Formwork
Formwork
Introduction
1
In-situ Reinforced Concrete Process
Lumber
Plywood sheet
Form Components
2
In-situ Reinforced Concrete Process
Ground level
Base form
3
In-situ Reinforced Concrete Process
Concreting
of base
Stump form
4
In-situ Reinforced Concrete Process
Concreting of
stump
Ground
beam form
10
5
In-situ Reinforced Concrete Process
Concreting of
ground beam
11
Column form
12
6
In-situ Reinforced Concrete Process
Concreting
of column
13
14
7
In-situ Reinforced Concrete Process
15
16
8
Basic requirements of
formwork
• Quality
• Safety
• Economy
17
Quality
• Accuracy
– Produce accurate shape, size and
alignment of structure
– Designer should specify allowable
dimensional tolerance
18
9
Quality
• Rigidity
– Resist any distortion during
concreting therefore formwork should
be supported, tied, braced
19
Quality
• Watertight joints
– loss of water, cement and fines affect
final strength of concrete
– affect appearance, honeycombs,
uneven colour
– Less rectification costs
20
10
Quality
• Good surface finish
– formwork surface in contact with
concrete should be even
– no screws, nails
– To achieve good surface application
apply mould oils called release agents
21
Safety
22
11
Safety
23
Safety
24
12
Safety
25
Safety
26
13
Economy
27
Economy
Reinforcemet: Labour
and equip (7%):material
(12%)
19%
28
14
Economy
29
Economy
Factors to achieve economy
• Standardisation
• Simplification
– Less labour
– Less time
• Reusability
30
15
Economy
31
Economy
• Simplification
– Easy installation and removal of
formwork and all joints and supports
therefore less labour and time
– Easy handling size therefore less
labour
32
16
Economy
• Reusability
– Durable material
– Design for ease of striking without
damage therefore a greater number
of times of uses
33
Types of Formwork
Categorised by material
• Timber
• Metal eg. steel and aluminium
• Plastic (PVC) and GRP (glass reinforced
plastics)
• Laminated paper products (cardboards)
• Fiber cement materials moulded to shape
• Pre-cast concrete units used as permanent
formwork
34
17
Timber Formwork
35
Timber Formwork
• Advantage
– Custom manufactured in large panel
sizes
– Curved for special shapes
– Reuse many times
36
18
Timber Formwork
• Disadvantage
– Liable to damage at corners and
edges
– Wear out quicker
– Greater chance of leakage for boards
– Variability of absorbency
37
Plywood
• Varies in thickness from 12 to 20 mm
• Common sheet sizes – 2400×1200 mm,
1800×900 mm
• Produce smooth concrete surface
• Coated in each face with phenolic resin film
or has a face layer of resin impregnated
paper
• Does not absorb water from wet concrete
38
19
Timber Formwork
Timber boards
39
Metal Formwork
• Mainly proprietary system, consists of stiff
metal sheets and edges, mechanically
handled and self climbing formwork
• Use where high stresses occur
• Steel sections as a frame for plywood
sheeting
• Steel plate may be used to replace plywood
sheeting for repeated number of uses
• Panels are made in a range of sizes and
shapes for the convenience of other
combinations 40
20
Metal Formwork
Advantage:
• Stiff and durable thus advantageous for reuse
• Closer tolerance
• Aluminium- for light weight construction
Disadvantage:
• Chemical reaction with fresh concrete which
may cause adverse effect to concrete
properties
41
Timber Formwork
• Requirements
• Well-seasoned
• Not liable to warp when exposed to sun and
rain
• Stiff enough to resist deflection and
distortion- all panels supported on strong
frame
• Face in contact with concrete should be
smooth (wrought)
42
21
Plastic – GRP
• Advantages:
• Rigid or flexible
• GRP although expensive, very light,
high impact resistance
• Good resistance to scour and corrosion
• High quality face finishes
• Less expensive for forms of special
profiles
43
Types of Formwork
Categorised by shape
• Column formwork
• Beam formwork
• Floor slab formwork
• Wall formwork
44
22
Column Form
Bracing
45
Column Form
46
23
Beam and Slab Form
47
48
24
Forms for Elevated Slab
49
Mudsills
50
25
Staircase Form
51
52
26
Formwork Ties
Function of ties
To allign the two faces of formwork lining
Formwork Ties
54
27
Formwork Systems
55
Formwork Systems
56
28
Column Formwork System
57
58
29
Selection of Types of
Formworks
Factors to be considered
• Cost of construction (materials and labour)
• Easy installation and removal
• Reusability
• Safety
• Requirements of decorative finishes
• Availability of materials, instruments (lifting)
and labour
59
60
30
General Safety Measures
• Control the rate and location of concrete
placement so that design loads are not
exceeded
• Ensure that forms and shoring are not
removed before concrete has developed the
required strength
• When placing prefabricated form sections in
windy weather careful of swinging forms
which may cause injury
61
Design of Formwork
62
31
Design of Formwork
Design principles
• Adequate strength to resist failure
1. Bending
2. Shear
• Will not deflect excessively when
forms are filled
3. Deflection
63
Design of Formwork
• Procedure:
– Establish design loads
– Each component analysed as a beam
– Determine max. bending and shear
stresses and max. deflection
– Then vertical supports and lateral bracing
are analysed for compression and tension
loads
64
32
Basis Of Design
• Structural Requirements
– BS 5975 :1982 – Falsework
– BS 8110 :1985 – Structural use of
concrete
– BS 5950 :1990 – Structural Steelwork
– MS544 :1978 – Malaysian Standard for
the structural use of
timbers
65
66
33
Formwork Striking Time
Structural member formwork Minimum striking time
Surface temperature of
concrete
16°C 7°C 2°C
Formwork to columns, beam 9 hours 12 hours 1 day
sides and walls
Formwork to slabs – props left 4 days 7 days 11 days
in position
Formwork to beam soffits – 8 days 14 days 21 days
props left in position
Props to slabs 11 days 14 days 21 days
Props to beam soffits 15 days 21 days 30 days
67
34
Methods of assessing formwork striking
time (cont.)
Method Advantages Disadvantages
3. Measuring 1. Can also be 1. Assumes concrete is as specified
maturity with used to 2. Need to establish and agree
thermocouples measure relationship
temperature 3. Frequent temperature readings
gradient across are required unless automatic
a section logging system is used
4. Measuring 1. Relatively 1. Assumes concrete is as specified
maturity with simple to use 2. Need to establish and agree
meter or 2. Maturity can be strength/maturity relationship
COMA-probe read as many
times as
necessary
69
70
35
The first floor circular columns were constructed using steel column forms. The steel column form should be
oiled before concreting.
71
After concreting to the first floor columns, the steel column forms were dismantled easily.
72
36
The second and the third floor construction continues.
73
When the building construction reached the third floor, both safety net and scaffolding were employed to
prevent falling objects and also to prevent the workers falling from such a high working place.
74
37
The steel props were erected to support the upper floors temporarily. The props would not
be removed until the reinforced concrete floor slab gained sufficient strength.
75
Formwork collapse
causes injuries, loss
of life, property
damage, and
construction delays
38
Causes of Formwork Failure
• The main causes of formwork failure are:
1 - Improper stripping and shore removal
2 - Inadequate bracing
3 - Vibration
4 - Unstable soil under mudsills
5- Inadequate control of concrete
placement
6 - Lack of attention to formwork details.
*Mudsill: A plank, frame, or small footing on the ground used as a base
for a shore or post in formwork.
Causes of Failure
Improper Stripping and Shore Removal
Premature stripping of forms, premature removal of
shores, and careless practices in reshoring can
produce catastrophic results.
Case study:
Too early shore removal at Bailey's
Crossroads in Virginia (1972):
26-stories + apartment building
Forms were supported by floors 7-
days old or older
Failure occurred on the 24th floor,
where it was shored to the 5-day-old
23rd floor.
The overloaded 23rd floor failed in
shear around one or more columns,
triggering a collapse that carried
through the entire height of the
building.
39
Causes of Failure
Inadequate Bracing
The more frequent causes of formwork failure,
however, are other effects that induce lateral force
components or induce displacement of supporting
members.
Inadequate cross bracing and horizontal bracing of
shores is one of the factors most frequently involved
in formwork accidents.
Investigations prove that many accidents causing
thousands of dollars of damage could have been
prevented only if a few hundred dollars had been
spent on diagonal bracing for the formwork support.
Causes of Failure
Inadequate Bracing Use of Diagonal Bracing
High shoring with heavy load at the top is
vulnerable to eccentric or lateral loading.
Case study:
New York Coliseum
Formwork collapse,
where rapid
delivery of
concrete
introduced lateral
forces at the top of
high shoring.
Causes of Failure
Inadequate Bracing Use of Diagonal Bracing
Case study: New York Coliseum
Increased diagonal bracing was added to all
remaining shoring, following partial collapse of
formwork.
41
Causes of Failure
Inadequate Bracing Use of Diagonal Bracing
When a failure occurs at one part, inadequate
bracing may permit the collapse to extend to a
large portion of the structure and multiply the
damage.
Suppose a worker accidentally rams or
wheelbarrow into some vertical shores and
dislodges a couple of them. This may set up a
chain of reaction that brings down the entire
floor.
One major objective of bracing is to prevent
such a minor accident or failure from becoming
a disaster.
Causes of Failure
Vibration
Forms sometimes collapse when their
supporting shores or jacks are displaced by
vibration caused by:
passing traffic
42
Causes of Failure
Unstable Soil under Mudsills, Shoring not Plumb
Formwork should be safe if it is adequately braced
and constructed so all loads are carried to solid
ground through vertical members.
Shores must be set plumb and the ground must be
able to carry the load without settling.
Shores and mudsills must not rest on frozen ground;
moisture and heat from the concreting operations, or
changing air temperatures, may thaw the soil and
allow settlement that overloads or shifts the
formwork.
Site drainage must be adequate to prevent a
washout of soil supporting the mudsills.
Causes of Failure
Inadequate Control of Concrete Placement
The temperature and rate of vertical placement of
concrete are factors influencing the development of
lateral pressures that act on the forms.
If temperature drops during construction operations,
rate of concreting often has to be slowed down to
prevent a build up of lateral pressure overloading the
forms. If this is not done, formwork failure may
result.
Failure to regulate properly the rate Fresh
and order of placing concrete on Concrete
horizontal surfaces or curved roofs H
may produce unbalanced loadings
and consequent failures of
formwork.
43
Causes of Failure
Lack of Attention to Formwork Details
• Even when the basic formwork design is soundly conceived,
small differences in assembly details may cause local
weakness or overstress loading to form failure.
• This may be as simple as insufficient nailing, or failure to
tighten the locking devices on metal shoring.
• Other details that may cause failure are:
– Inadequate provisions to prevent rotation of beam forms
where slabs frame into them on the side.
– Inadequate anchorage against uplift for sloping form
faces.
– Lack of bracing or tying of corners, bulkheads, or other
places where unequal pressure is found.
44