BoMI Concrete Pouring Plan NO.1
PROJECT = Establishment of Kenya Advanced]
Institute of Science and Technology Project |
Rocation: SH2 GF Girder and Slab
Date: 24 / Jan / 2023
i
io
Equipment | Standard | Number Division | Members | Remarks
Pune car| 49 M 1 cons weer, 10
Vibelator 2 PEngineer | 1 |
Equipment
au Manpower | @Aiac 1)
plan
Safely 1 |
Heath | 1
Other's Signalman
1) Ready-mixed conerete suppliers : RHOMBUS
2) Time taken to arrive on site : 1HOUR ~ 1HOUR 30MIN
3) Scheduled pouring start time 15 PM
Consumed
quantiy | 4 Scheduled pouring end time 21 PM
(basis of | 5) Total Time 6H
calculation) =
6) Total quantity to be poured: 130 «* ~ Standard : 25~30-150
7) Total Mixer Truck Inputs: (7 ~ 8m / truck) Total 10 Mix-trucks
8) Pouring speed of the pump + 130. (fh)