Commissioning Manual (08-01-2019)
Commissioning Manual (08-01-2019)
Commissioning Manual
PART I – Volume I
PART II – Volume II
TABLE OF CONTENTS
Page No.
1. GENERAL 4
4.1 General
4.1.1 Overall Project Objectives 9-10
4.1.2 Contractual Completion Date 10
4.1.3 Plant Inspection and Test Program (ITP) 10-11
Page 2 of 139
Page No.
6.1 Organization 21
6.2 Commissioning Manpower 21
6.3 Vendor Specialists 22
6.4 OWNER’s Operators and Maintenance Staff Involvement During Commissioning 22
11. SAFETY 24
Page 3 of 139
1. GENERAL
This procedure gives an outline of the Pre-commissioning, Commissioning, Start-up,Test-runs, Reliability Test
Run (RTR) and Performance Test (PT) activities to be carried-out by NEPC as EPC Contractor for 15 MW DMTPP
Project.
It describes the coordination between the PARTIES involved in the test and commissioning, operations and the
related responsibilities.
The Overall Test and Commissioning Program shall cover all the activities from erection completion to handing
over of the Plant to the Owner/PMT and provides a procedure to cover the follow-up work during the period from
the Provisional Acceptance to the Final Acceptance of the 15MW DMTPP Project.
The 15MW DMTPP Project is configured and designed to augment the power generation capacity to supply
electric power to the Masbate Grid and it is located in Barangay Tugbo, Mobo, Masbate beside the existing DMPC
Bunker/Diesel Plant .
• One CFB boiler with rated steam flow of 75 t/h, 5.3 MPa rated pressure and 495°C rated SH steam
temperature
• Vacuum Pumps
Page 4 of 139
• Fly and Bottom Ash Handling Equipment
• Desalination RO units
• Demineralization Plant
• Chlorination System
• CCWS system
• MCB, Power and Aux.Transformers, Bus Ducts, MV and LV distribution Systems, Switchgears, Relay
Protection System
• DC System
• UPS
• Emergency Diesel-Generator.
• Cathodic Protection
• HVAC
Page 5 of 139
• Fire Fighting Detection, Alarm and Suppression Systems
• Telecommunication System
3. SCOPE OF SUPPLY
The major components and systems have been presented above in order to give the main features and
characteristic of the plant as a whole.
STEAM TURBINE
STEAM BOILER
Page 6 of 139
11 Boiler SH and RH Live Steam
12 Electrostatic Precipitator (ESP)
13 Bottom Ash Handling
14 Fly Ash Handling
15 Boiler Vent, Blowdown and Drain Systems
16 Sootblowers System
17 Chemical Dosing and Injection System
18 Steam and Water Sampling & Analyzer System
19 Boiler Safety Valves
20 Exhaust Gas Emission Control System (CEMS)
ELECTRICAL SYSTEM
Page 7 of 139
3.2 Stand-By Unit Auxiliary Transformer
3.3 Start-up Transformer
4 High-voltage Distribution Panel
4.1 13.8kV High-voltage Distribution Panel
4.2 St 13.8kV High-voltage Start-up Panel
5 13.8kV High-voltage Bus-duct
6 480V Low Voltage Bus-duct
7 Emergency Diesel Generator
8 Low Voltage MCC
8.1 Low Voltage Unit UAT PC Panel
8.1 480V Emergency MCC
8.2 480V Unit Auxiliary MCC
8.3 Lighting Power MCC
8.4 Control Power MCC
9 LV Transformer
9.1 Control Transformer
9.2 Lighting Transformer
10 110V DC System (Battery and Charger)
11 UPS System
12 Grounding and Lightning System
13 Lighting System
14 MV and LV Cables
14.1 MV Cables
14.2 LV Cables
15 Electrical Motors
16 Communication and CCTV System
17 Fire Detection and Alarm System
18 Generator Panels
18.1 Generator VT Panel
18.2 Generator Neutral Panel
18.3 Generator Control panel
I & C SYSTEM
Page 8 of 139
4. OUTLINE OF PRE-COMMISSIONING, COMMISSIONING AND START-UP
4.1 General
- The activities that must be carried-out to reach a safe and successful start-up of the Unit.
- The activities necessary to be completed before the conduct of pre-commissioning and commissioning
activities.
- Time frame of the main activities that must be completed in order to reach the target dates of
Provisional or Final Acceptance in accordance with the Overall Project Master Schedule.
- Main checks and tests with brief procedures/instructions to be carried out as part of pre-commissioning
- Commissioning, Start-up Procedures and Test Run to be carried out as part of Commissioning.
- Commissioning organization and manpower deployment in accordance with the schedule and as per
priorities and in accordance with the agreed schedule.
- The coordination procedures among the various groups involved in the test & commissioning and plant
operations, identifying individual responsibilities.
The construction/installation activities in their final phase shall lead to erection completion. At this
stage, the facilities shall be ready for the pre-commissioning activities and eventually for
commissioning activities. The later shall employ the use of process fluids in actual operation
conditions leading to start-up of the Unit.
The main objectives while carrying out these activities shall be:
- To provide a safe and reliable functioning of the systems/units, with an aim to achieve the goal of
producing the contractual electrical power;
- To ensure proper documentation for Owner’s future use;
- Ensuring that Owner’s operational staff are capable of handling the operations through proper
involvement in accordance with the training programs;
The Pre-commissioning and Commissioning Plan for various Systems/Units shall be prepared
indicating all the inputs, supports required and their timing well defined.
The Plant shall be subdivided into Turnover Packages (TOPs) so that each one can be pre-
commissioned separately without interfering with the others, either still under construction or not
Page 9 of 139
completely ready for pre-commissioning (refer to Appendix II - Turnover Procedure).
The procedures shall include the list of documents and test records that shall be used and generated
in obtaining Commissioning Completion Report for each turnover package.
A full-pledged team to carry out these activities under the leadership of the NEPC Commissioning
Manager shall be mobilized at site in accordance with the Construction/Commissioning Schedule.
The Commissioning schedule and manpower plans are discussed in a subsequent section of this
manual.
The Guaranteed Project Completion Date for 15MW DMTPP Project as per DMPC-NEPC EPC
Contract is 16-October-2019.
The Inspection and Test Program is the basic element of pre- commissioning and commissioning
documentation. The ITP lists and defines all the activities to be carried-out and the forms to be used for
the parts or components to be commissioned.
It shows the inspection and test sequences to be performed to bring the plant from initial condition of
erection completion up to the final condition of “plant in operation” on each system/unit included in the
scope of supply. It gives reference to documents, procedures, test forms, checklists, applicable
drawings and manuals to be used as guideline for the specific step, and the type of quality record.
A graphical representation of the inspection and test program in the next page shows diagrammatically
the composition of the documentation associated to each system/unit of the plant.
The ITP gives the indication about the “witness” or “hold” points by NEPC, Owner/PMT or Third
Parties (if required).
Witness and hold points agreed with Owner/PMT are entered into the final negotiated version of the
ITP. The Owner/PMT will be informed of readiness for such witnessing within the period agreed upon.
In case of inspections defined and agreed as witness points but the witnessing party is unable to
participate on an agreed date, the inspection will be performed by NEPC and the work will be
continued.
In case of acceptance test by official authorities, the work will be stopped until the witnessing party is
able to attend. In such case, NEPC shall not be held responsible for the delay.
Where a joint inspection is mentioned, it is proposed that both NEPC and Owner/PMT’s
representatives attend to witness the inspection.
In case of inspections defined as Owner/PMT’s hold points, the work will be stopped until witnessing
party will be able to attend or witnessing is officially waived. Delay resulting from failure to respond to
the notification will not be the responsibility of NEPC.
Page 10 of 139
The ITP for the whole plant is shown in Appendix III. The test forms are in a separate volume titled
“Commissioning Manual (Volume II, Part II – Standard Test Forms)
Erection
Completion
Turn Over
Package
INSPECTION AND
TEST PROGRAM
Vendor’s Documents
Drawings/P&ID,Flow COMMISSIONING
Diagrams Special Procedures
(If applicable)
(If applicable)
(If applicable)
Page 11 of 139
4.2 Pre-commissioning Plan
Pre-commissioning is defined as those activities and tests necessary to achieve readiness for
commissioning stage and carried-out in accordance with contractual requirements.
The pre-commissioning is carried out on the individual equipment of a turnover package without the
final fluid but with auxiliary electrical power and main electrical power supply.
During this stage, the following minimum requirements shall be made available:
• Auxiliary and main power supplies for motor bumping, phase rotation checks and for flushing and
blowing operation.
• Accessories for flushing and blowing-out
• Instrument air
• I&C systems (DCS-PLC)
NEPC can start pre-commissioning after the issuance of the Handing Over Certificate as described
Appendix II - Turnover Procedure.
Prior the start of pre-commissioning, the Turnover Package (TOP) must be put in a clean, tight and
secured condition, properly managed with defined battery limits.
Prior the start of pre-commissioning, all punch list works are completed to the extent that it will not
affect the conduct of pre-commissioning activities. Clearing of all Category A punch list points is
defined in Appendix VII - Punch List Procedure.
The pre-commissioning activities on each turnover package are indicated in the Inspection and Test
Program (ITP). In this program, the referenced design document or the standard test form or the
relevant special procedures that are to be considered for each activity listed is also indicated. A brief
explanation of the tests to be performed and a log sheet for recording the data in the field are outlined
in each of the standard test forms.
The ITP also shows an indication for the tests in which the witnessing by the Owner/PMT is required
as per previous agreement.
NEPC’s Commissioning Team shall perform the following activities with the support of the
subcontractor’s labor (in certain cases with the presence of the Owner’s operators), prior the
declaration that the unit/system is ready for commissioning.
• Equipment Inspection
• Flushing, blowing, drying of lines and equipment
• P & ID conformity check
• Loop checking with DCS or PLC energized
• Valve Stroking (motor operated and pneumatic actuated)
Page 12 of 139
• Cold test of trip and interlocks with DCS or PLC energized
• Installation/removal of accessories for pre-commissioning
• Load chemicals, resins, etc.
• Check rotation alignment for rotating machinery
• Status of locked-open/locked-closed valves
• Valves line-up
• Pre-energization test and checks on electrical equipment
• Documentation check-out
For each Turnover Package, the completion activities to be performed in the final stage of construction
are identified and listed to give input to the Erection Team in planning their priorities and at the same
time allow the Commissioning Team to perform the necessary checks and inspection accordingly.
This kind of interface helps to facilitate the pre-commissioning activities to be successfully and
meaningfully carried-out.
The activities normally carried by the Erection Team in the final phase of construction with the pre-
commissioning checks and inspection being carried-out simultaneously can be broadly listed as
follows:
a. Vessels
- Internal inspection and cleaning of vessels, before installation of internals
- Field installation of internals in the erected vessels duly inspected before hand-over and
checks to be carried-out in accordance with erection specifications
- Hydrostatic testing, when required
- Perform purging of equipment, when required
- Checking of insulation
b. Heat Exchangers
- Check of supports, guides and anchors to ascertain that they can expand in the correct
manner
- Check tube bundles, nozzles, etc.
- Cleaning and flushing of tubes
Page 13 of 139
- Presence of Vendor’s specialist during these phases, when required
- All checks as per P & IDs
d. Boiler
- Check that refractory materials have been correctly laid
- Check and removal of all temporary supports and blocks
- Check that various components can expand in accordance with drawings and specifications.
- Hydraulic testing
- Removal of testing water
- Cleaning of boiler by boil-out or chemical methods
- Checking against P & ID’s
- Package Control System checks
e. Piping
- Check of valve glands
- Check of piping arrangement in general, installation of valve & instruments as per P & ID’s
- Hydrostatic or pneumatic test, as required by the codes, specifications, supply and installation
of temporary blinds
- Flushing and draining of the systems after hydraulic test
- Draining of the system, removal of temporary blinds, and installations of gaskets, as required
- Checking that no water remains in piping and equipment
- Check of pipe hangers, supports, guides, expansion joints, etc. to verify the removal of all
shipping and erection stops and the correctness of cold setting for the design service
- Flushing steam of steam pipelines
- Air blowing of large lines, as required
g. Tanks
- Check that instruments and accessories are correctly assembled
- Hydraulic test and check of foundation settlement
- Removal of foreign bodies from roof and bottom
- Fit final gaskets and close flanged connections and manholes
- Check of cathodic protection installation
h. Instrumentation
- Conduct any non-operating checks to ensure instrument operability
- Clean all transmissions, air supply header control tubing by blowing cooled & filtered clean air
- Carry out hydraulic or pneumatic tests of process primary connections
- Check connections on ”control loops and interlock system” both for pneumatic and electrical/
electronic instruments
- Check installation of all thermometers and pressure gauges - check proper connections,
tightness of joints
- Calibration of set point of pressure switches, thermostats, level switches
- Installation and connection of all system components and verification of their conformance to
specifications
Page 14 of 139
- Check out associated PLC’s
i. Packaged Units
- Check that mechanical/electrical/instrumentation equipment are installed in accordance with
Project Specification and approved Vendors’ Drawings.
- Make all non-operating checks that may be required.
- Check conformity of Package & Plant P & I D’s.
j. Electrical Parts
- Insulation tests on all wiring
- Insulation tests on motor and transformer windings from phase to phase and phase to group
- Grounding system tests to determine the continuity of connections and the value of resistance
to ground
- Perform trial and adjustment on LV switchboards and motor control equipment
- Checks of all control system wiring
- Testing and setting switchgears and circuit breaker relays for proper coordination
- Check of installation of emergency power and lighting system, including illuminated levels
- Check of the interlocking system of motor and motorized valve
- Check of cathodic protection installation
With the above checks and tests and when the Plant is mechanically and structurally complete, all
systems have been put in a tight and clean condition, all punch list points have been attended to and
vendors requirements have been taken into consideration, the subsequent pre-commissioning
activities can be started.
The detailed list of pre-commissioning activities are shown in Inspection and Test Program, which in
general can be summarized as follows:
Page 15 of 139
4.2.5 Requirement for Pre-commissioning
In order to perform the pre-commissioning activities in a smooth and uninterrupted manner the
following pre-requisites are to be considered:
- All the necessary tools and equipment required for testing are available in proper working
conditions and duly calibrated (see Appendix X - List of Tools, Instruments and
Consumables);
- The working group such as the operators and technicians are fully familiarized with the process
and operation of the plants;
- The main utility, which is the uninterrupted and regulated electric power is available.
The dedicated substations are ready to be energized and the “Work Permit System/Forms” has
been prepared and applied as described in Appendix VIII - Permit to Work Procedure during
Commissioning.
- Treated water for various purposes such as flushing & hydrotest is available;
- Oil free air is available to blow the biggest lines/equipment. For this purpose, portable air
compressors may be utilized instead of main air compressors in case of non-availability of the
Plant’s main air system.
- For boiler auxiliary burner firing, the light fuel oil is available, which means that it shall be already
hydraulically tested and flushed with valves/instrumentation systems properly checked and
tested.
4.2.6 Responsibilities
NEPC shall be responsibility in the proper Planning and Scheduling of its activities, submit to
Owner/PMT the detailed schedule and procedures and co-ordinate the activities in the field involving
the subcontractors and Vendors personnel/specialists.
NEPC personnel, who shall report to NEPC Commissioning Manager, shall coordinate and supervise
all the operations/activities to be performed during Pre-commissioning, Commissioning, Reliability
Test Run (RTR) and Performance Test (PT). They shall also ensure that all the activities performed
conform to the relevant specifications, operating instructions and established procedures.
Vendor specialist services shall be called with the specific duty to check the equipment or package
installed.
Upon arrival of the Vendor’s representative at Site, a brief meeting, attended by NEPC and
Page 16 of 139
Owner/PMT representatives, will be held to discuss Pre-commissioning and Commissioning Plan and
personnel requirements.
Prior to leaving the Site, each Vendor’s representative shall prepare a report summarizing the checks
and test performed.
The authorized Owner/PMT’s representatives, as the witnessing parties, shall countersign the report
issued for most of the pre-commissioning activities.
NEPC shall perform all the required pre-commissioning activities, accordingly to established standards
and the standard operating procedures.
NEPC shall keep a correct and complete record of all pre-commissioning activities and shall prepare
and submit appropriate reports to Owner/PMT.
NEPC inform the Owner/PMT regarding the readiness of turnover packages and notify them for
proceeding with the pre-commissioning activities for the said package.
NEPC shall carry-out rectification/addition/completion of work within the limits of the contract, if so
required by the Owner/PMT.
Upon completion of pre-commissioning of the portion or section of the Plant, NEPC shall submit to
Owner/PMT all documents pertaining to the pre-commissioning activities.
Commissioning means all the works, activities and tests associated with start up, performance tests
and operation of the installations up to the plant Provisional or Final Acceptance.
The commissioning starts with the operational tests of the package or system with the final fluids
being loaded and the process starts to work to produce energy, steam or water as per intended
purpose.
These include but not limited to: running-in of equipment, performing all the possible mode of
operations, tuning in steady conditions, test and the stability of the protections, tuning in transient
conditions, test of the stand-by equipment, etc.
During this period, it is NEPC’s responsibility to make continuous adjustments to reach the best
system operation configuration.
When the adjustments are completed and the Plant has its final configuration, it is declared as ready
for start up.
The start-up is defined as the activities and tests that can prove its operability in transient and steady
conditions without any further adjustments.
The Performance Tests are the steady condition tests having the scope to demonstrate the specific
performance guarantees.
Page 17 of 139
For these last tests, special instrumentation shall be used and a dedicated procedure shall be issued.
4.3.2 Commissioning Steps
The commissioning can start when all the pre-commissioning activities related to a commissioning
package are mechanically completed and certified.
The commissioning activities to be carried out in each commissioning package are listed in the
Inspection and Test Program (ITP) and are described in details for each equipment or component in
the corresponding test forms or special procedures/instructions. The forms include also the checklists
to verify readiness for start-up.
A certain sequence must be followed as there are requirements necessary to start the commissioning
of a package that are available only from other commissioning packages and/or systems. This
commissioning sequence can be traced from the commissioning program described in Section 5 of
this manual.
In the ITP, as previously explained in the section of pre-commissioning, the tests that are required to
be witnessed by the Owner/PMT Inspectors are indicated.
All procedures and documents related to a commissioning package together with those for pre-
commissioning shall be submitted to Owner/PMT prior the start of commissioning.
NEPC shall request in writing the requirements for fuel oil, coal and other media requirements and
shall coordinate with Owner/PMT’s personnel for the introduction of the same into the Plant for
commissioning in a timely manner.
At the end of the commissioning activities, the duly filled-up and signed documents shall be compiled
by the NEPC Commissioning Manager and submit them together with the Commissioning Completion
Report.
The main activities to be carried out during commissioning include but not limited to the following:
- Run-in electric motors
- Water fill equipment for pumps run-in
- Run-in pumps and drain water
- Energize electrical equipment
- Hot alignment checks, necessary adjustments and running of component parts as a unified
system
- Electrical protection stability test, turbine and boiler protection test
- Overall plant operation and functional test
- Steady operation, transient operation and process tuning at various loads
- Emergency take-over of main auxiliary
- Cold, warm and hot plant start-up
- Load run back test and load rejection test
- Overall Test on Completion, flue gas emission, noise measurement test, liquid effluent test
- Fire alarms and gas detectors functional checks
- Fire fighting system functional checks
Page 18 of 139
- PLC and DCS functional tests (cabinets)
- First filling of chemicals
- Running-in of pumps
- Maintain daily commissioning log sheet of running equipment
- Verify proper operability of equipment
- Instrument testing
- Setting and tuning of control system
After commissioning and start-up activities, Performance Test runs shall be carried out leading to
Provisional or Final Acceptance.
To carry out the commissioning activities, NEPC and Owner/PMT shall provide the following
requirements in compliance with contractual obligations:
NEPC shall:
• Ensure that all consumables and chemicals to operate the equipment and systems are readily
available.
• Provide qualified commissioning staff and specialized manpower to carry out commissioning
activities in accordance with the contract.
• Be responsible for the timely presence of Vendors specialists who shaill assist NEPC’s
commissioning personnel during commissioning and start-up of the Unit.
OWNER shall:
• Provide NEPC the fuels and other consumables according to the contract and load configuration
requirements
• Allow NEPC to store or use the water produced by the Water Treatment Plant prior the Provisional
or Final Acceptance.
• Ensure that the operators and maintenance staff are available for the required orientation and
training as per required discipline and agreed number.
At the completion of all the activities, the NEPC Commissioning Manager, after collecting all the
supporting documents (signed forms/checklists, special procedures and instructions, ITP
requirements, etc.) shall issue the Commissioning Completion Report to the Owner/PMT.
The Overall Teast and Commissioning Program has been developed based on the operational priorities
respecting the contractual completion dates for Provisional or Final Acceptance:
The program has been developed taking into account that some utilities could be temporarily provided in the initial
stage prior commissioning of the main unit such as instrument air and demineralized water supply.
Temporary electrical power (13.8kV) must be made available at the substation from the very beginning of pre-
Page 19 of 139
commissioning activities for the energization of substation boards until stable power is provided from a permanent
source.
A detailed commissioning schedule shown on Appendix 1 has been prepared by NEPC for 15MW DMTPP Project
taking into account the use of all the permanent Power Plant facilities and equipment.
All pre-commissioning and commissioning activities for the whole plant shall be performed by specialized
manpower provided by NEPC in accordance with its contractual obligations.
These activities shall be performed under the supervision of NEPC Commissioning Manager and his staff in
close coordination with the Owner/PMT.
NEPC commissioning personnel shall prepare the equipment or packages assisted by skilled personnel
provided by Sub-contractor and in special cases at the presence of the Vendor Specialists.
During pre-commissioning and commissioning activities, the Owner’s operating personnel shall follow all the
required operations carried out under the responsibility of NEPC commissioning personnel, and coordinated
by NEPC’s Training Coordinator.
The Pre-commissioning activities shall be intended as the best time for the Owner/PMT’s operations and
maintenance personnel to:
Page 20 of 139
• All personnel involved in start-up activities, shall work round the clock on eight or twelve hours shifting,
as the case may require.
• NEPC’s commissioning organization chart and the staff assignment chart are shown in Appendix IV –
Commissioning Staff Organization and Job Description.
A detailed program is developed based on the established Overall Project Master Schedule previously
agreed by NEPC and Owner/PMT.
Each activity on the master schedule shall be broken down further (Detailed Schedule) to show a more
detailed sequence of the tasks to be performed.
This Detailed Schedule shall be used as reference in implementing the day-to-day activities and in
monitoring progress of pre-commissioning, commissioning, and start-up.
Each task shown on detailed schedule activity shall be weighted based on estimated manhours calculated
from the quantity of work to be performed (e.g. no. of loops, no. of drives, etc.) and NEPC’s standard
productivity for the respective tasks. These task’s weight shall be used to roll up the progress of the master
schedule activity which in turn shall be used in updating the Overall Project Schedule from where the
required progress curves (S-curves) are generated.
The detailed schedule of commissioning activities for 15MW DMTPP Project is shown in Appendix I.
6. COMMISSIONING PERSONNEL
6.1 Organization
The organization chart for NEPC commissioning staff is shown in Appendix IV – Commissioning Staff
Organization and Job Descriptions.
Owner’s personnel having undergone intensive classroom training sessions shall be associated with the
NEPC Commissioning team in their respective disciplines.
NEPC shall utilize OwnerPMT personnel during the commissioning in a manner to take the Unit towards
successful Provisional or Final Acceptance and also to prepare them to take over the responsibilities of the
operations thereafter. However, the entire responsibility for the commissioning activities remains under
NEPC’s obligation.
Skilled manpower and technicians to support the commissioning engineers shall be NEPC’s direct hire
personnel though to some extent shall be provided by erection sub-contractors, if any, as they are already
aware of the activities carried-out during construction on the various equipment and systems and they are
already familiar with the method of work.
NEPC personnel assignment chart (mobilization schedule) is shown in Appendix IV - Commissioning Staff
Organization and Job Descriptions.
Page 21 of 139
6.3 Vendor Specialists
Vendors specialist will be called to the site with at least two (2) weeks advance notice according to the
commissioning schedule.
These specialists shall assist NEPC commissioning personnel in the preparation of relevant equipment or
package. They will be coordinated by NEPC commissioning engineers.
Before leaving the site, each Vendor shall prepare a suitable Report and Test Forms summarizing the tests
performed, the reading parameters and situation of the equipment or package, specifying on details:
Assistance of Vendors not foreseen in the schedule may be requested when strictly necessary to solve
specific problems and when the need arises.
During the commissioning, NEPC shall fully involve the Owner personnel whom, after having undergone
training and having been associated with some pre-commissioning activities, would be by then, fully
acquainted with operational aspects of the Unit.
It is during the commissioning phase that the Owner’s Operations personnel shall obtain the complete
command over the operating parameters, calibrations and controls, settings, start-up and shutdown
sequence, DCS operations, generation of reports, etc.
The Owner’s Maintenance staff shall as well get a great advantage of being involved in the preparation of
equipment and machinery.
7. COMMISSIONING COMPLETION
Upon completion of the commissioning works as documented via test certificates and reports duly-noted,
witnessed and accepted by the Owner/PMT related to each turnover package, such that they are fully ready for
Page 22 of 139
operation, a commissioning completion report shall be prepared and submitted by NEPC to Owner/PMT.
The standard format in the preparation of completion report is shown in Appendix V- Commissioning
Completion Report.
Plant Performance Test Runs shall be performed by NEPC together with Owner/PMT’s properly qualified
appointed personnel (and with assistance of the Vendors / Licensors when required).
Performance Test Runs will be performed to ascertain whether the Plant can attain the process performance
guarantees as specified in the EPC Contract and the Owner’s Operations personnel/PMT shall witness these
tests.
Detailed performance test procedures shall be issued by NEPC and approved by Owner/PMT prior the execution
of the tests.
The Plant shall be handed over to Owner/PMT at the date of the Provisional or Final Turnover Completion (PTOC
or FTOC) date. At this stage, all the plant equipment, systems and components have been started-up and
successfully tested.
Owner/PMT operating personnel have been fully involved in the work since the pre-commissioning stage and
should be acquainted with all the commissioning procedures and normal operation of the Unit.
NEPC shall give the required handing over documents pertaining to their scope of supply. NEPC Commissioning
Manager shall compile all documentation pertaining to the commissioning operations in a specific hand over
dossier, arranged by systems/units, which will contain all the information required to demonstrate to the
Owner/PMT that the plant has reached the PTOC or FTOC date.
All punch list items detected during all the phases from pre-commissioning throughout the test run activities shall
be duly-acted upon by NEPC subject to Owner/PMT approval/acceptance.
All Plant defective items, process and/or engineering faults detected during all the phases of the work/preparation
will be repaired, replaced or remedied, as the case may be, as soon as the problems are identified and defined.
Such defect or faults should not be confused with improvement that Owner/PMT may request.
Page 23 of 139
Plant improvements shall be treated separately and shall be considered exception from the Provisional or Final
Acceptance Certificate issued by Owner.
Throughout the Defects Liability Period (DLP), NEPC shall provide status updates regarding site and/or DMPC
Head Office follow-ups of the pending problems/issues listed in the punch list until satisfactory solutions have
been formulated and carried-out.
A system for the proper follow-up and closing of outstanding items is presented In Appendix VII - Punch List
Procedure. In this procedure, the database system and the method of follow-up of such outstanding items by
NEPC are explained in detail.
11. SAFETY
The avoidance of accidents involving injury to personnel or damage to equipment is to be a major objective in the
performance of the work.
NEPC shall appoint an experienced and qualified person as safety supervisor who will prepare all those
procedures to make the pre-commissioning, commissioning and start-up operations safe.
These procedures that are already being utilized by NEPC Construction Team are to be implemented keeping in
mind the fact that during the execution of pre-commissioning and commissioning activities, electrical power,
utilities and process fluids are present.
Other important argument to be highlighted in these procedures is the safeguarding of those sections where the
erection works are still in progress while parts of the Unit are already in operation. This involves the proper
implementation of the Permit to Work Procedure as described in Appendix VIII and definition of
“Commissioning Battery Limits” which is well explained in Appendix II - Turnover Procedure,.
Page 24 of 139
12. APPENDICES
Page 25 of 139
Appendix I
Page 26 of 139
(Attach the Commissioning Schedule in this page)
Page 27 of 139
Appendix II
Page 28 of 139
1. SCOPE
2. REFERENCES
The turn-over of completed systems from construction to commissioning are carried-out on the basis of the
following project-related documents, as applicable:
• P&I Diagrams
• Functional Control Drawings or Logic Diagrams
• Instrumentation Loops
• Single Line Diagrams
• Cabling and Interconnection Lists
• Layout Drawings
• Equipment List.
• Equipment Data Sheet
• Tie-in List.
• Punch List Procedure.
• Pre-commissioning and Commissioning Procedure.
• Inspection and Test Programs
• Contract and Technical Specifications
• Project Quality Plan
• List of Turnover Packages
• Commissioning Logic Diagram
A copy of the above listed documents shall be provided by NEPC Commissioning Team. .
Erection completion is achieved when all the equipment included in a package or system have been
installed according to the erection documents and all the checks that do not need main power, auxiliary
power, final fluids, compressed air, etc. have been successfully carried-out in accordance with speific
plant documents.
Page 29 of 139
As a general rule, erection completion is achieved when the following conditions are fulfilled:
Turn Over Package (TOP) is defined as a systematic grouping of equipment and/or components
interconnected and interrelated in such a way that all together, it can perform an operation and/or specific
function (Example: to feed water to the Boiler).
From this view point, it is consequential that, to perform an operation function, the TOP should include
mechanical equipment, electrical equipment, I&C equipment and all the interconnections in between as
well as the Plant Operator interface.
One TOP can include a full system or a sub-system depending on the criticality and sequence of pre-
commissioning and commissioning activities.
That means that, when a TOP is accepted for pre-commissioning, all the equipment and components
related to that particular TOP are ready to work/operate.
From the moment when a package is turned-over from the Erection Team to the Commissioning Team
for the execution of pre-commissioning and commissioning activities, it will be energized or charged with
fluids which involve risks if not properly monitored and controlled. For that reason, each TOP should be
contained within a boundary of isolation points (Terminal Points) in order to prevent any untoward
incident to the Erection Team who could still be working, outside this limit, on other TOPs.
Any erection work inside the boundary of the terminal points shall be handled in accordance with the
“Permit to Work Procedure”.
The terminal points should always be in the form of breakers, isolators, valves, removable links, blind
flanges, fuses, etc. which can isolate a system. All terminal points of any system not turned over must be
in a safe condition (e.g. breakers racked out, valves locked with proper locking device if available or with
chain and padlock).
Page 30 of 139
4. APPLICABILITY
This procedure is applicable to the 15MW DMTPP Project under NEPC‘s scope of work.
5. RESPONSIBILITY
5.1 General
Construction Team shall be responsible for all works related to any system prior to handing-over; that is
when erection completion is achieved (see definition in Section 3.1)
Construction Team shall be responsible to support the Commissioning Team in undertaking the following
activities after hand-over:
• Temporary erection work for testing or flushing (e.g. piping for steam blow out or condensate system
flushing) including removal and restoration
• Correction of errors in construction (e.g. wire swap of motors)
• Final assembly (e.g. assembly of definitive components after testing and flushing)
• Execution of Punch List items
QA/QC shall guarantee that the work is done according to established quality standards by undertaking
the following activities according to approved QA/QC procedures:
• Inspections
• Documentation
• Non-conformance
• Review of Punch List
Page 31 of 139
5.7 Responsibility of Commissioning Team
Commissioning Team shall execute the activities including but not limited to the following:
Pre-commissioning Checks:
• All I & C tests that needs DCS energized
• Oil flushing
• Water flushing / air blowing
• Steam blow-out
• Motor test-run (rotation, power)
• Calibration and adjustment of components
• Chemical cleaning
• Protection system for generators and transformers
From the detailed commissioning sequence, the Turn-Over Engineer shall identify the Turn-Over Packages
(see Attachment B) of which the extent shall be mutually agreed between the Construction and
Commissioning Teams. For each one of these TOPs, the following documents shall be prepared:
• List of equipment included in the package
• List and status of the terminal points
• List of outstanding work (punch list) with category
• List of pre-requisites for erection completion
• Inspection and Test Program (ITP) for pre-commissioning and commissioning
• Marked-up P & IDs, mechanical Flow Diagrams, Single Line Diagrams (SLDs) and other applicable
documents/drawings
The procedure described herein is summarized in the attached flow diagram (Attachment A).
7.1 The documentation listed in Section 4 is prepared by the Turn Over Engineer long in advance and
distributed to the Erection Team. This documentation becomes the guide for the planning and
execution of all the erection completion activities and finishing works (pre-requisites for erection
completion) associated with the package.
7.2 The inspection forms related to each TOP are filed and collected by QA/QC.
Page 32 of 139
7.3 The checklist associated to a TOP are filled-in by the Discipline Supervisors; the completion of
outstanding works and remedial actions shall be verified by the Turn Over Engineer and Discipline
Supervisors during the inspection checks.
7.4 The punch list of the system or turn over package inspected is prepared by Construction, updated and
categorized by Turn Over Engineer and reviewed/verified by QA/QC.
7.5 When all the above documents are ready, the final inspection shall be performed and the relevant
Handing-Over Certificate for particular system or package shall be submitted to the Owner/PMT for
information (Attachment C).
Page 33 of 139
Attachment A – Flow Chart for Erection Completion Activities
Resp.
Execute the
RECTIFICATION completion of
erection activities
Discip. Supervisors
Correction of
Defects or
Making Good Punch List
Team Schedule &
Request for QA/QC
Inspection
T.O. Engr–QA/QC
Review
Perform Commissioning Mgr.
Deficiency Inspection
Inspection and Discip. Supervisors
Forms
Safety Audit QA/QC
Safety Engineer
Turn Over Engineer
Notification NO Commissioning
Accepted?
for Mgr.
Deficiency Cat. A
QA/QC registers
and file
YES (Cat. B / C)
Release of Handing
Over Certificate Turn Over Engineer registers and files
Consultant / CLIENT (for information)
Start Pre-
commissioning Commissioning Team
Activities
Page 34 of 139
Attachment B – Identification of Turn Over Packages
The following is the list of Turn Over Packages identified for the balance of plant of 15MW DMTPP Project and their
relevant system numbers for proper identification (these numbers shall be used in all documents related to the same
Turn-Over Package).
Page 35 of 139
Attachment C – HANDING OVER CERTIFICATE
This is the form for Handing Over Certificate to be completed for each Turn Over Package.
Construction Department
System construction is completed and ready for commissioning
Construction Manager Date Signature
QA/QC Department
System is inspected and found to be complying with Project Quality Plan.
QA/QC Manager Date Signature
Owner/ Engineer
System is accepted for hand over to Commissioning.
O/E Representative Date Signature
Commissioning Department
System is accepted for pre-commissioning and commissioning.
Commissioning Manager Date Signature
Remarks:
Page 36 of 139
Appendix III
Page 37 of 139
Project Doc. Ident No Index Rev. Page Total
Project-Document-Number
Title
POWER PLANT
TURNOVER PACKAGE
Derived from Replaced by Replaces Format Lang. Off. resp. Ref. File name
En
Issued: (Date / dept. / sign) Checked: (Date / dept. / sign) Standard checked: (Date / dept. / sign) Released: (Date / dept. / sign)
Date Date Date
Name Name Name
Page 38 of 139
TABLE OF CONTENTS
i. System Outline
5. Punch List
8. Special Procedures
Page 39 of 139
HANDING OVER CERTIFICATE
Construction Department
System construction is completed and ready for commissioning
Date Signature
Construction Manager
QA/QC Department
System is inspected and found to be complying with Project Quality Plan.
Date Signature
QA/QC Manager
Owner/ Engineer
System is accepted for hand over to Commissioning.
Date Signature
O/E Representative
Commissioning Department
System is accepted for pre-commissioning and commissioning.
Date Signature
Commissioning Manager
Remarks:
Page 40 of 139
1. EQUIPMENT LIST
Page 41 of 139
No. Code No. DESCRIPTION
33 HYDROCHLORIC ACID TANK
34 NEUTRALIZATION TANK
35 FUME SCRUBBER
36 FLAME ARRESTOR
37 FLAME ARRESTOR
38 FLAME ARRESTOR
39 FLAME ARRESTOR
40 HCL TRANSFER EDUCTOR
41 NaOH TRANSFER EDUCTOR
Page 42 of 139
2. DOCUMENT LIST
Page 43 of 139
3. LIST AND STATUS OF TERMINAL POINTS
Page 44 of 139
3.2 Terminal Points – Electrical and I&C
Page 45 of 139
4. PRE-REQUISITES FOR ERECTION COMPLETION
Page 46 of 139
5. PUNCH LIST
INSPECTED BY:
Page 47 of 139
6. INSPECTION AND TEST PROGRAM
1 CHLORINATION SYSTEM
1.1 Joint inspection for completion of erection (Prerequisites) P&ID
Page 48 of 139
INSPECTION AND TEST PROGRAM: COMMISSIONING
PROCEDURE
Sheet
CHLORINATION SYSTEM 2/ 3
EQUIPMENT DESIGNATION: SYSTEM: P&I D
Page 49 of 139
INSPECTION AND TEST PROGRAM: COMMISSIONING
PROCEDURE
Sheet
CHLORINATION SYSTEM 3/ 3
EQUIPMENT DESIGNATION: SYSTEM: P&I D
Page 50 of 139
7. TEST FORMS AND SUBSUPPLIER INSTRUCTIONS
Page 51 of 139
7. 1 ELECTRICAL TEST FORMS
Witnessed By :
Witnessed By :
Witnessed By :
Page 52 of 139
Equipment Description : M.V. & L.V. A.C. MOTOR OVER OR EQUAL TEST SHEET NO. AT339 AX
TO 100 kW sh. 1 of 5
Description :
Item : IDPID :
TEST RESULTS
1) Visual Inspection
1.1) Name plate data : rated power _______ kW; P.F. ______
rated voltage ________ V; _________Ph
rated current ________ A; freq. _______Hz
rated speed ________rpm; Isol. cl _______
wind. connect. _________________________
Page 53 of 139
Equipment Description : M.V. & L.V. A.C. MOTOR OVER OR EQUAL TEST SHEET NO. AT339 AX
TO 100 kW sh. 2 of 5
Mohm (10’)
------------------------------------------------------ = _____
Mohm (1’)
2.4) Shaft Voltage Measurement (for insulated bearings M.V. motors only)
3) Operating Tests
3.1) Control circuit tested
Page 54 of 139
Equipment Description : M.V. & L.V. A.C. MOTOR OVER OR EQUAL TEST SHEET NO. AT339 AX
TO 100 kW sh. 3 of 5
TEST PROCEDURE
The test shall be made on equipment completely mounted in usual service conditions, in dry and
clean conditions.
1) Visual Inspection
Visual Inspection shall be made to verify :
1.1) Equipment nameplate data
1.2) Equipment completeness without damages
1.3) Frame securely bolted
1.4) Frame grounded at least at one point
1.5) Rotor alignment checked
1.6) Coupling protection installed (if required)
1.7) Proper connections and tightness of bolted connections in terminal boxes
1.8) Bearing lubrication
1.9) Motor cooling system
1.10) Temperature detectors connection (if provided)
Page 55 of 139
Equipment Description : M.V. & L.V. A.C. MOTOR OVER OR EQUAL TEST SHEET NO. AT339 AX
TO 100 kW sh. 4 of 5
2) Insulation Tests
- Insulation resistance measurement shall be performed for each winding against the others
connected to ground.
- Stator winding shall be tested applying the voltage of 1000 Vdc.
- If necessary heat the windings to improve their insulation resistance; records of the insulation
resistance of the windings are to be taken during heating every 24 hours, until satisfactory
value is obtained.
- The tests shall be carried out before and after the applied voltage test.
- Attention shall be made to connect to ground the winding already tested at the end of the test
and before dismounting the circuit.
- During test, RTDs shall be short circuited & earthed.
- The test shall be carried out according to BS Standards 2613 by applying for 60 sec.
alternatively between each phase and the others connected to the frame and earthed, the
voltage of :
a) for motors above 2 kV up to 6 kV :
2,5 x rated voltage x 1,6 x 0,8 = ________ kV d.c.
b) for motors above 6 kV up to 17 kV :
(2 x rated voltage + 3 kV x 1,6 x 0,8 = _____ kV d.c.
- The test voltage must not be applied suddenly but gradually at the gradient rate of 1,5
kV/sec, starting from zero. Similarly the voltage shall be gradually reduced when the test is
finished.
- Attention shall be made to connect to ground the winding at the end of the test and before
dismounting the circuit.
Note :
Applied voltage test must not be run if result of insulation measurement gives a value lower
than the recommended minimum value (Rm) at 400 C, estimated by the formulae :
Rm = kV + 1 = Mohm (kV : motor nominal voltage in kV)
If this happens, reason of the low insulation resistance should be removed and test repeated.
If the insulation test performed after the dielectric test gives a value lower than 80 % of the
value found before testing, the cause of the fact shall be investigated and removed.
Page 56 of 139
Equipment Description : M.V. & L.V. A.C. MOTOR OVER OR EQUAL TEST SHEET NO. AT339 AX
TO 100 kW sh. 5 of 5
The test shall be carried out according to IEEE Standards, Publications 43 and 115.
- The voltage of 1000 Vdc shall be applied between the winding and the ground; readings of
the insulation resistance shall be made after one minute and ten minute voltage application;
the index is given by formula :
- The value obtained shall not be lower than 2. Otherwise warm up the machine until this
minimum value is obtained.
The shaft voltage measurement shall be made for M.V. bearing insulated motors.
A voltmeter having very high internal resistance (over 40.000 ohm per Volt an electronic one
is advisable) (i.e. once a year), using the same instrument.
A reading of some millivolt shall be obtained (normally 5 to 10 mV approx. but no more than
50 millivolt).
Measure can be easily taken by removing the motor bottom cover (joint opposite side) and,
with the motor running at nominal speed, measuring the voltage between the shaft center point
(axle) and the ground.
3) Operating Tests
3.3) Make hand turning by the motor coupling and check that motor is rotating freely (if feasible).
3.4) Bumping operation shall be made on the motor to check proper rotating direction.
If no abnormal condition is found, the motor shall be restarted to check (in normal operating
condition) :
Page 57 of 139
Equipment Description : SMALL L.V. A.C. MOTOR < 100 kW TEST SHEET NO. AT339 BX
Sh. 1 of 2
Description :
Item : IDPID :
TEST RESULTS
1) Visual Inspection
1.1) Name plate data: Rated power _______ kW; P.F. ______ Wind. Con. ___
Rated volt./curr./freq.: _____ V/____A/ _____Hz
Rated speed __________ rpm; Isol. cl _____
1.2) Completeness and damages
1.3) Stator bolted
1.4) Frame grounded
1.5) Rotor alignment done (if applicable)
1.6) Coupling protection installed (if any)
1.7) Proper and tightened connections, supply cable checked
1.8) Overload range _______ A, setting at ________ A vis. check
Magnetic protection set at ______ A visually checked
2) Insulation Tests
2.1) Windings to ground: RYB / ground = ________ Mohm ________
Amb. Temp. + ________0 C
3) Operating Tests
3.1) Control circuit tested
3.2) Hand motor rotation (if feasible)
3.3) Rotation direction _______________
3.4) On-load current _______ A (only if ammeter equipped)
3.5) Bearings temperature (if applicable) _______ 0 C
Page 58 of 139
Equipment Description : SMALL L.V. A.C. MOTOR < 100 kW TEST SHEET NO. AT339 BX
Sh. 2 of 2
TEST PROCEDURE
The test shall be made on equipment completely mounted in usual service conditions, in dry and
clean conditions.
1) Visual Inspection
Visual Inspection shall be made to verify :
- Insulation resistance measurement shall be performed for each winding against the
others connected to ground by meggering at 500/1000 Vdc for 1 minute.
- If necessary heat the windings to improve their insulation resistance; records of the
insulation resistance of the windings are to be taken during heating every 2 hours, until
satisfactory value is reached.
- Attention shall be made to connect to ground the winding already tested at the end of the
test and before dismounting the circuit.
3) Operating Tests
If no abnormal condition is found, the motor shall be restarted to check (in normal operating
conditions):
Page 59 of 139
Equipment Description : MOTOR RUNNING TEST (> 100 kW) TEST SHEET NO. AT339 DX
sh. 1 of 2
Description :
Item : IDPID :
TEST RESULTS
1) Running Test
Bearing Temperature: A = Coupling side, B = Opposite
Winding point (description) 1) ______________ 2) ___________________
3) ______________ 4) ___________________
Vertical
Axial
Page 60 of 139
Equipment Description : MOTOR RUNNING TEST (> 100 kW) TEST SHEET NO. AT339 DX
sh. 2 of 2
TEST METHOD
1) Running Test
Running Test is normally required only for motors which have temperature monitoring facilities
built-in by the Manufacturer. It is not applicable for STARTING MOTORS. In both cases only
on-load (*) current shall be recorded. Running test shall be made to check bearings / windings
temperatures until normalization, normally reached within two hours with motors in normal
operating conditions. Readings shall be taken each 10’ minutes for the first half-hour and then
each 15’ minutes, and recorded in the attached table.
2) Vibrations Monitoring
During Running Test, Vibrations shall be observed, especially on Fans’ motors and, if required,
monitored. If any vibration should be found abnormal, the cause shall be investigated and
removed.
Page 61 of 139
Turnover Package: CHLORINATION PLANT
Witnessed By :
Witnessed By :
Witnessed By :
Page 62 of 139
Equipment Description : LOGIC CONTROL TEST SHEET NO. AT503 X
Sh. 1 of 1
DESCRIPTION:
ITEM:
FCD IDENT.:
P & ID IDENT.:
The control logic functions have been checked according to listed documents where
available:
- _________________
- _________________
- _________________
- _________________
Page 63 of 139
Equipment Description : CONTROL CABINET TEST SHEET NO. AT524 X
Sh. 1 of 2
DESCRIPTION: ITEM:
P & ID IDENT.:
DATA SHEET:
1) Pre-operational Checks
Page 64 of 139
Equipment Description : CONTROL CABINET TEST SHEET NO. AT524 X
Sh. 2 of 2
2) Operational test
Note: Operational tests are intended to check common parts only, as Logic/Analog
tests are performed under separate Test Forms.
2.1) Internal P.S.U. and / or power supply voltage / polarity checked for all and each section of
system (A.C. / D.C.).
2.2) (Automatic) change over between power supply units as well power failure alarm checked
(if applicable) and check effects on supplied systems.
2.3) Inter-panel supply voltage polarity and zero voltage bars checked (if applicable).
2.5) Common alarm section (if provided) checked as per ________ sequence.
Page 65 of 139
Equipment Description : REMOTE INDICATOR TEST SHEET NO. AT510 X
Sh. 1 of 1
DESCRIPTION:
DATA SHEET:
1) Pre-operational Checks
2) Function checks
* In case of direct temperature measurement, 0% reading will be done at ambient
temperature.
increase decrease
0+/ -5%
25+/ - 5%
50+/ - 5%
75+/ - 5%
100+/ - 5%
Page 66 of 139
Equipment Description : TRANSMITTER TEST SHEET NO. AT511 X
sh. 1 of 1
DESCRIPTION :
DATA SHEET
1) Pre-operational Checks
2) Function checks
increase decrease
0+/ -5%
25+/ - 5%
50+/ - 5%
75+/ - 5%
100+/ - 5%
Page 67 of 139
Equipment Description : PNEUMATIC PISTON ACTUATOR TEST SHEET NO. AT512 X
OR OPERATED VALVE sh. 1 of 2
DESCRIPTION : ITEM :
DATA SHEET
1) Pre-Start Up Checks
Page 68 of 139
Equipment Description : PNEUMATIC PISTON ACTUATOR TEST SHEET NO. AT512 X
OR OPERATED VALVE sh. 2 of 2
2) Operational Checks
0 0 0 0
25 25 6, 25 50
50 50 25 70, 71
75 75 56, 25 86, 66
Page 69 of 139
Equipment Description : FLOW METER TEST SHEET NO. AT519 AX
Sh. 1 of 1
DESCRIPTION: ITEM:
P & ID IDENT.:
DATA SHEET:
DESCRIPTION
1) Visual inspection
2) Operational test
Page 70 of 139
Equipment Description : pH ANALYZER TEST SHEET NO. AT517 AX
Sh. 1 of 2
DESCRIPTION: ITEM:
P & ID IDENT.:
DATA SHEET:
1) Pre-operational checks
2) Operational test
Page 71 of 139
Equipment Description : pH ANALYZER TEST SHEET NO. AT517 AX
Sh. 2 of 2
0 *
50 *
100 *
Page 72 of 139
Equipment Description : WATER ANALYZER TEST SHEET NO. AT517 BX
sh. 1 of 2
DESCRIPTION : ITEM :
P & ID IDEN :
DATA SHEET
1) Pre-operational checks
SPECIFICATIONS
Page 73 of 139
Equipment Description : WATER ANALYZER TEST SHEET NO. AT517 BX
sh. 2 of 2
2) Operational test
2.7) Alarms (if any) : 1st step : ______ ; 2nd step ______
Page 74 of 139
Equipment Description : GAS ANALYZER TEST SHEET NO. AT517 CX
sh. 1 of 2
DESCRIPTION : ITEM :
P & ID IDEN :
DATA SHEET
1) Pre-operational checks
Page 75 of 139
Equipment Description : GAS ANALYZER TEST SHEET NO. AT517 CX
sh. 2 of 2
SPECIFICATION
2) Operational test
2.7) Alarms (if any) : 1st step : ______ ; 2nd step ______
Page 76 of 139
Equipment Description : SWITCHING DEVICE TEST SHEET NO. AT521 X
sh. 1 of 1
DESCRIPTION : ITEM :
P & ID IDEN :
DATA SHEET
1) Visual Inspection
1.1) Installation check
2) Function checks
2.1) Switching Device
Page 77 of 139
Equipment Description : GENERIC SWITCHING DEVICE TEST SHEET NO. AT621 X
sh. 1 of 1
DESCRIPTION : ITEM :
P & ID IDEN :
DATA SHEET
1) Visual Inspection
2) Function checks
Page 78 of 139
Equipment Description : THERMOCOUPLE & R.T.D. TEST SHEET NO. AT629 X
sh. 1 of 2
DESCRIPTION : ITEM :
P & ID IDEN :
DATA SHEET
TEST : 1)
Continuity & Insulation Checks
Thermoelement relevant to :
_____________________________________________________________________________
02
03
04
05
Page 79 of 139
Equipment Description : THERMOCOUPLE & R.T.D. TEST SHEET NO. AT629 X
sh. 2 of 2
Page 80 of 139
Turnover Package: CHLORINATION PLANT
Witnessed By :
Witnessed By :
Witnessed By :
Page 81 of 139
Equipment Description : ATMOSPHERIC TANKS TEST SHEET NO. AT104 BX
sh. 1 of 3
Item :
Description :
_______________________________________________
Page 82 of 139
Equipment Description : ATMOSPHERIC TANKS TEST SHEET NO. AT104 BX
sh. 2 of 3
Page 83 of 139
Equipment Description : ATMOSPHERIC TANKS TEST SHEET NO. AT104 BX
sh. 3 of 3
Page 84 of 139
Equipment Description : FANS (BLOWERS) TEST SHEET NO. AT114 X
Sh. 1 of 1
Item :
Description :
___________________________________________________________________________
Service: _________________________
2) Operational checks
Page 85 of 139
Equipment Description : PUMPS TEST SHEET NO. AT102 X
Sh. 1 of 3
Item :
Description :
_____________________________________________________________________________
1.1) Lubrication:
- Cleaning and flushing completed (if applicable) ___________
1.6) Shaft seals sealing and / or purging available (if any) ___________
Page 86 of 139
Equipment Description : PUMPS TEST SHEET NO. AT102 X
Sh. 2 of 3
tick
Page 87 of 139
Equipment Description : PUMPS TEST SHEET NO. AT102 X
Sh. 3 of 3
2.9) Set liquid seal flow and verify discharge outlet __________
(*) To be recorded only when specifically required and normally for power 40 kW
(50 HP) and over.
Page 88 of 139
Equipment Description : ATMOSPHERIC TANKS TEST SHEET NO. AT104 BX
Sh. 1 of 3
Item :
Description :
_______________________________________________
Page 89 of 139
Equipment Description : ATMOSPHERIC TANKS TEST SHEET NO. AT104 BX
Sh. 2 of 3
Page 90 of 139
Equipment Description : ATMOSPHERIC TANKS TEST SHEET NO. AT104 BX
Sh. 3 of 3
Page 91 of 139
Equipment Description : PIPEWORK TEST SHEET NO. AT106 X
sh. 1 of 1
Item :
From :
To : Diam. :
2) Operational checks
Page 92 of 139
Equipment Description : FANS (BLOWERS) TEST SHEET NO. AT114 X
sh. 1 of 1
Item :
Description :
___________________________________________________________________________
Service : _________________________
2) Operational checks
Page 93 of 139
Equipment Description : MIXERS TEST SHEET NO. AT115 X
sh. 1 of 1
Item :
Description :
___________________________________________________________________________
Service : _______________________________
2) Operational checks
Page 94 of 139
Equipment Description : ROTATING EQUIPMENT TEST SHEET NO. AT119 X
sh. 1 of 1
Item :
Description :
___________________________________________________________________________
- Tolerance :
___________________________________________________________
Radial Axial
1 1
4 ------------------------------- 2 4 ------------------------------- 2
3 3
RADIAL
AXIAL
Page 95 of 139
Equipment Description : EJECTORS TEST SHEET NO. AT140 X
Sh. 1 of 2
Item :
Description :
___________________________________________________________________________
Page 96 of 139
Equipment Description : EJECTORS TEST SHEET NO. AT140 X
Sh. 2 of 2
2) Operational checks
Page 97 of 139
8. SPECIAL PROCEDURES (acid cleaning, blowing off, etc.)
N.A.
Page 98 of 139
9. LIST OF COMPONENTS BY TYPE
Page 99 of 139
9.3 Control Loops
10. PERMIT TO WORK (see sample PTW form in Appendix VIII, Attachment D)
It is imperative that all possible means of fire prevention be practiced continuously. Quick and
efficient action by site personnel in the first few minutes of fire outbreak, can save hours of
harzardous fire fighting and reduce the risk of damage to equipment and physical injury to personnel.
If a small fire has been extinguished by the operator, the competent authority must be informed.
In case a serious fire matter occurrs, shut down the chlorination unit by local push button (if possible)
and inform immediately the fire brigade.
The hydrogen production in sea water electrolysis plant is about 0.03 kg H2/kg CL2. The hydrogen
gas disengages from the liquid phase in the upper part of the storage tanks and it is discharge to the
atmosphere in a safe area, after that an air injection for hydrogen dilution is provided to avoid
explosion hazard.
The prevention of explosive mixture formation is efficiently made by frequent checking that all the
During the performance of commissioning activities and normal operation the safety prescription of
cell room and storage tanks area, no smoking and no use of free flames, are to be kept in mind.
Before allowing any work (repair or maintenance) to be done in these areas, be sure that hydrogen
has been previously and completely removed from the area and the permit to work system has been
strictly implemented.
Since the electrolytic cells in operation are supplied with DC voltage, the commissioning and operation
personnel must wear rubber shoes and rubber gloves for safety even in case of a hand touch. The
energized parts shall not be touched. Therefore, unauthorized personnel shall not be allowed to enter
the cell room or other electrical equipment room. During the operation of the electrochlorination plant,
no work except for switching, valve handling and sampling shall be carried out. If metal tools or other
conductive tools must be used near the electrolytic cells for repair or maintenance purposes, the
supply power of the electrolytic cells shall be stopped in advance to prevent short-circuit trouble, and
the permit to work system shall be strictly implemented.
This procedure describes the composition, deployment and job descriptions of Contactor commissioning key
personnel, who will manage, supervise and perform the commissioning, operation and maintenance of 15MW
DMTPP Project from handing-over of completed systems up to the Owner/PMT’s acceptance of the Unit.
In order to ensure continuity in the commissioning processes, since the pre-commissioning and commissioning
activities are mostly sequential and for certain aspects overlapping, NEPC commissioning organization outlined
in this procedure is structured to manage both phases.
2.0 APPLICABILITY
This procedure is applicable to the commissioning of 15MW DMTPP Project under NEPC scope of work.
With reference to the attached organization chart (Attachment 1), the positions outlined are described here
below:
4.01.5.2.4 Organize and supervise the operation during all phases of commissioning and
testing in cooperation with partners and customers.
4.01.5.2.5 Planning of short-term schedules of site activities and allocation of the required
number of commissioning personnel and vendor specialists.
4.01.5.2.6 Issue of non-conformity reports according to established procedure and make sure
that the non-conformance is resolved.
4.01.5.2.7 Sporadic check of Operation and Maintenance Manuals (if complete and adequate).
4.01.5.2.8 Definition of the operating procedure.
4.01.5.2.9 Organize and supervise the updating and completion of the technical documentation
within the limits of the scope of supply as required by the contract in time for
Owner/PMT’s acceptance.
4.01.5.2.10 Issue monthly and weekly progress report to the NEPC Site Project Manager.
4.01.6 Responsibility
4.01.6.1 Overall responsability of the execution of the Commissioning in accordance with the
Technical requirement and the time schedule including implementation of the safety
procedure.
4.01.6.2 Technical and operational interface between NEPC operating structure and the
operating structure of the Owner/PMT.
4.01.6.3 Implementation of the Permit to Work procedure for the activities to be performed on
the systems already handed over to commissioning.
4.01.6.4 Implementation of the project quality plan dedicated to the commissioning phase.
4.01.6.5 Authorize solution to non-conformance pertaining the whole power plant.
4.02.5 Tasks:
4.02.5.1 Identification of the systems / turn over packages.
4.02.5.2 Identification of terminal points for each system or turn over package.
4.02.5.3 Preparation of the documents required for checking the erection completion of the
systems / turn over packages.
4.02.5.4 Review and follow up the status of erection completion of each system or package in
accordance with the established schedule for handing over; review the status of
punch list and follow up the timely clearance of the punch points.
4.02.5.5 Categorization of punch list points.
4.02.5.6 Organization of the final inspection with the concerned parties to check the erection
completion of the systems / packages.
4.03.5 Tasks:
4.03.5.1 Overall organization, coordination and supervision of the commissioning activities of
Steam Boiler/ Turbine and thermal cycle/operation and process systems for whole PP
(including manpower, documentation, tools and relevant forms).
4.03.5.2 Overall supervision of engineers and technicians; Owner/PMT’s personnel on training;
and plant operation personnel during commissioning.
4.03.5.3 Determine the needs and the duration of the presence of vendor’s specialist in the
commissioning of process systems.
4.03.5.4 Coordination and support to all vendor specialists involved during commissioning of
process systems.
4.03.5.5 Coordination and supervision of on-the-job training program for the operation
personnel.
4.03.5.6 Responsible for the implementation of safety rules for systems handed over to
commissioning.
4.04.5 Tasks:
4.04.5.1 Overall organization, coordination and supervision of the commissioning of all
electrical systems (including manpower, documentation, tools and relevant forms).
4.04.5.2 Overall supervision of electrical commissioning technicians, Owner/PMT’s personnel
on training and plant operation personnel assigned under his scope of responsibility.
4.04.5.3 Determine the needs and the duration of the presence of vendor’s specialist in the
commissioning of electrical systems.
4.04.5.4 Coordination and support to all vendor specialists involved during commissioning of
electrical systems.
4.04.5.5 Check if the established safety procedure is implemented for the systems within his
scope and responsibility that are handed over for commissioning.
4.04.5.6 Responsible for the start-up, testing and operation of electrical systems.
4.04.5.7 Verification that all contractual and technical requirements are met at the end of
commissioning of the completed electrical systems,
4.04.5.8 Preparation of weekly and monthly programs of the commissioning activities of the
systems under his responsibility.
4.04.5.9 Preparation of weekly and monthly progress report for his scope of work.
4.05.5 Tasks:
4.05.5.1 Overall organization, coordination and supervision of the commissioning of all
process control systems, DCS interfaces and instrumentation (including manpower,
documentation, tools and relevant forms).
4.05.5.2 Overall supervision of I&C commissioning technicians, Owner/PMT’s personnel on
training and plant operation personnel assigned under his scope of responsibility.
4.05.5.3 Determine the needs and the duration of the presence of vendor’s specialist in the
commissioning of l&C systems.
4.05.5.4 Coordination and support to all vendor specialists involved during commissioning of
I&C systems.
4.05.5.6 Responsible for the start-up, testing and operation of I&C systems and process
controls.
4.05.5.5 Verification that all contractual and technical requirements are met at the end of
commissioning of the completed I&C systems,
4.05.5.6 Preparation of weekly and monthly programs of the commissioning activities of the
systems under his responsibility.
4.05.5.7 Preparation of weekly and monthly progress report for his scope of work.
4.06 Chemist
4.06.5 Tasks:
4.06.5.1 Commissioning, supervision, control and trouble shooting related to the chemical
process systems under the area of responsibility.
• Sampling systems water/steam/flue gas.
• Steam boiler, thermal cycle and steam turbine.
• Chemical injection/dosing systems of boiler, thermal cycle and ash handling.
• Water demineralization plant
• Chlorination Plant
• Sewage water, Oily Water, Coaly water treatment plants
• Potable water system
4.07.5 Tasks:
4.07.5.1 Organization, coordination and supervision of the preparation works for the
mechanical equipment of systems handed over for tests and first operation.
4.07.5.2 Organization, coordination and supervision of erection and dismantling of temporary
equipment and piping necessary for pre-commissioning activities.
4.07.5.3 Overall responsibility for routine maintenance (lubrication, greasing, cleaning, etc.) of
systems handed over to commissioning.
4.07.5.4 Recording of information relevant to maintenance to the equipment card and
lubrication card.
4.07.5.5 Overall supervision of all personnel assigned to maintenance.
4.07.5.6 Coordination and support to all mechanical vendor specialists during commissioning.
4.07.5.7 Scheduling of daily and weekly maintenance and preservation activities to the plant
equipment.
Tasks:
Lead the Electrical Technicians under his responsibility in performing the following commissioning activities:
Tasks:
Lead the I&C Technicians under his responsibility in performing the following commissioning activities:
Tasks:
• Checking and trouble shooting of connections to marshalling kiosks, distribution panels, PC/MCC boards.
• Checking of indication signals from/to switchgears
• Checking and adjusting of settings of various electrical devices
• Checking of grounding systems.
• Assist in testing, energizing and trouble shooting of electrical equipment
• Assist in testing and adjustments of electrical protections.
• Assist in testing of alarm and trip circuits
Tasks:
4.13 Operator
Tasks:
Tasks:
• Assist in testing and trouble shooting of mechanical, hydraulic and pneumatic auxiliaries.
• Taking readings of data for plant systems
• Checking of temperatures, levels, pressures, noise, vibrations, etc.; of balance of plant systems
• Perform routine checks for equipment
Tasks:
Tasks:
4.17 Lubricator
Tasks:
• Performing all minor and major lubrication works for plant equipment
• Re-filling or replacement of lubricants
• Supervising of lubricant consumption
• Perform routine checks of lubricants
• Perform lubrication purification
STEAM BOILER
ERB-LFO-001 Light fuel oil system
MID-LPC-001 Limestone power conveying system
HFB-CCF-001 Coal feeding system
ENF-SBC-001 Start-up material conveying (Bed of sand)
HAD-FWS-001 Boiler feed water supply system
HJA-FSB-001 Start up burner and ignition system
HLB-FDF-001 PAF – SAF – IDF -& dumpers
HDB-FSS-001 HP fluidizer and sealing air system
HNA-FGS-001 Flue gas system
HLA-SAS-001 Boiler SH&RH live steam
HDE-ESP-001 Electrostatic precipitator ESP
HDA-BAH-001 Bottom ash handling
HDA-FAH-001 Fly ash handling
HAN-DBD-001 Boiler vent, blow-down and drain system
HCB-SBS-001 Sootblower system
QCC-PHI-001 Chemical dosing and injection system
QUW-SWS-001 Steam and water sampling & analyzer system
HAJ-SVF-001 Boiler safety valves
HNY-CEM-001 Exaust gas emission control system –CEMS-
HAH-ELE-001 Boiler elevator
STEAM TURBINE
LBA-SHS-001 Main live steam – SH & RH
LBG-AUS-001 Auxiliary and start-up steam
MAW-GST-001 Shaft sealing (Gland steam)
MAL-VAD-001 Turbine vent, drain and exaust system
ELECTRICAL
AEA-GIS-001 230 KV GIS Substation
BAT-BCT-001 Power transformer GSTU – UAT - SAT
BFT-AUT-001 Auxiliary transformer
BAA-BAB-001 IPBD MV
BBA-MVS-001 MV Switchgear
BFA-LVS-001 LV Switchgear
BFB-LVS-001 LV Subdistribution boards
BTA-BTB-001 Battery charger and DC system
BRU-UPS-001 UPS System and distribution boards
1. SCOPE
2. RESPONSIBILITY
2.1 QA/QC Department
2.2 Turn Over Engineer
2.3 Punch List Coordinator
2.4 Technical Office
2.5 Procurement Office
During the construction and commissioning phase of the Unit up to the Provisional or Final Acceptance by
the Owner/PMT, the deficiency in the construction or shortfall in equipment, materials or systems that need
to be made good are classified as punch list.
This procedure defines the methods adopted for the management of such punch list and the relevant
corrective actions necessary to address and close this punch list items.
2. RESPONSIBILITY
The responsibility of each section internal to NEPC site organization with respect to the management of
punch list are described here below:
The categories for the classification of punch points are defined as follows:
• Category A – punch point that manifests unsafe conditions which may put to risks the personnel and
equipment (for punch point under this category, it will not be possible to turnover a system or package to
the Commissioning Team)
• Category B – punch point which may affect the safe operation of the system (normally cleared before the
start of hot commissioning)
• Category C – punch point of minor importance (normally cleared before the Provisional or Final
Acceptance of the Unit)
4.1 General
The Punch List shall be developed to cover the outstanding works from erection completion up to the
Provisional or Final Acceptance of the Unit..
The scope of the Punch List is to establish a unique document where the concerned parties
(construction and commissioning) agree to carry-out the outstanding activities necessary for the
completion of the Unit.
The list shall include the activities relevant to all the disciplines, i. e. civil, mechanical, electrical and
instrumentation & control.
The list shall be implemented starting from the erection completion stage of the systems.
The Punch List status shall be constantly updated and the relevant reports shall be distributed
periodically to the concerned parties; the contents and the structure of the reports shall be progressively
defined accordingly to the needs of the interested parties.
All correspondence regarding existing Punch List items should refer to the Punch List registration
number.
10 Inspected by Identification of the person who raised the defect (it is presumed
that the same person verifies and accepts the item to clear the
punch point, Field No. 16)
11 Reference Document It is the document that is made in reference for the determination of
the defect (letters, contract, technical specifications).
12 Workability Indication of the prerequisites for making good:
1. There are no particular requirements.
2. Technical assistance is required.
3. Materials/spare parts are required.
4. Shutdown of the system or plant is required.
13 Responsibility Field Supervisor who is given the responsibility of making good.
14 Expected date of clearing Date expected when the punch point is to be made good and
cleared.
15 Actual date of clearing Date of actual clearing of the punch point.
1.0 SCOPE
2.0 DEFINITIONS
4.0 RESPONSIBILITY
5.0 REMARKS
6.0 PROCEDURE
Attachments:
Attachment A
Attachment B
Attachment C
Attachment D
This procedure applies only to the installation or maintenance work on systems or packages handed-over from
Construction Team to the Commissioning Team within the boundaries of the construction area.
For some systems or packages having interfaces with the existing installation of Owner, the Permit to Work
system of Owner shall be applied.
2.0 DEFINITIONS
The Permit to Work (PTW) is a written and signed document that authorizes the work supervisor to carry out
installation or maintenance activities on a turned-over system to commissioning.
The PTW referred hereto is the one issued by NEPC Commissioning Manager within the construction area to
their personnel to perform during the commissioning stage of the Unit.
The Shift Charge Engineer keeps all the keys related to the PTW in a safety box located in the MCR.
A. Electrical System
Breaker racked out (if possible locked out) or isolator opened and locked out. Earth switch inserted if work
is being performed on electrical parts. Feeders grounded if work is being performed on bus bars.
B. Process System
Isolation valves upstream and downstream of section under PtW locked close, vents open, drains open to
allow the system to be cooled, depressurized and emptied.
The same as B), but in addition, the section should be purged and washed under supervision of a Safety
Engineer.
In addition to C), any fire source or forced fluid has to be under safety conditions. Continuous purging or
4.0 RESPONSIBILITY
The Work Supervisor is responsible to identify correctly the activity and the equipment described in the PTW
and to carry out the work within the isolation points according to the indication listed in PTW form, Attachment C.
He is also responsible that the works are done according to the work safety rules.
The Shift Charge Engineer is responsible to implement the safety conditions in the portion of the Plant under
PtW, and to maintain the same conditions during the performance of the works foreseen (see Attachment D).
Finally, upon completion of the works and when he receives back the area from the Work Supervisor, it is
always the Shift Charge Engineer who is authorized to remove those safety conditions.
5.0 REMARKS
For systems or packages having interfaces with the existing installation of the Owner, the Permit to Work system
of Owner shall be applied.
In each isolation point of the system or part thereof under PTW, the Shift Charge Engineer provides tags printed
clearly with “CAUTION – WORK IN PROGRESS” (see Attachment A). Only him can remove these tags after
the work is completed, inspected and the work permit is signed off for resumption of activities on taking over by
operation.
6.0 PROCEDURE
The procedure for PTW system is illustrated in the attached flow chart (see Attachment B). By issuing a Permit
to Work, the Shift Charge Engineer guarantees the safe conditions at the work place and for the whole duration
of the work. He is also responsible that the work place does not become a danger source for other parts of the
plant.
Examples of the form for the authorization of a PTW and the register of PTW issued are attached in this
procedure (see Attachment C and D).
During the commissioning phase of the plant, safety rules to be implemented inherent to
safety at work shall be the same rules applied during the construction phase.
ATTENTION
WORK
IN
PROGRESS
P.T.W. No.______
CONSTRUCTION MAINTENANCE
WORKS WORKS
Construction
Supervisor
The equipment is handed over to NO responsible to
commissioning? authorize the
work (PTW not
YES required).
The Shift Charge Engineer implements
the safety conditions (Sect. 3.0)
The compilation of the PTW Register is the responsibility of Shift Charge Engineer.
The activities that necessarily require the use of the test equipment during commissioning are:
Laboratory activities:
Calibration of transmitters and controller and trouble shooting on cards and apparatus.
High-quality instruments are required for these activities.
Field activities:
Functional checks on equipment.
These activities do not need special quality instruments.
This plan covers the following instruments, which shall be utilized in the temporary commissioning laboratory:
• Pressure gauges
• Laboratory multi-meters
• Thermometers associated with test oven or oil bath
3. RESPONSIBILITY
The person in-charge of the temporary laboratory is responsible for all QA-activities.
2. TOOLS
3. CONSUMABLES