
13. Power cables and conduits from central control panel to the various
equipment controlled from the same panel, such as exhaust fans, supply
air fans, etc..
A. The manufacturer's of all materials and equipment must have at least ten
years of experience in the design and manufacture of their products.
A. In addition to the mentioned above, the works shown herein after shall be
applicable along with the requirements of the related divisions and sections.
A. The Drawings are based on design and include general layouts and typical
details of various systems to be installed. The Contractor shall make the
installations in a workmanlike manner to conform to the structure, to avoid
obstructions, to preserve head room, and to keep openings and passage
ways clear without additional instruction and without additional cost to the
owner.
A. The Contractor shall submit Shop Drawings showing the exact routing and
locations of all the piping, ducting, equipment, etc., all in their respective
locations and according to the dimensions of the approved manufacturer.
Shop Drawings scale shall be 1/10, 1/20, 1/50 and 1/100 as applicable and
as approved by the Engineer.
B. The Contractor shall submit catalogue cuts and brochures of products with
reference to proper paragraph in specifications. All submittals shall be
binded in one Booklet.
E. All materials shall be supplied from the main factories in the country of
origin of the manufacturer. Any deviation from this, like supplying
equipment assembled in another different country under a license or
another name is not accepted unless approved by the Engineer.
A. The Contractor shall furnish and submit to the Engineer in electronic and
hard copy triplicate bound, A4 size, Instruction Manuals containing the
following material:
B. Brief description of each system and its service and basic operation
features.
J. The Contractor shall furnish all the foregoing to the Engineer for his review
as to the fulfilment of the specified requirements.
K. All items shall be available at least four weeks prior to the substantial
completion date.
1.12 ABBREVIATIONS
1.13 WORKMANSHIP
(NOT USED)
PART 3 EXECUTION
3.2 TESTS
D. All defective work shall be promptly repaired or replaced and the tests shall
be repeated until the particular system and component parts thereof
receive the approval of the Engineer and authorities having jurisdiction,
and at no additional cost to the Owner.
3.5 PERMITS
A. The Contractor shall obtain and pay for all necessary permits, inspections
and tests, for the proper installation of his work, as may be required by the
various administrative authorities having jurisdiction.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
B. SEC SUPPLY
Incoming Power Supply and Connection which will be provided by Saudi Electricity
Company (SEC) shall consist of MV […] kV power supply from SEC.
It shall be the full responsibility of the Contractor to coordinate with SEC, for the
existing nearest tie-in manhole of MV network in order to ensure all necessary
electrical connection between SEC, MV network and the transformer room of the
project. No variation order shall be accepted with respect to interface with SEC
after contract award.
Medium voltage switchgear and MV/LV dry type transformers shall be in conformity
with relevant European IEC Standards in order to be compatible with prevailing
voltage frequency (cycle) and available SEC grid supply network.
C. TELEPHONE PUBLIC EXCHANGE LINES will be connected the premises by the SAUDI.
Contractor shall do necessary follow up with local Authority and secure the
required approvals for the telephone system.
All electrical work from and including motor control centers/panels to and including
motors and other electrically operated equipment, which is included in the
Specification for Mechanical Work or other work, does not form part of the Electrical
Work, unless otherwise noted.
Unless otherwise noted on drawings the Motor Control Centers / Panels of the
following Mechanical System Motors are included in the Electrical works.
Unless otherwise noted on drawings the following motor control panels / centers
are not included in Electrical works, but their incoming and outgoing feeders are
included in Electrical works.
1. All pumps
2. All VFDS
E. CONTRACTOR will undertake detailed design of the systems that are specified in the
form of "performance specifications" in accordance with the criteria stated in the
Specifications and as shown on the Drawings. Detailed design drawings / shop
drawings / as built drawings design will be submitted for approval. Contractor will
also undertake all necessary coordination with relevant authorities having
jurisdiction prior to completing the design.
A. INSTALLATION GENERALLY:
Carry out electrical work in accordance with the Drawings, Specification and
Regulations, ensuring compliance with design and performance requirements,
to provide safe and protected systems with equipment readily accessible for
operation, maintenance and repair. Installations are to be complete, ready for
operation and fully integrated and coordinated with all other work.
C. POWER SUPPLY: liaise with the SEC to confirm and execute as required by
SEC.
Space requirements and associated builders work (Civil) and MEP for the
Authority's installations.
D. TELEPHONE PUBLIC EXCHANGE LINES: liaise with the Local MPT Authority to
confirm location of connection of public telephone exchange lines into the
premises.
1. REGULATIONS: Carry out electrical work in accordance with the current issue
of the local codes of practice the IEC 60304, where not in contradiction with
the local codes of practice and regulations, herein referred to collectively as
'the Regulations'.
Local standards, such as, but not limited to, SASO (Saudi Arabia Standards
Organization) where enforced and relevant, are to have precedence over the
Standards.
C. WIRING LAYOUTS shown on the Drawings for work not included in the Electrical
Work, such as motor control centers/panels, cables to motors and other similar
electrically operated equipment are shown for convenience and reference only.
I. SPARE PARTS: not later than the date of substantial completion, provide spare
parts required by the Specification, together with suitable means of identifying,
storing and securing same.
J. TOOLS AND INSTRUMENTS: not later than the date of substantial completion,
provide sets of tools and instruments required by the Specification, together with
suitable means of identifying, storing and securing same.
K. LABEL AND IDENTIFY all equipment, instruments, control and electrical devices
etc. to indicate duty, service or function, to the satisfaction of the Engineer.
Labels are to be laminated plastic or anodized aluminum discs with black
surface and white core with incised lettering in Arabic & English. Alternative
methods of labeling may be submitted for approval. Fix labels with non-
M. FIREPROOFING: Where cables, cable trays, bus ducts or conduits pass through
floors and fire rated walls, pack space between wiring and sleeve full with
materials and seal with approved caulking compound.
1.6 SUBMISSION:
D. SHOP AND CONSTRUCTION DRAWINGS are to demonstrate to the Engineer that the
design requirements are understood by indicating all equipment and material
proposed to be supplied and installed and by detailing fabrication and installation
methods proposed to be used. Shop and construction drawings are to clearly
state the name and location of the work, the names of the Engineer and
Contractor, submission date, cross- references to the Drawings and
Specification and the specific reference number, location, service and function
of each item.
H. TEST CERTIFICATES AND REPORTS: submit manufacturers type and routine test
certificates and reports for equipment and devices. Complete test results are to
be submitted in clearly identified and organized booklets, indicating item of
equipment, make, model, type, date of tests, type of tests, descriptions and
procedures. Include in the test reports the Quality Assurance Certification, the
standards to which the equipment comply, and the standards to which the
equipment was tested.
J. SPARE PARTS SCHEDULES: submit with the Tender itemized schedules of spare
parts to be provided, as required by the Specification, and state against each
item the manufacturer's unit price including packaging and delivery to site.
E. INDICATOR LIGHTS other than LV pilot lamps are to be light emitting diodes
(LEDs).
K. POWER SUPPLY UNITS: for low current systems which are fed from the LV
supply are to be independently fused on the live conductor and are to have
front panel mains indicator light, on/off switch and standard cartridge type fuse
holder. Blown fuse indicator lamp is to be provided when fuse does not have
an indicator.
A. Tests on Site:
1. Carry out inspection and acceptance tests on site on each complete system,
before final placement into service, in accordance with the Regulations and
Standards, as described in the Specification and required by the Engineer.
2. TEST SCHEDULES AND PROCEDURES are to be submitted for approval and are
to include details of testing equipment to be provided.
3. WITNESSING: inspection and acceptance tests are to be carried out in the
presence of the Engineer, and when required, by an authorized
representative of the Local Power Authority.
4. VISUAL INSPECTION: visually check proper installation, connections and
nameplate data before testing.
5. INSULATION RESISTANCE test the feeders, lighting and power circuits, motors
and other power equipment of low voltage installations with a megger of not
less than 500 V d.c. for installations rated up to 500 V (r.m.s. value of a.c.
supply) and 1000 V d.c. for installations rated above 500 V up to 1000 V. and
as required by the particular Section of the Specification.
6. INSULATION RESISTANCE: unless otherwise specified or approved, test the
circuit insulation resistance related to communications and security systems
with a megger of not less than 500 V operating voltage, with equipment
10. VOLTAGE CHECKS: perform voltage checks throughout the building and if
directed by the Engineer, adjust the transformer tap settings where a
transformer is provided on the supply end, or report to power authority for
adjustment necessary.
11. CURRENT CHECKS: In cooperation with the mechanical sub-contractor, take
clip-on ammeter readings on all phases of all mechanical equipment motors
with motors operating under full load conditions. Test readings shall be
submitted to the Engineer.
1.9 RECORDS
A. GENERALLY: not later than the date of substantial completion, provide the
Engineer with the required copies of all approved as-installed drawings, test
records, manufacturers' guarantees and warranties, operating and
maintenance manuals and other records required by the Specification.
1. Layout plans including all conduiting and wiring installations for all systems
2. All changes to the work during construction including corrections that are
made on floor plans and riser diagrams and detail drawings etc., as
applicable.
3. Exact dimensioned location of all services embedded in the structure
4. Invert of all services entering and leaving the building and at property lines.
5. Dimensions and elevations of underground services in relation to building
at key points of every run.
6. Riser diagrams for all systems
10. Manufacturers' lists of recommended spare parts for items subject to wear
and deterioration, giving expected running period and indicating specifically
those items, which may involve extended deliveries.
END OF SECTION
PART 1 – GENERAL
1.1 SUMMARY
1.3 DEFINITIONS
A. ATS: Acceptance Testing Specifications.
B. EPDM: Ethylene-propylene-diene monomer rubber.
C. NBR: Acrylonitrile-butadiene rubber.
1.4 SUBMITTALS.
A. Test Equipment Suitability and Calibration: Comply with NETA ATS, “Suitability
of Test Equipment” and “Test Instrument Calibration.
1.6 COORDINATION
C. Coordinate location of access panels and doors for electrical items that are behind
finished surfaces or otherwise concealed. Access doors and panels are specified
in Division 8 Section “Access Doors and Frames”.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. In other articles where titles below introduce lists, the following requirements
apply to product selection:
A. Steel Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40,
galvanized steel, plain ends.
C. Sleeves for Rectangular Openings: Galvanized sheet steel with minimum [0.052
– or 0.138] inch ([1.3-or 3.5] mm) thickness as indicated and of length to suit
application.
D. Coordinate sleeve selection and application with selection and application of fire-
stopping specified in Division 7 Section “Fire stopping”.
A. Description: Modular sealing device, designed for field assembly, to fill annular
space between sleeve and raceway or cable.
B. Measure indicated mounting heights to bottom of unit for suspended items and
to center of unit for wall-mounting items.
E. Right of Way: Give to raceways and piping systems installed at a required slope.
C. Concrete Slabs and Walls: Install sleeves for penetrations unless core-drilled
holes or formed openings are used. Install sleeves during erection of slabs and
walls.
I. Size pipe sleeves to provide [6.4] mm annular clear space between sleeve and
raceways or cable unless sleeve seal it to be installed.
J. Seal space outside of sleeves with grout for penetrations of concrete and masonry
(and with approved joint compound for gypsum board assemblies).
END OF SECTION
PART 1 GENERAL
1.1 SUMMARY
A. This Section specifies general requirements for the equipment supplied under
this Contract.
B. Equipment supplied under this Contract shall be new, shall not have been in
service at any time before delivery, except as required by tests, and shall fit to
the purpose.
E. The manufacturer shall ascertain to its satisfaction the actual conditions and
services under which the equipment will operate and shall warrant that
operation under those conditions will be successful. The materials, installation
and other services provided under this Contract shall be project specific and
shall provide solid, dependable services for the period of time specified
elsewhere in the Specification.
H. Drawings
1. The Drawings are diagrammatic and show the general layout of the
completed construction work.
2. Determine the location of equipment, inserts, anchors, motors, panels,
conduits, stub-ups, fittings, fixtures, air, water, power and process inlets to
suit field conditions and the equipment actually provided.
1.6 IDENTIFICATION
A. Provide all equipment with a data plate.
1. Fabricate from minimum 2 mm thick, Grade 316L stainless steel sheet.
2. Use permanent embossed or preprinted lettering in English and Arabic.
3. Use letters and numerals not smaller than 5 mm high.
4. Fasten to the frame using corrosion-resisting pins.
5. Identify, as a minimum, the following:
a. Manufacturer
b. Serial number
c. Model number
d. Type
e. Operating and performance data
f. Other pertinent data.
B Use name tags attached to the equipment or device where data plates cannot
be used.
1. Make tags approximately 40 mm by 75 mm in size with square corners.
2. Fabricate from minimum 2 mm thick, Grade 316L stainless steel sheet.
3. Engrave or etch letters and numerals in English and Arabic using a
professional engraver.
4. Use letters not smaller than 3 mm high in size.
5. Identify the name and equipment tag number as shown on the
Instrumentation Drawings.
6. Provide a 5 mm diameter hole in the upper left-hand corner of each name
tag
7. Attach the name tags to the equipment or item using a 3 mm stainless steel
cable.
B. Shop Drawings
1. Provide shop drawings for all equipment before fabrication or installation.
2. Submit certified equipment assembly drawings showing dimensions,
fabrication, foundation, fixing, parts identification and material, power drive
assembly and other devices and accessories forming complete equipment.
If equipment comes from a different source than the manufacturer’s works,
the Contractor shall give clear indication and references for the part
identification and vendor.
3. No equipment can be shipped before drawings approval.
C. The Contractor shall notify the Engineer in the event that any equipment or
material is damaged after receipt at the jobsite and before acceptance of the
installation by the Engineer.
1.10 WARRANTY
A. The Contractor shall comply with the requirements of Sections 01 33 00 and
01 78 23.
C. The Contractor shall furnish and replace all equipment and component parts
that are defective or show undue wear within the Defects Liability Period
unless extended periods of warranty for specific pieces of equipment are
specified elsewhere. This does not include expendable items.
E. Field Tests
1. Following completion of the installation and satisfactory start-up of the
equipment, the Contractor shall field test each equipment item to
demonstrate compliance with specified performance requirements.
a. A record of bearing and coupling clearances and alignments shall be
tabulated to show the "as-built" condition of each pump.
b. A record of all overload, timing relay and oil pressure relays shall be
tabulated to show the "as-built" condition of each motor starter.
c. All cables shall be "megger" tested to confirm the integrity of the
insulation. A tabulated record of results shall be made.
d. The control panel shall be statically tested with motors disconnected to
confirm the correct sequence of operation.
e. Each pump shall be operated individually over the range from closed
valve to maximum emergency top water level on a recirculation basis
using fresh water and for a minimum of four hours continuously. During
this test the following parameters will be recorded: -
f. Motor current
i. Pump output
ii. Ambient and test water temperatures
iii. Bearing temperature shall be determined by a contact type
thermometer, or lubricant temperature may be measured.
iv. Vibration shall be tested using a vibration meter. The vibration of
the pump measured at any point on the pump and motor when
operating at full speed shall not exceed the amplitude allowed by
Hydraulic Institute Standard.
g. The field test trials shall extend until each pump unit has run
'continuously' for at least 3 days under all operating conditions. The
term 'continuously' shall include running at various speeds or on a
start/stop basis as determined by the control system.
2. The full speed vibration of all pumps shall be equal to or less than the
amplitude limits recommended in the Hydraulic Institute Standards and/or
the manufacturer's recommendation, whichever is more stringent.
3. Document each unit’s performance by obtaining concurrent readings
showing motor voltage and amperage, suction head and discharge head.
a. Readings shall be documented for at least three conditions to ascertain
the actual performance curve.
b. One test shall be at shutoff conditions.
c. Each power lead to the motor shall be checked for proper current
balance.
4. Determine bearing temperatures using a contact type thermometer.
Alternatively, lubricant temperature may be measured.
F. The test results submittal to the Engineer shall be checked against guaranteed
pump performance data provided by the pump Manufacturer. The test results
will be accepted, if the tolerances are within the limits set forth in [ISO 2548
Code, Class C].
G. The Contractor's supervisory staff shall be present during the period of the
tests and trials and the Contractor shall be responsible for any failure of the
whole plant or any part thereof, whether such failure shall be determined by
the methods detailed herein or otherwise. If the pump test or trial is interrupted
by the Contractor, or through negligence on the part of the Contractor's staff,
it shall be completely repeated for the pumpset concerned.
B. Checks shall be detailed and complete, requiring not less than 8 hours at the
site, and shall be performed under the observation and to the satisfaction of
the Engineer.
C. All costs for in-service checks shall be provided at no additional cost to the
Engineer.
PART 2 – PRODUCTS
A. Design and size all equipment parts to withstand all stresses that may occur
during fabrications, shipment, erection, and intermittent or continuous
operation.
B. Design, fabricate, and assemble all equipment in accordance with the best
modern engineering and shop practice.
1. Manufacture individual parts to standard sizes and gauges so that repair
parts, furnished at any time, can be installed in the field.
2. Make like parts of duplicate units interchangeable.
3. Materials shall be suitable for the service conditions.
4. All castings for equipment shall be free of blow and sand holes, cracks or
any defects. Any repairs, welds or corrections to castings will be conducted
only with consent of the Contractor and tested thereafter in a manner as
directed and witnessed by the Engineer.
A. Cover all belt or chain drives, fan blades, couplings, exposed shafts and other
moving or rotating parts on all sides by safety guards.
1. Conform to the requirements of BS 5304.
B Fabricate safety guards from either 1.5 mm or thicker, Type 316 stainless
sheet steel fabricator steel, GRP or combination of materials including
perforated steel sheet, wire mesh, etc. as per Engineer’s approval.
1. Design each guard for easy installation and removal.
2. Provide all necessary supports and accessories for each guard.
3. Use Type 316 stainless steel supports and accessories, including bolts.
4. Design all safety guards in outdoor locations to prevent the entrance of
blowing sand, rain and dripping water.
5. Provide openings for grease nipples where required.
C. Automatic Equipment
1. All equipment, except centrifugal pumps, which is under automatic control,
shall have a red warning label supplied and fixed alongside each access
point or point of physical danger.
2. The warning sign shall have an overall size not less than 200 mm x 150
mm and shall have red lettering on a black background.
3. Unless otherwise specified or agreed by the Engineer the legend shall be
in both English and Arabic as follows:
DANGER: THIS EQUIPMENT IS AUTOMATICALLY CONTROLLED
AND MAY START WITHOUT WARNING
4. When specified an audible warning shall sound for [20 seconds] before the
mechanism starts to operate. This delay shall be non-adjustable.
5. Guards and or handrails shall be provided to prevent accidental contact
with normally accessible moving parts.
A. The Contractor shall provide a heavy cast-iron or welded steel base for each
item of equipment to be installed on a concrete foundation.
1. Mount equipment assemblies, unless otherwise specified or shown on the
Drawings, on a single, heavy, cast-iron or welded steel bedplate.
2. Provide bases and bedplates with machined support pads, tapered dowels
for alignment of mating surfaces or adjacent items, adequate openings to
facilitate grouting, and openings for electrical conduits.
3. Continuously weld all seams and contact edges between steel plates and
shapes and grind smooth.
4. The plates shall have a minimum thickness of 6mm.
5. Include a drip lip and provision for directing accumulated gland leakage to
a single disposal drain point.
6. Provide concrete plinth for all equipment 100 mm above the finish floor
unless approved otherwise by the Engineer. Plinths shall have chamfered
B. Pipe all accumulated gland and seal water leakage and spent cooling water to
a floor drain provided by Contractor adjacent to each piece of equipment.
1. A single floor drain may be used for more than one piece of equipment
provided the equipment drain line does not create a safety or tripping
hazard.
2. If drain piping creates a hazard, provide an additional floor drain adjacent
to the equipment at no additional cost to the Engineer.
3. Drains shall be minimum 30 mm, weather protected uPVC where exposed
to sunlight.
4. Drain line shall be supported and anchored as necessary to prevent
movement and sloped to drain.
5. Where drain media is of high temperature, material shall be chlorinated
PVC or equivalent high temperature resistant material and insulated for
protection.
6. Fittings shall be drainage pattern type with clean outs at all 90° turns.
7. All cold drainage lines such as AC condensate drains shall be insulated
and protected from damage by traffic.
B. Equipment suppliers shall furnish anchor bolts, nuts, washers, and sleeves of
adequate design for proper anchorage of the bases and bedplates to the
concrete bases.
1. Sleeves shall be a minimum of 1.5 times the diameter of the anchor bolts.
2. Unless otherwise shown or specified, anchor bolts for items of equipment
mounted on baseplates shall be long enough to permit 25 mm of grout
beneath the baseplate and to provide a minimum of adequate anchorage
into structural concrete.
3. Anchor bolts, together with templates or setting drawings, shall be
delivered sufficiently early to permit setting the anchor bolts when the
structural concrete is placed.
4. Anchor bolts, nuts, washers and sleeves shall be Type [316L stainless
steel] conforming to ASTM A-167 and ASTM A-267.
5. Where anchor bolts and equipment bases are of different material provide
dielectric protection by coating of holes in the bases and insulating sleeves
and washers.
6. Anchor bolts shall extend through nuts a minimum of three threads but not
exceed 12 mm.
B. Electric Motors
1. All low voltage electric motors supplied under this Contract shall conform
to all requirements specified in Section 26 06 20.01. Additional or
superseding requisites for certain motors may be found elsewhere in this
Specification, and to a lesser extent, in other parts wherein electric motor
driven equipment is specified.
2. The Contractor shall coordinate the work of all trades, including the
functional, safety and Code requirements for each installation, in order to
comply with these Specifications.
C. V-Belt Drives
1. Where motors are mounted above the driven machine on a pedestal, belt
tensioning shall be accomplished using four studs which are double nutted
to the motor plate to raise and lower the motor plate. Hinges with a jacking
screw to tension the belts shall not be used.
2. Where motors are mounted horizontally adjacent to the driven equipment,
belt tensioning shall be accomplished using a sliding rail type motor mount,
with manual adjustment of motor location. Manual adjustment shall be
accomplished through a permanently mounted hand crank mechanism.
3. All V-belt tensioning devices shall be such that under no circumstances will
it be possible for any device, once set to the desired adjustment, to go out
of the adjustment due to the load being imposed upon the drive at that
setting. This requirement shall not be construed to mean that a set belt
tension may not go out of adjustment due to gradual stretching of belts, but
shall mean that no portion of any device or devices used to accomplish belt
tensioning may slip, become loose, or otherwise move from the desired set
point, once selected, except when manually reset by operating personnel
by use of the adjustment device or devices.
D. Gears
1. Provide oil-lubricated totally-enclosed gear reducers and increasers.
2. Service Ratings
a. Provide a nameplate service power rating equal to the nameplate rating
of the driving motor.
E. Bearings
1. Provide anti-friction bearings throughout.
2. Unless otherwise specified, select bearings to provide a minimum 50,000
hours B10 life for the specified load in continuous operation.
3. Select thrust bearings for loads of at least 1.5 times the maximum thrust
loadings anticipated.
2.6 LUBRICATION
B. Add the prescribed amount and type of lubricant as required by the equipment
manufacturer to each equipment item before testing and/or operation.
C. Provide a […] year supply of lubricants for each piece of equipment installed.
PART 3 – EXECUTION
3.1 COORDINATION
A. The Drawings are diagrammatic and generally show the desired arrangements
for principal apparatus, piping, and similar appurtenances.
1. Follow the Drawings as closely as possible.
2. Exercise proper judgment in carrying out the work to obtain the best
possible headroom and space conditions, to secure a neat arrangement
for piping, valves, fixtures, hangers, and similar appurtenances and to
overcome local difficulties and interferences wherever encountered.
B. The Contractor shall measure its work at the installation sites, verify all Lower
Tier Contractor drawings before submittal and be completely responsible for
properly installing equipment as shown on the Drawings and within the
available space.
C. The Contractor shall secure the Engineer’s approval for all variations and/or
substitutions before making any changes.
D. The Contractor shall coordinate all installation with all disciplines to prevent
interference.
A. The Contractor shall box, crate, or otherwise completely enclose and protect
all equipment during shipment, handling and storage.
1. Protect all equipment from exposure to the elements. Keep dry and clean
at all times.
2. Store pumps, blowers, motors, electrical equipment and other equipment
having anti-friction or sleeve bearings in weather tight storage facilities
such as warehouses. Turn shafts during storage as recommended in
writing by the equipment manufacturer to prevent “bearing set”.
3. Clean and restore all materials and equipment showing evidence of rust,
dirt contamination or other surface or subsurface deterioration to the
Engineer’s satisfaction before installation.
E. The Contractor shall store all equipment in approved storage facilities from
delivery until installation.
G. The Contractor shall provide continuous power supply and wiring to energize
any and all motor heaters to prevent moisture build up while in storage and in
installed location until such time as equipment is put in service.
I. All unpainted surfaces subject to corrosion shall be coated with rust inhibitor
and reapplied as necessary to protect the finish until equipment is put into
service.
3.3 INSTALLATION
A. The Contractor shall install all equipment in full accordance with the equipment
manufacturer's recommendations and good practice.
1. Where specified in other sections of this Specification, factory-trained
service personnel shall be on-site to supervise the installation.
2. Sufficient notice shall be given to the Engineer before equipment
installation in order that the Engineer or its representative may be present
during installation.
E. All costs for this work shall be included in the priced bid by the Contractor.
B. Surfaces to be painted at the project site shall be shop painted with one or
more coats of a primer which will adequately protect the equipment until
finishes are applied at the project site.
1. Primers shall be as specified in paint sections.
C. Machined and polished metallic surfaces which are not to be painted shall be
coated with a rust preventive compound as specified in paint sections.
3.5 COMMISSIONING
C. The Contractor shall notify the Engineer [fourteen (14)] calendar days in
advance of the time when the equipment will be placed into operation.
D. During the course of initial operation, the Contractor shall instruct the Owner
personnel in proper operation and maintenance of the equipment, as specified
herein.
B. The Contractor shall provide not less than [8] hours of instruction for each item
of equipment or set of identical pieces of equipment provided, unless
otherwise specified.
1. More days shall be provided if called for in the individual equipment
specifications.
2. Each manufacturer shall include this service in the price of its equipment.
END OF SECTION
General Specifications
UPDATING
The BE Department or the document owner will issue updates to all registered holders of each “hard copy” of this document. The registered
holder will be responsible for updating the document by replacing pages or sections as instructed. Printed copies will automatically assume as
“unmaintained” status.
Copyright Notice ©Copyright 2021
All rights reserved. This is the property of National Water Company “NWC” The contents of this document, either in full or in part, are not allowed
to be copied in any form or used by anyone outside NWC unless specifically authorized in writing by the document owner of other authorized
representative of NWC.
Issue Page
Prepared By
Name Signature Department/ Designation Date
Reviewed By
Name Signature Department Date
Owned By
Name Signature Department Date
Majed Mohamed
Technical Services General Manager
Alruwaili
Approved By
Name Signature Department Date
History Page
Prepared
Issue Issue Reviewed By Owned By Endorsed Approved By
By
No. Date (Name) (Name) By (Name) (Name)
(Name)
Bander Alshammari
Abdulhameed Alomar
Ahmed Awad
Alshehri Ahmed Saleem
Khalid Alhusain
Mohammed Alamoudi
Consultant
Team Farhan Alenezi
Abdullah Alanazi
Majed Almalki